Kerala State Housing
Board & ANR. Vs. Grace Joseph & ANR. [2008] INSC 1694 (3 October 2008)
Judgment
CIVIL APPELLATE
JURISDICTION CIVIL APPEAL NO. 6097 OF 2008 (Arising out of SLP [C] No.21221 of
2006) Kerala State Housing Board & Anr. ... Appellant(s) Grace Joseph &
Anr. ... Respondent(s)
O R D E R
1.
Leave
granted. Heard both parties.
2.
The
appellant, Kerala State Housing Board (`Board' for short) allotted a premises
(land and building) to the respondent in terms of agreement of sale dated
8.4.1992.
Clause (4) of the
agreement fixed a sum of Rs.31260/- as the tentative land value and tentative
service charges (for providing amenities). The said clause also fixed the
(final) cost of the structure as Rs.86992/-. Clause 10 enabled the Board to
re-fix of the final price of the land 2 and service charges, on account of
enhancement of compensation for acquisition of the land and increase in the
cost of amenities. Clause 11 provided for the interest payable on the
difference between the tentative price and the final price fixed. The said
Clauses 10 & 11 are extracted below :
"10. It is
agreed that the Kerala State Housing Board shall be entitled to re-fix the
final price of the land and service charges thereon taking into account inter
alia the enhanced compensation awarded by Courts and Tribunals. The cost
incurred by the Board or and its predecessors in interest for prosecuting such
proceedings in courts and tribunals and also the increased cost of development
works and amenities undertaken with respect to the scheme after a final
settlement of accounts in connection therewith.
It is agreed that the
decision of the Board in fixing the revised price of the land and service
charges shall be conclusive and final.
11. It is expressly
agreed between the parties hereto that after the finalization of the price of
the land and service charges by the Board the party of the second part shall
pay to the Board together with interest at 15.5% and 13% per annum, the
difference between the tentative price fixed therefor and the price finally
fixed for both the land and service charges by the Board, within thirty days of
the date of a registered notice demanding the payment thereof or in such
instalments such rate of interest to be determined by the Board."
Clause 12 provides
that the allottee shall be entitled to get a registered sale deed conveying the
premises on payment of all the amounts due in terms of the said 3 agreement
and after complying with all the terms and conditions of the said agreement.
3.
It
is stated that the respondent has paid the tentative land value and tentative
service charges aggregating to Rs.31260/- as also the cost of structure being
Rs.86992/- by 1994 and secured possession of the premises. More than a decade
after the agreement, the Board send a demand notice dated 7.1.2004 claiming
Rs.13406/- as the difference in building cost (with interest) and Rs.163821/-
as additional land value (with additional development and LAR) in all
Rs.177227/-.
4.
Feeling
aggrieved, the respondent approached the High Court contending that no
particulars of the increased cost were furnished to her and that she was not
liable to pay the additional amount claimed by the Board. A learned Single
Judge of the Kerala High Court, by order dated 14.6.2005 disposed of the writ
petition by directing the appellant Board to furnish a detailed statement of
account (showing the actual cost and the interest) to the respondent. Learned
Single Judge also observed that if on receiving the statement of account the
respondent wanted to 4 dispute any part of the claim, she may have to approach
the civil court, as that was in the nature of a civil dispute.
5.
The
order of the learned Single Judge was challenged by the respondent in a writ
appeal before the Division Bench. The Division Bench found that in so far as
cost of the structure, the sum of Rs.86992/- mentioned in the agreement was not
a tentative but final figure and neither clause 10 nor clause 11 of the
agreement enabled the Board to make a claim for increase in the cost of
construction.
The Division Bench
was therefore of the view that increase of Rs.13406/- claimed in regard to the
cost of the structure was unwarranted. In so far as the increase in land cost
and service charges, the Division Bench found that the Land Acquisition Officer
had made an award in regard to the acquired land (where the project was
executed) on 25.11.1981 and the reference court had enhanced the compensation
by its award dated 5.12.1989. The Division Bench held that as the said increase
by the Reference Court was more than two years prior to the agreement, the said
increase would have been already worked into land cost and service charges
shown as Rs.31260/- under the agreement dated 8.4.1992. The Division Bench also
noted that the award of the Reference Court was not 5 challenged by the land
owners and therefore, there was no question of any increase after 8.4.1992; and
that the award of the Reference Court was challenged by the Board before the
High Court and the High Court had reduced the amount awarded by the Reference
Court and that had attained finality. The Division Bench was therefore of the
view that there was no justification for demanding any increase in cost towards
land. It held that the increase in cost, if any, that could be demanded was
only in regard to the development work and amenities. In view of its findings,
the Division Bench allowed the appeal, by its judgment dated 22.6.2006, set
aside the judgment of the learned Single Judge and quashed the demand notice
dated 7.1.2004.
It however left it
open to the Board to make a fresh demand only in regard to service charges
(that is the increased cost of development work and amenities undertaken in
regard to the scheme)after final settlement of account. The Division Bench also
directed that the title deed should be issued to the respondent on execution of
an undertaking that she will pay the amount due towards increased cost of
development work and amenities. The Board sought review, which was rejected on
13.10.2006.
6.
The
said judgment and order are challenged by the Board in this appeal. The Board
is not able to challenge the quashing of the demand for Rs.13406/- towards
extra cost of structure, as the contract shows that Rs.86992/- paid by the
respondent was the final price and the contract did not provide for any
increase therein. In regard to the land cost, the Board submitted that the sum
of Rs.31260/- shown as tentative land value and service charges in the
agreement dated 8.4.1992 did not take into account the compensation enhancement
granted under the award dated 5.12.1989 of the reference court as the said
amount had not been paid to the land-owners by then and, the final cost was
worked out after payment to the land-owners and after the litigation ended. It
was further submitted that the Division Bench could not have assumed that the
enhanced land cost had been taken into account in the tentative price shown in
the agreement.
7.
We
find considerable force in the contention of the appellant. The appeal filed
against the award of the Reference Court, by the Board, was pending till 1996
and therefore the land price mentioned in the agreement dated 8.4.1992 could
not be said to be final. We also find that the Division Bench, before passing
the impugned judgment, 7 did not secure the working sheets in regard to the
price of the land nor examined the accounts. The agreement (clause 10)
specifically stated that the land price was tentative and any increase demanded
was payable. If the entire cost of land including enhancement had already been
taken into account while fixing the cost of land mentioned in the agreement, it
would not have stated that the land price was tentative and subject to increase
in final settlement. The fact that the cost of construction was shown as the
final price and the cost of land and development was shown as tentative clearly
demonstrate that the amount shown in the agreement towards land cost and
service charges was not the final cost. The Division Bench could have at best
directed the Board to give actual calculation/break up of the increased amount
(as was directed by the learned Single Judge). If the Division Bench did not
want to refer the parties to a civil court in the event of any part of the
calculation being disputed, it ought to have examined the accounts, considered
the objections of the respondent and finally decided the issue. The direction
issued by the High Court in regard to the tentative service charge should
equally apply to the tentative land cost also.
8.
We
therefore allow this appeal in part and set aside the judgment of the High
Court in so far as it relates to the cost of land and service charges. The
matter is remanded to the High Court with the following directions:
(a) The Board shall
furnish to the respondent the calculation-sheet in regard to Rs.177227/-
claimed as the increased cost of land and service charges (for development and
amenities) within two months from today;
(b) If the respondent
agrees with the calculation and pays the amount, the Board shall execute the
sale deed within one month from the date of payment;
(c) If the respondent
disputes the amount claimed by the Board, either in regard to land cost or
service charges, she may file objections to the calculations and the Division
Bench shall decide the same.
(d) If there is any
delay in the disposal by the High Court, it is open to the respondent to
furnish a bank guarantee for the amount claimed by the Board, without prejudice
and obtain the sale deed.
(e) The quashing of
the demand in respect of increase in cost of construction is upheld.
..............................................................J
[R. V. Raveendran]
..................................................................J.
[Lokeshwar Singh Panta]
New
Delhi;
October
3, 2008.
Back
Pages: 1 2