Haryana
State Industrial Development Corporation Vs. M/S Cork Manufacturing Co [2007] Insc
866 (27 August 2007)
Tarun
Chatterjee & P.K. Balasubramanyan
CIVIL
APPEAL NO. 3940 OF 2007 (Arising out of SLP(C) No.11683 of 2006) P.K.
BALASUBRAMANYAN, J.
1. Leave
granted.
2. The
defendant in Suit No. 8 of 1995 in the court of Senior Sub-Judge, Gurgaon is
the appellant in this appeal. The appellant allotted plot No. 259 on 12.3.1986
to the respondent through its sole proprietor Om Prakash Saharan. The approximate
area of the plot is 1000 square meters and the tentative price was Rs. 1,20,000/-.
On 12.2.1988, a formal agreement was entered into between the parties.
According to the agreement, the allottee had to start construction of a
building for the setting up of an industrial unit within a period of three
months and had to complete the construction within one and half years from the
date of issue of the letter of allotment. The construction had to be completed
and the installation of the machinery had also to be completed and the
commercial production was to be started within a period of two years from the
date of allotment. The Agreement also provided that failing compliance with the
above condition by the allottee, the plot was liable to be resumed and 10% of
the cost of the plot deposited by the allottee at the time of allotment was
liable to be forfeited. The letter of allotment was issued on 24.12.1987. The allottee
did not fulfil the condition of starting commercial production within two years
of the letter of allotment. This fact is not in dispute. The appellant
thereupon issued various notices to the allottee. On 19.7.1991, the allottee
requested for extension o time. That request was rejected.
On
13.9.1991, according to the appellant, the appellant issued an order of
resumption which specifically referred to the contravention of the terms and
conditions of allotment by the allottee. According to the appellant, possession
was taken back on 20.9.1991. The plot was thereafter re-allotted to M/s
Insulation & Electrical Products (P) Ltd., New Delhi on 2.4.1992. Since that allottee also did not fulfil the
conditions, the said allotment was cancelled on 6.1.1994.
3. The
respondent, the plaintiff, filed an application for referring the dispute to
Arbitration. The same was rejected. Respondent then approached the Consumer
Forum, but that complaint was also dismissed.
4. On
5.10.1995, the respondent filed the present suit No. 8 of 1995 for a permanent
injunction restraining the defendant appellant from interfering, disturbing or
in any manner tampering with the possession of the plaintiff over the plot in
dispute, and restraining the defendant appellant from re-allotting the plot in
question to any other person on the basis of the resumption order, if any, or otherwise.
Though there was no prayer regarding any resumption order, it was asserted that
the resumption order, if any passed by the defendant was void, illegal, non-est
and not binding upon the plaintiff in any manner.
A
decree for mandatory injunction directing the defendant appellant to remove an
existing high-tension wire going over the plot in question and also to remove
an electrical pole existing in the plot and to make available the plot free
from all kinds of hindrances for raising the construction was also prayed for.
The plaint was signed by one Uma Shankar who was said to be a power of attorney
of the plaintiff firm. The plaint proceeded on the footing that there was also
an agreement between the parties that the electric pole located in the plot
would be got removed by the appellant and it was in view of the failure of the
appellant to get it done, that the construction could not be started by the
plaintiff. It was also admitted in the plaint that there might have been an
order of resumption of the plot, but if there was any such order, it was
illegal, void and ineffective and not binding on the rights of the plaintiff
because of lack of opportunity of hearing given to the plaintiff. The plaint
proceeded to state that the defendant was threatening to dispossess the
plaintiff pursuant to that order of resumption; that the plaintiff was in
possession and that the plaintiff was entitled to relief as claimed.
5. The
defendant filed a written statement contending that the plot in question was
resumed on 13.9.1991 in view of the plaintiff contravening the terms of the
allotment and possession was taken back on 25.9.1991. The plot had been
re-allotted to another concern. The plaintiff had neither any right over the
plot in question nor any possession over the same. Since the plaintiff had
defaulted, the plot had been rightly resumed.
There
was no stipulation or condition in the allotment that the appellant had the
obligation to remove the electric post located in the plot or the overhead
electrical line. The plaintiff was not in posssession. The suit was liable to
be dismissed.
6. On
behalf of the plaintiff, one Jai Bhagwan was examined as P.W. 6. He gave
evidence to the effect that the plot in dispute was allotted to Om Parkash
Saharan.
He had
been appointed as General Power of Attorney by the said Om Parkash Saharan on
9.4.1996. Om Parkash Saharan was the sole proprietor of the business of the
plaintiff company. Obviously, this witness who entered the picture by virtue of
a power of attorney executed on 9.4.1996, was not a party to any of the things
that had taken place prior to the grant of power of attorney in his favour and
had no knowledge of them. Om Parkash Saharan in whose name the allotment was
made did not go to the box. In the box, P.W. 6 admitted that the company had
received the letter warranting of the proposal to resume the plot because of
its failure to fulfil the condition of allotment. He stated that because of the
high-tension wire passing over the plot in dispute, it was not possible to
raise construction thereon. He admitted that one week prior to the institution
of the present suit, the plaintiff came to know that defendant had resumed the
plot in dispute and had also prepared a report that possession had been taken
back. He asserted that the plaintiff had not surrendered the possession of the
suit property and the plaintiff was in possession till date. He stated that
letters sent intimating the proposal to resume the plot were illegal and void.
No opportunity of hearing was afforded prior to the resumption of plot in
dispute.
He
admitted that the defendant had issued Exhibit PW4/11 letter to Om Parkash
Saharan, but no payment was made by Saharan in pursuance thereof. He stated
that he knew Om Parkash Saharan since 1983. He admitted that the allottee had
to start construction within two years from the date of allotment. He admitted
that within the prescribed period, no construction was raised but claimed that
that was because of the passing of the high-tension wire over the property. He
denied the suggestion that the plot was resumed on 13.9.1991 and possession was
taken on 25.9.1991. He pleaded ignorance of the fact that the plot in question
was re- allotted to another Om Parkash, son of Arjan Lal and that possession
had been given to him since 2.9.1994. He denied the suggestion that he was
aware at the time of execution of the Power of Attorney in his favour that the
plot in dispute was re-allotted to Om Parkash son of Arjan Lal. He pretended
ignorance of the filing of a complaint in the District Consumer Forum earlier
by the plaintiff and about the dismissal of the same. He also pretended
ignorance of the fact that a petition under the Arbitration Act was filed by
the plaintiff and that was also dismissed.
But,
he admitted that no construction was started by the time the suit was filed. He
denied the suggestion that he had no right to file the present suit. The power
of attorney in his favour was marked as PW6/1.
7.
Letter PW-4/5 produced by the plaintiff and proved through P.W. 4 examined on
behalf of the plaintiff, was a final show cause notice given to the plaintiff company
on its failure to set up an industrial unit in the plot in question. In that
notice, after informing the plaintiff that no further extension of time was possible,
the plaintiff was called upon to show cause within a period of 35 days from the
date of issue of that letter as to why the plot allotted to the plaintiff be
not resumed on account of the failure of the plaintiff to set up the unit
within the extended period. The plaintiff was informed that in case no
satisfactory explanation was received within the period specified, the
Corporation would be constrained to resume the plot without making any further
reference to the plaintiff. Exhibit PW4/16, the letter dated 1.4.1991 sent in
reply to the above letter dated 4.3.1991 after acknowledging the threat of
resumption stated that the plaintiff was quite eager and sincere in its desire
to set up an industrial unit but since Shri Om Parkash Saharan, who signed the
letter, was under severe stress and strain due to a serious accident which made
him almost incapacitated for a long period, he could not take effective steps
to undertake the work, and that the plaintiff hoped to take up the work and
complete it in four months and praying that some more time may be allowed for
that purpose. It is also seen from an earlier letter PW 4/6 dated 27.3.1991,
that the appellant had specifically brought to the notice of the plaintiff that
the plaintiff had contravened the terms of the agreement by not taking up the
construction and calling upon the plaintiff to show cause within 35 days why
the plot of land should not be cancelled. This was followed by PW4/9 dated
15.9.1991 conveying the decision of the appellant to resume the plot for
non-compliance with the terms of allotment. Thus the correspondence marked on
the side of the plaintiff itself clearly indicated that the plaintiff had been
given notice of the resumption for failure of the plaintiff to fulfil the terms
of the allotment. The correspondence produced by the plaintiff also indicates
that there was no stipulation outside the terms of the written allotment letter
about any promise of removal of any electrical pole or electrical line passing
over the plot in question. Otherwise, that would have been mentioned in Ex.
PW4/16 dated 1.4.1991.
8. The
case tottered out on behalf of the plaintiff in the trial court was that the
authorities had agreed to have the electrical pole removed from the plot and
since it was not removed, the work could not be started. This is not reflected
by the written allotment letter. In other words, there is no term therein to
that effect. Such a claim is also belied by the letters written by the
plaintiff which have been marked on the side of the plaintiff as exhibits and
reference to one of them has been earlier made. Some correspondence with some
officers of the appellant regarding the removal of the electric pole was relied
on to say that outside the written agreement, the appellant had agreed to get
the electric pole and overhead line removed.
There
was also no evidence to prove the possession claimed by the plaintiff as on the
date of suit.
9. In
spite of such glaring factors emerging, the trial court proceeded to accept the
story of the plaintiff that it had not been given notice of the resumption of
the land and that it continued to be in possession and that there was a
condition for removal of the electric pole and the electrical line and since
the pole and the line were removed only by 30.11.1995, the plaintiff had time
to take up the project thereafter. I must say that the decision of the trial
court shows total lack of application of mind and non consideration of the
pleadings and the evidence in the case. The suit was thus decreed declaring the
resumption order dated 13.9.1991 illegal and against the principles of natural
justice and setting it aside, a relief that does not even seen to be sought in
the plaint. The lower appellate court also toed the line of the trial court and
dismissed the appeal, again, without proper advertence to the relevant
materials available in the case and even without adverting to the fact that
P.W. 6, the power of attorney holder had no knowledge of what had transpired
earlier even on his own showing and that the original grantee Om Parkash
Saharan had not even come forward to speak to the case of the plaintiff. The
appeal was dismissed by the Appellate Court. I must say that as a court of
first appeal and as the final court of facts, the Appellate Court had a duty to
reappraise the entire material to decide the points arising and the appellate
court in this case has miserably failed to perform its duty.
10.
The defendant filed a Second Appeal. Along with the Second Appeal, since the
plaintiff had pretended ignorance of the order of resumption, on behalf of the
defendant, a legal notice sent by counsel for the plaintiff was also produced
by way of additional evidence by invoking Order 41 Rule 27 of the Code of Civil
Procedure.
We
must say with regret that the Second Appellate Court without any application of
mind ---- in fact it pains me to record out of my experience in this Court for
three years, that the particular High Court is disposing of Second Appeals in
such a cavalier manner that nothing else is needed to bring discredit the
system itself --- rejected the Second Appeal by stating that no substantial
questions of law arose in the Second Appeal. This was after dismissing the
application filed under Order 41 Rule 27 of the Code, I get the impression,
even without trying to understand what the suit is for, what was the nature of
disposal of the suits by the courts below and what that document implied and
what it established. The decree thus granted is under challenge before us.
11.
Learned counsel for the appellant submitted that it was not a condition of the
grant or allotment, that the appellant would get removed an existing electric
pole or electric wire passing over the property before handing over possession
to the respondent. It is pointed out that the plaintiff had unconditionally
taken possession pursuant to the allotment. Learned counsel pointed out that
the written letter of allotment does not contain any such stipulation, on the
other hand it contained a clear stipulation that the allottee had to complete
the entire construction and start the commercial production within two years
from the date of issue of the letter of allotment.
Learned
counsel further pointed out that even the letters on the side of the plaintiff
seeking extension of time did not put forward any such claim and what was put
forward was only the incapacitation of the proprietor of the plaintiff and the
consequent delay in starting the construction. Learned counsel further pointed
out that P.W. 6 examined as the power of attorney of the plaintiff, came into
the picture only in the year 1996 and had no knowledge of things that
transpired in the year 1991 when the allotment was cancelled, the resumption
order was passed and the land was resumed. Om Parkash Saharan who was the eo
nominee allottee, had not even gone to the box to speak about the letters
relating to the failure of the plaintiff to fulfil the conditions of allotment
and speak about the so called absence of knowledge about the order of
resumption. Learned counsel submitted that it was in that context that the
original notice sent by one P.
Bhaskaran,
Advocate on behalf of the plaintiff to the appellant defendant was sought to
be produced in the Second Appeallate Court so that the conscience of the court
may be satisfied in that regard since the said notice clearly acknowledged the
letter conveying the factum of the resumption of the plot allotted to the
plaintiff by the appellant. Learned counsel submitted that the High Court was
clearly in error in rejecting the application under Order 41 Rule 27 even
without applying its mind as to the purpose for which the said document was
produced and the need for that document for rendering a decision more
satisfactory to the conscience of the Court and without even properly
understanding the scope of Section 100 of Code of Civil Procedure and the duty
a Second Appellate Court is called upon to perform. Learned counsel pointed out
that even a finding of fact ignoring vital documents or without advertence to
the relevant evidence and without asking itself the relevant questions, was a
finding that was not binding on a Second Appellate Court under Section 100 of
the Code. Learned counsel pointed out that there was no evidence of the
possession being with the plaintiff as on the date of the suit and even the
local Commissioner's report taken at the instance of the plaintiff showed that
the land was lying vacant. The appellant had allotted the land to another
person though it had to be resumed again because of failure of that person to fulfil
the terms of the allotment to him. The decree for injunction in favour of the
plaintiff restraining the appellant from interfering with the so called
possession of the plaintiff was clearly a decree not supported by the necessary
finding required under law and a relief granted, unsupported by the necessary
finding based on evidence in that behalf, clearly amounted to the lower
appellate court making a substantial error of law warranting correction by the
High Court in Second Appeal.
Learned
counsel submitted that the relief of declaration granted was also unwarranted
in the nature of the reliefs claimed in the plaint.
12. On
behalf of the respondent plaintiff, it was contended that the understanding
was that the electric pole and the overhead electric lines will be got removed
by the defendant Corporation and since that was not done till the year 1995,
there was no default on the part of the plaintiff. The High Court was justified
in not admitting fresh evidence in Second Appeal since the defendant had the
opportunity to produce the same before the trial court.
Learned
counsel also submitted that the finding of possession was a finding of fact and
the High Court was justified in not interfering with the same. Learned counsel
submitted that there is no reason to interfere with the decree passed in the
case.
13.
The plaintiff had come forward with a dubious case regarding the order of
resumption of the plot in question. There was clearly a default on the part of
the plaintiff in complying with the requirement of putting up an industry in
the plot and starting commercial production within two years of allotment. The
excuse put forward by the plaintiff for not doing anything in the plot was the
existence of a electric pole and overhead electric wires, which stood in the
way of the construction. It was the further case of the plaintiff that it was
for the defendant Corporation to have got them removed while delivering
possession of the plot. We find from the written instrument of allotment, that
there was no such stipulation therein. Having accepted the allotment on its
basis and taken possession of the plot, it is not open to the plaintiff to
raise a contention based on some other subsequent understanding between the
plaintiff and some of the officers of the defendant or outside the agreement.
In
fact, in the letter PW4/16, when such a case if true, should have been put
forward, such a case is not put forward. There is also no evidence of any
subsequent agreement in that regard. Merely because the officers of the
appellant were induced to write letters regarding removal of the pole long
after the resumption does not establish any such condition of allotment.
14.
The plaintiff's plea that it was not aware of the order of resumption is belied
by the letters marked on its side through PW4 and the admission of PW6. These
letters clearly show that the plaintiff was given notice of the resumption and
was informed that if he did not comply with the requirement and sent
satisfactory reply, the land will be resumed without any further notice within
the time stipulated therein. Thus obviously, adequate notice and adequate
opportunity was given to the plaintiff before the order of resumption was
passed. The non- examination of Om Prakash Saharan was fatal to the case of the
plaintiff under the circumstances. The courts below acted perversely in
entering a finding that the order of resumption was illegal and was not binding
on the plaintiff. I find that the courts below have not adverted to the
relevant materials available. Moreover, it is seen that P.W.6, who is examined
on behalf of the plaintiff came into the picture only in the year 1996 and was
not a competent witness to speak about anything that transpired in the year
1991 and that the original allottee Om Parkash Saharan had not even come
forward to give evidence on behalf of the plaintiff. It was a clear case for
drawing an adverse inference against the plaintiff for non examination of Om Parkash
Saharan. These vital aspects have been ignored by the trial court and by the
first appellate court when they purported to find that the order of
cancellation was not binding on the plaintiff. I am of the view that a finding
ignoring legal evidence available in the case and ignoring the inferences to be
drawn from the circumstances established, is a finding that can only be
described as perverse and such a finding is not binding on a Second Appellate
Court under Section 100 of the Code.
In
fact, it compels interference by the Second Appellate Court. The High Court has
unfortunately not adverted to anything relevant and was incorrect in thinking
that the findings of fact are not liable to be interfered with in the case on
hand. At least, it should have seen that parole evidence to alter the terms of
a written instrument was not permissible and the fact that the courts below had
relied on such evidence justified interference by the High Court in Second
Appeal.
15.
Same is the position regarding the finding on possession. The correspondence
with the Electricity Board does not establish that the plaintiff continued to
be in possession notwithstanding its default and the order of resumption with
notice to the plaintiff. . The evidence of P.W. 6 is not evidence at all of
possession of the plaintiff as on the date of the suit or of possession
subsequent to 1991. There is no evidence to show that the plaintiff Om Parkash
Saharan, the allottee continued in possession until the power of attorney was
executed in favour of P.W. 6. The suggestion to P.W. 6 that he was aware of the
resumption and re-allotment to another entity when he filed the suit, is a
justifiable suggestion on the facts of this case. The finding on possession is
also found to be based on no legal evidence and consequently infirm and liable
to be interfered with by this Court as it should have been interfered with by
the Second Appellate Court.
16. I
am also of the view that the Second Appellate Court was clearly in error in
refusing to admit in evidence the notice sent on behalf of the plaintiff by its
advocate to the defendant. It must be noticed that not even an objection was
filed on behalf of the plaintiff to the application under Order 41 Rule 27 of
the Code denying the issue of such a notice. There was no denial of the status
of the counsel who had issued the notice on behalf of the plaintiff. There is a
presumption that when an Advocate sends a notice on behalf of a client, the
notice is sent by him on instructions from his client. The plaintiff had no
case before the High Court that it had not instructed the concerned counsel to
send such a notice.
After
all, the purpose for which the notice was produced was only to show that the
plaintiff was aware of the resumption made in the year 1991 and the specific
acknowledgement of receipt of the concerned letters in that behalf. Even
otherwise, the letters produced at the trial do indicate that the plaintiff was
aware of the resumption of the plot. Therefore, this was a case where the
document produced under Order 41 Rule 27 of the Code was required to enable the
High Court to pronounce a judgment more satisfactory to its conscience
constituting other sufficient cause within the meaning of Order 41 Rule 27 of
the Code for production of additional evidence. The authenticity of the notice
had not been questioned by filing an objection and the High Court was therefore
in error in thinking that it was not a document which could be straight away
accepted.
17.
Thus, on the whole, I am satisfied that the plaintiff had not made out any case
for relief in the present suit. The judgments of the courts below therefore
call for interference. I am satisfied that the appeal deserves to be allowed.
If the decree now passed is not set aside, I apprehend that I would be failing
in my duty exercising jurisdiction under Article 136 of the Constitution of
India. After all, the jurisdiction of this Court is a corrective jurisdiction
and not a restricted one.
18.
The appeal is therefore allowed. The judgments and decrees of the courts below
are set aside and the suit filed by the plaintiff is dismissed with costs
throughout.
19.
During the course of the hearing, the defendant -- appellant offered that the
plot could be allotted afresh to the plaintiff, if the plaintiff was willing to
pay the price at the rate of Rs.13,000/- per square meter which is the current
rate. The plaintiff was not willing to pay that price. But learned counsel for
the plaintiff contended that the plaintiff had, obviously subsequent to the
decreeing of the suit, had put up a construction in the property. It is obvious
that on the date of suit, there was no construction. The Local Commissioner's
report establishes that and the evidence of P.W. 6 also indicates that. In that
situation, taking note of the circumstances, I think it proper to give the
plaintiff an opportunity to have the land allotted to it afresh, on its paying
a price for the plot at the rate of Rs.10,000/- per square meter. In other
words, if the plaintiff respondent pays to the defendant appellant, the price
of the plot at Rs.10,000/- per square meter within four months from today,
there will be a fresh allotment of the plot by the defendant to the plaintiff.
While
calculating the amount, the plaintiff will be entitled to adjust any sum that
might have been paid towards the allotment of the plot originally made in the
year 1987 and it need only pay the balance amount. In case, the price at the
rate of Rs.10,000/- per square meter is not paid by the plaintiff to the
defendant within a period of four months as stipulated above, the defendant
would forthwith take physical possession of the land and report that fact to
the trial court by way of the affidavit and deal with the plot in accordance
with law.
20.
Before leaving this case, I think it necessary to issue a direction and to make
an observation. The direction is to the appellant to initiate action against
those officers who were dealing with the cancellation of the allotment and
taking possession of the property, and more particularly those who were in
charge of the litigation and who failed to produce vital documents including
the notice issued on behalf of the plaintiff that was sought to be produced in
Second Appeal. It is absolutely necessary to take such action in the interests
of the appellant, the citizens and the State since it should not be forgotten that
the appellant is a trustee of public property and is expected to deal with it
as a trustee with all care and caution. The second is to exhort the trial
courts, the first appellate courts and the second appellate courts in the State
to show better application of mind while deciding a lis keeping in mind that
what they are performing is a divine function that is onerous and at the same
time challenging. I am making these observations regarding the courts in the
concerned State since for the last three years I have been noticing with regret
the lack of application in many a case that had come before this Court.
Back
Pages: 1 2