Kasam
Ali Momin Vs. Municipal Corporation of Greater Bombay & Ors [2008] Insc 7 (4 January 2008)
G.P.
Mathur & D.K. Jain
O R D
E R D.K. JAIN, J.:
1.
These petitions under Article 136 of the Constitution, are directed against the
judgment, dated 14th September, 2005, rendered by the High Court of Judicature,
at Bombay in First Appeal No.580 of 2005 and order dated 28th October, 2005,
passed in the review petition, whereby the appeal as well as the review
application preferred by the petitioner against the judgment of the Bombay City
Civil Court, dismissing his suit have been dismissed.
2. In
order to appreciate the controversy involved, a few relevant facts may be
stated.
3. The
petitioner is the original plaintiff. He filed a suit for declaration and permanent
injunction against the Bombay Municipal Corporation (hereinafter referred to as
the Corporation), restraining them from carrying out demolition of
the property bearing Shed No.80, Bombay Talkies Compound, Malad (West) Bombay.
The case of the petitioner is that since 1969 he is the tenant in respect of an
open piece of land admeasuring 1118 sq. feet, owned by a Trust, namely, Ram
Kumar Jalan Public Charitable Trust, respondent No.2 herein. This land was
given to him with a right to put up construction thereon as per the rent
receipt dated 13th May,
1969. He carried out
further construction on the plot prior to 1981 and constructed ground plus two
upper floors.
According
to the petitioner, a fire broke out in the suit premises and the adjoining premises
on 25th August, 1999, affecting the second floor along
with the loft therein. On being informed, an officer of the Corporation
inspected the site, prepared the inspection report and observed that no major
damage was caused to the structure.
4. On 1st September, 1999, a notice under Section 354-A of
the Bombay Municipal Corporation Act (for short the Act) was issued
to the petitioner, alleging unauthorised reconstruction of the structure by
him, to which he responded vide his reply dated 5th September, 1999. On 6th October, 1999,
the Corporation issued yet another notice under Section 351 of the Act,
requiring the petitioner to show cause as to why the notice structure be not
pulled down or unauthorised change be not restored to its sanctioned user. He
was called upon to produce documentary evidence to show that the building or
work or change of user was not unauthorised. The petitioner furnished
explanation to the said notice vide letter dated 11th October, 1999, refuting the allegation of unauthorised construction. In
the same letter the petitioner issued a notice to the Corporation, purporting
to be a notice under Section 527 of the Act, threatening a legal action against
the said show cause notice.
5. The
explanation so furnished by the petitioner came to be rejected by the
Corporation vide their letter dated 3rd December, 1999, inter alia, on the
ground that the petitioner had failed to produce documentary evidence to show
that the structure was in existence prior to datum line of 1st April, 1962. Aggrieved,
the petitioner filed the suit challenging the said notice and order passed by
the Corporation, seeking a declaration to the effect that the order and notice
were illegal.
Relief
of injunction, restraining the Corporation from demolishing the structure which
was referred to as Shed bearing No.180, was prayed for.
6.
Initially, the suit was filed only against the Corporation.
However,
subsequently the said owner of the property, namely, the Trust was also impleaded.
The Corporation did not file its written statement. However, the suit was
contested by the Trust, by filing written statement. The stand of the Trust was
that the petitioner was never given an open piece land on lease but a built up
Shed (No.180), on the ground floor only, was given to him on rent. However, the
petitioner carried out unauthorised construction under the guise of repairs to
the portions of the Shed which was partially damaged in the fire, which broke
out in the year 1999. It was also the stand of the Trust that the Shed was
initially admeasuring 450 sq. feet only but the petitioner constructed ground
plus two upper floors illegally without permission, consent and approval of the
Trust and without getting the plan sanctioned from the Corporation.
7. On
the basis of the pleadings, the Trial Court framed six issues. The petitioner
and the Trust led evidence and the Corporation was permitted to cross examine
the witnesses.
On
consideration of the evidence, so adduced, the trial court came to the
conclusion that the petitioner had failed to prove that the first floor was in
existence in the year 1969, when he had taken possession of the suit premises
or that construction above the first floor was in existence before the datum
line.
Accordingly,
the suit was dismissed.
8. Being
aggrieved, the petitioner filed First Appeal to the High Court. The main point
urged before the High Court was that the datum line for construction in the
Bombay Talkies Compound being 1981 and since the structure of the petitioner
was put up prior thereto, it was not liable to be demolished. The stand of the
petitioner did not find favour with the High Court. Consequently, the appeal
was dismissed.
Against
the said judgment, the petitioner unsuccessfully preferred Review Application.
Both these orders are questioned in the present Special Leave Petitions.
9. We
have heard learned counsel for the parties. It was vehemently contended by Mr.
U.U. Lalit, learned senior counsel on behalf of the petitioner that the trial
court as well as the High Court have failed to return a clear finding on the
question of datum line, though it was specifically pleaded.
Learned
counsel submitted that in view of this fallacy in the order of the High Court,
the matter deserves to be remitted back to the High Court for fresh consideration
on this vital question.
10. We
are unable to persuade ourselves to agree with learned counsel for the
petitioner.
11.
Indubitably, in the plaint as well as in his affidavit it was the specific case
of the petitioner that the datum line for industrial units at the Bombay
Talkies Compound was 3rd March, 1981 as according to the petitioner this fact
had been recognised by virtue of various orders issued by the officers of the
Corporation as well as by the Government and the order passed by the High Court
in the writ petition filed by the association of the unit holders. In support
of his stand the petitioner produced several documents; examined himself and
deposed on the lines of the averments in the plaint. The Corporation led no
evidence, necessitating the petitioner to summon some official records. His
application seeking leave to lead secondary evidence was also allowed. The
Corporation was called upon to produce certain documents. As noted above,
though the Corporation had not filed its written statement yet they were
allowed to cross examine the petitioner. By giving certain suggestions, the
Corporation set up a specific case that the datum line was never changed from
1st April, 1964, as applicable to all industrial sheds existing all over the
city of Bombay, to 3rd March, 1981 as pleaded by the petitioner. Therefore, the
onus was on the petitioner to prove that the Corporation had extended the datum
line to 3rd March, 1981. It is manifest that no specific
issue was framed, as claimed by the petitioner, with regard to the datum line.
Nevertheless,
while collectively dealing with the issues No.2, 3 and 4, relating to the
question whether the notice structure was unauthorised and/or tolerated, the
trial court examined threadbare the entire documentary and ocular evidence,
referred to various orders passed by the High Court, brought on record by the
petitioner and returned the findings that :
(i) in
none of the orders passed by the High Court, there was direction regarding regularisation
and there was no mention of any datum line or policy statement on behalf of the
Corporation much less 3rd March, 1981;
(ii)
the communication between the Corporation and the State Government was only
draft guidelines sent for approval, inter alia, suggesting that because of
litigation started by the occupants of the sheds, 3rd March, 1981 may be
treated as a cut off date but there was no material on record to show that the
proposal, sent as far back as in 1988, was accepted by the Government,
(iii) admissions
in the plaint as well as in the statement of the petitioner showed that he did
not have any documentary evidence to show that the suit structure was in
existence prior to 1st
April, 1962
(iv)
the petitioner had failed to prove the existence of the first floor and, in any
case, the existence of the first floor when gala No.80 was taken into
possession by him and
(v) the
petitioner had failed to prove that the first floor was in existence on or
before the datum line.
12. In
the light of the aforenoted findings returned by the trial court and affirmed
by the High Court, which are primarily findings of fact, we do not find any
reason to entertain the plea sought to be raised by learned counsel for the
petitioner that the matter may be remanded back for determination of the datum
line. It needs little reiteration that in exercise of its extraordinary power
under Article 136 of the Constitution, ordinarily this Court does not interfere
on questions of fact, except in exceptional cases when the finding is such that
it shocks the conscience of this Court. In our opinion, the present case does
not fall in the latter category.
13. In
the conspectus of the circumstances aforesaid, the petition is devoid of any
merit. We decline to grant leave.
Dismissed.