V.S. Achuthanandan Vs
R. Balakrishna Pillai & Ors.
J U D G M E N T
P. Sathasivam, J.
1.
The
challenge in this appeal, by special leave, is to the legality of the order dated
31.10.2003 passed by the High Court of Kerala at Ernakulam allowing Criminal Appeal
Nos. 822, 823 & 824 of 1999 filed by the accused setting aside the order dated
10.11.1999 passed by the Special Judge Idamalayar Investigations, Ernakulam in C.C.
No. 1 of 1991 convicting all the accused for the offences punishable under
Sections 120-B and 409 of the Indian Penal Code (in short `IPC') and Sections 5(1)(c)
and 5(2) of the Prevention of Corruption Act, 1947 (Act 2 of 1947) (hereinafter
referred to as`the P.C. Act') and sentencing them to undergo rigorous
imprisonment.
2.
Brief
Facts:-
a. Idamalayar Hydro
Electric Power Project, a multi-purpose power project in Kerala was conceived and
completed in the year 1985. The project report was approved by the Central
Water and Power Commission in 1973.
b. After the completion of
the Dam, the remaining construction work relating to the power tunnel and surge
shaft, which are integral part of the water conductor system of the project,
was awarded on contract basis to one K.P. Poulose (A4), as per the decision of the
Kerala State Electricity Board (hereinafter referred to as the "Board"),
on 19.11.1982. The work relating to power tunnel was awarded at 188% above the
Probable Amount of Contract (PAC) and the work relating to surge shaft and allied
works at 162% above the estimated amount with many special conditions, as requested
by the contractor, involving heavy financial implications/advantages to him at the
expense of the Board. Further, there was inordinate delay in completion of the
work. 2
c. During the trial run,
on 15.07.1985, several leaks and cracks were noticed in the tunnel lining which
was a matter of great public concern and caused considerable anxiety and fear
among the public and State as well. Discussions and debates were held in this regard
in the State Legislative Assembly. There was a public outcry for a judicial probe
in this matter. Extensive rectification work to remedy the defects in the
tunnel lining and surge shaft was undertaken at a considerable cost which was
to the tune of Rs. 1.75 crore.
d. On 02.08.1985, the
Public Undertaking Committee of the State Legislature inspected the site and submitted
its report recommending a judicial probe. The State Government appointed a sitting
Judge of the Kerala High Court as Commissioner of Inquiry to conduct the probe.
The Commission recorded its enquiry, collected considerable evidence and submitted
its report in June, 1988. The Commission came to the conclusion that materials placed
before it prima facie disclosed commission of offences punishable under I.P.C. and
P.C Act against persons responsible for the same and recommended for investigation
into these offences. The State Government accepted the recommendations and constituted
a special team, headed by Superintendent of Police for Investigation. The report
of the special squad was filed in the Court of Special Judge on 14.12.1990 in
Crime No. C.C. No. 1 of 1991.
e. During pendency of the
case, an application for withdrawal of the prosecution against accused No. 5 - G.
Gopalakrishna Pillai, who was the Secretary to the Kerala Government, Irrigation
and Power Department was made by the then Special Public Prosecutor on 24.08.1992
under Section 321 of the Code of Criminal Procedure (in short `Cr.P.C.') on the
ground of absence of any material to sustain a successful prosecution of offences
alleged against him. At this stage, the appellant herein - V.S. Achuthanandan, the
then Opposition leader in the Assembly, in public interest, filed statement of
objections against the move for withdrawal of the case against G. Gopalakrishna
Pillai (A5). After full fledged enquiry, the application filed by the Special
Public Prosecutor was dismissed by the Special Judge on 16.10.1992.
f. On 03.02.1993, Criminal
Revision Petition No. 762 of 1992, filed by the State against the order of
Special Judge was allowed by the High Court. On the strength of the
observations made in the order of the Kerala High Court, the State Government took
the decision to withdraw the criminal case against all other accused.
g. The appellant challenged
the above order of the High Court in Criminal Appeal No. 122 of 1994 before this
Court which set aside the order of the High Court and restored the order of the
Special Judge declining consent for withdrawal [vide V.S. Achuthanandan vs. R.
Balakrishna Pillai & Ors., (1994) 4 SCC 299]. Subsequently, the matter was further
proceeded in the Court of Special Judge.
h. During trial, Accused
No. 22, Paul Mundakkal became insane and the case against him was allowed to
split, Accused No.4 - K.P. Poulose, Contractor, died, Accused nos. 11 and 14 to
21 were discharged by the Court of Special Judge in the final report holding that
there was no prima facie case made against them.
i. On 14.12.1995, charges
were framed against other accused for various offences under Sections 120-B, 409,
430 and 201 IPC and Section 5(2) read with Section 5(1)(c) and (d) of the P.C.
Act. This order of the Special Judge was confirmed by the High Court, but found
that the charge under the P.C. Act is not sustainable against A5 and A8 for want
of proper sanction as per the orders passed in Criminal Revision Petitions
filed by the accused in the High Court. Charge was amended accordingly and the
accused were rearranged as A1 to A11. In the meantime, A7 died.
j. The Special Court, after
analyzing the oral and documentary evidence on record, vide its judgment and
order dated 10.11.1999 found R. Balakrishna Pillai (A1), P.K. Sajeev (A3) and Ramabhadran
Nair (A6) guilty of the offences punishable under Section 120-B and 409 IPC and
Sections 5(1)(c) and 5(2) of the P.C. Act read with Section 120-B of IPC. They were
sentenced to undergo rigorous imprisonment for a period of five years for the offence
punishable under Section 120-B of IPC and to undergo rigorous imprisonment for a
period of four years each under Section 409 IPC and Section 5(2) of the P.C.
Act read with Section 120-B IPC and to pay a fine of Rs.10,000/- each, in default,
to undergo simple imprisonment for one year each. However, A1, A3 and A6 were acquitted
of the charges under Sections 161, 201 and 430 IPC read with Section 5(1)(d) of
the P.C. Act. It was also directed that the sentences shall run concurrently. Accused
Nos. 2,4,5,8,9,10 and 11 were found not guilty of the offences and they were acquitted
of all the offences with which they were charged.
k. Aggrieved by the
order of conviction and sentence, all the three accused i.e. (A1), (A3) and (A6)
filed separate appeals before the High Court of Kerala at Ernakulam. By the
common impugned judgment dated 31.10.2003, the High Court set aside the conviction
and sentence of all the three accused and acquitted them from all the charges levelled
against them.
l. Questioning the order
of acquittal, the appellant - V.S. Achuthanandan, filed special leave petition against
the common impugned judgment and, this Court, by order dated 27.03.2006,
granted leave to appeal.
1.
2.
3.
Heard
Mr. Shanti Bhushan, learned senior counsel for the appellant, Mr. U.U. Lalit, learned
senior counsel for R.Balakrishna Pillai (A1), Mr. Amarendra Sharan, learned
senior counsel for P.K. Sajeev (A3), Mr. S. Gopakumaran Nair, learned senior counsel
for Ramabhadran Nair (A6) and Mr. R.S. Sodhi, learned senior counsel for the
State of Kerala. Submissions:
4.
Mr.
Shanti Bhushan, learned senior counsel for the appellant after taking us
through the entire materials relied on by the prosecution, stand taken by the defence,
elaborate reasonings of the trial Court in convicting the accused and the
reasonings of the High Court in acquitting them, raised the following
submissions:-
i.
There
was enough material to show that (A1) was very much interested in favour of (A3)
and with the connivance/assistance of the Board officials, more particularly
through (A6) Member of the Board, made the Board to accept the tender offered by
K.P. Poulose (A4) at an exorbitant rate with various special conditions.
ii.
The
criminal breach of trust has been committed by the accused in the following
ways:-
a. By awarding both the
works of Idamalayar at a very high and exorbitant rate with special conditions
having heavy financial implications.
b. By reducing the
retention and security amount.
c. By allowing the
contractor to return only fifty per cent of the empty cement bags.
d. By accepting the
special condition for the sale of T & P items (tools & plants) which
could not be sold as per the general conditions of the contract
i.
ii.
iii.
Contrary
to the norms and circulars/procedures of the Board, in order to favour K.P.
Poulose (A4), who was a friend of (A1), the Board has accepted all the conditions
just to favour (A1) and (A3).
1.
2.
3.
4.
5.
Mr.
U. U. Lalit, Mr. Amarendra Sharan and Mr. S. Gopakumaran Nair, learned senior
counsel appearing for (A1), (A3) and (A6) respectively supporting the ultimate decision
of the High Court submitted that:
i.
The
outcome of the contract in favour of K.P. Poulose (A4) was based on a "collective
decision" by the Board and there was no external pressure from anyone
including (A1).
ii.
All
the decisions taken were in terms of rules/norms applicable to the contract including
accepting special conditions.
iii.
Mere
acceptance of higher rate would not amount to criminality.
iv.
There
is no allegation that by awarding contract in favour of K.P. Poulose (A4), (A1)
was monetarily benefited.
v.
No
material to show that there is any wrongful loss to the Board.
vi.
Inasmuch
as the High Court acquitted all the accused in respect of all the charges on appreciation
of oral and documentary evidence, interference by this Court is very limited. In
the absence of perversity in such conclusion, normally, this Court would not interfere
with the order of acquittal.
vii.
In
any event, inasmuch as the State has not challenged the order of acquittal, the
present appellant being neither a complainant or heir nor a party to any of the
proceedings is not entitled to pursue the present appeal. Accordingly, the
appeal is not maintainable and on this ground liable to be dismissed without
going into the merits of the claim.
1.
2.
3.
4.
5.
6.
We
have carefully analysed the materials placed by the prosecution, the defence, the
decision and reasonings of the trial Court and High Court and considered the rival
contentions. Interference by this Court in an order of acquittal
7.
Learned
senior counsel for the respondents by drawing our attention to the reasoning of
the High Court and in respect of all the charges leveled against acquitting
them submitted that in the absence of perversity in the said decision, interference
by this Court exercising extraordinary jurisdiction is not warranted. It is settled
principle that an Appellate Court has full power to review, re-appreciate and
reconsider the evidence upon which the order of acquittal is founded. The Code of
Criminal Procedure (in short `Cr.P.C') puts no limitation, restriction or condition
on exercise of such power and an Appellate Court is free to arrive at such conclusion,
both on questions of fact and of law. An Appellate Court, however, must bear in
mind that in case of acquittal, there is double presumption in favour of the accused.
The presumption of
innocence is available to a person and in the criminal jurisprudence that every
person shall be presumed to be innocent unless he is proved guilty by a competent
court of law. It is also settled law that if two reasonable conclusions are possible
on the basis of the evidence on record, the Appellate Court should not disturb the
finding of acquittal recorded by the trial Court. Keeping the above principles in
mind, let us discuss the charges leveled, materials placed by the prosecution
in support of those charges, reasoning of the Special Court convicting the accused
and impugned order of the High Court acquitting all the three accused in respect
of the said charges. Statutory Provisions
8.
The
Electricity (Supply) Act, 1948 (in short `the Act') was in force at the relevant
time. Section 5 of the Act mandates each State to constitute State Electricity Board
for the management and supply of electricity. As per Section 78A, which was inserted
by Act 101 of 1956 and came into force w.e.f. 30.12.1956, in discharge of its
functions, the Board shall be guided by such directions and questions of policy
as may be given to it by the State Government. As rightly pointed out by Mr. Shanti
Bhushan, learned senior counsel for the appellant that except on policy
matters, the State Government has no role in the affairs of the Board. In view
of the charges levelled against A1 who was the Minister for Electricity,
Government of Kerala, we adverted to these statutory provisions. A1's
interference in the affairs of the Board:
9.
It
is the case of the prosecution that A1 while he was holding office of the Minister
for Electricity, Government of Kerala was interfering in the day-to-day affairs
of the Board including transfers, promotions, appointment of employees,
granting electric connection to consumers by giving directions to the Board officers.
It is also alleged that A1 used to interfere even in awarding of contracts of
the Board during his period as Minister for Electricity. One of the main charges
leveled against A1 and others is that he, in his capacity, as Minister for Electricity
intended to settle contracts of the Board in the name of his favourites or
persons of his choice at exorbitant rates with the ulterior object of making
illegal profit either to himself or to his favourites. With regard to the above
claim, the prosecution has produced evidence through Kuriakose Chennakkadan
(PW-64), Jagannad Prasad (PW-66), Managing Partner, C.S. Company, Kottayam, Alexander
Vellappally (PW-138), Managing Director, Asian Tech and Kamalasanan (PW-146), Managing
Director of M/s We-Build.
According to
Kamalasanan (PW-146), though he was one of the tenderers for surge shaft work,
quoted acceptable rates, could not get the contract work because of the
interference of A1. He deposed that, the then Chief Engineer, late Bharathan
recommended his work for acceptance by the Board, but he was further told by Shri
Bharathan that he should meet A6 and also to give 5% of PAC as procuring expenses
and if the said amount is not given, the work could not be awarded, hence he
met A6 who told him that the rate quoted by him is very low and advised him to settle
whether it is workable or not. He further deposed that at the time when A1 was the
Minister, A6 was a Member of the Board who was very powerful having influence
over the Minister. According to him, the voice of A1 is reflected through A6 with
regard to the affairs of the Board.
10.
Shri
Alexander Vellappally (PW-138), Managing Director of Asian Tech, in his evidence
deposed that he was asked by A1 to quote for the Lower Periyar Project Headrace
Power Terminal in 1980-81 when the pre-qualification system was introduced in the
Board. The tender of Shri Alexander Vellappally was qualified and the lowest when
it was evaluated. However, he was informed that further steps for negotiation and
discussion regarding the acceptance of the tender would take place only with the
concurrence of the Minister. He further deposed that he met A1 several times
and also sent letters to him and one letter sent by him to A1 is marked as Ext.
P-544. According to him, though he was the lowest tenderer, the work was not
awarded to him, but given to HCC. He also explained that pre-qualification bid
system was misused by the Board officers, more particularly, in the case of
Lower Periyar Works.
11.
The
next witness who highlighted the above issue is Kuriakose Chennakkadan (PW-64).
According to him, the Minister used to interfere in the award of contracts and
when he met A6, he was asked to meet A1. He also deposed that A1 was interested
for one K.P.Poulose (A4). His work was terminated and it was re-tendered and
awarded to K.P.Poulose (A4).
12.
Jagannad
Prasad (PW-66), Managing Partner of M/s C.S. Company deposed before the Court that
while he was doing the contract work of a tunnel for Kakkad Hydro Electric Project,
he approached the Chief Engineer Bharathan, who told him that the work could be
awarded only as per the directions of the Minister (A1). He further deposed
that he had executed a promissory note for Rs.5,30,000/- in favour of one
Yackochan, who acted as a middle man for the commission payment. He informed the
Court that this contract was terminated by the Board.
13.
It
was highlighted on the side of the appellant that it was during that period, when
A1 was Minister for Electricity, the tender process of Idamalayar Tunnel and its
concrete lining and surge shaft work was started. It is relevant to note that
R. Balakrishna Pillai (A1) was the Minister for Electricity from 27.01.1980 to 21.10.1981,
26.05.1982 to 05.06.1985 and 25.05.1986 to 25.03.1987. The tender for surge shaft
was invited and awarded to one E.M. Varkey at 21% below estimated rate. The
estimated rate was Rs 74 lakhs for surge shaft. However, the work was abandoned
on 28.03.1981 due to labour strike. Thereafter, tenders were invited again for
the surge shaft and four persons submitted their offers for tenders.
The lowest rate was quoted
by M/s We-Build Pvt. Ltd. and the next lowest rate was by E.M. Varkey at 57%
above PAC. It is pointed out that though the work was recommended to be awarded,
the Board decided to re-tender the work. Accordingly, the tenders were invited again
and E. M. Varkey alone quoted for the work. His tender was not accepted since
he quoted exorbitant rate. In the meanwhile, pre-qualification bid system was
introduced in the Board which is evident from Ext. P-576 dated 24.09.1981, which
was made applicable to Idamalayar contract works. Thereafter, tender for both the
works were invited by Shri Bharathan, the then Chief Engineer which is evident from
Ext. P-46 dated 05.06.1981. However, the tender was cancelled by him which is
also clear from Ext P-47 dated 22.10.1981. The Chief Engineer extended the
validity of the tender upto 29.04.1982 and after his demise, the then Chief Engineer
(PW-7) extended the validity upto 30.06.1982. During that time, two tenders
were received, one by K.P.Poulose and other by Kuriakose Chennakkadan (PW-64), quoting
special conditions. The cover containing the conditions and deviations was opened
on 30.06.1982, when K.P.Poulose was present in the Board's Office. However,
Kuriakose, the other tenderer was not informed and later on 09.09.1982, K.P. Poulose
was pre-qualified and Kuriakose was disqualified which, according to him, was
without notice. The contract for the balance power tunnel and concrete lining
work of Idamalayar works was ultimately awarded to K.P.Poulose at 188% of the above
estimated rate and the surge shaft work was also awarded to him at 162% above
the estimated rate.
14.
It
is clear from the above materials that the process of tendering of Idamalayar works
was interrupted on several occasions mainly by the Board by cancelling the tenders
and ordering re-tender and by extending the period of validity of tenders more
than once. It was on the last date of extension of the validity of the tender i.e.
on 30.06.1982, K.P.Poulose appeared and submitted his tender with special conditions
which was later accepted in the Board's meeting dated 19.11.1982. The Special Judge,
basing reliance on Board's resolution (Ex. P550(a)), has rightly concluded that
there was inordinate delay in awarding the work which reasoning was not
accepted by the High Court. The materials placed clearly show that it was nearly
three years to take a decision. It is also clear from the evidence of PWs 64,
66, 138 and 146 which clingingly established the circumstances under which A1
conceived the idea for fixing contract of the Board at exorbitant rate in order
to derive monetary benefits. From the above, the contrary conclusion arrived by
the High Court, according to us, is not in terms of the evidence led in by the
prosecution. Whether Idamalayar contract was awarded at exorbitant rate causing
loss to the Board
15.
The
basic stand of the prosecution is that A1 entered into criminal conspiracy to award
the disputed contract involving heavy financial gain to K.P.Poulose (A4) and the
conspiracy and abuse of power by certain officials enabled the conspirators to earn
a pecuniary advantage of Rs.2,39,64,253/-, in addition to the financial loss caused
to the Board. It is the specific case of the prosecution that rate awarded in both
the contracts is exorbitant. It is not in dispute that the contract was awarded
at 188% above PAC in the case of tunnel work and 162% above PAC for the surge
shaft work. Verification of Ext. P-52(b) shows that the sanctioned estimate for
the tunnel work was Rs.1,17,20,633.90. On the other hand, the accepted tender
amount as per the award of contract was Rs.2,45,80,796/- which is clear from
Ext P 52. It is further seen as per Ext P-68 agreement, the sanctioned estimate
for surge shaft was Rs. 74 lakhs and it was awarded for Rs.1,42,94,901/- The
estimate for floor concreting was Rs.479.5 per M3 and the estimated rate for
sides and arches was Rs.476.20 per M3. All the above details were highlighted in
the evidence by PW-151 a competent Engineer. Likewise, the rate for floor concreting
awarded to K.P.Poulose was Rs.825.47 per M3. In fact, the calculations made by PW-151
were not seriously disputed by the defence.
16.
In
order to appreciate the stand that the estimated rate and the tender quoted by K.P.Poulose
was exorbitant was demonstrated by Mr. Shanti Bhushan by taking us through the estimated
cost of the work awarded to skilled workers brought from Kulamavu and
Moolamattom, who were awarded the tunnel driving work on piece rate basis. It
is seen that the tunnel driving work was awarded to them at the rate of Rs.
1,250/- per M3 which was enhanced later, and finally, at the time, when the workers
stopped the work, the rate was Rs. 1,900/- per M3. This is clear from the settlement
memorandum Ext. P-212 signed between the labourers and the Board. This fact was
highlighted in the oral evidence of PW-7, Chief Engineer of the Board. In his evidence,
he explained that the rate awarded to workers will be Rs. 2,500/- per M3 including
cost of materials. PW-156, the Investigating Officer, also gave evidence on the
basis of records collected during his investigation. Ext.P-52 agreement shows that
the estimated rate for driving one meter tunnel was Rs. 4,090/-. Ext.
P-19/Contract Certificate of the Power tunnel shows that the amount paid to the
contractor for 24 meters tunnel driving was Rs. 2,39,961/-. It was highlighted that
when the total work was done by the labourers at piece rate basis, they were
given Rs. 2,500/- only per M3. The remuneration for 24 meters driving tunnel would
come to only Rs.60,000/- the difference i.e. Rs.1,79,961 (2,39,961-60,000)
would show that the tunnel driving work was given to K.P.Poulose (A4) at an
excessive rate.
17.
It
is pointed out that there is enough material to show that the labourers, who
did the tunnel work, were prepared to carryout the balance work of the tunnel
at the estimated rate of Rs. 4,090/-. At the relevant time, the representatives
of the workers made a representation to the then Minister for Electricity, namely,
R Balakrishna Pillai (A1) informing him that they are prepared to do the tunnel
work and allied works at the estimated rate. Divakaran Kutty (PW-24),
Vadayattupara Radhakrishnan (PW-33), Sasidharan Nair (PW-34) and Muraleedharan
Pillai (PW-46) have given evidence that they represented before the Minister as
well as the officials of the Board and informed their preparedness to do the
work at the estimated rate and also requested for absorption in the Board's service.
In this regard, Mr.
Shanti Bhushan, learned senior counsel appearing for the appellant heavily
relied on the evidence of PW-46 who had gone to meet A1 along with (late) N
Sreekantan Nair and submitted a Memorandum Ext.P-287 dated 01.06.1982. It is relevant
to note the response of the Minister (A1) for the above said request. PW-46
stated that A1 told them that there is no question of giving the works to the
workers and he wants to give the work to K.P.Poulose. This instance pointed out
that A1 had personal interest in K.P.Poulose and had decided to entrust the contract
to him, though at that time, the said K.P.Poulose did not submit the tender for
the work. We have already noted that K.P. Poulose submitted his tender only on
30.06.1982 i.e. a month after the memorandum dated 01.06.1982 submitted by PW-46.
In support of the same, the evidence of PW-122, T.M. Prabha, the then President
of the Kerala Construction Labour Union that he met A1 and gave representations
and requested for award of work to the workers at estimated rate and also
absorption of the workers in the Board's service on permanent basis is also
relevant.
Here again, it is relevant
to note that PW-122 was also informed that there is no question of awarding work
to workers, but the work had to be given to K.P.Poulose. The evidence of PWs-46
and 122 and the statement made by A1 to both of them clearly show that K.P.
Poulose was the contractor chosen in advance by A1 and other accused who were also
interested in him. As rightly pointed out by Mr. Shanti Bhushan, this evidence should
be connected with the conspiracy to award the work to K.P.Poulose at exorbitant
rate originated even prior to the submission of tenders to the work by
K.P.Poulose and other tenderers. The contrary conclusion arrived at by the High
Court justifying the award at higher rate to K.P.Poulose cannot be legally sustained.
The Board is empowered with the authority to award contracts and has discretion
to accept and being an authority constituted under the Statute and a Pubic
Undertaking is not expected to accept tenders at exorbitant rates with
financial implications causing loss to the Board.
The Board is always
expected to protect its financial interest while awarding contracts. The Board
mainly relied on the labour problem that was prevailing at the relevant time. In
this regard, it is relevant to point out that the tender for the Idamalayar
work was invited in March, 1982 and four persons, namely, Kamalasanan (PW-146),
Managing Director, We-Build, C.K. Verghese, E.M.Varkey and V.A. Thankachan submitted
tenders vide Exts. P78 series dated 21.03.1982. It is true that the tunnel
workers went on strike on 20.04.1981 and the contractors submitted their tenders
when there was labour unrest. However, the reason attributed for the delay
cannot be accepted.
As rightly pointed
out, there were procedural irregularities and omissions by the Board
authorities in the manner of dealing with tenders submitted by K.P.Poulose and Kuriakose,
which ultimately eliminated Kuriakose from the scene, keeping K.P.Poulose as the
sole tenderer, qualified by pre-qualification Committee of the Board and hasty
steps were taken by the Board in awarding contract in favour of K.P.Poulose in the
meeting held on 19.11.1982 lead to the conclusion that the award of contract in
favour of K.P.Poulose was an exorbitant one. It is relevant to point out that the
Special Judge, by adverting to Ext 550(a) expressed that the reasons stated by the
Board in awarding contract in favour of K.P. Poulose at exorbitant rates are
not acceptable. No serious discussion by the Board
18.
It
is pointed out and in fact taken us through evidence that there was no serious discussion
in the Board meeting held on 19.11.1982 and the minutes of the Meeting were
prepared as dictated by A7, the then Chairman of the Board. It is the responsibility
of the members, more particularly, full time members of the Board, who were responsible
for the scrutiny of the deviations and conditions suggested by the contractor which
involved huge financial implications to see that all transactions are
beneficial to the Board and within the permissible limit. Mr. Lalit and Mr. Sharan,
learned senior counsel appearing for A1 and A3 respectively heavily contended that
it was a collective decision of the Board and there was no external pressure
from anyone including A1. It is relevant to point out that the decision ultimately
taken for awarding the contract with special conditions, which we will discuss in
the later paras, as suggested by the contractor, involved huge financial
implications at the risk and loss of the Board.
Though the High Court
has concluded that the part-time members who were signatory to Ex550(a) had approved
the minutes, subsequently, the Special Court made a distinction between the responsibility
of full-time members and that of part-time members in the matters of awarding of
contract. It is true that all the members present subscribed their signature in
the minutes in awarding contract to K.P.Poulose. It was highlighted that in evidence,
A8, the Financial Adviser to the Board, in his report has stated that the rates
awarded to the contractor are very high. The letters sent by A8 were marked as Exs.
P-415 and 416. It is also relevant to point out that the then Law Secretary, Shri
Viswanathan Nair also conveyed his opinion during the meeting of the Board that
the rates are exorbitant. These aspects were taken note of by the Special Court
while considering the culpability of the accused and the High Court was not serious
about their views. In other words, the High Court has concluded that the award
of contract to K.P.Poulose was a collective decision of the Members of the Board.
The High Court also pointed
out which was again highlighted by the learned senior counsel appearing for the
accused that majority of the Members of the Board were highly qualified and
responsible officers and it cannot be said that they were only mute witnesses
to the decision of the Board. In this regard, it is relevant to point out that the
Special Court has rightly concluded that there was no serious discussion in the
Board Meeting dated 19.11.1982 when the question of award of contract was taken
up and the minutes of the meeting were prepared as dictated by A7, the then
Chairman of the Board. The then Deputy Secretary of the Board, R. Sankaran was
examined as PW-140, also admitted this aspect and stated that there was no serious
discussion in the meeting held on 19.11.1982. He explained that Ex.550(a) minutes
of the meeting is a reproduction of the dictation given by the Chairman of the
Board (A7).
19.
The
High Court has pointed out that the prosecution has not produced any
contemporaneous agreement for proving the rates prevalent during the relevant period
of award of the contract. The High Court found that the contract was awarded at
188% above PAC for the tunnel work and 162% above PAC for the surge shaft work.
It was pointed out from the side of the Board that the estimate rate was prepared
taking into account the prevalent PWD rates for similar items of work like tunnel
driving, concrete lining, earth work, cost of materials, labour charges,
transportation charges of materials to worksite etc. It is not in dispute that the
contractor was also given opportunity to conduct site inspection and decide
other aspects connected with the execution of the works for submitting his
tender rate.
Though contractor can
also quote special conditions involving financial implications and other
conditions in the contract, which is usually settled by negotiations, but the general
conditions of contract shall not be superseded while accepting special conditions
to the detriment of the Board. The Special Judge had noted that the rate quoted
by N.K.Kuriakose (PW-30) for tunnel driving and surge shaft work was below
21.75% of the estimated rate and there was much difference in the rate quoted by
K.P.Poulose and Kuriakose. It is further seen that the work was awarded to Kuriakose
at the rate of Rs. 1,092.3 per M3 for sides and arches. The work awarded to Kuriakose
was abandoned by him since the Board did not provide him with necessary
materials for proceeding with the work as per the agreement. He adduced evidence
for the said abandonment and also suffered loss in that regard for which Board
was subsequently held liable and he was paid compensation as per the Court
orders.
The work was awarded to
N.K. Kuriakose in 1979. The Special Court has pointed out that even though
there was an increase of 25% of the actual rate awarded to Kuriakose, still
there was wide difference between the rates at which the two works were awarded
and on this ground also, the Special Court held that the works for floor concreting
and for sides and arches were awarded to K.P.Poulose at a higher rate. However,
the High Court disagreed with the conclusion of the Special Court. In this
regard, it is useful to refer Ext.P174(2), which is a report with regard to the
rate of award of Idamalayar contract. It was stated in the report that the
estimate was prepared with the scheduled rate of 1980 which had been enhanced
by 25% on labour to obtain 1982 schedule and the work was awarded after the enhancement
of the scheduled rates. It is further seen that the estimate was prepared with the
scheduled rate of 1980 for the purpose of obtaining the rate of 1982 i.e.
increase of 25% in the rate was given in 1980. The High Court has justified the
increase of 25% by pointing out the increase mentioned in Ext.P299 which
relates to contractor's profit of 10%, overhead charges of 10% and 5% for
labour benefits. Though the High Court has agreed with the 25% increase in the rate
of 1980-82, no acceptable evidence was adduced over-riding the documentary
evidence furnished by Ext.P-299 and P174(2). Award of contract to K.P. Poulose
(A4)
20.
It
is the argument of Mr. Shanti Bhushan, learned senior counsel for the appellant
that the tendering process adopted by the Board was with a view to eliminate
other tenderers and to choose the tenderer of their choice, namely, K.P.Poulose.
This was elaborated by pointing out that Kuriakose was disqualified without giving
him adequate opportunity to present before the pre-qualification Committee and
ultimately K.P.Poulose was declared as qualified. In the said meeting, only A6
and A7 were present and A8, and another member of the pre-qualificaton
Committee was not present. Pursuant to the decision that Full Board meeting should
be held on 19.11.1982 to decide the question of award of Idamalayar contract, PW-7
was directed to issue notice to all the tenderers. The materials relied on by the
prosecution shows that on 18.11.1982, notices were issued to HCC, E.M.Varkey,
Sunny K. Peter and K.P.Poulose.
It is seen that only
K.P.Poulose was present on 19.11.1982. Sunny K. Peter PW-4 sent a telegram on
19.11.1982 stating that he is not physically well. HCC conveyed their inability
to the Board by their letter which was received in the office of the Chief Engineer
on 22.11.1982 stating that there was no sufficient time given to attend the Board
Meeting on 19.11.1982. Without verifying the fact that whether all the other tenderers
were ready, a decision was taken on 19.11.1982 itself by accepting the offer of
K.P.Poulose with special conditions. As rightly pointed out the Board being a
statutory authority, ought to have waited for a reply from the other tenderers to
ascertain whether they actually received notices and reason for their inability
to attend. It was demonstrated that it was a pre-planned attempt to award the
work to K.P.Poulose alone and the notices issued to other tenderers were in the
form of an ultimatum. It was also pointed out that for the negotiation on 04.11.1982,
i.e. prior to 19.11.1982, held by PW-7, with the tenderers, in the office of
the Board only K.P.Poulose and Sunny K. Peter were present. It is further seen
that E.M. Varkey and HCC were not invited.
The fact remains that
PW-7 did not invite E.M.Varkey who quoted less rate and HCC, a reputed construction
company for the second negotiation. Though a telegram was sent on behalf of E.M.Varkey,
one of the tenderers that since he was away and request was made to fix another
date, it was recorded that the tenderer had already lost his opportunity
offered. This has been demonstrated by the appellant that the Board was not
prepared to allow the request of E.M. Varkey for a discussion. It is useful to refer
here that the pre-qualification Committee, headed by A7, gave chances to K.P.Poulose
to correct the errors and mistakes in the tender form submitted by him for the
impugned works, on the other hand, such concession was not afforded to the other
tenderers, more particularly, E.M. Varkey. Both Sunny K. Peter and Kuriakose were
examined as PWs-4 and 22 respectively. The evidence of Kuriakose shows that he
was an experienced contractor, quoted 124% above PAC for the work and submitted
his tender on 30.06.1982. According to him, he was not invited for any
discussion.
He was disqualified
on 09.09.1982 and was not invited for being present for opening his deviations
and conditions in the tender. In the same way, the evidence of Sunny K. Peter
PW-4 also highlighted how he was discriminated, though he has quoted only 135% above
PAC, he was not given opportunity to consider the reasonableness of the rates
quoted by him. According to him, he received notice only at 2.40 p.m. on 18.11.1982
and because of his illness, he could not attend the meeting on 19.11.1982. The
fact remains, the Board has not considered his request and finalised the
contract on 19.11.1982 in favour of K.P.Poulose.
21.
Another
aspect highlighted by the learned counsel for the appellant relates to the conduct
of A1 with regard to settlement of labour dispute. The evidence shows that there
was labour strike in the tunnel area which started in April, 1981 and continued
from the time of inviting tenders on 05.06.1981 till the time of award of contract.
It was highlighted that there was no effort on the part of A1 to settle the
labour dispute before tendering process was initiated. We have highlighted the
Memorandum submitted by the labourers to A1 on several occasions requesting for
settlement of labour problems. It was not settled and the matter was kept alive
till the tender was fixed in the name of K.P.Poulose on 19.11.1982. It was only
after the award of the contract, A1 took initiative to settle the labour dispute,
more particularly, when he came to know that K.P.Poulose cannot enter the site
because of the obstruction of the workers to begin the contract work. It is
relevant to point out that PW-7 informed A1 and A6 more than once that in case the
labour dispute could be settled in advance, the contract could be awarded at a reasonable
rate. The evidence of PW-7 clearly shows that his request was not accepted by
A1 and A6.
22.
The
evidence discussed above show that the rate quoted by Sunny K. Peter (PW-4) vide
his evidence in Court, was 135% above PAC, which was less than 188% above PAC,
quoted by K.P. Poulose and approved by the Board. The High Court failed to take
note of the importance of evidence of PW-4 and justified the action of the Board
in not pursuing the tender submitted by Sunny K Peter (PW-4) with a lesser rate
on the ground that his tender is liable to be rejected since he wanted an arbitration
clause in the agreement. Further, though PW-4 has quoted lesser rate than K.P.
Poulose, in his evidence, he has highlighted that he was not given an opportunity
to consider the reasonableness of the rate quoted by him i.e. 135% above PAC. The
High Court has not only ignored his assertion but found that the rate quoted by
him for the surge shaft work is not a lesser rate when compared to one quoted by
K.P. Poulose i.e., 188% above PAC. Though the Special Court has correctly found
that Sunny K. Peter quoted less than the rate quoted by K.P. Poulose, the High
Court, on erroneous assumption found fault with the finding of the Special
Court which correctly appreciated prosecution case.Acceptance of Special
Conditions & Concessions
23.
With
regard to allegation of the prosecution that certain Special Conditions were accepted
by the Board (Ex. P588) involving huge financial commitments favourable to the
contractor causing loss to the Board, it is relevant to mention that one of the
special conditions, is condition No. 4 which relates to tools and plants sold
to the contractor in violation of the General Conditions of the contract. These
special conditions along with other conditions were accepted by the Board superseding
corresponding agreement provisions. Ex P52 (c) is the general conditions of
contract and instructions to the contractors issued by the Board. Among various
clauses, Clause E1-091 in Ex. P52(c) deals with tools and plants issued to the contractors.
This clause provides that
the Board is bound to make available to the contractors only such tools and plants
listed in the Schedule attached thereto, that too subject to availability. Such
items of tools and plants which are listed in Ex. P52 agreement marked as Ex.
P52 (d) shows items of tools and plants which can be hired out to the
contractors if requested on the specified rates. In Ex. P58, deviations and
conditions submitted by the contractor as Item No 4, stated that such tools and
plants listed in Ex. P52(d) shall be sold to him on outright sale at book value
deducting depreciation and the cost may be recovered on prorata basis from his bills.
The full Board, in its decision dated 19.11.1982, had accepted the above special
condition of the contractor. It is relevant to point out that these items
includes tipper wagons loco, louder, existing truck lines and pipes, items
which can only be hired to the contractor as per clause E1-091 of the General Conditions
of the contract.
It is the case of the
prosecution that it was the decision of the Board to sell those items of tools
and plants which includes very costly foreign imported materials. The official
examined on the side of the prosecution pointed out that there is no provision
in the general conditions of the contract enabling the Board to effect sale of those
tools and plants to the contractor. However, certain materials belonging to the
Board mentioned in Clause E1-093 and not covered by the list mentioned in Clause
E1- 091 could be sold to the contractors if available to the Board. The evidence
led in clearly shows that the sale of materials listed in Clause E1-093 supersedes
the general conditions of contract. In other words, it is clear from the evidence
that those materials which were not mentioned in the Special Conditions were
sold to the contractor on outright sale.
In this regard, it is
useful to refer the evidence of Udayabhanu Kandeth PW-136, Auditor attached to
the Accountant General Office which shows that 126 items of tools and plants were
sold to the contractor of which the cost of 117 items was Rs. 16.5 lakhs. The Auditor
of the Board, who was examined as PW-130, also explained about the sale of tools
and plants to the contractor, which was not provided in the agreement. It is
clear from the evidence that the sale of tools and plants which could only be
hired to the contractor as per the list in E1-091 was against the objections
raised by A8, the Financial Advisor and Chief Accounts Officer of the Board during
the relevant period.
In his report, A8 had
noted that the financial implications involved in the sale of items of tools and
plants were not considered either by the Board or by the officers of the Board
at the time when the full Board decided to sanction the above special condition
No. 4 of the contract. These aspects have been duly considered by the Special Court,
namely, that the tools and plants which are only to be hired as per Clause E1-091
to the contractor, however, the Board permitted outright sale which is detrimental
to the financial interest of the Board. These important aspects have been
overlooked by the High Court while upsetting the decision of the Special Court.
24.
In
addition to the same, the prosecution has led in further evidence to show that the
contractor was favored in several aspects. PW-128, V. Ramanarayanan, Superintending
Engineer, in his evidence has stated that pental placer, an imported item not included
in the list for issue on hire, was sold to the contractor, the sale value of
which was Rs. 4 lakhs and according to him only lump sum recoveries were made
from the CC bills of the contractor, instead of prorata recovery as provided in
the agreement. This also caused loss of interest on the sale price of materials.
He further deposed that 30 items of spares were issued to the contractor costing
Rs. 6 40lakhs and when he calculated the total value of spares and materials issued
to the contractor it came around Rs. 36 lakhs, out of which, only a portion was
recovered by the Board from the contractor vide Ex P517-P519. This witness has
also pointed out that there were several items sold to the contractor without
obtaining sanction of the Board. Return of empty cement bags by the Contractor
25.
Another
special condition sanctioned by the Board in favour of the Contractor relates
to the return of empty cement bags. This special condition provided that the
Contractor shall return only 50% of empty cement bags in good condition. Ext.
P-33, Audit Enquiry Report of Idamalayar Project Circle states that the
Contractor had to return 65,100 empty cement bags, the value of which was calculated
at more than Rs.1 lakh. According to the Auditor, because of the special
condition, the Board had sustained a loss of Rs.1,08,879.75. The Financial
Advisor and Chief Accounts Officer, who arrayed as A8, had stated in Ext. P-416
that without evaluating the exact financial implications, sanction was accorded
by the Board to the special condition regarding return of empty cement bags to
the advantage of the Contractor for getting financial gain. Though it is stated
that the condition only provides for return of 50% empty cement bags in good condition
and for the remaining, the rate provided by the general conditions of contract could
be realised from the Contractor, the fact remains, the special condition which we
are concerned does not provide for the realisation of value of the remaining
unreturned cement bags.
26.
With
regard to special conditions, the High Court has held that inasmuch as there is
a provision in tender to enable the Contractor to get special conditions, it
cannot be said that the special conditions and deviations of the Contractor
should not be accepted. Here, the High Court has missed the real issue as to
whether all special conditions as requested by the Contractor can be sanctioned
by the Board in violation of general conditions of contract, which is the standing
order of the Board applicable to all contracts and the policy adopted by the
Board. Simply because there is a provision to enable the contractor to suggest
special conditions advantageous to him, it does not mean that the Contractor
can suggest any special condition which involved financial implication to the
detriment of the Board. As correctly found by the Special Court, the special
condition No.4 relating to sale of tools and plants is a favour done by the Board
to the Contractor for obtaining financial gains at the risk of Board's loss.
The Special Court has
substantiated its finding on the point based on evidence furnished by the
auditors. However, the High Court relying on Ext D-28 provided for recovery of balance
50% of empty cement bags not returned or returned in damaged condition and recovery
will be effected as stipulated in the tender condition, erroneously concluded
no loss could be sustained to the Board. It is relevant to point out that the
special condition No.10 clearly states that the contractor is bound to return
only 50% empty cement bags in good condition. To make it clear, this condition
supersedes the corresponding general condition of the contract. Therefore, the
Contractor is bound to return 50% of empty cement bags in good condition and there
is no need to pay the price of balance 50%. Accordingly, the Board can act only
on the basis of the special condition No.10 regarding the return of empty
cement bags and is not entitled to recover the value of balance 50% of unreturned
cement bags. The contrary conclusion arrived at by the High Court relating to
return of empty cement bags cannot be accepted. Fixation of security and
retention:
27.
Yet
another special condition involving financial implications sanctioned to the
Contractor is with regard to the fixation of security and retention amount. Special
Condition No.1 of Ext.P-588 deals with this subject. It is the prosecution case
that restriction of security and retention amount is in violation of the
provisions contained in the general conditions of the contract and it is a favour
shown to the Contractor to make illegal gains at the expense of the Board. Clause
E1-008 of Ext. P52(c) is the provision relating to security deposit of the
Contractor which states that for major works where the cost of construction
exceeds Rs.25 lakhs, the security deposit should be 2% of the PAC. In the case
on hand, the PAC of Idamalayar contract works exceeds Rs.25 lakhs. There is no dispute
for the same.
The security for both
works should be fixed at 2% of the PAC. Clause E1-011 of ExtP-52 is the general
conditions of contract and instruction to the tenderers dealing with retention of
the money from the bills payable to the Contractor. As per this clause, from each
bill of the Contractor 10% should be deducted towards additional security. However,
the retention was not to exceed 5% of the PAC where cost of work exceeds Rs.25
lakhs. Therefore, 5% of PAC is to be retained as retention amount for both these
works. In this regard, it is relevant to refer the special condition. In the case
of tunnel work, the retention and security is limited to Rs.5 lakhs which is
clear from Ext.P-71. Likewise, in the case of surge shaft, security is limited
to Rs.1 lakh as evidenced by Ext.P-69. This is also strengthened from the evidence
of PW-8 who was the Executive Engineer in the Idamalayar project.
He explained that the
security amount and retention amount due from the contractor would come to
Rs.12 lakhs. Inasmuch as the PAC for both works would come to Rs.2,45,80,796/-,
the retention amount in the case of surge shaft work would come to Rs.7.2 lakhs,
which is 5% of the PAC. PW-8 has explained that the restriction of retention
amount is a benefit shown to the Contractor. In Ext.P-65, report of PW-7, also calculated
financial loss that will be sustained by the Board in limiting security and retention
amount of the Contractor. In the same report, PW-7 also mentioned the loss of
interest for the same. It is also pointed out that due to restricting the security
and retention amount as per the special condition No.1, sanctioned to the
Contractor, the liquidated damages payable by the contractor shall not exceed the
whole amount of retention plus security deposit. The result of restriction of security
and retention is that the liquidated damages payable by the Contractor is also
automatically restricted accordingly. In that event, the Board is not entitled to
recover any amount by way of liquidated damages even if the Contractor is guilty
of negligence or default.
All these aspects have
been properly scrutinized by the Special Court. No doubt, the High Court relied
on the evidence of Madhavan Potti (PW-5) that acceptance of special conditions in
a contract is a normal procedure. In the same way, the High Court has also
placed reliance on the evidence of Ramanarayanan (PW-21) that reduction of security
and retention amount is also a normal procedure. A perusal of Kerala State Electricity
Board Tender Regulations show that the reduction of security deposit is
permissible only in the case of established firm/Company and that the security
deposit of a new contractor shall not be reduced. The course adopted by the
Board is contrary to the condition contained in Regulation No.25(c) of the Board's
Regulations.
Though the High Court
has observed that in all major contracts, it is an accepted practice to put a
ceiling on the security and retention amount and there is no acceptable
evidence to support such a finding, we are unable to accept the observation of
the High Court that "for the success of execution of major contract works,
small favours are inevitable". We conclude that the above observation of the
High Court is based on a general opinion not supported by any material or
evidence on record. Criminal Conspiracy
28.
On
this aspect, the Special Court has analysed the evidence of witnesses and
considered the documents produced and marked by the prosecution and concluded that
there is sufficient evidence for finding that a criminal conspiracy was hatched
out at the instance of A1 (R.Balakrishna Pillai, the then Minister for Electricity)
and P.K. Sajeev (A3) who was a close associate and political ally of A1. This
was strengthened by the evidence of I.K. Prabhakaran, Assistant Engineer,
Quality Control, Idamalayar project who was examined as PW-21 and other witnesses.
Nobody has challenged the relationship between A1 and A3.
It is the case of the
prosecution that a conspiracy was hatched out at the instance of A1 and others with
the illegal object of getting the Idamalayar project fixed on one among themselves
at exorbitant rates and make illegal profits. It is also the definite case of
the prosecution that though the work was awarded in the name of K.P.Poulouse,
one of the accused, it was actually executed by A3 and another accused Paul Mundakkal
(deceased). It has come in evidence that the amount of work was invested and payments
were made by Paul Mundakkal and A3. As rightly observed by the Special Court, the
relationship between A1 and A3 is a relevant factor in arriving at the circumstances
leading to the formation of the conspiracy.
The evidence led in
normally show that A3 was an intimate friend of A1 and very closely moving with
him who was the Minister for Electricity during the relevant period. PW-21, in his
evidence, has stated that A3 was an active member and leader of Kerala Congress
Party led by A1 at the time when works were allotted. PW-3, who was a watchman
of the Inspection Bungalow at Idamalayar was examined on the side of the prosecution
has stated that A1 and A3 used to come and stayed in the Inspection Bungalow. He
further asserted that it was A3 and the deceased Paul Mundakkal, who were supervising
the work at site. In addition to the evidence of PW-3, the evidence of PWs 6, 7
and 8 who were Engineers at the relevant time at Idamalayar worksite and
supervising execution of works corroborated the evidence of PW-3. PWs 24, 25
and 26 also supported the above claim of the prosecution. PW-25, one of the
workers at Idamalayar also deposed that he was working with A6, who was managing
Idamalayar works. PW-26, another worker also stated that when he went to the
house of A3, he saw A1 in his house.
29.
The
prosecution has established the relationship and friendship between A1 and A3
by placing acceptable evidence. The nomination of A3 to Board's Consultative Council
was made at the instance of A1. Under Section 16 of the Electricity (Supply) Act,
1948, the Constituting Authority is the State Government. The evidence led in by
the prosecution shows that A1 took initiative to include the name of A3 in the
list of nominees for constituting the Consultative Council. The evidence of PWs
18, 27 and 51 and Ext.180(c) establish the case of the prosecution. The
evidence further shows that the mandatory requirements contemplated under
Section 16 of the Act regarding the constitution of Consultative Council was
not adhered to by A1 who wanted to include A3 in the panel which states that the
State Government may constitute the Consultative Council considering all representatives
of power generating companies and other persons in consultation with the representative
bodies of various interests, namely, industry, commerce, agriculture, transport
etc.
It makes it clear that
consultation with the representative bodies of various interests is a mandatory
condition precedent for appointment of a Member by the Government in the Board's
Consultative Committee. But in the case on hand, from the evidence, it is clear
that there was no such consultation by the Government before making nomination of
A3 who was the Secretary of Kothamangalam Bus Owners Association. It was pointed
out that usually the representatives of State Level Organisers representing various
interests alone were nominated after consultation by the Government with such
bodies. Admittedly, A3 was not representing any State Level Bus Owners
Association. This is evident from the evidence of PWs 31 and 16. It has also come
in evidence that on 30.07.1983, in a Conference held on Idamalayar Inspection
Bungalow, attended by various officers of the Board and others connected with the
execution of Idamalayar work, A1 declared in public that A3 was his bosom
friend and requested everybody to cooperate with him for the successful
completion of the project work.
30.
The
prosecution has established the relationship of A1 and K.P Poulose even before awarding
of contract. In November 1982 itself, A1 had chosen K.P. Poulose as prospective
contractor for execution of the work which fact is spoken to by T.M. Prabha (PW-122)
and also by Muraleedharan Pillai (PW-46). We have already adverted to the evidence
of PW-46 in detail in the earlier paragraphs. Their evidence shows that when
they met A1 requesting for the award of the tunnel driving work to the workers
at Idamalayar, who were brought from Idukki, Kulamavu etc, A1 told them that the
execution of the Idamalayar work is proposed to be given to K.P. Poulose. This
was on 29.06.1981 i.e. well prior to the execution of the contract, and
indicate that there was prior contract between A1 and K.P. Poulose regarding
the award of contract work at Idamalayer.
31.
The
role played by A3 in fixing the contract to K.P. Poulose is also relevant to infer
the formation of agreement between himself and A1, the Minister for
Electricity. In addition to the same, the prosecution has adduced acceptable
evidence that a company by name Hydro Power Construction Company was registered
as a partnership firm with K.P. Poulose as Managing Partner and A3 and Paul Mundakkal
as Working Partners. Further, close relatives of K.P. Poulose, A3 and Paul
Mundakkal were parties to the partnership deed.
The object of the partnership
was to execute the Idamalayar tunnel work and also the surge shaft work in the name
of the Company. The said firm was an assessee under the income tax Act which is
evident from Ex. P245, the income-tax assessment of the 52firm in the year
1984-85 and 1985-86. K.P. Poulose, A3 and Paul Mundakkal were submitting income
tax returns and this is evident from the evidence of PW-123, an Income-tax
practitioner. In addition to the same, when A3 was questioned under Section 313
Cr.P.C., he admitted that he invested good amount for the work and visited the
site to watch the progress of the work. The fact that A1, while as a Minister for
Electricity, interfered with the award of the contracts of the Board were
spoken to by PW-64, PW-66, PW-138 and PW-146 which we have already discussed in
the earlier paragraphs. It is also clear that A1 was awaiting for a probable
contractor of his choice to undertake the Idamalayar works at exorbitant rates.
32.
There
was labour agitation prevailing at Idamalayar work site. The workers brought
from Moolamattom, Kulamavu etc. went on strike demanding execution of the work
on piece rate basis and also for absorption in permanent service of the Board. At
the time, when the tendering process of the work was started by the Chief
Engineer, Bharathan, strike situation was pending at Idamalayar which continued
till the work was awarded in 1982. It is in evidence that after execution of
the agreement of the Idamalayar work by K.P. Poulose, there was obstruction from
the striking workers preventing him from entering the worksite and consequently
A1 interfered and settled the labour dispute by awarding a compensation of Rs.
11 lakhs to the striking workers and the worksite was made clear free of any labour
unrest.
It is the prosecution's
case that this was done to help the contractor, a party to the conspiracy for execution
of the work and make illegal profit therefrom. The evidence of PW-7, Chief Engineer
and other witnesses stated that the awarding of Idamalayar work at exorbitant rate
could have been avoided in case the labour issue was settled earlier. The
prosecution has also highlighted labour unrest at Idamalayar which was kept pending
at the instance of A1 and other interested parties so as to make it appear that
no contractor will come forward to undertake the contract, so much so that there
is possibility of choosing a contractor of their choice for the execution of the
work at exorbitant rate. 54
33.
The
prosecution has also highlighted that to achieve the illegal object of finding the
contract in the name of K.P. Poulose at exorbitant rate, the pre-qualification system
was introduced by the Board vide order Ex. P576 dated 24.09.1981. This was
after tendering process has started for the Idamalayar work. One Alexander Vellappally,
who was examined as PW-138, explained before the Court that pre-qualification bid
system was misused by the Board to safeguard vested interest by choosing contractors
of their choice. From the proceedings initiated by the Board on 19.11.1982, passing
a resolution to award the work to K.P. Poulose, a scheme of pre-qualification bid
was successfully operated by the Board authorities at the instance of A1 for
paving the way clear to K.P. Poulose to get the work at a very high rate.
34.
With
regard to the relationship between A1 and A3, the prosecution has relied on the
evidence of PW-19, receptionist of the Paramount Tourist Home who has stated that
A3 was occupying a room on 17.11.1982 and 19.11.1982 on rent at Paramount Tourist
Home. Exs. P185, 186 and 187 are registers maintained in the Tourist Home and
relevant entries therein were marked and proved by PW-19. According to him, A3,
took a room in the Tourist Home at 11:50 a.m. on 17.11.1982 and vacated the
room on 5:00 p.m. on 19.11.1982. The Special Court noted the significance of
his stay during the above period at Thiruvananthapuram. A3, in all probability,
was at Thiruvananthapuram to meet A1 and also to meet PW-7, Chief Engineer, A6 and
A7, to work out the scheme for getting the contract in favour of K.P. Poulose
at a higher rate after avoiding other tenderers. It is further evident that A3
took the room on 17.11.1982 when the Full Board meeting was considering the tender
of K.P. Poulose and left the room on 5:00 p.m. on 19.11.1982 after the tender was
awarded to K.P. Poulose.
The close intimacy of
A3 with A1 is well known and his influence over A1 might have persuaded A6 and
A7 to fix the contract on K.P. Poulose. PW-7, Chief Engineer has deposed before
the Court that A3 met him on 04.11.1982 and requested him to make a recommendation
for awarding the contract to K.P. Poulose. A3 also told PW-7 that when A1 was
talking over phone to PW-7, while in the office of the Chairman of the Board, the
witness was present in the chamber of A1 and asked PW-7 what was the difficulty
in recommending the contract even after A1 directed him to do so. The Special
Court, after analysing the evidence in detail found that A3 is the man behind
the manuring for getting the contract awarded to K.P. Poulose. K.P. Poulose,
however, was only a benamidar and A3 and Paul Mundakkal were the beneficiaries
though the work was awarded in the name of K.P. Poulose. The prosecution has also
highlighted and proved that A1 was awaiting for a better contractor, who would
quote higher rate, when PW-146 Kamalasanan, Managing Partner,
We-Build was not willing
to quote a higher rate as desired by A1. The role played by A6 in the matter of
hatching out the conspiracy and the fulfillment of the unlawful object is proved
by evidence, particularly, from the evidence of PW-7. From the above materials,
it is clear that a criminal conspiracy among A1, A3 and A6 can be inferred. A1,
as Minister for Electricity is all in all dealing with the efforts of the Board
including the awarding or cancellation of the contracts. The officers and the Board
members were under his pressure and fear which clearly seen from the statements
of prosecution witnesses, namely, PWs 8, 36, 60, 62, 138, 140, 64, 66 etc. It
is also relevant to point out that A6 and A7 avoided considering the request of
PW-4 in his telegram sent to the Board. We have already adverted to the fact
that it was Sunny K. Peter, PW-4, who quoted a lesser rate than K.P. Poulose. He
quoted only 135% above PAC. By arranging the Board meeting on 19.11.1982, with
short notice of less than 24 hours, the intention was to avoid other tenderers
and to achieve the object of conspiracy to award the contract to K.P. Poulose
who alone was present on 17.11.1982 and 19.11.1982. The request of E.M. Varkey
for fixing another date for participating in the discussion for award of the
contract was also rejected. From these materials, as rightly concluded by the Special
Court, it leads to a conclusion that several out of way methods were adopted by
the Board at the instance of A1 for achieving the object of conspiracy.
35.
As
rightly pointed out by the Special Court, the confirmation of Hydro Power Construction
Company consisting of A3, A4 and Paul Mundakkal and their close associates and relations
for execution of Idamalayar contract work, A3 supervising the execution of the contract
work and the visit of A4 at the worksite only on rare occasions, the payment of
wages to the labourers by A3 and Paul Mundakkal are all proved various circumstances
that the conspiracy among the accused continued to operate even after the award
of the contract.
The High Court failed
to consider various instances and materials placed by the prosecution in respect
of charge relating to conspiracy. According to the High Court, "the proved
circumstances are not sufficient to hold that there was conspiracy as alleged by
the prosecution or as found by the Special Court." Before us, it was
demonstrated that several material aspects have not been considered by the High
Court, for example, the stay of A3 at Paramount Tourist Home, Thiruvananthapuram
on the crucial dates i.e., on 17.11.1982 to 19.11.1982 has not been considered by
the High Court in the correct perspective. As pointed out by the appellant, the
High Court ought to have found that the evidence relating to A3 at Paramount
Tourist Home is only to bring out one of the circumstances leading to the
formation of criminal conspiracy hatched out by the accused.
In fact, A3 has
admitted his stay in his Section 313 Cr.P.C. statement at Thiruvananthapuram on
those dates, hence, finding by the High Court on this aspect, faulting with the
Special Court cannot be sustained. Even though, the High Court has admitted
that A1 and A3 belonged to the same political party and close relationship
exists between the two, the nomination of A3 in the Consultative Council of the
Board as evidenced by Ex.P-180 was unfortunately not recognised by the High
Court as a material evidence proved by the prosecution. Insofar as claim of PW-3
that it was he who settled the bill in the inspection bungalow, the perusal of his
entire oral evidence clearly supports the case pleaded by the prosecution
insofar as the close association between A1 and A3 during their visit to the worksite.
PW-7, former Chief Engineer, a most reliable witness was examined in the
presence of A3 on 04.11.1982 in the Board's office. There is no necessity to corroborate
or further material in addition to the oral evidence of PW-7. As rightly
analysed and concluded by the Special Court, there is no infirmity in the
evidence of PW-7 merely because there is no documentary evidence in respect of
the presence of A3 at the Board's meeting. The evidence of PW-7 cannot be
ignored.
36.
The
High Court very much accepted the stand of the accused that it was a collective
decision of the Board, we have already discussed the reasons stated in Ex P-550(a)
for awarding contract in favour of K.P. Poulose at exorbitant rate. The reasons
relied on by the Board exposes the omission and negligence on its part in fixing
the contract with PW-146 Kamalasanan or E.M. Varkey or with Kuriakose PW-22 or
PW-4 Sunny K. Peter, who quoted lower rates then K.P. Poulose. Even before us, learned
senior counsel appearing for the accused reiterated that it was a collective decision
of the members of the Board to award the contract in favour of K.P. Poulose. We
have already highlighted the reasoning of the Special Court relating to the
important fact that contract was awarded at exorbitant rate, reduction in
retention and security amount, return of 50% empty cement bags and also
acceptance of special conditions for the sale of tools and plants. In the instant
case, all the ingredients of criminal conspiracy are satisfied for convicting A1,
A3 and A6 for the offence charged against them. Special mention about PW-7,
retired Chief Engineer of the Board & PW-46
37.
The
High Court as well as learned senior counsel appearing for the accused
commented the evidence of PW-7 by saying that there are inherent improbabilities
and inconsistencies and his evidence is not cogent and convincing whereas among
several witnesses examined, prosecution heavily relied on the statement of PW-7,
a retired Chief Engineer. He retired from service on March 1985. He joined the
service of the Board on July 1954 as Junior Engineer and prior to that he was
in the Electricity Department. It has come in evidence that he gained vast
experience since he worked in various projects such as Chakulam project,
Neriyamangalam, Idukki, Kakakd and Idamalayar project. It is also seen from his
evidence that he participated in four major projects. He first examined on the side
of the prosecution on 28.03.1996 and at that time he was 66 years old. In this
background, let us test his evidence as discussed in the earlier part of our
order.
The prosecution
heavily relied on his evidence and, in fact, Mr Shanti Bhushan in support of his
argument mainly relied on the evidence of PW-7. By his rich experience and
worked as a Chief Engineer at the relevant time, namely, when Idamalayar
project was commissioned, PW-7 furnished all the details with reference to
various documents such as his report, opinion, minutes of the meeting of the
Board with reference to Idamalayar project. No doubt, all the three senior counsel
appearing for the accused A1, A3 and A6 severely criticized his conduct in not answering
many of the questions in his cross examination. It is true that in chief-examination,
PW-7 highlighted various aspects with reference to documents such as opinion, report
and Board's proceedings and minutes thereon. From the perusal of his
cross-examination, it cannot be concluded that he didn't answer or elaborate any
of the question put by the counsel for accused. It is true that for certain questions
he answered that he has to verify from the records and for certain questions he
didn't answer or answered stating that "he do not remember".
It is relevant to
point out that he retired from service in March 1985 and he was called upon to give
evidence only in March 1996 nearly after 15 years of the commissioning of the
Idamalayar project. If we consider all these aspects, there is no reason to
reject his entire evidence as claimed by the respondents/accused. In his
evidence, he has mentioned that on the submission of tender by K.P. Poulose, it
was noted that he quoted 189% above PAC. Agreement submitted by K.P. Poulose
has been marked as Ex. P-52 and in that Paul Mundakkal was signed as witness. It
is further seen that as Chief Engineer, he sent letters to K.P. Poulose and Kuriakose
who was another persons submitting tenders on 28.07.1982. He made a note that
the tender is not in proper form and it contains many mistakes and requested
them to rectify the mistakes within a time schedule. In this regard, it is
useful to refer his categorical statement which, he deposed before the Court that
"I considered it as a special case because the engineer member Mr.
Ramabhadran Nair (A6) informed me that Mr. Balakrishna Pillai (A1) has a special
interest to award this work to Mr. K.P. Poulose (A4), hence the mistakes
happened in the tender should be rectified with K.P.Poulose himself and make a circumstance
to award the work to K.P. Poulose..." About the disqualification of tender
offered by Kuriakose, PW-7 64 deposed the decision was taken by a committee because
he could not rectify the mistakes as directed by him. In respect of a question put
to PW-7 about the response of A6 and A7, he answered "they stated that
they are happy in disqualifying
Mr. Kuriakose". It
is also seen from his evidence that after noting that the rate quoted by K.P.
Poulose is higher rate, he forwarded the said information for remarks of FA and
CAO. He also asserted that A6 told him that A1-Minister Balakrishna Pillai is very
much particular to award both the works to K.P. Poulose. It is further seen that
he highlighted that without solving the problem of tunnel workers no contractor
can do the work. According to him, because of this reason he informed A6 to take
steps to solve the problem of workers and in fact PW-7 met A6 at his office on
04.11.1982 at 11:00 a.m. When the issue relating to labour problem was under discussion,
according to PW-7, the P.A. of Board Chairman Sankaran Nair approched him and informed
that Minister Balakrishna Pillai is willing to talk to me through telephone of the
Board's Chairman.
In view of the same,
according to PW-7, he suddenly entered into the cabin of Board's Chairman which
is the next room and took the telephone. He introduced himself through the phone
and according to PW-7 "A1 asked him why you were not recommended the
tenders of Idamalayar tunnel and surge shaft to the Board. I replied to A1 I am
going to talk about it with the contractor today and I am having same problem in
this matter. There is only one tender submitted by K.P. Poulose, the rate is
very exorbitant, if the work is awarded without solving the problem of tunnel workers,
K.P. Poulose cannot start the work. A1 replied that you don't look upon it,
K.P. Poulose will purchase all these workers, we granted this higher rate for that
also, hence you recommend the Board to award both the works to K.P. Poulose
without any delay.
Then the conversation
was concluded. I immediately visited the room of A6. I told to A6 about the call
of Minister and my reply and difficulties. At that time A6 told him that the Minister
directly asked you, so you do it as he say." The following statement is also
relevant about the conduct of A1 and how much he was interested in awarding
contract in favour of K.P. 66 Paulose. PW-7 deposed "the face of A1 shows
much anger. He explained A1 that if tenders are invited after solving the
problem of tunnel workers, rate will be reduced, that is profitable to the
Board. A1 replied with higher anger that I know how to look after the Board, I do
not want any advice from your people, are you approaching me with intimate
talks, after this, I had no talk anything about it."
It is further seen that
thereafter a note was sent by Sreedharan Pillai and Unnikrishnan to recommend for
awarding both the works to K.P. Poulose. According to him, he received all the
documents as per the direction of A1. Though, several reports and minutes of
the Board meeting were pressed into service by the respondents/accused in order
to strengthen their case that all important decisions accepting the contract in
favour of K.P. Poulose including several special conditions etc., it is clear that
due to the pressure of A6, the then member of the Board, who was close to A1, as
well as the desire of A1 in awarding the contract in favour of K.P. Poulose
with higher rate, PW-7 had no other option except to execute the directions of
A6 and A1.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
Another
incident which is relevant about the performance of PW-7 and response from A1 and
A6, in his evidence, he explained that since the progress of both the works
were very slow, he inspected the site on 23.09.1983. Due to slow progress in the
works, he castigated Paul Mundakkal who conducted the works. After few days, A3
and Paul Mundakkal came to his house and A3 told him that he is disturbing them
without any reason by way of sending letters and reports, A3 further warned
that if it continues, it will be harmful to them. He also informed him that the
Minister agreed to avoid concrete lining works of surge shaft but only PW-7
opposed it. He also assured that if PW-7 gives his consent, they are ready to
give anything. He further explained that he informed them that it is impossible
for him because the technical design is his duty, being a Chief Engineer. After
few days from this incident, on 13.10.1983, he was transferred and appointed as
an Advisor of Electricity Board in respect of Hydroelectric Projects. He
further explained that such a Post was not there and his transfer order was
signed and taken on 13.10.1983 at 8.00 p.m. in a lodge where he was residing at
Thiruvananthapuram. He highlighted that for the post of Advisor, except chair, table,
no other facilities including telephone facility, official vehicle steno and typist
were provided. After him, A2 was appointed as Idamalayar Chief Engineer. He
also informed the Court that he believed that he was transferred due to the difference
of opinion with P.K. Poulouse, A3 and Paul Mundakkal
39.
As
regards the decision of the Board and his role, he has stated that the Chief Engineer
has no right to question the Board's decision. However, he clarified that when he
was asked to give his opinion or report, he is bound by the said direction. ExP-65
is the note submitted by him in connection with the work. P-64 is the note submitted
by him in connection with the surge shaft work which is also dated 06.11.1982. Thereafter,
in 1982, he was transferred
40.
With
regard to his financial and family position, he answered that he built two-storied
building having built-up area of 2700 sq. ft. in 1965 after taking loan from the
Board and he sold this building and property after his retirement. He is having
six daughters. He constructed a shop room having 15 ft. length and 12 ft width.
41.
The
analysis of the evidence of PW-7 coupled with the other prosecution witnesses and
other notes and report prepared for the Board clearly indicate that though he
reminded that certain things are not permissible, because of the fact that the
beneficiaries of the contract are known to A1 and A6, he has no other option except
to prepare notes in such a way and ultimately the Board accepted the same.
42.
We
have already pointed out the statements of PW-46 who was a member of RSP, a
political party. According to him, the workers of Idamalayar have a Union. The
name of the said Union is Kerala Construction Labour Union and he was the
General Secretary of that Union. In his evidence, he has informed the Court
that the labourers who were doing tunnel work in Idamalayar became jobless from
10.04.1981. They were skilled labourers and had good experience from projects
like Idukki, Kulanam etc. He, as the President and others decided to file a
memorandum before the Minister Balakrishna Pillai. The memorandum was prepared in
the letter pad of Kerala Construction Labour Union. PW-46 and Srikantan Nair
signed the said memorandum. It has also come in his evidence that at the time of
submission of his memorandum PW-46 and others requested the Minister to give work
to the poor labourers at least on piece rate basis for which A1 replied
"no question of giving work to the labourers. It was given as contract to K.P.
Poulouse...." The prosecution has highlighted the above statement of PW-46
to the effect that A1 decided and determined to award Idamalayar contract to
group of persons headed by K.P.Poulouse and not to the workers who prepared to
work on piece-rate basis. About maintainability of the appeal by the present
appellant:
43.
Mr.
Lalit and Mr. Saran at the end of their arguments submitted that the appellant
being a third party unconnected with the Board or the State is not entitled to challenge
the decision of the High Court acquitting the accused from all the charges
levelled against them. In support of the above claim, they very much relied on the
decision of this Court dated 23.07.2010 rendered in SLP Criminal No 2506 of 2009
- National Commission for Women vs. State of Delhi and Another 2010 11 Scale
17. In this case, one Sunita then aged 21 years, committed suicide by consuming
Aluminium Phosphide tablets on 14.04.2003. She left behind a suicide note wherein
it was stated that she had taken tuitions from the accused, Amit, at her residence
in Rajgarh Colony and during that period she had developed a deep friendship with
him leading to physical relations as well. The accused also held out a promise
of marriage but later backed off. She also stated in her suicide note that not
only the accused continued to have sexual relation with her but also compelled
her to have sexual relation with others as well, which was the reason for
committing the suicide.
The trial Judge relied
on the dying declaration, which was the suicide note, convicted the accused
under Section 306 IPC and sentenced him to undergo rigorous imprisonment for 10
years with a fine of Rs.5000/- and also imprisonment for life under Section 376
IPC and a fine of Rs.5000/-. Questioning the above order of conviction and
sentence, the accused preferred an appeal before the High Court. The High Court
ultimately found that as the case under Section 306 was not made out confirmed
the conviction under Section 376 IPC. Taking note that the accused had already undergone
imprisonment for 5 years and 6 months and his entitlement for remission on
account of his conduct in jail, his term of imprisonment for life has been
modified to one that of period already undergone. Neither the State nor the
complainant or her relatives has chosen to file an appeal to this Court. However,
National Commission for Women (in short `NCW') filed a special leave petition against
the order of the High Court reducing the term of life imprisonment to that of period
already undergone in respect of the conviction and sentence awarded by the High
court under Section 376. The question in that case was whether the NCW is competent
or entitled to file an appeal in this Court against the conviction and sentence
imposed by the High Court. This Court, after adverting to the relevant
provisions namely, Section 377 Cr.PC and other decisions and finding that
neither the State, which is the complainant, nor the heirs of the deceased have
chosen to file a petition in the High Court or in this Court dismissed the SLP filed
by NCW as not maintainable and revoked the permission to file SLP vide this Court's
order dated 02.04.2009.
44.
In
the above referred NCW's case, admittedly the complainant was the State and
neither the State nor the heirs of the deceased filed any appeal/petition
before the High Court for enhancement of punishment or challenged the same by
way of SLP before this Court.
45.
In
our case, certain special features exist. Though we discussed earlier, it is apt
to quote once again. During the pendency of the trial before the special Judge,
an application for withdrawal of the prosecution only against G. Gopalakrishna
Pillai - accused No.5 was made by the Special Public Prosecutor on 24.08.1992 under
Section 321 Cr.P.C. which was registered as Criminal Appeal No. 79 of 1992 in
CC No. 1 of 1991. The main ground for such withdrawal was that with the available
material successful prosecution against G. Gopalakrishna Pillai - accused No. 5
cannot be launched, hence, the trial against him will be unnecessary and the
State also is of that opinion that the prosecution of A-5 may not be
sustainable. With this information, the Special Public Prosecutor requested
that by virtue of provisions contained in Section 321 of the CrP.C, necessary
consent may be granted to withdraw the prosecution against the 5th accused - G.
Gopalkrishna Pillai and the said accused may be discharged.
The Special Judge considered
the issue at length and after analyzing the entire material and finding that
there are enough materials to proceed against A-5 refused to give consent for
withdrawal. This was taken up by way of revision before the High Court. The High
Court set aside the aforesaid order passed by the Special Judge in the revision
filed by the State of Kerala represented by the Superintendent of Police. The
said order of the High Court was challenged by the present appellant namely, V.S.
Achuthanandan, to this Court by way of special leave petition. After granting
leave, the said special leave petition was converted into Criminal Appeal No. 122
of 1994. After adverting to the elaborate reasonings of the special Judge and
the conclusion of the High Court, this Court concluded that "there was no ground
available to the High Court to set aside the well reasoned and justified order
of the learned Special Judge rejecting the application of the Special Public
Prosecutor and declining to give consent for withdrawal of prosecution. We may
also add that there is nothing in the impugned order of the High Court which provides
any legal basis for interfering with the aforesaid order made by the Special
Judge. The High Court's order must obviously be set aside."
By setting aside the
order of the High Court, this Court restored the order of the Special Judge and
declined to give consent for withdrawal of the prosecution and permitted the
Special Judge to proceed further. It is not in dispute that when the very same appellant,
namely, V.S. Achuthanandan filed special leave petition and later leave was
granted, the very same respondent-accused parties in the said appeal did not
raise any objection as to the maintainability of the appeal at the instance of V.S.
Achuthanandan. Further though the State has not filed any appeal against the impugned
order of acquittal by the High Court being arrayed as one of the respondents reported
by a senior counsel to highlight its stand, in fact, Mr. R.S. Sodhi, learned senior
counsel for the State highlighted and supported the ultimate conviction and
sentence imposed by the Special Judge and informed this Court that if this Court
permits, they are ready to file an appeal with an application for condonation of
delay.
While appreciating the
prayer made by Mr. R.S. Sodhi, we are not inclined to entertain such request at
this stage. However, the fact remains that taking note of the importance of the
issue, allegations against the Minister and higher officials of the Board in
respect of award of contract with the ulterior motive, the appellant approached
this Court on earlier occasion when the State wanted to close the prosecution against
all the accused including the Minister based on the order of the High Court in
respect of G. Gopalakrishna Pillai, A-5. Further when the very same appellant
filed special leave petition before this Court and later leave was granted by this
Court neither of these respondents raised any objection as to the
maintainability of the petition. On the other hand, a Bench of three Judges
accepted the appellant's claim and set aside the order of the High Court based on
which the Special Judge proceeded further and ultimately convicted and
sentenced A-1, A-3 and A-6. In view of these factual details, learned senior
counsel for the respondents-accused were not serious in projecting the issue relating
to maintainability as their first objection. We hold that the decision in NCW's
case (supra) which was disposed of at the special leave petition stage is not
applicable to the case on hand.
46.
For
the same reasons, the decision of this Court in Lalu Prasad Yadav & Anr.
Vs. State of Bihar & Anr., (2010) SCC 1 is also not applicable to the case
on hand since in the said decision, the question was whether the State
Government (of Bihar) has competence to file an appeal from the judgment dated 18.12.2006
passed by the Special Judge, CBI (AHD), Patna, acquitting the accused persons
when the case has been investigated by the Delhi Special Police Establishment (CBI)
and this Court held that the appeal at the instance of the State Government is not
maintainable. In view of the special circumstances highlighted in the case on hand,
we reiterate that the present appeal by the appellant - V.S. Achuthanandan against
the order of acquittal by the High Court is maintainable. Our view has been strengthened
by a decision of this Court in K. Anbazhagan vs. Superintendent of Police and Others
(2004) 3 SCC 767. Accordingly we reject the contention raised by the learned senior
counsel for the respondents. Conclusion
47.
The
analysis of the materials placed by the prosecution, the plea of defence by the
accused, the decision of the Special Court and the reasoning of the High Court,
we are satisfied that the prosecution has established the following aspects
insofar as the accused (A1), (A3) and (A6) are concerned:- a) By awarding both
the works of Idamalayar at a very high and exorbitant rate with special conditions
having heavy financial implications. b) By reducing the retention and security
amount. c) By allowing the contractor to return only fifty per cent of the
empty cement bags.Having arrived at such conclusion, we are of the view that
the High Court failed to appreciate in its proper sense the materials placed by
the prosecution and brushed aside several important items of evidence adduced by
the prosecution. Equally, we are unable to accept the conclusion of the High Court,
namely, "the proved circumstances are not sufficient to hold that there was
conspiracy as alleged by the prosecution". On the other hand, we are satisfied
that the Special Court after framing various points for consideration and after
thorough discussion has accepted the case of the prosecution insofar as the work
of driving the surge shaft, lining the surge shaft, balance driving the power tunnel
and other allied works of Idamalayar Hydro Electric Power Project at a higher or
exorbitant rates to the contractor K.P. Poulose and the accused persons have abused
their official positions.
The Special Court has
also accepted the prosecution case founding that A1 along with K.P. Poulose, Paul
Mundakkal and other accused persons entered into criminal conspiracy and
rightly convicted them. In our considered view, the High Court committed a grave
error in acquitting the accused without adverting to the reliable and acceptable
evidence adduced by the prosecution.
48.
Now,
coming to the sentence part, it is relevant to note that the contract was awarded
to K.P. Poulose, (since deceased) the fourth accused, as early as on
19.11.1982. After various agitations, discussions in the Assembly, appointment
of a Commission by the Government and based on the report of the Commission, the
State Government initiated a prosecution which resulted in C.C. No. 01 of 1991 and
trial prolonged upto November 19, 1999. Thereafter, the matter was kept pending
at the High Court from 1999 to October 2003, when the High Court pronounced its
order acquitting all the accused and the matter was taken up to this Court by
the present appellant initially by way of special leave petition in 2005, leave
was granted in 2006 and it was kept pending till this date, we feel that all the
three accused have undergone agony of these proceedings for nearly two decades,
we are of the opinion that ends of justice would be met by awarding rigorous imprisonment
for one year with fine of Rs. 10,000/- each, and the same shall be paid within eight
weeks, in default, to undergo simple imprisonment for one month each.
49.
Before
winding up, it is our duty to point out in all the cases in which charges relating
to corruption by public servants are involved, normally, take longer time to reach
its finality. The facts and figures, in the case on hand, which we have already
mentioned clearly show that the contract relates to the year 1982 and the State
Government initiated prosecution in 1991, however, the trial prolonged for nearly
nine years and the Special Court passed an order convicting the accused only on
19.11.1999. When the matter was taken up by way of appeal by the accused to the
High Court even in 1999 itself, the decision was rendered by the High Court
acquitting all the accused only in 2003. In the same manner, though the appellant
challenged the order of the High Court acquitting all the accused before this Court
even in 2005, it has reached its finality only in 2011 by the present order.
Though the issue was
handled by a Special Court constituted for the sole purpose of finding out the
truth or otherwise of the prosecution case, the fact remains it had taken nearly
two decades to reach its finality. We are conscious of the fact that the Government
of India, Department of Law & Justice is making all efforts for expeditious
disposal of cases of this nature by constituting Special courts, however, the fact
remains that it takes longer time to reach its destination. We are of the view
that when a matter of this nature is entrusted to a Special Court or a regular
Court, it is but proper on the part of the court concerned to give priority to the
same and conclude the trial within a reasonable time. The High Court, having overall
control and supervisory jurisdiction under Article 227 of the Constitution of
India is expected to monitor and even call for a quarterly report from the court
concerned for speedy disposal. Inasmuch as the accused is entitled to speedy
justice, it is the duty of all in charge of dispensation of justice to see that
the issue reaches its end as early as possible.
50.
Considering
all the materials and in the light of the above discussion, we agree with the conclusion
arrived at by the Special Court and hold that the High Court has committed an
error in acquitting the accused persons. Accordingly, R. Balakrishna Pillai
(A1), P.K. Sajeev (A3) and Ramabhadran Nair (A6) are awarded rigorous
imprisonment for one year with fine of Rs. 10,000/- each, and the same shall be
paid within eight weeks, in default, to undergo simple imprisonment for one
month each. All the three accused are entitled remission for the period already
undergone, if any, by them. The criminal appeal is allowed to the extent
indicated above.
..........................................J.
(P. SATHASIVAM)
...........................................J.
(DR. B.S. CHAUHAN)
NEW
DELHI;
FEBRUARY
10, 2011
Back