Dedicated Freight
Corridor Corporation of India Vs. Subodh Singh & Ors.
J U D G M E N T
R.V.RAVEENDRAN, J.
1.
Leave
granted.
2.
The
first respondent was the owner of lands bearing Gata Nos.106, 118, 119, 123, 126
and 145 in village Kakrahi, District Auraiya, Uttar Pradesh. The said lands,
among others, were acquired for a special railway project, that is, the
Dedicated Freight Corridor at Kanpur (Rural), Auraiya and Etava Districts. The
acquisition was under chapter IVA of the Railways Act, 1989 (`Act' for short) which
dealt with land acquisitions for special 2railway projects. A notification dated
10.6.2008 (gazetted on 10.6.2008) under section 20A(1) of the Act was published
by the Central Government declaring its intention to acquire lands in question
for execution of a special railway project. This was followed by a declaration dated
12.12.2008 (gazetted on 16.12.2008) under section 20E(1) of the Act declaring
that the lands mentioned therein should be acquired for the purpose mentioned
in the notification under section 20A(1) of the Act. On such declaration, the
land vested absolutely in the Central Government free from encumbrances, in
view of the vesting provision in section 20E(2) of the Act. A public notice
referring to the notifications dated 10.6.2008 and 12.2.2008 under section
20A(1) and 20E(1) of the Act and inviting claims from all persons interested in
the lands was published by the competent authority in two newspapers (Amar
Ujala and Dainik Jagran) dated 20.2.2009. Thereafter an order dated 8.2.2010 was
made by the competent authority determining the compensation payable, under
section 20F(1) of the Act.
3.
The
first respondent filed W.P.No.14945/2010 for quashing the award dated 8.2.2010
and for a declaration that the entire acquisition proceedings stood lapsed under
section 20F(2) of the Act, as the award was not made within one year from the
date of publication of the date of declaration dated 312.12.2008. A Division bench
of the High Court allowed the said writ petition by the impugned order dated
12.5.2010. It quashed the award dated 8.2.2010 and declared that the acquisition
proceedings stood lapsed.
The said decision was
based on the following findings recorded by the division bench : (a) The award
was made beyond one year from the date of publication of the declaration under
section 20E(1) of the Act.(b) The benefit of the first proviso to section 20F(2)
of the Act which enabled the competent authority to make the award within an extended
period of six months (after the expiry of one year specified in section 20F(2)
of the Act) was not available to save the acquisition, as the competent authority
failed to record in writing any reason to show that he was satisfied that the delay
was caused due to unavoidable circumstances. Questions for consideration
4.
Feeling
aggrieved the appellant has filed this appeal. The appellant contends that the
award was validly made within one year from the date of declaration under
section 20E(1) of the Act, as it was made within one year from 20.2.2009, the date
on which public notice of the said notification dated 12.12.2008 was published in
the newspapers. According to the 4appellant, where the publication is made in the
official gazette and the newspapers, the last of the dates of such publication shall
be the date of publication of the declaration. It is alternatively contended
that as the award was made within 18 months of the date of publication of the
declaration, the acquisition did not lapse. On the contentions urged the
following questions arise for consideration :(i) Whether the period of one
year, stipulated under section 20F(2) of the Act, for making the award, has to be
reckoned from the date of publication of the declaration under section 20E(1)
of the Act in the official gazette or from the date of any subsequent
publication of the declaration in newspapers?(ii) Whether an award made within
six months after the expiry of one year from the date of publication of the
declaration, is valid under the first proviso to section 20F(2) of the Act,
even if reasons are not recorded by the competent authority in writing to show that
he was satisfied that the delay had been caused due to unavoidable
circumstances?The relevant legal provisions
5.
A
reference to the relevant provisions will be necessary to provide answers to these
questions. Chapter IVA was inserted in the Act by Amendment Act 11 of 2008 with
effect from 31.1.2008. The said chapter is 5a self contained code in regard to land
acquisitions for special railway projects.
5.1.
Sub-section
20A relates to power to acquire land and reads thus : "20A. Power to
acquire land, etc.: (1) Where the Central Government is satisfied that for a
public purpose any land is required for execution of a special railway project,
it may, by notification, declare its intention to acquire such land. (2) Every notification
under sub-section (1), shall give a brief description of the land and of the special
railway project for which the land is intended to be acquired. (3) The State
Government or the Union Territory, as the case may be, shall for the purposes of
this section, provide the details of the land records to the competent
authority, whenever required. (4) The competent authority shall cause the substance
of the notification to be published in two local newspapers, one of which shall
be in a vernacular language.
5.2.
"Special
railway project" is defined in section 2(37A) of the Act and means a project,
notified as such by the central government from time to time, for providing
national infrastructure for a public purpose in a specified time-frame, covering
one or more states or the union territories. Clauses (7A) and (26) of section 2
of the Act define "competent authority" and notification as under : "2(7A).
`competent authority' means any person authorized by the Central Government, by
notification, to perform the functions of the competent authority for such area
as may be specified in the notification. 2(26). `notification' means a notification
published in the Official Gazette."
5.3.
Section
20B deals with power to enter for survey etc. Section 20C relates to evaluation
of damages during survey, measurement etc. Section 20D provides for hearing of
objections to the acquisition.
5.4.
Section
20E deals with declaration of acquisition and the same is extracted below : "20E.
Declaration of acquisition : (1) Where no objection under subs- section (1) of section
20D has been made to the competent authority within the period specified
therein or where the competent authority has disallowed the objections under sub-section
(2) of that section, the competent authority shall, as soon as may be, submit a
report accordingly to the Central Government and on receipt of such report, the
Central Government shall declare, by notification, that the land should be
acquired for the purpose mentioned in sub-section (1) of section 20A. (2) On the
publication of the declaration under sub-section (1), the land shall vest absolutely
in the Central Government free from all encumbrances. (3) Where in respect of any
land, a notification has been published under sub-section (1) of section 20A
for its acquisition, but no declaration under sub-section (1) of this section
has been published within a period of one year from the date of publication of that
notification, the said notification shall cease to have any effect : Provided that
in computing the said period of one year, the period during which any action or
proceedings to be taken in pursuance of the notification issued under sub-section
(1) of section 20A is stayed by an order of a court shall be excluded. (4) A declaration
made by the Central Government under sub- section (1) shall not be called in question
in any court or by any other authority."
5.5.
Section
20F deals with determination of amount payable as compensation. Sub-sections 1,
2 and 4 which are relevant for our purpose are extracted below : "20F.
Determination of amount payable at compensation - (1) Where any land is
acquired under this Act, there shall be paid an amount which shall be
determined by an order of the competent authority. (2) The competent authority shall
make an award under this section within a period of one year from the date of the
publication of the declaration and if no award is made within that period, the entire
proceedings for the acquisition of the land shall lapse :
Provided that the
competent authority may, after the expiry of the period of limitation, if he is
satisfied that the delay has been caused due to unavoidable circumstances, and
for the reasons to be recorded in writing, he may make the award within an
extended period of six months. Provided further that where an award is made
within the extended period, the entitled person shall, in the interest of justice,
be paid an additional compensation for the delay in making of the award, every
month for the period so extended, at the rate of not less than five per cent of
the value of the award, for each month of such delay. xxx xxx xxx (4) Before
proceeding to determine the amount under sub-section (1) or sub-section (3), as
the case may be, the competent authority shall give a public notice published
in two local newspapers, one of which shall be in a vernacular language
inviting claims from all persons interested in the land to be acquired." xxx
xxx xxxRe : Question (i)
6.
Sub-section
(1) of section 20E of the Act provides that the central government shall, on
receipt of the report of the competent authority, declare by notification that
the land should be acquired for the purpose mentioned in 8section 20A(1).
Sub-section (2) of section 20E of the Act provides that on the publication of such
declaration by notification, by the central government, under sub-section (1), the
lands shall vest absolutely in the central government free from all encumbrances.
Clause (26) of section 2 defines "notification" as a notification published
in the official gazette. Section 20E thus requires the notification to be
published only in the official gazette.
The section does not require
the notification of declaration to be published in any newspaper or by any
other mode. By way of contrast, we may refer to section 20A(4) relating to
preliminary notification and 20F(4) relating to public notice inviting claims
before making the award of the Act. Section 20A(4) requires that in addition to
publication of a notification by the central government, of the declaration of its
intention to acquire any land, the competent authority shall cause the
substance of the notification to be published in two local newspapers one of
which will be in a vernacular language. Section 20F(4) of the Act requires that
before proceeding to determine the compensation, the competent authority shall give
a public notice in two local newspapers inviting claims. Wherever newspaper
publication is required, it has been specifically provided by the legislature.
The absence of a similar provision in section 20E for publication in
newspapers, makes it clear that the publication of the declaration under 9section
20E(1) is complete when it is published in the official gazette. The
publication of the notification under section 20E(1), or its substance, in any
newspaper, is not therefore a requirement under the Act. Even if it is
published in any newspaper, such publication will be only for general
information and will not serve any purpose under the Act.
7.
The
appellant submits that a public notice under section 20F(4) of the Act was published
in two newspapers on 20.2.2009 notifying the public about the declaration under
section 20E(1) and inviting claims from persons interested and consequently,
the period of one year should be reckoned from 20.2.2009 and not from 16.12.2008
(date on which the notification was gazetted). According to appellant, if the date
of publication in the newspapers (20.2.2009) is taken into account, the award
made on 8.2.2010 would satisfy the requirement of making the award within one year
stipulated in section 20F(2) of the Act. We find no merit in this contention.
The public notice dated 20.2.2009 published in the newspapers was not a
publication of the notification of declaration under section 20E(1) of the Act,
but a public notice required to be issued under sub-section (4) of section 20F
by the competent authority inviting claims, after the publication of a
notification under Section 20E(1) of the Act. Even if the public notice in the newspapers
dated 20.2.2009, is to be regarded as publication of the declaration under
section 20E(1) of the Act, it would not be of any relevance to calculate the period
of one year under section 20F(2) of the Act. As noticed above what is relevant
for the purpose of reckoning the period of one year is the date of publication of
notification of declaration under section 20E(1) of the Act in the official
gazette and nothing else. Re : Question (ii))
8.
Sub-section
(2) of section 20F of the Act requires the competent authority to make an award
within a period of one year from the date of publication of the declaration and
provides that if no award is made within that period, the entire proceedings for
acquisition of land shall lapse. The term "publication" in section
20F(2) refers to publication of the declaration in the official gazette. In
this case, the declaration under section 20E(1) was made by a notification
dated 12.12.2008 which was published in the official gazette on 16.12.2008.
Therefore the award ought to have been made within one year from 16.12.2008.
The award made on 8.2.2010, was clearly beyond one year from the date of publication
of the declaration. If the benefit of additional period of six months under the
first proviso to section 20F(2) is taken, the award made on 8.2.2010 would be in
time and the acquisition 11proceedings would not lapse. The question is whether
it is permissible to do so on the facts of this case.
9.
Though
sub-section (2) of section 20F provides that if the award is not made by the competent
authority within one year from the date of publication of the declaration, the
entire proceedings for acquisition of land shall lapse, the proviso thereto
enables the competent authority to make the award within an extended period of six
months if he is satisfied that the delay had been caused due to unavoidable circumstances
and reasons therefor are recorded in writing. In this case admittedly the competent
authority has not recorded any reasons in writing to hold that the delay was
due to unavoidable circumstances.
10.
In
view of the inconsistencies and ambiguities in section 20F of the Act, (enumerated
in para 12 below), it becomes necessary to read the provisions of the section harmoniously.
The effect of such harmonious reading will be as under : (a) The award has to be
made within one year from the date of publication of the declaration. (b) If the
competent authority is satisfied that the award could not be made within a
period of one year due to unavoidable circumstances, 12 which are to be
recorded in writing, he could make the award within eighteen months. The requirement
regarding recording of reasons is not mandatory. (c) The acquisition
proceedings will stand eclipsed at the end of one year from the date of
publication if no award is made within one year. If no award is made within eighteen
months, the proceedings for acquisitions would lapse. (d) If the award is made within
eighteen months, the acquisition will emerge out of the eclipse and will not lapse.
But additional compensation will become payable for the period beyond one year,
as provided in the second proviso to section 20F(2). If the reasons are not recorded
or if the reasons are not satisfactory, the additional compensation under the
second proviso can be at a rate higher than the minimum of 5% per month stipulated
in the second proviso to section 20F(2).
11.
The
award dated 8.2.2010 by the competent authority proceeds on the basis that the
notification of declaration under section 20E(1) of the Act has to be published
not only in the official gazette, but also in the form of a public notice in two
newspapers and that the latter of the two dates of publication would be the
date of commencement of the period of one year, under section 20F(2) of the Act.
This is evident from the following observations in the said award dated 8.2.2010
of the competent authority: "Thereafter, the proposal for the issuance of the
notification for the acquisition of land under section 20E of Indian Railways
Act and report of the competent officer has been presented before the Central Government.
The Central Government issued notification through Gazette No. Ka.Aa.2903 (A)
dated 12.12.2008 for the acquisition of total 1.2180 hectare land in village Kakahari.
The publication of above
mentioned notification has been issued in two daily newspapers Amar Ujjala and Dainik
Jagran under the amended provisions of section 20E(4) of the Indian Railways
Act 1989 on 20.2.2009." (emphasis supplied)It is evident from the award
that the competent authority proceeded under the bona fide impression that
publication of the public notice under section 20F(4) in the two newspapers
(Amar Ujala and Dainik Jagran) on 20.2.2009 referring to the declaration under
section 20E(1), subsequent to the date of gazette publication (16.12.2008) is
also part of the process of publication of the declaration under section 20E(1).
As a consequence, he applied the principle that when publication is required to
be made by more than one mode, the date of publication by the last of the
prescribed modes is the date of publication. He therefore assumed that the date
of publication of the public notice in the two newspapers dated 20.2.2009 to be
the date of publication of declaration for the purposes of section 20E(1) and
20F(2) of the Act and that consequently the award was made within one year from
such date. On the facts of the case and on a harmonious reading of the
provision of section 20F of the Act, the aforesaid reasoning in the award can
be treated as the reason for the delay in making the award. The acquisition did
not, therefore, lapse. However, having regard to the second proviso to section 20F(2),
the land owners (described as "entitled persons") will be 14entitled
to additional compensation for the delay in making of the award at a rate not
less than 5% of the value of the award for each month of delay. Certain
anomalies in the provisions of Chapter VIA of the Act
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
Before
parting we may refer to several apparent anomalies noticed in Chapter IVA of the
Act, in particular in section 20F, which requires the attention of the law makers.
As neither the validity of Chapter VIA of the Act nor the validity of any provision
therein is under challenge in this appeal, but as we have faced difficulties in
the application of section 20F, we are referring to some of the anomalies in the
provisions of Chapter IVA, without pronouncing upon the validity of the
provision.(i) Sub-section (2) of section 20F provides that if no award is made
within one year from the date of publication of the declaration, the entire
proceedings for the acquisition shall lapse. The first proviso to sub-section
(2) provides that the competent authority may, after the expiry of the period of
one year, if he is satisfied that the delay has been caused due to unavoidable
circumstances and for reasons to be recorded in writing, make an award within
an extended period of six months.
This means that when
an award is not made within one year from the date of publication of the
declaration, the proceedings for acquisition would lapse, but if within six months
of such lapsing, the competent authority makes an award after recording reasons
for the delay, what stood lapsed would stand revived. But if the acquisition proceedings
had already lapsed at the end of one year, mere making of an award thereafter cannot
revive the acquisition proceedings, in the absence of any provision in the Act
providing for revival of the lapsed acquisition. (ii) Sub-section (2) of
section 20F requires the award to be made by the competent authority and the
first proviso requires the competent authority to record the reasons for the delay.
What are "unavoidable circumstances" leading to the delay which would
enable the competent authority to make an award beyond one year, would
invariably lead to litigations as to whether there were unavoidable
circumstances, whenever the award is made beyond one year. As the consequence of
making an award beyond one year but within eighteen months, involving payment of
additional compensation, is set out in the second proviso to section 20F(2),
there is no need for requiring the competent authority to record reasons in
writing showing that the delay was due to unavoidable circumstances. (iii) The
second proviso to section 20F(2) requires payment of additional compensation
for the delay in making of the award, at the rate of not less 16than five
percent of the value of the award, for each month of delay.
This vests unguided discretion
in the competent authority or the Arbitrator to award additional compensation at
any higher rate and gives room for unnecessary litigation at the instance of
"entitled persons" claiming higher percentages as additional
compensation. It is necessary to consider whether specifying a fixed monthly
rate of increase would serve the ends of justice better instead of indicating a
minimum rate per month.(iv) Sub-section (1) of section 20F refers to an
"order" of the competent authority determining the amount to be paid for
the land acquired. Sub-section (2) refers to the competent authority making an "award".
It is not clear whether the award by the competent authority is consequential
to the order that is made under sub-section (1) of section 20F or whether the
order under sub-section (1) is itself the award referred to in sub-section (2) of
section 20F. Confusion can be avoided by using only one of the words -`order' or
`award' - to refer to the decision of the competent authority determining
compensation, at all places.(v) Sub-section (4) of section 20F provides that
before determining the amount under sub-section (1) or sub-section (3), the competent
authority shall give a public notice inviting claims from all persons
interested in land 17to be acquired.
The issue of such
public notice under section 20F(4) is after the publication of notification of declaration
under section 20E(1). Sub- section (2) of section 20E provides that on
publication of the declaration, the land vests in the central government. If
the land has already vested in the government on publication of the declaration
under section 20E(1), the question of issuing a public notice thereafter,
inviting claims under section 20F(4) from persons interested in the lands
"to be acquired" does not arise. The words "to be acquired"
may have to be replaced by the words "acquired". (vi) If the land has
already vested absolutely in the Central Government on publication of declaration
of acquisition in the Official Gazette under section 20E(1), it is not clear how
the proceedings for acquisition could lapse if the award is not made within one
year or even 18 months. This Court while dealing with other enactments relating
to acquisition has held that acquisition would not lapse as consequence of not making
the award within the specified time, if the land had already vested in the
government and the Act does not provide for re-vesting in the land owner. [See :
Satendra Prasad Jain vs. State of U.P. - 1993 (4) SCC 369, Awadh Bihari Yadav
vs. State of Bihar - 1995 (6) SCC 31, UP Jal Nigam, Lucknow vs. Kalra Properties
(P) Ltd. - 1996 (3) SCC 124,
Allahabad Development
18Authority vs. Nasiruzzaman - 1996 (6) SCC 424 and Ginnar Traders (3) vs. State
of Maharashtra - 2011 (3) SCC 1].(vii) Section 20 I of the Act provides that though
the land vests in the central government on publication of the declaration
under section 20E(1), the competent authority can demand the surrender or
delivery of possession only after the compensation is determined under section 20F
and is deposited under section 20 H. However section 20 J provides that once
the land vests in the central government on publication of a declaration under
section 20E(2), it shall be lawful for any persons authorized by the central
government "to enter and do other act necessary upon the land for carrying
out the building, maintenance, management or operation of the special railway
project or part thereof or any work connected therewith". In other words
section 20-J enables the central government to enter upon possession of the
land on publication of the declaration under section 20E, even before the award
is made, and carry on the activities connected with the special railway project
for which the land was acquired. The provisions of section 20-J apart from being
badly worded, are contrary to provisions of section 20-I. Section 20 J would
lead to deprivation of possession of the land to the land owner without even
determining or offering any compensation.
This requires to be
examined and corrected. Further, there is no indication as 19to what should
happen if the central government or person authorized by it starts executing the
special railway project in the acquired land under section 20 J and thereafter,
the acquisition lapses on account of the award not being made within the time
frame mentioned in section 20F(2). We have referred to these anomalies as they are
likely to give room for considerable avoidable litigation, in regard to acquisitions
under Chapter IVA of the Act. These anomalies may also defeat the very
legislative intent to provide a progressive form of land acquisition when compared
to the provisions of Land Acquisition Act, 1894. Be that as it may. Conclusion
12.
13.
In
view of our finding that the acquisition has not lapsed, we allow this appeal, set
aside the judgment of the High Court, and dismiss the challenge to the acquisition.
It is however made clear that in view of the delay in making the award beyond one
year, the first respondent shall be entitled to additional compensation as
provided under the second proviso to section 20F(2) of the Act. Parties to bear
their respective costs.
14.
The
Registry is directed to send copies of this order to the Law Commission of
India and Ministry of Railways.