M/S Channy
Enterprises Vs. Commissioner of Central Excise, Chandigarh [2005] Insc 222 (5 April 2005)
Ruma
Pal & C.K. Thakker
(Arising
out of SLP ) No. 14175 of 2003) RUMA PAL, J.
Leave
granted.
The
appellant has two mills in which it manufactures hot rolled steel products.
With effect from 1st
September 1997, the
Government of India notified ingots and billets under Section 3-A of the
Central Excise Act, 1944 for levy of excise duty on the basis of the annual
capacity of production (ACP) of the factory. To give effect to the scheme,
Rules were framed for determination of the annual capacity of production of a
factory producing such notified goods known as the Induction Furnace Annual
Capacity Determination Rules 1977. By the Rules, the ACP of a factory was taken
to be a fixed multiple of the total capacity of the furnaces installed in the
factory. The manner of levy and collection of duty was governed by Rule 96(ZP)
of the Central Excise Rules, 1944 also issued under Section 3A of the Act.
Circular dated 26th
February 1998 had been
issued by way of a clarification in answer to questions raised in connection
with the operation of the Rules. One of the questions so raised was:
"How
would the annual capacity of production be determined if a unit has more than
one rolling mill in the same premises but operates only one rolling mill at a
time." In answer to this, it was clarified that:
"If
a unit has one re-heating furnace with two rolling mills, then the capacity of
the higher of the two mills should be taken as the assessed annual capacity for
the unit. However, if each rolling mill has a reheating furnace, the capacity
of the unit would be the sum total of the capacity of each rolling mill in the
unit".
Prior
to 1st September 1999, the appellant had one heating
furnace and the appellant's ACP was fixed on that basis. The appellant then
installed a second furnace but, according to the appellant, there was only one
electric motor which meant that the both furnaces could not be operated
simultaneously. The appellant notified the change to the Commissioner under
Rule 4 of the Rules. According to the appellant, the approval was communicated
to the appellant by the Commissioner's letter dated 25th August 1999 after which the appellant filed a revised declaration on 1st September 1999. Response was given to this on 17th October 2000 by the Commissioner's office which
sought to club the capacity of both the rolling mills since the second heating
furnace had been installed on the basis of the circular dated 26th February 1998. The appellant's submission that
the circular did not have any application to the appellant's case because both
the furnaces could not be operated simultaneously was rejected by the
Commissioner who then proceeded to fix the ACP by clubbing the capacity of both
the rolling mills. An appeal was preferred by the appellant to the Customs
Excise and Gold Control Appellate Tribunal (CEGAT) which rejected the
appellant's appeal and affirmed the Commissioner's order. The appellant filed a
Reference Petition under Section 35-H (I) of the Act as well as a writ petition
contending that the respondents were not justified in determining the ACP of
the appellant by taking the capacity of both the mills together. The High Court
dismissed the Reference Application and the Writ Petition holding that no
question of law arose from the order of the Tribunal. It was also found that
the CEGAT had considered all aspects of the matter and had correctly determined
the question raised.
The
appellant has contended that all the fora had erred in overlooking the formula
provided under Rule 3 for determination of the ACP which showed that a vital
element of the formula included the revolutions per minute of the drive. This,
according to the appellant, showed that the formula for calculating the ACP was
on the basis of one motor per unit. It is therefore submitted that despite
having two electric furnaces since there was only one motor which was common to
both, then in terms of the circular issued by the Board itself the capacity of
the higher of the mills should have been taken as the ACP. The second
submission is that the appellant had submitted a certificate from the National
Institute of Secondary Steel Technology, a Government Institute, which
certified that the two mills could not be run simultaneously with the same
motor and common flywheel. It is contended that the Commissioner could not
discard the opinion of an expert and determine the technical issue on the basis
of his own opinion. It was finally submitted that the Commissioner had himself
approved the setting up of the second furnace within the ACP of the units.
Learned
counsel appearing for the respondents has submitted that the circular dated 26th February 1998 relied upon by both the parties had
been misconstrued by the appellant. It is submitted that the question of taking
the higher capacity of the two mills would only arise if there was one
re-heating furnace. According to the respondents, the installation of the two
rolling mills and two heating furnaces had not been disputed by the appellant
before the Commissioner. It is said that the Commissioner had applied his mind
to the expert's certificate but had rejected it because it was issued after a
lapse of nine months from the date of the withdrawal of the capacity based
assessment scheme on 31st
March 2000. The
Commissioner in fact determined the issue on the basis of the admitted facts
and on an interpretation of the 1998 circular.
The
respondent's contentions are correct. It is not the appellant's case that the
1998 circular was incorrect. On the contrary it has been relied on to claim
that the ACP should have been determined with reference to the mill which had
the higher capacity alone. The circular in answer to a query which exactly
reflects the issue in this case, clearly says that the capacity of the higher
of the two mills would be taken for assessing the ACP only if each rolling mill
did not have a separate re-heating furnace. If each rolling mill had a separate
heating furnace, as the appellant admittedly does, then the capacity of the
unit would be the sum total of the capacity of each rolling mill in the unit
irrespective of the fact that only one mill operated at a time. The language
could not be plainer. What the appellant's argument overlooks is that the
scheme did not operate on the basis of the actual production but on the
capacity of the rolling mills to produce. We, therefore, see no reason to
differ with the view expressed by the Commissioner, CEGAT and the High Court.
The
criticism of the action of the Tribunal in Hindustan Ferodo Ltd. v. Collector
of Central Excise:1997 (89) ELT 16(SC) where the Tribunal had entered into the
arena of dispute and in effect given evidence on behalf of the Revenue before
itself, would not apply here. The Revenue in that case had led no evidence in
support of its case. The assessee had. In the present case CEGAT proceeded on
the basis of the admitted facts and relied on the language of the circular to
reject the appellant's appeal.
The
appellant has also sought support from a decision of the Kolkata Bench of CEGAT
in Aditya Steel Industries Ltd. v. CCE & C, Bhubaneswar: 2002 (53) RLT 1068. The Tribunal relied upon the Board's
circulars No.325/41/97-CX dated 25.7.1997 and 326/42/97-CX to hold that where
it was not technically possible to run two mills simultaneously because of a
common power supply, the capacity of the stand by mill was not to be taken into
consideration for determining the ACP.
We do
not agree. Separate schemes were formulated under Section 3A of the Act in
relation to induction furnaces and hot re-rolling mills. Circular 325 dated
25.7.1997 dealt with induction furnaces and specifically provided:
"In
this context, it is understood that some induction furnace units have, what
they call "idle" crucible. It is reported that at any point of time
only one crucible is used and the other remains idle. In such cases, it is
claimed, the induction furnace unit has one transformer and one electrical
panel. As such the capacity of the induction furnace is relatable to
crucible(s), excluding the "idle (separate or stand by)" crucible.
This aspect may kindly be examined on basis of facts of each such case and the
furnace capacity may be ascertained accordingly".
Circular
No. 326 also dated 25.7.1997 dealt with the capacity of production of hot
re-rolling mills. There is no paragraph in this circular similar to the quoted
paragraph relating to the ACP of induction furnaces.
Paragraph
18 of Circular No. 326 says that the paragraphs in the circular explain the
salient features of Section 3A scheme as applicable to re-rolling mills. It
also says that the scheme, in general terms, is on the same lines as that for
the Induction Furnace units and that therefore the explanation on some of the
common features are the same as those contained in circular No. 325. This does
not tantamount to saying that all the features of the induction furnace scheme
were to be incorporated into the hot rolling mill scheme.
The
appellant's contention that the second mill was set up after the approval of
the Commissioner is of no consequence. The approval granted by the Commissioner
did not in any way affect the assessment required to be made in accordance with
the Rules.
In the
circumstances, the appeal is dismissed but without any order to costs.