Tamil
Nadu Water Supply & Drainage Board Vs. M/S. Satyanarayana Brothers Pvt. Ltd
[2007] Insc 107 (7 February 2007)
Dr.AR.LAKSHMANAN & ALTAMAS KABIR
Dr.AR.LAKSHMANAN, J.
-
Heard Mr.Mohan Parasaran, learned Additional Solicitor General for the
appellant and Mr.Dipanker P.Gupta and Mr.T.L.V.Iyer, learned senior counsel for
the respondent.
-
Aggrieved against the order passed by the Division Bench of the High
Court of Madras dt.24.03.2004 in OSA Nos.248 of 1989 and 59 of 1993, the above
two appeals were filed.
-
The case on hand has a chequered history .
The Government of Tamil Nadu formulated a scheme known as "Veeranam
Project" to provide drinking water to the city of Chennai and thereby
overcome the problem of acute water scarcity in the city of Chennai. In order
to implement the aforesaid scheme, the Government invited tenders for
manufacturing, supplying and delivering 1676 mm pre-stressed concrete pipes and
fittings including transporting to site, laying, jointing and testing for raw
water and clear water conveying, from Veeranam Tank to Chennai City. The
Secretary to Government, Public Works Department requested for clearance of
foreign exchange from the Government of India. This was done with a view to
avoid delay in the project. The respondent herein submitted their tender. The
tender submitted by the respondent was the lowest tender and on negotiation the
same was accepted by the Government and the Government issued G.O.Ms.No.1607
Public (Twad) Department accepting the tender of the respondent. Subsequently,
the Government suggested that the respondent should approach ICICI Ltd. for
foreign exchange loan. The Government accepted the request of the respondent
for a hike in the tender amount in view of the reduction on foreign exchange
component. An agreement was entered into between the respondent and the Chief
Engineer, Public Works Department. The Government of India also approved the
foreign collaboration arrangements. The import license for the gasket
manufacturing unit was also cleared and a factory at Thirukalikundram was
commenced and the equipment for manufacturing pipes was also received. The
factory at Panrutti also commenced the operation and the equipment for
manufacturing rubber gaskets was received in two shipments. The respondent sought
extension of time till 31.12.1975 in order to complete the work. On considering
the prevailing circumstances, the time for completion of work was extended till
30.06.1975. Again the respondent wrote to the appellant informing it that the
work will not be completed even by 30.06.1976 and that it is impossible for
them to carry out the work as per the original agreement, unless the rates are
revised and on 30.06.1975, the work was abandoned by the respondent. Again a
request was made for further extension of time and the time was also extended
for completion of the work till 31.12.1975. The respondent stated that they
were prepared to continue the work only if the rates are revised. The appellant
further extended the time for completion of the work till 31.03.1976.
-
Since disputes arose between the parties, the respondent invoked the
arbitration clause in the agreement and appointed Sri.P.S.Subramaniam as their
Arbitrator. The appellant appointed Sri.C.K. Sreenivasan as their Arbitrator.
Both the Arbitrators appointed Hon'ble Mr.Justice K.S.Palaniswamy, a retired
Judge of the High Court as their umpire. The arbitrators entered upon the
reference on 18.03.1978. The statement of claim of Rs.13,92,00,478.17 was also
filed by the respondent before the Arbitrators. The appellant Board also made a
claim of Rs.50,29,63,320/- filed before the Arbitrators.
-
The learned Arbitrator Sri.P.S.Subramaniam gave an award in favour of the
contractor for a sum of Rs.6,98,54,780/-. However, the other Arbitrator,
namely, Sri.C.K.Sreenivasan gave notice of his disagreement to the award.
Therefore, on 02.04.1979, the Umpire entered upon the reference. The Umpire
passed his award, inter alia, holding that the respondent-contractor is
entitled to Rs.40,02,591/- from the appellant and that after allowing deduction
for the same the respondent is liable to pay to the appellant a sum of
Rs.2,69,93,674/- with interest at 9% p.a. from the date of the Award. Out of
the said Award only a sum of Rs.5,000/- was awarded as damages for breach of
contract.
-
The Umpire filed the Award in the
High Court of Madras and the same was numbered as O.P.No.428 of 1979. The
appellant filed Application No.560 of 1980 in O.P.No.428 of 1979 praying for a
decree to be passed in terms of the Award. Aggrieved by the Award, the
respondent filed O.P.No.122 of 1980 before the High Court for setting aside the
aforesaid Award dated 10.09.1979. The learned Single Judge allowed O.P.No.122 of
1980 filed by the respondent and set aside the award passed by the Umpire and
consequently application No.560 of 1980 in O.P.No.428 of 1979 and O.P.No.428 of
1979 were dismissed. On the same day, C.S.No.176 of 1978 was also dismissed.
Aggrieved by the order allowing O.P.No.122 of 1980, the appellant preferred an
appeal in O.S.A.No.248 of 1989 and aggrieved by the order dismissing Application
No.560 of 1980 in O.P.No.428 of 1979, the appellant herein preferred an appeal
in O.S.A.No.59 of 1993. Aggrieved by the order dismissing C.S.No.176 of 1978,
the appellant herein preferred an appeal in O.S.A.No.211 of 1990.
-
The Division Bench allowed O.S.A.Nos.248 of 1989 and 59 of 1993,
preferred by the appellant, inter alia, holding that the respondent had stopped
work without any cause, that the respondent had abandoned the work, that the
award amount arrived at by the Umpire is correct and, therefore, passed a
decree in terms of the Award dated 10.09.1979 passed by the Umpire. It was
further held that the appellant is entitled to costs throughout and to interest
at 9% p.a. from the date of Award.
-
Aggrieved by the aforesaid order, the respondent herein preferred Special
Leave Petition (Civil) Nos.2096-2097 of 2002. The Division Bench dismissed
O.S.A.No.211 of 1990. The Special Leave Petition (Civil) Nos.2096-2097 of 2002
were filed which were re- numbered as Civil Appeal Nos.9136-9137 of 2003 and
this Court remitted the matter to the Division Bench of the High Court to be
considered in the light of the observation made in the paragraph 16 of the
Judgment. [Sathyanarayana Brothers (P) Ltd. vs. T.N.Water Supply & Drainage
Baord, reported in (2004) 5 SCC 314]. On remission, the Division Bench
dismissed the appeals holding that foreign exchange was to be obtained by the
joint efforts of the appellant and the respondent, that the Government was not
extending the time reasonably but in piecemeal, that the respondent had not
committed breach of contract.
-
Aggrieved by the order dt.24.03.2004,
the appellant preferred the above appeals.
-
It is also pertinent to notice that the SLP filed by the respondent-contractor
against the very same judgment was also dismissed by this Court at the
admission stage.
-
Before dealing with the matter on merits, it is beneficial to refer to
the order passed by this Court in Sathyanarayana Brothers (P) Ltd. vs. T.N.Water
Supply & Drainage Baord, reported in (2004) 5 SCC 314. This Court after an
elaborate consideration of the entire materials placed before it held that the
learned Single Judge has given it as one of the reasons to hold that it
vitiated the award.
The Division Bench was of the view that the learned Single Judge was right
in inferring that such an infirmity would vitiate the award. However, this
Court held that the order of the Division Bench, reversing the decision of the
Single Judge was not sustainable and the matter be required to be remitted to
be considered in the light of the "handing over note" of the Chief
Engineer in respect whereof an application was moved by the appellant before
the Arbitrator as well as before the Umpire which remained unattended to by the
forum and which later did not accede to the request. Considering the fact that
it is an old matter and it being a speaking award, the matter having also been
considered by the learned Single Judge, this Court felt that it would better serve
the ends of justice to ensure expeditious disposal of the matter and,
therefore, the Division Bench of the High Court was requested to consider the
matter afresh taking into account the "handing over note" of the
Chief Engineer of the project and other relevant documents. In the result, this
Court allowed the appeals filed by the contractor-Sathyanarayana Brothers (P)
Ltd.- and set aside the order of the Division Bench of the High Court and
remitted the matter to the High Court for being decided afresh by the Division
Bench in the light of the observations made in the Judgment.
-
We have carefully perused the order
passed by the Division Bench in O.S.A.Nos.248 of 1989 and 59 of 1993 after
remittance.
After hearing extensive arguments advanced by Mr.Mohan Parasaran, learned
ASG and countered by two learned senior counsel appearing on behalf of the
respondent, we are of the view that on remand, the learned Judges of the
Division Bench have considered the entire matter afresh and came to the
conclusion that the reasons recorded in the said Judgment and that the
sustainability of the claims of the contractor need not be considered in these
appeals and equally the Board is also not entitled to any decree on the basis
of the Award for the reasons given in the said Judgment. It was also further
observed that the Bench was not dealing with the respective claims of the
contractor and the Board against each other on different headings and they were
inclined to set aside the award passed by the Umpire.
-
In the instant case, the appellant is
still proceeding under a false premises that the contractor is solely
responsible for the delay in the execution of the work and the breach of
contract which have been conclusively found against the appellant by the learned
Single Judge as well as the Division Bench of the High Court while setting aside
the award passed by the Umpire in the present case. The appellant has not raised
any substantial question of law that needs to be considered by this Court. The
questions raised are only question of fact and in view of the concurrent
findings by both the learned Single Judge and the Division Bench, no
interference by this Court is called for particularly when a matter was fully
heard in the earlier round by the Supreme Court. The matter was remitted to the
Division Bench of the High Court by this Court only after considering all
aspects and the questions involved in the case.
Now, it has been conclusively found that the respondent-contractor was not
responsible for any breach of contract. According to the contractor, all the
advances were granted only for the mobilization of the work with specific
condition that pro-rata deductions will be made in the bills for the work
carried out by the contractor and now the completion of the contract the
advances will be adjusted from the bills for the dues to be paid to the
contractor.
-
As already noticed, the appellant has not raised any ground that warrants
interference with the impugned judgment. The High Court, in our opinion, has
decided the matter strictly in accordance with the remand order made by this
Court in the judgment in Civil Appeal Nos.9136-9137 of 2003 reported in [(2004)
5 SCC 314]. The High Court also has not entered into any finding regarding the
respective claims of the parties but set aside the award of the Umpire only on
the ground of legal mala fides.
-
In our opinion, the well-considered
judgment rendered by the High Court on remission from this Court does not call
for any interference. We, therefore, affirm the order passed by the Division
Bench and dismiss the Civil Appeal Nos.2880-2881 of 2005 filed by the appellant.
-
We also make it clear that if any claim survives with reference to this
particular contract, the parties will be free to agitate the same before the
sole Arbitrator in terms of the Arbitration Clause. For the said purpose, we,
by consent of both parties, appoint Hon'ble Mr.Justice S.Mohan, a retired Judge
of this Court as the sole arbitrator. The parties are at liberty to file any
claim if it survives and also documents, records etc. The sole arbitrator is
requested to dispose of the arbitration proceedings within six months from the
date of entering upon the reference.
-
The Arbitrator is at liberty to fix
his remuneration and other expenses to be equally shared by both the appellant
and the respondent.
-
The Arbitrator should file his Award
in this Court.
-
The Civil Appeals stand dismissed. No
costs.
Back
Pages: 1 2