Delhi Development
Authority Vs. M/S. R.S. Sharma & Co., New Delhi [2008] INSC 1433 (26 August
2008)
Judgment
IN THE SUPREME COURT
OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO. 2424 OF 2002 Delhi
Development Authority .... Appellant (s) Versus M/s R.S. Sharma & Co., New
Delhi .... Respondent(s)
P. Sathasivam, J.
1) This appeal, by
special leave, is directed against the judgment and final order dated 10.8.2001
passed by the High Court of Delhi at New Delhi in FAO(OS) No. 104 of 1996,
whereby the Division Bench of the High Court had set aside the order passed by
the learned single Judge in favour of the Delhi Development Authority - the
appellant herein and directed that the Award passed by the Arbitrator be made a
rule of the Court along with interest @ 12% p.a. from the date of the decree
till the date of payment on the entire amount as awarded by the Arbitrator.
2) The facts, in a
nutshell, are as under:
On 18.4.1990, an
Agreement was entered into between the appellant-Delhi Development Authority
(hereinafter referred to as "DDA") and the respondent - M/s R.S.
Sharma & Co.
(hereinafter referred
to as "the Company") for carrying out the work for development of the
land at Pappankalan (Dwarka) Project in South-West Delhi, Phase I according to
the terms and conditions mentioned in the contract. On disputes having arisen
during execution of the work, mainly with respect to the extra cartage, the
same were referred to the Sole Arbitrator, Shri A.P. Paracer, Additional Director
General (Retd.), C.P.W.D., for adjudication. During the pendency of the
arbitration proceedings, the work was still being executed by the Company. 13
Claims (including additional claims) for a sum of Rs. 55.19 lacs approximately
were raised by the Company before the Arbitrator. Claim Nos. 1 to 3 were on
account of extra lead involved in procurement of stone aggregate specified in
agreement Item No.2 i.e., supplying and stacking of graded stone aggregate of
size range 90 mm to 40 mm at site. While additional Claim Nos. 1 to 3 pertain
to extra lead involved in bringing stone specified in agreement Item Nos. 3
& 4 i.e., supplying and stacking of stone screenings/chipping at site 12.5
mm nominal size. Under Claim No.1, the respondent-Company claimed an extra amount
of Rs.30/- per cubic meter over and above the rates mentioned in the Agreement
Item No.2 on account of extra lead involved in the procurement of the stone
aggregates from the quarries at Nooh in Haryana instead of quarries at Delhi.
Under Claim No.3, the
respondent-Company sought declaratory Award to the effect that for all
quantities of aggregate to be brought from Nooh in future, they are entitled to
additional lead @ Rs.30/- per cubic meter excluding the quantity already
claimed under Claim No.2. Similarly, under Additional claim Nos. 1 to 3, the
respondent-Company claimed the rate of Rs.30 per cubic meter for extra lead
involved in bringing stone, specified in agreement item Nos. 3 & 4, from
the quarries at Nooh (Haryana). On 29.7.1992, the Arbitrator made the Award in
favour of respondent-Company. Suit No.2981 of 1992 was filed by the
respondent-Company for making the Award a rule of the Court. Cross Objections
were filed by DDA. On 25.9.1995, the learned single Judge of the Delhi High
Court set aside the Award with respect to Claim Nos. 1 to 3 as well as
Additional Claim Nos. 1 to 3 and made the remaining part of the Award a rule of
the Court and awarded interest @ 12% p.a. from the date of the decree till the
date of payment by DDA. Aggrieved by the judgment of the learned single Judge,
the Company filed FAO (OS) No.104 of 1996 before the Division Bench for setting
aside the order to the extent it deals with Claim Nos. 1-3 and for making the
Award dated 27.9.1992 a rule of the Court. The Division Bench of the High Court
of Delhi, vide order dated 10.8.2001, set aside the order of the learned single
Judge to the extent by which the Award of the Arbitrator on Claim Nos. 1 to 3
and Additional Claim Nos. 1 to 3 were set aside and the Award made by the Arbitrator
on aforesaid Claims were made a rule of the Court. The Respondent - Company was
also awarded interest @ 12% p.a. from the date of decree till the date of
payment on the entire amount as awarded by the Arbitrator.
Aggrieved by the said
judgment, the present appeal is filed by DDA before this Court.
3) Heard Mr.
Amarendra Sharan, learned Additional Solicitor General, appearing for the
appellant and Mr. U.A. Rana, learned counsel, appearing for the respondent.
4) Mr. Amarendra
Sharan, learned Additional Solicitor General, appearing for the appellant-Delhi
Development Authority, vehemently contended that the Division Bench of the High
Court was not justified in setting aside the order passed by the learned single
Judge with respect to Claim Nos.
1-3 and additional
claim Nos. 1-3 inasmuch as the Arbitrator had clearly failed to advert to
clause 3.16 of the Agreement which does not provide for extra cartage.
According to him, clause 3.16 of the Agreement stipulates that the contractor
is responsible for all the extra leads over and above the rate of payment
specified in the Agreement. He further contended that since the Arbitrator
failed to take note of the relevant condition, namely, clause 3.16, which
prohibits extra cartage over and above the rate of payment specified in the
Agreement, there is a clear error apparent on the face of the Award and liable
to be set aside in terms of Section 34(2) of the Arbitration and Conciliation
Act, 1996 (hereinafter referred to as "the Act"). On the other hand,
Mr. U.A. Rana, learned counsel appearing on behalf of the respondent, while
supporting the order of the Division Bench contended that in view of the fact
that stone was brought from Nooh in Haryana which was found to be more blue,
better in appearance and quality, the Arbitrator was fully justified in making
the Award in favour of the respondent herein on Claim Nos. 1-3 and additional
Claim Nos. 1-3. He also submitted that the Arbitrator is the sole Judge of the
quality as well as quantity of evidence and the Courts cannot judge the
evidence placed before the Arbitrator. In the absence of plausible ground in
terms of Section 34(2) of the Act, the learned single Judge is not justified in
setting aside the award of the Arbitrator.
Thereby, he prayed
for dismissal of the appeal.
5) We have considered
the rival contentions, perused the relevant materials including the terms of
the Agreement, award of the Arbitrator and the orders passed by the learned
single Judge as well as by the Division Bench of the High Court.
6) The work relating
to development of land at Pappankalan (Dwarka) Project in South West Delhi,
Phase-I was awarded under Agreement No. 6/EE/WD 10-A/90-91/DDA to M/s R.S.
Sharma & Co.-
respondent herein. During the execution of the said work, certain disputes
arose between the parties and ultimately they were referred to Mr. A.P.
Paracer, Additional Director General (Retd.) C.P.W.D. for adjudication. After
adjudication, the Arbitrator, on 29.7.1992, made and published his Award. The
said Award was filed in Court and after issuance of notice, DDA filed its
objections. The main dispute relates to Claim Nos. 1-3 and additional Claim
Nos. 1- 3 wherein the claimant had claimed extra rate of Rs.30/- per cubic
meter over and above the rate agreed to in the Agreement under Item Nos. 2, 3
and 4 for extra cartage involved in bringing the stone aggregate from Nooh
quarries to Delhi. According to the claimant, it was required to use Delhi
quartz stone conforming to CPWD specifications and as the claimant had obtained
blue quartz stone from Nooh quarries in Haryana and since DDA had failed to
indicate the approved quarry at Delhi for obtaining supplies of Delhi quartz
stone, the claimant was entitled to extra rates at the rate of Rs.30/- per
cubic meter for procurement of stone aggregate from the quarries at Nooh in
Haryana. According to DDA, the Arbitrator has misconstrued and misunderstood
the Agreement between the parties, particularly, clause 3.16.
Though the learned
single Judge set aside the Award in respect of claim Nos. 1-3 and additional
Claim Nos. 1-3 on the ground that there were no material before the Arbitrator
to accept those claims, the Division Bench, reversed the same and confirmed the
Award as granted by the Arbitrator.
7) In order to
consider the rival contentions, it is useful to refer the relevant provisions
of the Act. Chapter VII of the Act deals with `Recourse against Arbitral
Award'. Section 34 enumerates various grounds/circumstances on which the Award
can be set aside by the Court which reads as under:
"34. Application
for setting aside arbitral award. - (1) Recourse to a Court against an arbitral
award may be made only by an application for setting aside such award in
accordance with sub-section (2) and subsection (3).
(2) An arbitral award
may be set aside by the Court only if- (a) The party making the application
furnishes proof that- (i) A party was under some incapacity, or (ii) The
arbitration agreement is not valid under the law to which the parties have
subjected it or, failing any indication thereon, under the law for the time
being in force; or (iii) The party making the application was not given proper
notice of the appointment of an arbitrator or of the arbitral proceedings or
was otherwise unable to present his case; or (iv) The arbitral award deals with
a dispute not contemplated by or not falling within the terms of the submission
to arbitration, or it contains decisions on matters beyond the scope of the
submission to arbitration:
Provided that, if the
decisions on matters submitted to arbitration can be separated from those not
so submitted, only that part of the arbitral award which contains decisions on
matters not submitted to arbitration may be set aside; or (v) The composition
of the arbitral tribunal or the arbitral procedure was not in accordance with
the agreement of the parties, unless such agreement was in conflict with a
provision of this Part from which the parties cannot 9 derogate, or, failing
such agreement, was not in accordance with this Part; or (b) The Court finds
that- (i) The subject-matter of the dispute is not capable of settlement by
arbitration under the law for the time being in force, or (ii) The arbitral
award is in conflict with the public policy of India.
Explanation. -Without
prejudice to the generality of sub- clause (ii), it is hereby declared, for the
avoidance of any doubt, that an award is in conflict with the public policy of
India if the making of the award was induced or affected by fraud or corruption
or was in violation of section 75 or section 81.
(3) An application
for setting aside may not be made after three months have elapsed from the date
on which the party making that application had received the arbitral award or,
if a request had been made under section 33, from the date on which that
request had been disposed of by the arbitral tribunal:
Provided that if the
Court is satisfied that the applicant was prevented by sufficient cause from
making the application within the said period of three months it may entertain
the application within a further period of thirty days, but not thereafter.
(4) On receipt of an
application under sub-section (1), the Court may, where it is appropriate and
it is so requested by a party, adjourn the proceedings for a period of time
determined by it in order to give the arbitral tribunal an opportunity to
resume the arbitral proceedings or to take such other action as in the opinion
of arbitral tribunal will eliminate the grounds for setting aside the arbitral
award."
8) The grounds/
circumstances mentioned in sub-section(2) of Section 34 have been considered by
this Court in various decisions. In Grid Corporation of Orissa Ltd. & Anr.
vs. Balasore Technical School, (2000) 9 SCC 552, this Court in paragraph 3 held
as under:
"3. In this
case, the High Court is of the view that a civil court does not sit in appeal
against the award and the power of the court when an award is challenged is
rather limited.
The award of the
arbitrator is ordinarily final and conclusive as long as the arbitrator has
acted within his authority and according to the principle of fair play. An
arbitrator's adjudication is generally considered binding between the parties
for he is a tribunal selected by the parties and the power of the court to set
aside the award is restricted to cases set out in Section 30 of the Arbitration
Act. It is not open to the court to speculate where no reasons are given by the
arbitrator, as to what impelled him to arrive at his conclusion. If the dispute
is within the scope of the arbitration clause it is no part of the province of
the court to enter into the merits of the dispute. If the award goes beyond the
reference or there is an error apparent on the face of the award it would
certainly be open to the court to interfere with such an award. In New India
Civil Erectors (P) Ltd. v. Oil & Natural Gas Corpn.(1997) 11 SCC 75 this
Court considered a case of a non-speaking award. In that case the arbitrator
had acted contrary to the specific stipulation/condition contained in the
agreement between the parties. It was held that the arbitrator being a creature
of the contract must operate within the four corners of the contract and cannot
travel beyond it and he cannot award any amount which is ruled out or
prohibited by the terms of the agreement. In that contract it was provided that
for construction of a housing unit, in measuring the built-up area, balcony
areas should be excluded. However, the arbitrator included the same which was
held to be without jurisdiction. In the same manner it was also held that the
price would be firm and not subject to any escalation under whatsoever ground
till the completion of the work and awarding any sum as a result of escalation
was not permissible. To the same effect is the decision in Associated Engg. Co.
v. Govt. of A.P. (1991) 4 SCC 93. It was stated that if the arbitrator commits
an error in the construction of the contract, that is an error within his
jurisdiction. But if he 11 wanders outside the contract and deals with matters
not allotted to him, he commits a jurisdictional error and an umpire or
arbitrator cannot widen his jurisdiction by deciding a question not referred to
him by the parties or by deciding a question otherwise than in accordance with
the contract. A conscious disregard of the law or the provisions of the
contract from which he has derived his authority vitiates the award. The
principle of law stated in N.
Chellappan case on
which strong reliance has been placed by the learned counsel for the respondent
would make it clear that except in cases of jurisdictional errors it is not
open to the court to interfere with an award. That proposition is
unexceptionable. However, from a reading of the decisions of this Court
referred to earlier it is clear that when an award is made plainly contrary to
the terms of the contract not by misinterpretation but which is plainly
contrary to the terms of the contract it would certainly lead to an inference
that there is an error apparent on the face of the award which results in
jurisdictional error in the award. In such a case the courts can certainly
interfere with the award made by the arbitrator."
9) In General
Manager, Northern Railway & anr. vs. Sarvesh Chopra, (2002) 4 SCC 45, it is
worthwhile to refer the following conclusion as observed in paragraph 10 as
under:
"10. It was next
submitted by the learned counsel for the respondent that if this Court was not
inclined to agree with the submission of the learned counsel for the respondent
and the interpretation sought to be placed by him on the meaning of "excepted
matter" then whether or not the claim raised by the contractor is an
"excepted matter" should be left to be determined by the arbitrator.
It was submitted by him that while dealing with a petition under Section 20 of
the Arbitration Act, 1940 the court should order the agreement to be filed and
make an order of reference to the arbitrator appointed by the parties leaving
it open for the arbitrator to adjudicate whether a claim should be held to be
not entertainable or awardable, being an "excepted matter".
With this submission
too we find it difficult to agree. While dealing with a petition under Section
20, the court has to examine: (i) whether there is an arbitration agreement
between the parties, (ii) whether the difference which has arisen is one to
which the arbitration agreement applies, and (iii) whether there is a cause,
shown to be sufficient, to decline an order of reference to the arbitrator. The
word "agreement" finding place in the expression "where a
difference has arisen to which the agreement applies", in sub-section (1)
of Section 20 means "arbitration agreement".
The reference to an
arbitrator on a petition filed under Section 20 is not a function to be
discharged mechanically or ministerially by the court; it is a consequence of
judicial determination, the court having applied its mind to the requirements
of Section 20 and formed an opinion, that the difference sought to be referred
to arbitral adjudication is one to which the arbitration agreement applies. In
the case of Food Corpn. of India relied on by the learned counsel for the
respondent, it has been held as the consistent view of this Court that in the
event of the claims arising within the ambit of "excepted matters",
the question of assumption of jurisdiction by any arbitrator either with or
without the intervention of the court would not arise. In Union of India v.
Popular Builders (2000) 8 SCC 1 and Steel Authority of India Ltd. v. J.C.
Budharaja, Govt. and Mining Contractor (1999) 8 SCC 122, Ch. Ramalinga Reddy v.
Superintending Engineer (1999) 9 SCC 610 (para 18) and Alopi Parshad and Sons
Ltd. v. Union of India (1962) 2 SCR 793 at p. 804 this Court has unequivocally
expressed that an award by an arbitrator over a claim which was not arbitrable
as per the terms of the contract entered into between the parties would be
liable to be set aside. In Prabartak Commercial Corpn. Ltd. v. Chief
Administrator, Dandakaranya Project (1991) 1 SCC 498 a claim covered by
"excepted matter" was referred to the arbitrator in spite of such reference
having been objected to and the arbitrator gave an award. This Court held that
the arbitrator had no jurisdiction in the matter and that the reference of the
dispute to the arbitrator was invalid and the entire proceedings before the
arbitrator including the awards made by him were null and void."
10) In State of
Rajasthan vs. Nav Bharat Construction Co., (2006) 1 SCC 86, this Court in
paragraph 27 held as under:
"27. There can
be no dispute to the well-established principle set out in these cases.
However, these cases do not detract from the law laid down in Bharat Coking
Coal Ltd.
case or Continental
Construction Co. Ltd. case. An arbitrator cannot go beyond the terms of the
contract between the parties. In the guise of doing justice he cannot award
contrary to the terms of the contract. If he does so, he will have misconducted
himself. Of course if an interpretation of a term of the contract is involved
then the interpretation of the arbitrator must be accepted unless it is one
which could not be reasonably possible. However, where the term of the contract
is clear and unambiguous the arbitrator cannot ignore it."
11) In Hindustan Zinc
Ltd. vs. Friends Coal Carbonisation, (2006) 4 SCC 445, the following principles
laid down in paragraphs 13 and 14 are relevant for the disposal of the present
case:
"13. This Court
in ONGC Ltd. v. Saw Pipes Ltd. (2003) 5 SCC 705 held that an award contrary to
substantive provisions of law or the provisions of the Arbitration and
Conciliation Act, 1996 or against the terms of the contract, would be patently
illegal, and if it affects the rights of the parties, open to interference by
the court under Section 34(2) of the Act. This Court observed: (SCC pp. 718
& 727-28, paras 13 & 31) "13. The question, therefore, which
requires consideration is--whether the award could be set aside, if the
Arbitral Tribunal has not followed the mandatory procedure prescribed under
Sections 24, 28 or 31(3), which affects the rights of the parties. Under
sub-section (1)(a) of Section 28 there is a mandate to the Arbitral Tribunal to
decide the dispute in accordance with the substantive law for the time being in
force in India. Admittedly, substantive law would include the Indian Contract
Act, the Transfer of Property Act and other such laws in force. Suppose, if the
award is passed in violation of the provisions of the Transfer of Property Act
or in violation of the Indian Contract Act, the question would be--whether such
award could be set aside.
Similarly, under
sub-section (3), the Arbitral Tribunal is directed to decide the dispute in
accordance with the terms of the contract and also after taking into account
the usage of the trade applicable to the transaction. If the Arbitral Tribunal
ignores the terms of the contract or usage of the trade applicable to the
transaction, whether the said award could be interfered. Similarly, if the
award is a non-speaking one and is in violation of Section 31(3), can such
award be set aside? In our view, reading Section 34 conjointly with other provisions
of the Act, it appears that the legislative intent could not be that if the
award is in contravention of the provisions of the Act, still however, it
couldn't be set aside by the court. If it is held that such award could not be
interfered, it would be contrary to the basic concept of justice. If the
Arbitral Tribunal has not followed the mandatory procedure prescribed under the
Act, it would mean that it has acted beyond its jurisdiction and thereby the
award would be patently illegal which could be set aside under Section 34.
* * *
31. ... in our view,
the phrase `public policy of India' used in Section 34 in context is required
to be given a wider meaning. It can be stated that the concept of public policy
connotes some matter which concerns public good and the public interest. What
is for public good or in public interest or what would be injurious or harmful
to the public good or public interest has varied from time to time. However,
the award which is, on the face of it, patently in violation of statutory
provisions cannot be said to be in public interest.
Such
award/judgment/decision is likely to adversely affect the administration of
justice. Hence, in our view in addition to narrower meaning given to the term
"public policy" in Renusagar case, it is required to be held that the
award could be set aside if it is patently illegal. The result would be --award
could be set aside if it is contrary to:
(a) fundamental
policy of Indian law; or (b) the interest of India; or (c) justice or morality;
or 15 (d) in addition, if it is patently illegal.
Illegality must go to
the root of the matter and if the illegality is of trivial nature it cannot be
held that award is against the public policy. Award could also be set aside if
it is so unfair and unreasonable that it shocks the conscience of the court.
Such award is opposed
to public policy and is required to be adjudged void."
14. The High Court
did not have the benefit of the principles laid down in Saw Pipes, and had
proceeded on the assumption that award cannot be interfered with even if it was
contrary to the terms of the contract. It went to the extent of holding that
contract terms cannot even be looked into for examining the correctness of the
award. This Court in Saw Pipes has made it clear that it is open to the court
to consider whether the award is against the specific terms of contract and if
so, interfere with it on the ground that it is patently illegal and opposed to
the public policy of India."
12) From the above
decisions, the following principles emerge:
(a) An Award, which
is (i) contrary to substantive provisions of law ; or (ii) the provisions of
the Arbitration and Conciliation Act, 1996 ; or (iii) against the terms of the
respective contract ; or (iv) patently illegal, or (iv) prejudicial to the
rights of the parties, is open to interference by the Court under Section 34(2)
of the Act.
16 (b) Award could
be set aside if it is contrary to :
(a) fundamental
policy of Indian Law; or (b) the interest of India; or (c) justice or morality;
(c) The Award could
also be set aside if it is so unfair and unreasonable that it shocks the
conscience of the Court.
(d) It is open to the
Court to consider whether the Award is against the specific terms of contract
and if so, interfere with it on the ground that it is patently illegal and
opposed to the public policy of India.
13) With these
principles and statutory provisions, particularly, Section 34(2) of the Act,
let us consider whether the Arbitrator as well as the Division Bench of the High
Court were justified in granting the Award in respect of Claim Nos.
1-3 and additional
Claim Nos. 1-3 of the claimant or the appellant-DDA has made out a case for
setting aside the Award in respect of those claims with reference to the terms
of the Agreement duly executed by both parties.
14) The main dispute
relates to extra cartage that is, stone brought from Nooh, Haryana. It is the
stand of the claimant that apart from the Agreement dated 18.4.1990, both
parties were agreed to abide by the conditions mentioned in the letter dated
10.4.1990 of the claimant - M/s R.S. Sharma & Co. to the Chief Engineer
(WZ), DDA, Vikas Minar, New Delhi. In paragraph 6 of the said letter, it was
stated as under:
"6. We will use
Delhi Quartz stone as per CPWD specifications and specifications mentioned in
the tender documents. This condition has been accepted by the Department in the
case of Ist lowest tenderer for this work."
15) It is stated by
the learned counsel appearing for the claimant that since the DDA has not
approved Delhi Quartz stone which was not as per CPWD specifications and
specifications mentioned in the tender document, stones were brought from Nooh,
Haryana which satisfied those specifications. As rightly pointed out by the
learned ASG appearing for DDA, there is no specific clause in the terms of 18 agreement
for extra cartage for bringing stones from elsewhere. In this regard, the
appellant heavily relied on clause 3.16 of the Agreement which reads as under:
"3.16 - The
collection and stacking of material shall include all leads. The rates quoted
by the contractor shall hold good irrespective of the source from which the
material are brought so long as they conform to the specifications. The closure
of particular quarry will not entitle the contractor to any revision in the
rates."
16) The perusal of
the Award of the Arbitrator as well as the judgment of the Division Bench
clearly shows that they did not advert to the above clause 3.16. It is relevant
to point out that the extra cartage has been awarded by the Arbitrator without
adverting to clause 3.16 of the Agreement, hence, the learned single Judge was
wholly justified in partially setting aside the Award in respect of the claims
with respect to the extra cartage. We also perused the pleadings and evidence
placed on record pertaining to Claim Nos. 1-3 and additional Claim Nos. 1-3. As
rightly observed by the learned single Judge, there was no material on record
to substantiate the case of the claimant, viz., DDA had insisted upon the
claimant for using the stone aggregates brought from Nooh in Haryana.
In those circumstances
and of the fact that the terms and conditions of the Agreement are binding on
both the parties, in the absence of specific clause with regard to payment of
extra cartage and in view of clause 3.16, the respondent- claimant cannot claim
extra cartage @ Rs.30/- per cubic meter on the ground of extra lead involved in
bringing the stone aggregates from Nooh in Haryana. The Division Bench like the
Arbitrator proceeded on the sole basis that DDA had compelled the
claimant-Company from bringing the stone aggregates from Nooh in Haryana and
committed an error in affirming the erroneous conclusion arrived at by the
Arbitrator insofar as the additional claims are concerned. As rightly pointed
out by the learned Additional Solicitor General, the Division Bench proceeded
on an erroneous premise that the appellant-DDA has nowhere stipulated where the
stone was to be brought from. It is true that DDA had given certain
specifications required to be conformed. Further, the cost of the work was
irrespective of the source or lead from where the stone was brought. The award
is completely silent on the relevant clause viz. clause 3.16 of the Agreement
which makes it clear that the contractor is wholly responsible for all the
extra leads. In fact, the Arbitrator has given no reason whatsoever so far as
the rate claimed for the extra lead by the claimant and has verbatim accepted
the claim without giving any justification for the same. We are satisfied that
this is an error apparent on the face of the record as well as contrary to the
terms of the Agreement.
17) For the sake of
brevity, we point out that in terms of clause 3.16 of the Contract, it is the
responsibility of the Contractor to collect and stock the material and the
rates quoted by him including all leads irrespective of the source from where
the material was brought. However, if DDA had refused to accept the stone
aggregate brought to site by the contractor from a quarry in Delhi and insisted
upon bringing the material from Nooh quarry, Haryana, the Contractor will be
entitled to the extra lead for bringing the said material from Nooh. As rightly
pointed out by learned counsel for the appellant, in the present case, there is
nothing on record to show that the Department had insisted upon bringing the
stone aggregate only from Nooh. Hence, the contractor will not be entitled to
the increased rates for extra lead. Without a specific request or additional
clause, the Arbitrator in respect of Claim Nos. 1-3 and additional Claim Nos.
1-3 proceeded on the wrong assumption that the Department had insisted upon the
use of stone aggregate to be brought from Nooh, hence, the learned single Judge
is perfectly right in holding that there is an error apparent on the face of
the Award and the Award is liable to be set aside. As stated earlier, the
Arbitrator has ignored clause 3.16 of the contract and made a departure from
the contract while granting relief in respect of Claim Nos.
1-3 and additional
Claim Nos. 1-3 and the same, in our view, cannot be sustained.
18) Under these
circumstances, we allow the appeal of DDA and set aside the judgment and order
dated 10.8.2001 passed by the Division Bench in FAO (OS) No. 104 of 1996 and
restore the order of the learned single Judge insofar as Claim Nos. 1-3 and
additional Claim Nos. 1-3 are concerned.
There shall be no
order as to costs.
.........................................J. (P. Sathasivam)
........................................J.
(Aftab Alam)
NEW
DELHI
August
26, 2008.
Back
Pages: 1 2 3