Kanyaiyalal Motilal
Talera Vs. Pimpri Chinchwad Municipal & Ors. [2008] INSC 1623 (23 September
2008)
Judgment
IN THE SUPREME COURT
OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO. 5819 OF 2008 [Arising
out of SLP(C) No.20397/2005] KANHAIYALAL MOTILAL TALERA ... APPELLANT(S)
:VERSUS:
ORDER
Delay condoned.
Leave granted.
Appellant herein
filed a civil suit questioning the conduct of the Municipal Corporation and
other authorities as regards a purported attempt made by them to take forcible
possession of the land belonging to the appellant, without taking recourse to
proceedings under the Land Acquisition Act, 1894. An interim order of
injunction was passed in the said suit. Respondent No.1 filed an appeal
thereagainst.
2 Appellant and
Pimpri Chinchwad Municipal Corporation in Appeal From Order No. 89/2003, which
arose out of an order dated 7.10.2002 passed by the 5th Joint Civil Judge,
Senior Division, Pune, in Civil Suit No. 1111/2001, entered into a compromise,
the terms whereof read as under:
1.
"It
is hereby agreed that the appellant corporation shall commence the acquisition
proceedings with respect to land bearing serial No. 27B/1/B (part) and bearing
CTS No. 1054 (part) situate at Village Chinchwad Tal. Haveli Dist. Pune which
is required for road widening within a period of 15 days from today. The
Special Land Acquisition Officer shall complete the same and declare the Award
as expeditiously as possible.
2.
The
respondent is entitled to place in said Land Acquisition Proceedings all
material available with him and all contentions necessary for the purpose of
computing the compensation as per the provisions of law.
3.
It
is hereby agreed that as soon as the land acquisition proceedings are commenced
by the Appellant is entitled to construct road on the property, which has been
taken in possession by them for the said purpose.
4.
In
view of these consent terms the Order dated 7.10.2002 passed by the learned
Fifth Joint Civil Judge, Senior Division, Pune, below exhibit in Special Civil
Suit No. 1111 of 2001 stands vacated, and Special Civil Suit No. 1111 of 2001
stands disposed of in the above terms.
5.
No
order as to costs."
It is not in dispute
that pursuant to or in furtherance of the said consent terms, Pimpri Chinchwad
Municipal Corporation sent a requisition for acquisition of Civil Survey No.
1054 which belonged to the appellant. It is also not in dispute that by a
notification issued in the year 1988 under Section 4 of the Land Acquisition
Act, 1894, inter alia, Civil Survey No. 1057 was sought to be acquired.
3 A contempt
petition was filed by the appellant on the premise that despite an agreement
between the parties without initiating a fresh proceeding for acquisition of
C.S. No. 1054, the contemnors had taken recourse to obtaining forcible
possession thereof.
Before the High
Court, however, a plea was taken that C.S. No. 1057 had wrongly been mentioned
in place of C.S. No. 1054 and possession thereof was taken upon correction of
the mistake.
By reason of the
impugned judgment the contempt petition filed by the appellant herein was
dismissed by the High Court, opining:
"The learned
Advocates for the respondents while referring to the order passed by the lower
court on 7.10.2002 and drawing attention, particularly to para 5 thereof,
sought to argue that similar contention was raised by the respondents before
the trial Court and it was rejected. Obviously, it was rejected merely because
the records did not disclose the survey No. 1054 and its disclosed survey No.
1057. As it has been clarified in the affidavit that the same was on account of
mistake in recording of the number, the decision which was passed during the
pendency of the suit, which is an interim order, cannot amount to final
decision as regards the rights of the parties in relation to the said issue.
Undoubtedly, the said issue is wide open for adjudication in appropriate
proceedings.
Nevertheless, as it
has been clarified in these proceedings that there was a mistake in recording
of the number and the land in question has already been acquired, the question
of proceeding against the respondent for violation of the order dated 14.7.2003
does not arise at all. A mistake in recording of the number cannot change the
factual situation if the land in question has really been acquired.
Same cannot lead to
the conclusion about violation of the order dated 14.7.2003 as there is no
mandate to the respondents to acquire the land as such."
Appellant is, thus,
before us.
4 Ms. Bengani,
learned counsel for the appellant submitted that the Municipal Corporation
being the requisitioning authority was bound by the terms of the compromise. It
was furthermore contended that the plea raised on behalf of the respondents
that a mere clerical error has been corrected, is mala fide as would appear from
Section 13A of the Land Acquisition Act, 1894.
Mr. Adkar, learned
counsel appearing on behalf of respondent Nos.1, 2 & 4, on the other hand,
would contend that no contempt has been committed by his client as within a
period of 15 days from the date of entering into the consent terms steps have
been taken to acquire C.S. No. 1054.
Ms. Asha G. Nair,
learned counsel appearing on behalf of the State of Maharashtra, however, would
support the impugned judgment.
Keeping in view the
peculiar facts and circumstances of this case, we are of the opinion that the
question as regards applicability of Section 13A of the Land Acquisition Act is
a debatable one and the same should have been gone into by the High Court. The
High Court dealt with the said question merely stating:
"Undoubtedly, in
terms of Section 13A of the said Act, the collector is empowered to make
necessary corrections as regards the clerical and arithmetical mistakes in the
award. However, mere failure in that regard on the part of the collector cannot
ensure to the benefit of the petitioner to contend that there was violation of
the order of 14.7.2003, when in fact the said order did not direct acquisition
of land as such."
5 We may, however,
note that such a contention has not been raised by the appellant in the
contempt application.
Be that as it may,
keeping in view the peculiar facts and circumstances of this case, we are of
the opinion that interest of justice will be subserved if the contempt petition
filed by the appellant herein is treated to be a writ petition and the
questions raised therein are gone into by the High Court. It is directed
accordingly.
The State of
Maharashtra shall be impleaded in the said writ petition. The parties shall be
at liberty to amend their pleadings and all the contentions, including the
contentions raised herein shall be allowed to be raised before the High Court.
The appeal is allowed
accordingly.
..........................J
(S.B. SINHA)
..........................J
(CYRIAC JOSEPH)
NEW
DELHI,
SEPTEMBER
23, 2008.
Back