Food
Corporation of India Vs. M/S.Chandu
Construction & Anr [2007] Insc 379 (10 April 2007)
TARUN CHATTERJEE & D.K. JAIN
CIVIL APPEAL NO. 1874 OF 2007 [Arising out of S.L.P. (Civil) No. 3335 of
2006) D.K. JAIN, J.:
Leave granted.
2. Challenge in this appeal, by the Food Corporation of India (for short
"FCI"), is to the final judgment and order dated 14th October, 2005
passed by the Division Bench of the High Court of Judicature at Bombay,
affirming the judgment of the learned Single Judge in Arbitration Petition
No.334 of 2004. By the impugned order, the award of an amount of Rs.8,23,101/-
by the sole arbitrator against claim No.9 has been upheld.
3. A brief factual background giving rise to the appeal is as follows:
The FCI undertook construction of godowns at Panvel, District Raigad and
issued notice inviting tenders for construction of 50000 MT capacity
conventional godowns in 10 units alongwith ancillary work and services.
Pursuant thereto, the respondents (hereinafter referred to as the claimants) submitted
tender, which was accepted by the FCI. A formal contract was executed between
the FCI and the claimants on 19th September, 1984. As per the terms of the
contract, the work was to be completed within 10 months from 30th day of issue
of the orders and the time was deemed to be of the essence of the contract.
4. As the claimants could not complete the work within the stipulated time,
which was once extended, the FCI issued a show cause notice to them seeking to
terminate the contract. Ultimately the contract was terminated vide order dated
15th November, 1987. The claimants invoked the arbitration agreement and
requested the FCI to appoint an arbitrator. Since there was no response from
the FCI, the claimants filed a suit in the High Court for appointment of an
arbitrator. An arbitrator was appointed, who gave his award on 27th August,
1998. As payment in terms of the award was not made, the claimants again moved
the High Court. The FCI, in turn, filed a petition in the High Court for
setting aside of the award. With the consent of parties, the award was set
aside and the matter was remitted to the Arbitrator for fresh adjudication.
5. In fresh proceedings before the Arbitrator, the stand of the claimants,
qua Claim No.9 was that the rate quoted by them for filling the plinth under
floors including watering, ramming, consolidation and dressing in terms of item
No.1.7 of the Schedule of rates was only for labour and did not cover
"providing or supplying" sand for the said purpose and yet they were
required to supply sand for filling. As such the claimants were entitled to be
paid extra for supply of sand. Accordingly, they made a claim of Rs.8,23,101/-
for providing and supplying 5487.34 cubic meters of sand.
6. The claim was resisted by the FCI on the ground that the scope of work,
specifications and the item rates was governed by the terms of the contract and
as per clause (2) of the agreement dated 19th September, 1984, the claimants
were to be paid the "respective amount for the work actually done by him
at the 'Schedule of rates' as contained in the appended Schedule and such other
sums as may become payable to the contractor under the provisions of this
contract". The contract clearly stipulated that the work was to be carried
out as per specifications contained in Volume I and II of C.P.W.D.
manual, para 2.9.4 whereof provided that the "Rate"
includes the cost of materials and labour. Therefore, the claimants were not
entitled to any extra amount for supply of sand. The arbitrator gave his award
on 31st December, 2003 accepting the said claim. For reference, the relevant
portion of the award is extracted below:
"According to defence under the provision of 1967 CPWD specification
Vol.I & II, the nature of the item includes sand also and not merely the
labour charges, similarly the rate of sand filling is for consolidated
thickness or loose thickness or voids to any extent and this claim is denied
into to. Now here the dispute between the two parties is over the words
supplying and providing and in respect of this item the particular words are
missing whereas as observed earlier they were being found in respect of certain
other items. According to the Claimants since these words were missing in
respect of this item of work, they took it that the material i.e. sand would be
supplied and, therefore, they quoted only the labour rate. The tender of M/s
Gupta and Co. as pointed out to me, shows that in respect of this item of work,
these words providing and supplying were used. It is submitted that there can't
be two different phrapavlogies in respect of the same item and as observed
earlier, nothing prevented the FCI from using those words and not giving rise
of any confusion. Comparative statement showing contents and details of
schedule items based on tender working with PWD Bombay which clearly provides
for rates for quantity of work for schedule items. The Claimants here are
trying to establish that their quotations were based without including the cost
of materials supplied. If we see the figures in respect of the items, we find
substantial force in the say of Claimants that the rate quoted by them is so
low that it could not be in respect of price inclusive of cost of sand. If we
see the wording of specification with Contractor M/s. Gupta & Co., we find additional
words supplying and providing have been added under similar items of the
schedule. Why these words were missing in case of Claimants is difficult to
follow.
The Respondents content that 1967 CPWD's specification in Vol.I & II
covers the specifications not only for labour charges but also for providing
and supplying of the materials required. It is very difficult to understand
this defence, for if we look at the figures quoted in the tenders it would make
it absolutely clear that the inclusion of cost of sand could not have to be in
the mind of the Contractor Claimants. The figures are very low and I may be
permitted to say that these figures do not cover the cost of sand. There is
force in the say of the Claimant that he did not vouch that he himself was to
supply sand. Of course, I must say that there is no very satisfactory evidence
about the quantity of sand used, its price and amount paid by the claimant to
his suppliers but when the work was done the FCI was bound to take upon it to
make the payment though it may appear to be somewhat arbitrary. I allow this
claim of 8,23,101/- (Rupees Eight lacs twenty three thousand and one hundred
and one only)."
7. Being aggrieved, the FCI filed objections against the award under Section
30 of the Indian Arbitration
Act, 1940
praying for setting aside of the award on claim no.9, but without any success.
The learned Single Judge affirmed the view taken by the Arbitrator that the
rate quoted by the claimant did not include the cost of the material. The FCI
carried the matter in appeal before the Division Bench. Before the Division
Bench, the FCI also attempted to raise the issue of award of interest by the
Arbitrator, which was not permitted on the ground that the issue was neither
taken up before the Arbitrator nor was raised before the learned Single Judge.
As noted above, the Division Bench has dismissed the appeal.
Hence, the present appeal.
8. Learned counsel for the petitioner has submitted that the claim for
supply of sand against Claim No.9 was patently opposed to the terms of the
contract between the parties. It is urged that the relevant clause of the
contract is clear, unambiguous and admits of no such interpretation as has been
given by the arbitrator. It is, thus, pleaded that the arbitrator has
misconducted himself in awarding additional amount of Rs.8,23,101/- in favour
of the claimants, which part of the award deserves to be set aside.
9. On the other hand, learned counsel for the claimants submitted that it
was within the domain of the arbitrator to construe the terms of contract in
the light of the evidence placed on record by the claimants, particularly the
terms of similar contracts entered into by the FCI with the other contractors.
It is asserted that the view taken by the arbitrator being plausible the High
Court was justified in declining to interfere with the award.
10. While considering objections under Section 30 of the Arbitration Act,
1940 (for short 'the Act"), the jurisdiction of the Court to set aside an
award is limited.
One of the grounds, stipulated in the Section, on which the Court can
interfere with the award is when the arbitrator has 'misconducted' himself or
the proceedings.
The word "misconduct" has neither been defined in the Act nor is
it possible for the Court to exhaustively define it or to enumerate the line of
cases in which alone interference either could or could not be made.
Nevertheless, the word "misconduct" in Section 30 (a) of the Act
does not necessarily comprehend or include misconduct or fraudulent or improper
conduct or moral lapse but does comprehend and include actions on the part of
the arbitrator, which on the face of the award, are opposed to all rational and
reasonable principles resulting in excessive award or unjust result. (Union of
11. It is trite to say that the arbitrator being a creature of the agreement
between the parties, he has to operate within the four corners of the agreement
and if he ignores the specific terms of the contract, it would be a question of
jurisdictional error on the face of the award, falling within the ambit of
legal misconduct which could be corrected by the Court. We may, however, hasten
to add that if the arbitrator commits an error in the construction of contract,
that is an error within his jurisdiction. But, if he wanders outside the
contract and deals with matters not allotted to him, he commits a
jurisdictional error (see:
Andhra Pradesh and Anr. and Rajasthan State Enterprises & Anr. ).
12. In this context, a reference can usefully be made to the observations of
this Court in M/s. Alopi Parshad observed that the Indian Contract Act does not
enable a party to a contract to ignore the express covenants thereof, and to
claim payment of consideration for performance of the contract at rates
different from the stipulated rates, on some vague plea of equity. The Court
went on to say that in India, in the codified law of contracts, there is
nothing which justifies the view that a change of circumstances,
"completely outside the contemplation of parties" at the time when
the contract was entered into will justify a Court, while holding the parties
bound by the contract, in departing from the express terms thereof. Similarly,
in The Naihati Jute observed that where there is an express term, the Court
cannot find, on construction of the contract, an implied term inconsistent with
such express term.
Madhya Pradesh , it was emphasised that not being a conciliator, an
arbitrator cannot ignore the law or misapply it in order to do what he thinks
is just and reasonable. He is a tribunal selected by the parties to decide
their disputes according to law and so is bound to follow and apply the law,
and if he does not, he can be set right by the court provided his error appears
on the face of the award.
Construction while inter alia, observing that the arbitrator cannot act
arbitrarily, irrationally, capriciously or independent of the contract, it was
observed, thus:
"There lies a clear distinction between an error within the
jurisdiction and error in excess of jurisdiction. Thus, the role of the
arbitrator is to arbitrate within the terms of the contract. He has no power
apart from what the parties have given him under the contract. If he has
travelled beyond the contract, he would be acting without jurisdiction, whereas
if he has remained inside the parameters of the contract, his award cannot be
questioned on the ground that it contains an error apparent on the face of the
record."
15. Therefore, it needs little emphasis that an arbitrator derives his
authority from the contract and if he acts in disregard of the contract, he
acts without jurisdiction. A deliberate departure from contract amounts to not
only manifest disregard of his authority or a misconduct on his part, but it
may tantamount to a mala fide action of Andhra Pradesh & Anr. (supra)].
16. Thus, the issue, which arises for determination, is whether in awarding
Claim No.9, the arbitrator has disregarded the agreement between the parties
and in the process exceeded his jurisdiction and has, thus, committed legal
misconduct?
17. For deciding the controversy, it would be necessary to refer to the
relevant clauses of the contract, which read thus:
"1. GENERAL SPECIFICATIONS:
1.1 The civil sanitary, water supply and road works shall be carried out as
per Central Public Works Department specification of works at Delhi 1967 Volume
I & II with correction slips upto dateIn the case of civil, sanitary, water
supply and road works and electrical works should there be any difference
between the Central Public Works Department specifications mentioned above and
the specifications of schedule of quantities, the latter i.e. the specification
of schedule of quantities, shall prevail. For items of work not covered in the
C.P.W.D. specifications or where the C.P.W.D. specifications are silent on any
particular point, the relevant specifications or code of practice of the Indian
Standard Institution shall be followed.
1.2 Should any clarification be needed regarding the specifications for any
work the written instructions from the Engineer-in-Charge shall be
obtained."
18. Paragraph 2.9.4 of the C.P.W.D. specifications insofar as it is relevant
for the present appeal, reads as follows:
"Rate:- It includes the cost of materials and labour involved in all
the operations described above'."
19. From the above extracted terms of the agreement between the FCI and the
claimants, it is manifest that the contract was to be executed in accordance
with the C.P.W.D. specifications. As per para 2.9.4 of the said specifications,
the rate quoted by the bidder had to be for both the items required for
construction of the godowns, namely, the labour as well as the materials,
particularly when it was a turn key project. It is to be borne in mind that
filling up of the plinth with sand under the floors for completion of the
project was contemplated under the agreement but there was neither any
stipulation in the tender document for splitting of the quotation for labour
and material nor was it done by the claimants in their bid. The claimants had
submitted their tender with eyes wide open and if according to them the cost of
sand was not included in the quoted rates, they would have protested at some
stage of execution of the contract, which is not the case here. Having accepted
the terms of the agreement dated 19th September, 1989, they were bound by its
terms and so was the arbitrator. It is, thus, clear that the claim awarded by
the arbitrator is contrary to the unambiguous terms of the contract. We are of
the view that the arbitrator was not justified in ignoring the express terms of
the contract merely on the ground that in another contract for a similar work,
extra payment for material was provided for. It was not open to the arbitrator
to travel beyond the terms of the contract even if he was convinced that the
rate quoted by the claimants was low and another contractor, namely, M/s Gupta
and Company had been separately paid for the material.
Claimants' claim had to be adjudicated by the specific terms of their
agreement with the FCI and no other.
20. Therefore, in our view, by awarding extra payment for supply of sand the
arbitrator has out-stepped confines of the contract. This error on his part
cannot be said to be on account of misconstruing of the terms of the contract
but it was by way of disregarding the contract, manifestly ignoring the clear
stipulation in the contract.
In our opinion, by doing so, the arbitrator misdirected and misconducted
himself. Hence, the award made by the arbitration in respect of claim No.9, on
the face of it, is beyond his jurisdiction; is illegal and needs being set
aside.
21. Consequently, the appeal is allowed and the impugned judgment of the
High Court, to the extent it pertains to claim No.9 is set aside. However, on
the facts and circumstances of the case, there shall be no order as to costs.
Back
Pages: 1 2