M/S
Delta Mechcons (India) Ltd Vs.
M/S Marubeni Corporation [2007] Insc 632 (18 May 2007)
P.K. BALASUBRAMANYAN
O R D E R ARBITRATION PETITION NO.11 OF 2006 The respondent took up the
project of construction of a thermal power plant at Ramagundam in Karimnagar
District of the State of Andhra Pradesh. It entered into four sub-contracts
with the petitioner relating to that work. The general conditions of
sub-contracts were to be part of the four separate contracts. The sub-contracts
were terminated on 25.7.2001 with effect from 7.8.2001. It appears that there
were subsequent discussions between the parties and on the basis of
ascertainment of the sums due to the petitioner the same were paid by the
respondent and the petitioner in return gave in writing that it had received
full and final payment from the respondent in terms of the settlement between
the two and also a certificate that all payments against the said four
sub-contracts have been made by the respondent to the petitioner and received
by the petitioner and that no bills are pending with the respondent for
settlement. After the matters rested on this basis, the petitioner made a claim
in respect of the four sub-contracts.
The petitioner also named an arbitrator and called upon the respondent to
name an arbitrator in terms of the arbitration agreement. The respondent
disputed the claims of the petitioner and pleaded that there was no subsisting
claim for the petitioner based on any of the four sub-contracts. Even then
without prejudice to its contentions the respondent also named an arbitrator.
In terms of the arbitration agreement, the two nominated arbitrators had
together to name the Chairman of the Arbitral Tribunal or the presiding
arbitrator. The nominated arbitrators failed to do so.
2. Meanwhile the petitioner had also moved the concerned District Court
under Section 9 of the Arbitration and Conciliation Act seeking what it called
interim protection pending an arbitration. Four separate applications were
filed. The applications were dismissed by the District Court. The petitioner
filed appeals in the High Court of Gujarat. The High Court disposed of the
appeals recording the following:
"After having argued at some length, learned counsel on both sides
agreed and submitted that the main dispute between the parties is the
subject-matter of separate arbitration proceedings and at this stage it may not
be necessary or advisable to invite observations of this Court as regards the
legality and validity of any of the claims or liability of any of the parties
to satisfy such claims. It was, therefore, jointly submitted that all the
appeals may be disposed as withdrawn with the observation that the parties may
put forward their case before the arbitral tribunal, which may decide the
dispute referred to it without being influenced by any observation made in the
impugned judgment as also the fact that these appeals were not pressed for any
orders on merits."
3. The relevant clauses relating to arbitration, as contained in the
agreement between the parties are as under:
"21. SETTLEMENT OF DISPUTES If at any time any question, dispute, or
difference arise between the Contractor and the Subcontractor in connection
with or arising out of the Subcontract or the Subcontract Works, either party
shall give to the other notice in writing specifying the nature of such
question, dispute or difference and the point at issue, and the parties shall
discuss the matter and shall endeavour to reach an amicable settlement. In case
parties fail to reach an amicable solution within sixty (60) days after the
date of the said notice, the matter shall be referred to an arbitration in
accordance with Clause 22 hereof.
22. ARBITRATION
22.1 Any dispute which could not be resolved between the parties in
accordance with clause 21 hereof shall be settled exclusively by arbitration
conducted in accordance with the Rules of Concilation and Arbitration of the
International Chamber of Commerce. Each arbitral tribunal shall consist of
three arbitrators. The Contractor and the sub-contractor shall each appoint one
arbitrator and the two arbitrators thus appointed shall jointly agree upon the
third arbitrator to act as chairman. If such agreement cannot be reached within
thirty (30) days from the date of appointment of the later member, the third
arbitrator shall be appointed by the International Chamber of Commerce. The
said Chairman shall not be the same nationality of either party to the
sub-contract.
22.2 The arbitration shall be conducted in India
22.3 The language to be used on all written documents provided in each
arbitration shall be English.
22.4 The decision of the arbitral tribunal shall be considered final and
binding upon both parties and shall not be subject to any appeal whatsoever.
22.5 The cost and expenses of arbitration shall be borne by the party based
on the award of the arbitral tribunal.
22.6 Performance of the sub-contract work shall continue during the
arbitration proceedings notwithstanding the existence of any dispute,
controversy or question."
4. When the named arbitrators failed to nominate a presiding arbitrator, the
petitioner approached the International Chamber of Commerce (for short ICC)
with a request that the presiding arbitrator may be nominated by the ICC. There
was some correspondence between the ICC and the parties and ultimately the ICC
informed the petitioner that the ICC had decided not to appoint a Chairman of
the arbitral tribunal pursuant to the rules of ICC as appointing authority. It
was in that context that the petitioner approached this Court with this
application under Section 11 of the Arbitration and Conciliation Act.
5. Learned counsel for the petitioner submitted that going by the
arbitration agreement the petitioner and the respondent have nominated their
arbitrators but the nominee arbitrators had failed to appoint a presiding
arbitrator in terms thereof and in that context, as per the agreement, the
petitioner had approached the ICC for nominating a presiding arbitrator but the
ICC had refused the request without assigning any reason. In that context it
was submitted that the jurisdiction of the Chief Justice of India --- being an
international arbitration --- under the Act was attracted and it was just and
necessary to appoint a presiding arbitrator in terms of Section 11 of the Act. This
argument is controverted by the respondent, in addition to pleading on the
merits that there was no subsisting claim for the petitioner and that the
arbitration is barred by limitation, by contending that the petitioner had not
complied with the procedure set down by the ICC before calling upon ICC to name
the presiding arbitrator and in that context the jurisdiction of the Chief
Justice of India under Section 11 of the Act is not attracted. It was also
contended that there were four sub-contracts and a single application for the
appointment of a presiding arbitrator in respect of the disputes relating to
four different contracts was not maintainable. It was for the petitioner to
have agreed to follow the ICC Rules and to comply with those rules so as to get
an arbitrator appointed by the ICC in terms of their Rules and the petitioner
having failed to do so, the application filed by the petitioner had only to be
rejected. The arbitration agreement clearly provides that disputes between the
parties are to be settled exclusively by an arbitration conducted in accordance
with the Rules of Conciliation and Arbitration of the International Chamber of
Commerce. It is hence submitted that the petitioner not having adhered to the
said Rules, ICC was not justified in refusing to act.
6. It is true that there is a clause that the arbitration is to be conducted
in terms of the Conciliation and Arbitration Rules of ICC. But it also provides
that the arbitral tribunal shall consist of three arbitrators. The contractor and
the sub-contractor had to each appoint one arbitrator and the two arbitrators
thus appointed, should jointly agree upon the third arbitrator as Chairman. If
such agreement be not reached within the time provided, the third arbitrator
shall be appointed by the ICC. The Chairman was not to be of the same
nationality of either party to the sub-contract. The arbitration agreement has
to be read as a whole to know its purport.
7. It is open to the parties while entering into an arbitration agreement to
provide as to how the arbitral tribunal should be constituted. It is also open
to them to provide for the rules to be followed. As I read the arbitration
agreement, I find that the parties had reserved unto themselves the right to
nominate an arbitrator each stipulating that the two arbitrators so nominated,
should agree upon the third arbitrator to act as the Chairman. In other words,
the parties by their agreement have left it to the two arbitrators to appoint a
third arbitrator to act as the Chairman. They have also agreed that in case of
failure of the two arbitrators to appoint the third arbitrator, the third
arbitrator was to be appointed by ICC. The parties had also provided that the
arbitration should be conducted in accordance with the Rules of Conciliation
and Arbitration of the International Chamber of Commerce.
8. It was the contention of learned senior counsel for the respondent that
once the machinery contemplated by the parties failed, the petitioner could
only go by way of the Rules of Conciliation and Arbitration of the
International Chamber of Commerce and the petitioner not having proceeded in
terms of the said Rules, the ICC was justified in not appointing a presiding
arbitrator and in that context no cause of action has arisen for the petitioner
for approaching this Court. As I read the arbitration agreement it consists of
two parts. Firstly, the parties have agreed that the arbitration should be
conducted in accordance with the Rules of Conciliation and Arbitration of the
International Chamber of Commerce. Having agreed to that, the parties also have
agreed on the mode of creating the arbitral tribunal. This is by the parties
nominating one arbitrator each and the nominated arbitrators appointing the
Chairman of the tribunal or the presiding arbitrator. They have contemplated
the failure of the nominee arbitrators to name the Chairman or the presiding
arbitrator and they have provided the means for supplying that omission. They
have agreed that in that case, the presiding arbitrator should be got appointed
by the ICC.
According to me, the agreement to follow the Rules of ICC in the conduct of
arbitration proceedings is different from the agreement regarding appointment
of the arbitral tribunal. There is no obligation on the parties to undertake before
the ICC, to have the arbitration in accordance with its procedure and Rules
including even the constitution of the arbitral tribunal, for the ICC to act to
appoint the Chairman of the arbitral tribunal. In fact, except stating that it
refuses to appoint a presiding arbitrator, the ICC has not given any specific
reason for refusing to do so. Nor am I in agreement with the submission of
learned senior counsel for the respondent that unless the parties surrender
their rights of creating the arbitral tribunal to the ICC in toto the ICC would
be justified in refusing to name the presiding arbitrator.
After all, the process of settlement of disputes through arbitration is a
process of settlement extra cursum curiae and the parties are at liberty to
choose their judge and in the case on hand, the parties have provided the
manner of constituting the tribunal. Therefore, no invalidity is attached to
their agreement. They had agreed to approach ICC in case the nominated
arbitrators failed to name the Chairman. One of the parties had moved ICC to
supply the omission in terms of the arbitration agreement. The ICC for its own
reasons has filed to act. I have, therefore, come to the conclusion that the
named arbitrators have failed to nominate a presiding arbitrator in terms of
the agreement and in that respect the ICC has not supplied the vacancy
approached in terms of the agreement. In that context the procedure agreed upon
by the parties to constitute the arbitration tribunal has broken down
justifying the approach of the petitioner to the Chief Justice of India for the
appointment of a Chairman for the arbitral tribunal or the presiding
arbitrator.
9. I do not see much merit in the contention of learned senior counsel for
the respondent that there should have been four separate applications for
appointment of the presiding arbitrators since four sub- contracts were
involved. Even assuming that the contention has merit, I reject it as being too
technical.
10. There was not much argument before me on the merits concerning
non-subsistence of any further claim for the petitioner and the request being
barred by limitation. The parties proceeded on the basis that those were
questions for the arbitral tribunal to decide. This might have been so
particularly in the context of the stand adopted by them in the High Court of
Gujarat in the appeals arising from the orders of the District Court in the
applications under Section 9 of the Act. These questions have tobe decided by
the arbitral tribunal, in the circumstances of this case.
11. As per the arbitration agreement the Chairman of the arbitral tribunal
has to be of a nationality different from the nationality of the contracting
parties. Learned counsel for the petitioner contended that since the arbitrator
was being appointed by the Chief Justice of India or his nominee in terms of
Section 11 of the Act, this restriction would not apply and I was free to
appoint anyone as Chairman or the presiding arbitrator. I am not in a position
to agree. In the light of my reasoning above, it is obvious that this part of
the agreement between the parties must also be given effect to. Therefore, this
is a case where I have to appoint a Chairman of the arbitral tribunal who is of
a nationality different from the nationality of either of the parties. Suffice
it to say that for the moment I hold that my jurisdiction to name a Chairman of
the arbitral tribunal has rightly been invoked and that a Chairman of the
arbitral tribunal has to be appointed by me.
12. To enable me to name the Chairman, I direct, the parties either to
submit an agreed name with the consent of that person or in case they are not
able to agree, submit two names each with the consent of the nominees, for
being considered for appointment as the Chairman of the arbitral tribunal. The
parties are, therefore, directed to file either a joint statement or separate
statements in writing indicating the names as directed above on or before the
10th of July, 2007 and the matter will be posted for further orders on 13th
July, 2007.
Back
Pages: 1 2