Union of India Vs. M/s
Krafters Engineering & Leasing(P) Ltd.
J U D G M E N T
P. Sathasivam, J.
1.
This
appeal by Union of India arises out of the final judgment and order dated
24.04.2006 passed by the High Court of Judicature at Bombay in Appeal No. 219
of 2006 in Arbitration Petition No. 274 of 2005 whereby the Division Bench of
the High Court dismissed their appeal.
2.
Brief
facts:
a. On 16.05.1988, the respondent
was awarded with a contract for the work of Provision of Signaling Arrangements
at "C" Class Stations on Igatpuri-Bhusawal Section and 2
"C" Stations on Bhusawal-Badnera Section of Bhusawal Division of Central
Railway at the cost of Rs.18,10,400/-. On completion of the contract, the
respondent raised certain disputes/claims by filing Suit No. 2822 of 1993
before the High Court and demanded for adjudication through arbitration. The
High Court directed the General Manager of the Central Railway to appoint an
arbitrator and refer the disputes for adjudication. Since the Arbitrator appointed
could not deliberate the matter within the time limit, the respondent invoked the
jurisdiction of the Umpire. The Umpire, by order dated 26.04.2005, gave award for
Claim Nos. 1, 3, 6, 8, 9, 10, 11, 12 & 13 and rejected Claim Nos. 2, 5, 7 &
14 and mentioned that a bank guarantee towards security deposit against claim
No. 4 is to be returned.
b. Challenging the award
given by the Umpire for Claim Nos. 11 & 13, the appellant herein filed Arbitration
Petition No. 274 of 2005 before the High Court. The learned Single Judge of the
High Court, vide order dated 06.12.2005 dismissed their petition.
c. Aggrieved by the order
passed by the learned single Judge, the appellant herein filed an appeal being
Arbitration Appeal No. 219 of 2006 before the Division Bench of the High Court.
The Division Bench, by impugned order dated 24.04.2006, dismissed the appeal.
Challenging the said order, the Union of India preferred this appeal by way of
special leave before this Court.
1.
2.
3.
Heard
Mr. A. S. Chandhiok, learned Additional Solicitor General for the Union of India
and Mr. Ramesh Babu M.R., learned counsel for the respondent.
4.
Before
the High Court as well as before us, the appellant projected their case only
with regard to interest that was granted by the arbitrator and confirmed by the
High Court. Therefore, the only point for consideration in this appeal is whether
an arbitrator has jurisdiction to grant interest despite the agreement
prohibiting the same?
5.
Though
the appellant has challenged the award of the Umpire in respect of Claim Nos. 11
and 13, they are mainly concerned about grant of interest; hence there is no need
to traverse all the factual details except the required one which we have
adverted to. According to Mr. A.S. Chandhiok, learned ASG, in view of clause 1.15
of the General Conditions of the Contract between the parties, the arbitrator does
not have the power to award interest pendente lite. The said clause reads as
under: "1.15 Interest on Amounts - No interest will be payable upon the Earnest
Money or the Security Deposit or amounts payable to the Contractor under the
Contract but Government Securities deposited in terms of clause 1.14.4 will be
repayable with interest accrued thereon."
According to the learned
ASG, in view of the above-mentioned clause, no interest is payable on the amount
payable to the Contractor under the contract. On the other hand, Mr. Ramesh Babu
M.R., learned counsel appearing for the respondent submitted that irrespective
of the bar in the contract arbitrator has power to award interest for which he
strongly relied on the decision of this Court in Board of Trustees for the Port
of Calcutta vs. Engineers-De-Space-Age, and Madnani Construction Corporation
Private Limited vs. Union of India and Others,
1.
2.
3.
4.
5.
6.
We
have already extracted the relevant clause wherein the words "amounts payable
to the Contractor under the contract" are of paramount importance. If
there is no prohibition in the arbitration agreement to exclude the jurisdiction
of the arbitrator to entertain a claim for interest on the amount due under the
contract, the arbitrator is free to consider and award interest in respect of
the period. If there is a prohibition in the agreement to pay the interest, in
that event, the arbitrator cannot grant the interest. Clause 1.15 prohibits
payment of interest on the amount payable to the contractor under the contract.
7.
It
is not in dispute that the provisions of the Arbitration Act, 1940 alone are applicable
to the case on hand. Now, let us consider various decisions of this Court
dealing with similar prohibition in the agreement for grant of interest. In Secretary,
Irrigation Department, Government of Orissa and Others vs. G.C. Roy, the
Constitution Bench had considered Section 29 of the Arbitration Act, 1940 which
deals with interest pendente lite. After analyzing the scheme of the Act and
various earlier decisions, the Constitution Bench considered the very same issue,
namely, whether an arbitrator has power to award interest pendente lite and, if
so, on what principle. The relevant paragraphs are extracted hereunder:- "43.
The question still remains whether arbitrator has the power to award interest pendente
lite, and if so on what principle. We must reiterate that we are dealing with the
situation where the agreement does not provide for grant of such interest nor
does it prohibit such grant. In other words, we are dealing with a case where
the agreement is silent as to award of interest. On a conspectus of aforementioned
decisions, the following principles emerge:
i.
A
person deprived of the use of money to which he is legitimately entitled has a
right to be compensated for the deprivation, call it by any name. It may be called
interest, compensation or damages. This basic consideration is as valid for the
period the dispute is pending before the arbitrator as it is for the period prior
to the arbitrator entering upon the reference. This is the principle of Section
34, Civil Procedure Code and there is no reason or principle to hold otherwise
in the case of arbitrator.
ii.
An
arbitrator is an alternative form (sic forum) for resolution of disputes arising
between the parties. If so, he must have the power to decide all the disputes
or differences arising between the parties. If the arbitrator has no power to
award interest pendente lite, the party claiming it would have to approach the
court for that purpose, even though he may have obtained satisfaction in respect
of other claims from the arbitrator. This would lead to multiplicity of
proceedings.
iii.
An
arbitrator is the creature of an agreement. It is open to the parties to confer
upon him such powers and prescribe such procedure for him to follow, as they
think fit, so long as they are not opposed to law. (The proviso to Section 41 and
Section 3 of Arbitration Act illustrate this point). All the same, the agreement
must be in conformity with law. The arbitrator must also act and make his award
in accordance with the general law of the land and the agreement.
iv.
Over
the years, the English and Indian courts have acted on the assumption that
where the agreement does not prohibit and a party to the reference makes a claim
for interest, the arbitrator must have the power to award interest pendente lite.
Thawardas has not been followed in the later decisions of this Court. It has been
explained and distinguished on the basis that in that case there was no claim
for interest but only a claim for unliquidated damages. It has been said repeatedly
that observations in the said judgment were not intended to lay down any such
absolute or universal rule as they appear to, on first impression. Until Jena case
almost all the courts in the country had upheld the power of the arbitrator to award
interest pendente lite. Continuity and certainty is a highly desirable feature
of law.
v.
Interest
pendente lite is not a matter of substantive law, like interest for the period anterior
to reference (pre- reference period). For doing complete justice between the parties,
such power has always been inferred. 44. Having regard to the above
consideration, we think that the following is the correct principle which should
be followed in this behalf: Where the agreement between the parties does not prohibit
grant of interest and where a party claims interest and that dispute (along
with the claim for principal amount or independently) is referred to the
arbitrator, he shall have the power to award interest pendente lite.
This is for the reason
that in such a case it must be presumed that interest was an implied term of the
agreement between the parties and therefore when the parties refer all their
disputes - or refer the dispute as to interest as such -- to the arbitrator, he
shall have the power to award interest. This does not mean that in every case the
arbitrator should necessarily award interest pendente lite. It is a matter within
his discretion to be exercised in the light of all the facts and circumstances of
the case, keeping the ends of justice in view."
1.
2.
3.
4.
5.
6.
7.
8.
In
Executive Engineer, Dhenkanal Minor Irrigation Division, Orissa and Others vs. N.C
Budharaj (deceased) by LRs and Others, another Constitution Bench considered payment
of interest for pre-reference period in respect of cases arising when Interest Act,
1839 was in force. The following conclusion in para 26 is relevant which reads
thus:
"26. For all the
reasons stated above, we answer the reference by holding that the arbitrator appointed
with or without the intervention of the court, has jurisdiction to award
interest, on the sums found due and payable, for the pre-reference period, in the
absence of any specific stipulation or prohibition in the contract to claim or grant
any such interest. The decision in Jena case taking a contra view does not lay down
the correct position and stands overruled, prospectively, which means that this
decision shall not entitle any party nor shall it empower any court to reopen proceedings
which have already become final, and apply only to any pending proceedings. No
costs." (Emphasis supplied).
9.
In
the earlier paras, we have referred to the stand taken by the learned counsel for
the respondent and reliance based on the decision reported in Board of Trustees
for the Port of Calcutta (supra). It is true that in that decision, this Court has
held that arbitrator has jurisdiction to interpret the clauses of the contract
and to decide whether interest pendente lite could be awarded by him. The short
question that arose in that case was that the arbitrator had awarded interest
pendente lite notwithstanding the prohibition contained in the contract against
the payment of interest on delayed payments. Ultimately, the two-Judge Bench of
this Court has concluded that irrespective of the terms of the contract, the
arbitrator was well within his jurisdiction in awarding interest pendente lite.
It is useful to point
out that the ratio in that decision was considered by this Court in Sayeed Ahmed
and Company vs. State of Uttar Pradesh and Others, While considering the very same
issue, particularly, specific clause in the agreement prohibiting interest pendente
lite, this Court considered the very same decision i.e. Board of Trustees for the
Port of Calcutta (supra). After adverting to the clause in the Board of
Trustees for the Port of Calcutta (supra) and the Constitution Bench in G.C.
Roy's case (supra), this Court concluded as under: "23. The observation in
Engineers-De-Space-Age that the term of the contract merely prohibits the department/employer
from paying interest to the contractor for delayed payment but once the matter goes
to the arbitrator, the discretion of the arbitrator is not in any manner stifled
by the terms of the contract and the arbitrator will be entitled to consider
and grant the interest pendente lite, cannot be used to support an outlandish argument
that bar on the Government or department paying interest is not a bar on the arbitrator
awarding interest.
Whether the provision
in the contract bars the employer from entertaining any claim for interest or bars
the contractor from making any claim for interest, it amounts to a clear
prohibition regarding interest. The provision need not contain another bar
prohibiting the arbitrator from awarding interest. The observations made in the
context of interest pendente lite cannot be used out of contract. 24. The
learned counsel for the appellant next contended on the basis of the above observations
in Engineers-De-Space- Age, that even if Clause G1.09 is held to bar interest
in the pre-reference period, it should be held not to apply to the pendente lite
period, that is, from 14-3-1997 to 31-7-2001.
He contended that the
award of interest during the pendency of the reference was within the discretion
of the arbitrator and therefore, the award of interest for that period could
not have been interfered with by the High Court. In view of the Constitution
Bench decisions in G.C. Roy and N.C. Budharaj rendered before and after the decision
in Engineers-De- Space-Age, it is doubtful whether the observation in Engineers-De-Space-Age
in a case arising under the Arbitration Act, 1940 that the arbitrator could
award interest pendente lite, ignoring the express bar in the contract, is good
law. But that need not be considered further as this is a case under the new
Act where there is a specific provision regarding award of interest by the
arbitrator."
10.
Considering
the specific prohibition in the agreement as discussed and interpreted by the Constitution
Bench, we are in respectful agreement with the view expressed in Sayeed Ahmed and
Company (supra) and we cannot possibly agree with the observation in Board of
Trustees for the Port of Calcutta (supra) in a case arising under the Arbitration
Act, 1940 that the arbitrator could award interest pendente lite ignoring the express
bar in the contract.
11.
In
Union of India vs. Saraswat Trading Agency and Others, (2009) 16 SCC 504,
though it was under the Arbitration and Conciliation Act, 1996, this Court has
considered elaborately about the legal position in regard to interest after adverting
to all the earlier decisions and basing reliance on clause 31 of the agreement
held: "33. In the case in hand Clause 31 of the agreement is materially
different. It bars payment of any interest or damage to the contractor for any
reason whatsoever. We are, therefore, clearly of the view that no pre-reference
or pendente lite interest was payable to the respondent on the amount under
Item 3 and the arbitrator's award allowing pre-reference and pendente lite interest
on that amount was plainly in breach of the express terms of the agreement. The
order of the High Court insofar as pre-reference and pendente lite interest on the
amount under Item 3 is concerned is, therefore, unsustainable."
12.
At
the end of the argument, learned counsel for the respondent heavily relied on the
recent decision of this Court in Madnani Construction Corporation Private Limited
(supra) which arose under the Arbitration Act, 40. There also, Clause 30 of SCC
and Clause 52 of GCC prohibits payment of interest. Though the Bench relied on
all the earlier decisions and considered the very same clause as to which we are
now discussing, upheld the order awarding interest by the arbitrator de hors to
specific bar in the agreement. It is relevant to point out that the decision of
Madnani Construction Corporation Private Limited (supra) was cited before another
Bench of this Court in Sree Kamatchi Amman Constructions vs. Divisional Railway
Manager (Works), Palghat and Others, wherein the decision in Madnani Construction
Corporation Private Limited (supra) was very much discussed and considered. After
adverting to all the earlier decisions including the Constitution Bench judgments,
this Court has analyzed the effect of Madnani Construction Corporation Private Limited
(supra).
The following discussion
and ultimate conclusion are relevant: "17. In Madnani the arbitrator had awarded
interest pendente lite, that is, from the date of appointment of arbitrator to the
date of award. The High Court had interfered with the same on the ground that there
was a specific prohibition in the contract regarding awarding of interest. This
Court following the decision in Engineers-De- Space-Age reversed the said rejection
and held as follows: (Madnani case, SCC pp. 560-61, para 39) "39. In the instant
case also the relevant clauses, which have been quoted above, namely, Clause
16(2) of GCC and Clause 30 of SCC do not contain any prohibition on the
arbitrator to grant interest. Therefore, the High Court was not right in interfering
with the arbitrator's award on the matter of interest on the basis of the aforesaid
clauses. We therefore, on a strict construction of those clauses and relying on
the ratio in Engineers find that the said clauses do not impose any bar on the
arbitrator in granting interest.
"At the outset it
should be noticed that Engineers-De-Space-Age and Madnani arose under the old
Arbitration Act, 1940 which did not contain a provision similar to Section
31(7) of the new Act. This Court, in Sayeed Ahmed held that the decisions rendered
under the old Act may not be of assistance to decide the validity of grant of interest
under the new Act. The logic in Engineers-De-Space-Age was that while the contract
governed the interest from the date of cause of action to date of reference, the
arbitrator had the discretion to decide the rate of interest from the date of
reference to date of award and he was not bound by any prohibition regarding interest
contained in the contract, insofar as pendente lite period is concerned. This Court
in Sayeed Ahmed held that the decision in Engineers-De-Space-Age would not
apply to cases arising under the new Act.
We extract below, the
relevant portion from Sayeed Ahmed: "23. The observation in Engineers-De-Space-Age
that the term of the contract merely prohibits the department/employer from
paying interest to the contractor for delayed payment but once the matter goes to
the arbitrator, the discretion of the arbitrator is not in any manner stifled by
the terms of the contract and the arbitrator will be entitled to consider and
grant the interest pendente lite, cannot be used to support an outlandish
argument that bar on the Government or department paying interest is not a bar on
the arbitrator awarding interest. Whether the provision in the contract bars the
employer from entertaining any claim for interest or bars the contractor from
making any claim for interest, it amounts to a clear prohibition regarding
interest. The provision need not contain another bar prohibiting the arbitrator
from awarding interest. The observations made in the context of interest
pendente lite cannot be used out of contract.
24. The learned counsel
for the appellant next contended on the basis of the above observations in
Engineers-De-Space-Age, that even if Clause G 1.09 is held to bar interest in
the pre-reference period, it should be held not to apply to the pendente lite
period, that is, from 14-3-1997 to 31-7-2001. He contended that the award of interest
during the pendency of the reference was within the discretion of the arbitrator
and therefore, the award of interest for that period could not have been interfered
with by the High Court. In view of the Constitution Bench decisions in G.C. Roy
and N.C. Budharaj rendered before and after the decision in Engineers-De-Space-Age,
it is doubtful whether the observation in Engineers-De-Space-Age in a case
arising under the Arbitration Act, 1940 that the arbitrator could award
interest pendente lite, ignoring the express bar in the contract, is good law.
But that need not be considered further as this is a case under the new Act
where there is a specific provision regarding award of interest by the
arbitrator.
"The same
reasoning applies to the decision in Madnani also as that also relates to a
case under the old Act and did not independently consider the issue but merely
relied upon the decision in Engineers-De-Space-Age.19. Section 37(1) of the new
Act by using the words "unless otherwise agreed by the parties" categorically
clarifies that the arbitrator is bound by the terms of the contract insofar as
the award of interest from the date of cause of action to the date of award.
Therefore, where the parties had agreed that no interest shall be payable, the Arbitral
Tribunal cannot award interest between the date when the cause of action arose
to the date of award.
We are of the view that
the decisions in Engineers-De-Space-Age and Madnani are inapplicable for yet another
reason. In Engineers-De-Space-Age and Madnani the arbitrator had awarded
interest for the pendente lite period. This Court upheld the award of such
interest under the old Act on the ground that the arbitrator had the discretion
to decide whether interest should be awarded or not during the pendente lite period
and he was not bound by the contractual terms insofar as the interest for the
pendente lite period. But in the instant case the Arbitral Tribunal has refused
to award interest for the pendente lite period. Where the Arbitral Tribunal has
exercised its discretion and refused award of interest for the period pendente lite,
even if the principles in those two cases were applicable, the award of the arbitrator
could not be interfered with. On this ground also the decisions in Engineers-De-Space-Age
and Madnani are inapplicable..."13) Inasmuch as we have already expressed
similar view as mentioned above and conveyed our inability to apply the reasoning
in Madnani Construction Corporation Private Limited (supra), we fully endorse the
view expressed in Sree Kamatchi Amman Constructions (supra).
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
In
the light of the above discussion, following conclusion emerge: Reliance based
on the ratio in Board of Trustees for the Port of Calcutta (supra) is unacceptable
since the said view has been overruled in Sayeed Ahmed and Company (supra) and insofar
as the ratio in Madnani Construction Corporation Private Limited (supra) which is
also unacceptable for the reasons mentioned in the earlier paras, we reject the
stand taken by the counsel for the respondent. On the other hand, we fully
accept the stand of the Union of India as rightly projected by Mr. A.S.
Chandhiok, learned ASG. We reiterate that where the parties had agreed that no interest
shall be payable, the arbitrator cannot award interest for the amounts payable
to the contractor under the contract. Where the agreement between the parties does
not prohibit grant of interest and where a party claims interest and the said
dispute is referred to the arbitrator, he shall have the power to award
interest pendent elite. As observed by the Constitution Bench in G.C. Roy's
case (supra), in such a case, it must be presumed that interest was an implied
term of the agreement between the parties. However, this does not mean that in every
case, the arbitrator should necessarily award interest pendente lite. In the
subsequent decision of the Constitution Bench, i.e., N.C. Budharaj's case (supra),
it has been reiterated that in the absence of any specific stipulation or prohibition
in the contract to claim or grant any such interest, the arbitrator is free to
award interest.
15.
In
the light of the above principle and in view of the specific prohibition of contract
contained in Clause 1.15, the arbitrator ceases to have the power to grant interest.
We also clarify that the Arbitration Act, 1940 does not contain any specific provision
relating to the power of arbitrator to award interest. However, in the
Arbitration & Conciliation Act, 1996, there is a specific provision with
regard to award of interest by the arbitrator. The bar under clause 1.15 is absolute
and interest cannot be awarded without rewriting the contract.
16.
For
the aforesaid reasons, we set aside the award of the arbitrator granting interest
in respect of the amount payable to the contractor under the contract as well
as the order of the learned Single Judge and the Division Bench of the High
Court confirming the same.
17.
Consequently,
the appeal is allowed to the extent pointed out above with no order as to
costs.
..........................................J.
(P. SATHASIVAM)
..........................................J.
(A.K. PATNAIK)
NEW
DELHI;
JULY
12, 2011.
Back
Pages: 1 2