M.P.
Housing Board Vs. Anil Kumar Khiwani [2005] Insc 171 (14 March 2005)
Arijit
Pasayat & S.H. Kapadia
[Arising
out of SLP (Civil) No.22560 of 2004] WITH
CIVIL APPEAL No.1732 OF 2005 [Arising out of SLP (Civil) No.22616 of 2004] M.P.
Housing Board Appellant Versus Kishan Lal Mulani Respondent KAPADIA, J.
Leave
granted.
These
civil appeals by grant of special leave are directed against a common Order
dated 2.7.2004 passed by the High Court of Madhya Pradesh at Jabalpur in M.A.
No.1611 of 2003 and M.A. No.1628 of 2003.
Since
the impugned order is common in both the appeals, the same are jointly disposed
of by this judgment.
For
the sake of convenience, we may mention briefly the facts of Civil Appeal No.
1731 of 2005 [arising out of SLP (C) No.22560 of 2003].
On 18th January, 2000, M.P. Housing Board, appellant
herein, issued an advertisement in local newspaper "Dainik Bhaskar"
inviting offers to subscribe to two schemes floated by the Board, namely, Katara
Hills Residential Scheme and Centre Point Commercial Scheme. In these appeals,
we are concerned with the booking of a showroom in the commercial complex.
According
to the said advertisement, the estimated cost of a showroom and departmental
store in the commercial complex (Centre Point), having built up area of 3550
sq. ft. on the upper ground level, was Rs.39 lacs. The registration amount was
Rs.3.90 lacs i.e. 10% of the estimated cost of Rs.39 lacs. What was proposed to
be constructed was a seven storeyed commercial complex of showrooms, shops,
halls etc. near New Market Stadium, Bhopal. To give publicity to the said schemes, brochures were also
distributed.
On the
basis of the above advertisement, Anil Kumar Khiwani, the respondent herein,
submitted an application in the prescribed form enclosing his cheque for
Rs.3.90 lacs, being 10% of the estimated cost of the showroom. On 25.9.2000, a
temporary registration was made in favour of the said respondent. On the same
date, he was informed in writing that temporary registration stood granted to
him and further particulars would be conveyed to him on a later date regarding
the total consideration. Thereafter, the appellant herein took steps to prepare
a detailed Project Report, which was approved by the Town Planning Authority,
the Municipal Corporation and a Committee known as Building High-rise
Committee. The appellant also called upon the State government to forward the
actual land cost and the lease rent, which the State proposed to charge. The
appellant also called upon the electricity board to forward to them the
estimated strengthening charges. After getting all these informations and
approvals, tenders were invited and after receiving the tenders, the actual
cost was worked out which came to Rs.2000/- per sq. ft.
Accordingly,
by letter dated 27.9.2001, the respondent herein was called upon to give his
consent within one month.
By the
said letter, each of the contributors including the respondent was given an
option to withdraw from the scheme if he did not agree to the proposed actual
cost of Rs.2000/- per sq. ft. The contributors were told to collect the
registration amount with interest @ 8% per annum from the board if they opted
for withdrawal from the commercial scheme, provided they opted for refund by
10.10.2001.
By
letter dated 16.10.2001, the respondent wrote to the board stating that he was
not willing to accept the price nor was he willing to withdraw the registration
amount.
By
letter dated 27.11.2001, the board called upon the respondent to pay an amount
of Rs.71 lacs for the showroom on the upper ground floor admeasuring 3550 sq.
ft. This was objected to by the respondent vide notice given to the board.
Ultimately,
on 29.6.2002, the appellant cancelled the registration and called upon the
respondent to collect the registration amount of Rs.3.90 lacs with interest @
8% calculated up to June
30, 2002.
On
15.7.2002, the present suit was filed for declaration and injunction in the
Court of Additional District Judge, Bhopal (hereinafter referred to as "the trial Court"), being Civil Suit
No.39-A of 2002. In the said suit, an application was moved under order 39
rules 1 & 2 CPC.
By
impugned order dated 22.4.2003, the trial Court prima facie came to the
conclusion that the board was guilty of inordinate delay in the implementation
of the scheme; that the board had demanded almost twice the amount indicated in
the advertisement after accepting the advance and consequently, the board was
restrained from allotting the showroom in question to any other person, till
the final hearing and disposal of the suit.
By the
impugned order, the trial Court permitted the board to call upon the
contributor to deposit Rs.39 lacs in four instalments in terms of the schedule
indicated in the above advertisement.
Aggrieved
by the said decision, the matter was carried in appeal. By the impugned
decision dated 2.7.2004, the High Court dismissed the Miscellaneous Appeal
No.1611 of 2003 as well as Miscellaneous Appeal No.1628 of 2003.
Hence,
these appeals.
Normally,
this Court is reluctant to interfere with the interim orders passed under order
39 rules 1 & 2 CPC.
However,
in the present case, we are concerned with construction of a seven storeyed
commercial premises under a self-financing scheme floated by the appellant. In
the said complex, there are showrooms, departmental stores and halls for
commercial uses.
The
question involved in this case is whether the offer contained in the above
advertisement was for a fixed amount of Rs.39 lacs? In the present case, the
advertisement inserted by the appellant in "Times of India" indicated
Rs.39 lacs as cost of the built-up area admeasuring 3550 sq. ft., whereas the
advertisement inserted in the local newspaper "Dainik Bhaskar"
indicated Rs.39 lacs as estimated cost for the aforestated built- up area.
According
to the respondent herein, investment was made by him on the basis of the
advertisement in "Times of India". According to the respondent, Rs.39
lacs was a fixed cost and, therefore, the board was not entitled to raise the
price to Rs.71 lacs, particularly when it was guilty of delay in completing the
project. It was submitted that the board was not entitled to approbate and
reprobate and that it was bound by its offer of Rs.39 lacs as contained in
advertisement in "Times of India".
In
this case, we are concerned with a self-financing scheme under which a
commercial complex is constructed. In a self-financing scheme, costing plays an
important role. The building in question comprises of various units. These
units are self-financed. A buyer of the unit has to fund the cost of
construction. A buyer under such a scheme cannot be permitted to buy a unit at
a price which is less than the cost of construction. In a self-financing
scheme, pricing is generally based on cost of construction unlike sale of
houses after they are completed, in which cases pricing is generally market
related. In the case of a self-financing scheme, no buyer can claim a right to
purchase any unit at a price lower than the actual construction cost, as the
board raises its funds in turn from the banks and other financial institutions
to whom the board is required to pay interest periodically. In the case of a
self-financing scheme, even if there is failure on the part of one contributor
to pay the costs, the entire scheme falls in jeopardy and, therefore, there is
no merit in the contention advanced on behalf of the respondent that the
impugned orders should not be interfered with as they are confined only to a
particular unit purchased by the respondent.
It was
urged on behalf of the appellant that there was a mistake in the advertisement
inserted in "Times of India", inasmuch as the word
"estimated" stood omitted inadvertently from the fourth column
dealing with cost, though it has been so mentioned in the advertisement in the
local newspaper "Dainik Bhaskar". It was further contended on behalf
of the appellant that the respondent had filled-in an application form to which
the terms and conditions of allotment were attached. Clause 10 of the
conditions read as follows:
"The
cost of plot/house/flat which is mentioned in the table, is estimated. If there
is any increase then the same will be informed to the allottee." It was,
therefore, submitted that the respondent was fully aware that the amount of
Rs.39 lacs mentioned in the advertisement was an estimated cost and not a fixed
cost.
On the
other hand, it was urged on behalf of the respondent that the document on which
reliance is placed by the board was not placed before the trial Court as well
as before the High Court and, therefore, no interference was called for in the
matter. It was urged on behalf of the respondent that the respondent was ready
and willing to deposit Rs.39 lacs at the earliest and that the board should be
restrained from charging and recovering the entire amount of Rs.71 lacs,
pending hearing and final disposal of the suit. In this connection, reliance
was also placed on the decision of this Court in Indore Development Authority
v. Sadhana Agarwal (Smt.) & Others reported in [(1995) 3 SCC 1] as also the
decision of this Court in Kanpur Development Authority v. Smt. Sheela Devi
& Others reported in [AIR 2004 SC 400].
Time
has come when the Courts should be slow in interfering at interim stage with
schemes which are based on costing. India is having cost-push economy. In a self-financing scheme based on
costing, an interim injunction has a cascading effect. Failure on the part of
even one contributory in contributing the amount to the cost results in total
failure of the project. The developer, like the housing board, makes an initial
investment by borrowing funds from the market. Therefore, an interim injunction
at the initial stage of the project would result in the total collapse of the
entire project. It would also affect the contributions made by other
co-purchasers. Several components go into costing, including the lease rent
payable to the State Government. These aspects have not been considered by the
trial Court.
Our
observations herein however should not be read to mean that the developer in
the present case has an absolute right to increase the cost of flats initially
announced as estimated cost. The final cost should be proportionate to the
estimated cost mentioned in the offer keeping in mind the rate of inflation,
escalation of the prices of inputs, escalation in the prices of the
construction material and labour charges. These factors have got to be taken
into account on the basis of the evidence which may be considered at the time
of final hearing of the suit. In the present case, however, the appellant has
not placed before the trial Court the documents mentioned hereinabove and,
therefore, we are remitting the matter to the trial Court for fresh decision,
in accordance with law.
In the
case of Gujarat Bottling Co. Ltd. v. Coca Cola Co. reported in [(1995) 5 SCC 545]
this Court, while discussing the factors to be considered by the Courts in
exercise of the discretion under order 39 rules 1 & 2 CPC, has observed as
follows:
"The
grant of an interlocutory injunction during the pendency of legal proceedings
is a matter requiring the exercise of discretion of the court.
While
exercising the discretion the court applies the following tests
(i) whether
the plaintiff has a prima facie case;
(ii)
whether the balance of convenience is in favour of the plaintiff; and
(iii) whether
the plaintiff would suffer an irreparable injury if his prayer for
interlocutory injunction is disallowed.
The
decision whether or not to grant an interlocutory injunction has to be taken at
a time when the existence of the legal right assailed by the plaintiff and its
alleged violation are both contested and uncertain and remain uncertain till
they are established at the trial on evidence. Relief by way of interlocutory
injunction is granted to mitigate the risk of injustice to the plaintiff during
the period before that uncertainty could be resolved. The object of the
interlocutory injunction is to protect the plaintiff against injury by
violation of his right for which he could not be adequately compensated in
damages recoverable in the action if the uncertainty were resolved in his favour
at the trial. The need for such protection has, however, to be weighed against
the corresponding need of the defendant to be protected against injury
resulting from his having been prevented from exercising his own legal rights
for which he could not be adequately compensated. The court must weigh one need
against another and determine where the "balance of convenience"
lies. In order to protect the defendant while granting an interlocutory injunction
in his favour the court can require the plaintiff to furnish an undertaking so
that the defendant can be adequately compensated if the uncertainty were
resolved in his favour at the trial.
Under
Order 39 of the Code of Civil Procedure, jurisdiction of the Court to interfere
with an order of interlocutory or temporary injunction is purely equitable and,
therefore, the Court, on being approached, will, apart from other
considerations, also look to the conduct of the party invoking the jurisdiction
of the Court, and may refuse to interfere unless his conduct was free from
blame. Since the relief is wholly equitable in nature, the party invoking the
jurisdiction of the Court has to show that he himself was not at fault and that
he himself was not responsible for bringing about the state of things
complained of and that he was not unfair or inequitable in his dealings with
the party against whom he was seeking relief. His conduct should be fair and
honest. These considerations will arise not only in respect of the person who
seeks an order of injunction under Order 39 Rule 1 or Rule 2 of the Code of
Civil Procedure, but also in respect of the party approaching the Court for
vacating the ad interim or temporary injunction order already granted in the
pending suit or proceedings." The judgment of this Court in the case of Indore
Development Authority (supra) supports the appellant herein.
In
that case, an advertisement was issued by the development authority in the year
1977 inviting applications from persons interested in purchase of flats on
hire-purchase basis. The estimated cost for the LIG flat was mentioned at Rs.45,000/-.
In the
proforma attached to the application for registration, the development
authority had stated that the price mentioned by them was a probable price and
that the definite price shall be intimated at the time of allotment. The
purchasers were given possession in the year 1984. They instituted writ
petition before the High Court challenging the demand raised by the development
authority based on escalation. The writ petition was allowed by the High Court.
This Court, in the facts and circumstances of that case, came to the conclusion
that the High Court should not have interfered with the hike in the cost of
construction. This Court observed that the development authority owed a duty to
explain and satisfy the Court the reasons for such high-escalation but this did
not warrant the High Court while exercising the jurisdiction to examine every
detail of the cost of construction. Accordingly, this Court allowed the appeal
filed by the development authority observing:
"9..
Although this Court has from time to time, taking the special facts and
circumstances of cases in question, has upheld the excess charged by the
development authorities over the cost initially announced as estimated cost,
but it should not be understood that this Court has held that such development
authorities have absolute right to hike the cost of flats, initially announced
as approximate or estimated cost for such flats. It is well known that persons
belonging to middle and lower income groups, before registering themselves for
such flats, have to take their financial capacity into consideration and in
some cases it results in great hardship when the development authorities announce
an estimated or approximate cost and deliver the same at twice or thrice of the
said amount. The final cost should be proportionate to the approximate or
estimated cost mentioned in the offers or agreements. With the high rate of
inflation, escalation of the prices of construction materials and labour
charges, if the scheme is not ready within the time-frame, then it is not
possible to deliver the flats or houses in question at the cost so announced.
It will be advisable that before offering the flats to the public such
development authorities should fix the estimated cost of the flats taking into
consideration the escalation of the cost during the period the scheme is to be
completed. In the instant case the estimated cost for the LIG flat was given out
at Rs.45,000. But by the impugned communication, the appellant informed the
respondents that the actual cost of the flat shall be Rs.1,16,000 i.e. the
escalation is more than 100%. The High Court was justified in saying that in
such circumstances, the Authority owed a duty to explain and to satisfy the
Court, the reasons for such high escalation.
We may
add that this does not mean that the High Court in such disputes, while
exercising the writ jurisdiction, has to examine every detail of the
construction with reference to the cost incurred.
The
High Court has to be satisfied on the materials on record that the Authority
has not acted in an arbitrary or erratic manner.
10. So
far the facts of the present case are concerned, it is an admitted position
that in the pro forma attached to the application for registration, the
appellant said that the price mentioned by them was a probable and estimated cost,
the definite price shall be intimated at the time of the allotment. Thereafter,
the appellant had been informing the respondents and others who had got
themselves registered, from time to time regarding the escalation in the cost
of the flat. One of the reasons for the rise of the price for the LIG flat from
Rs.60,000 to Rs.1,16,000 appears to be the increase in the area of the flat
itself from 500 sq. ft. to 714.94 sq. ft. From 1982 to 1984, possession of the
flats could not be delivered because of the dispute pending in the Court which
also contributed to the increase in the cost of the flat.
Admittedly,
the respondents came in possession of the flats in the year 1984. In the facts
and circumstances of the case, we are satisfied that no interference was called
for by the High Court." The judgment of this Court in the case of Kanpur
Development Authority (supra), on which reliance is placed on behalf of the
respondent, has no application to the facts of the present case as in that
matter there was an express clause in the brochure that the escalation shall
not exceed 10%. In the present case, there is no such clause in the brochure.
In the present case, we are concerned with a commercial complex constructed
under a self-financing scheme and not with the residential houses as was the
case in the matter of Kanpur Development Authority(supra). Hence, the said
judgment has no application to the facts of the present case.
Before
concluding, we may point out that the observations made herein are only to give
reasons in support of this judgment and they will not bind the parties hereto
in the proceedings before the trial Court.
Subject
to above, both the appeals are allowed; the impugned judgment and orders are
set aside and the matter is remitted to the trial Court for fresh decision, in
accordance with law. However, in the facts and circumstances of this case,
there will be no order as to costs.
Back