M.C.
Mehta Vs. Union of India & Ors [2004] Insc 179
(18 March 2004)
Y.K.
Sabharwal & H.K. Sema.
INTERLOCUTORY
APPLICATION NO.1785/01 IN INTERLOCUTORY APPLICATION NO.22 AND IN WRIT PETITION
(CIVIL) NO.4677 OF 1985 [With IA Nos.1806, 1815, 1817-1818, 1819, 1822, 1823,
1824, 1825, 1794 and 1795 in IA No.1785 in WP (C) No.4677/85, WP (C)
NO.410/2002, IA No.1832, 1835-1836, 1838 and 1839-1840 in IA No.1785 in IA
No.22 in WP (C) No.4677/85, WP (C) No.661/2002, WP (C) No.428/2002, WP (C)
No.624/2002 and Contempt Petition (C) No.568/2002 in WP (C) No.428/2002] Y.K. Sabharwal,
J.
The
main question to be examined in these matters is whether the mining activity in
area upto 5 kilometers from the Delhi-Haryana border on the Haryana side of the
ridge and also in the Aravalli hills causes environment degradation and what
directions are required to be issued.
The
background in which the question has come up for consideration may first be
noticed.
The Haryana
Pollution Control Board (HPCB) was directed by orders of this Court dated 20th
November, 1995 to inspect and ascertain the impact of mining operation on the Badkal
Lake and Surajkund - ecologically sensitive area falling within the State of Haryana.
In the report that was submitted, it was stated that explosives are being used
for rock blasting for the purpose of mining; unscientific mining operation was
resulting in lying of overburden materials (topsoil and murum remain)
haphazardly; and deep mining for extracting silica sand lumps is causing
ecological disaster as these mines lie unreclaimed and abandoned. It was, inter
alia, recommended that the Environmental Management Plan (EMP) should be
prepared by mine lease holders for their mines and actual mining operation made
operative after obtaining approval from the State Departments of Environment or
HPCB; the EMP should be implemented following a time bound action plan; land
reclamation and afforestation programmes shall also be included in the EMP and
must be implemented strictly by the implementing authorities. The report
recommended stoppage of mining activities within a radius of 5 kms. from Badkal Lake and Surajkund (tourist place). The Haryana Government, on
the basis of the recommendations made in the report, stopped mining operations
within the radius of 5 kms of Badkal Lake and Surajkund.
The
mine operators raised objections to the recommendations of stoppage of mining
operations. According to them, pollution, if any, that was generated by the
mining activities cannot go beyond a distance of 1 km. and the stoppage was
wholly unjustified.
NEERI
Report and earlier directions By order dated April 12, 1996, the Court sought
the expert opinion of National Environmental Engineering Research Institute
(NEERI) on the point whether the mining operations in the said area are to be
stopped in the interest of environmental protection, pollution control and
tourism development and, if so, whether the limit should be 5 kms. or less.
NEERI in its inspection report dated 20th April, 1996, inter alia, recommended that:
"6.1
Mining.
(1)
Detailed exploratory operations need to be undertaken to facilitate the
estimation of reserves in the region, and for scientific management of mining
operations.
(2)
The mine lease-owners need to undertake the mining operations in series, i.e.
mining activities must be completed to full potential in a block before moving
to the next. This will help in reclamation of land in the block in which mining
operations have been completed.
(3 to
(9) ...
(10)
The Environmental Management Plans (EMP) being formulated by the mine-owners
should include land rejuvenation and afforestation programmes, and other
measures necessary to protect the quality of the environment and human health.
The mining operations should commence only after the approval of EMPs by a
designated authority. A time-bound action plan needs to be initiated for the
implementation of the measures delineated in the Environmental Management
Plans.
(11)
& (12) ...
(13)
The question of lifting the ban on mining operations needs to be considered in
conjunction with the implementation of stringent pollution control, land
reclamation, green belt, and other Environmental Management measures so as to
facilitate the availability of construction materials and employment
opportunities for the workers along with the protection of environment and
public health.
(14)
It is considered necessary to prepare a Regional Environmental Management Plan
for urgent implementation to enable eco-friendly regional development in the
area." On consideration of the reports, this Court came to the conclusion
that the mining activities in the vicinity of tourist resorts are bound to cast
serious impact on the local ecology. The mining brings extensive alteration in
the natural land profile of the area. Mined pits and unattended dumps of
overburdened left behind during the mining operations are the irreversible
consequences of the mining operations and rock blasting, movement of heavy
vehicles, movements and operations of mining equipment and machinery cause
considerable pollution in the shape of noise and vibration. The ambient air in
the mining area gets highly polluted by the dust generated by the blasting
operations, vehicular movement, loading/unloading/transportation and the
exhaust gases from equipment and machinery used in the mining operations. It
was directed that in order to preserve environment and control pollution within
the vicinity of two tourist resorts, it is necessary to stop mining activity
within 2 kms. radius of the tourist resorts of Badkal Lake and Surajkund. The Court further
directed the Director, HPCB to enforce all the recommendations of NEERI
contained in para 6.1 of its report so far as the mining operations in the
State of Haryana are concerned. Further, it was
directed that failing to comply with the recommendations may result in the
closure of the mining operations and that the mining leases within the area
from 2 kms. to 5 kms. radius shall not be renewed without obtaining prior no
objection certificate from the HPCB as also from the Central Pollution Control
Board (CPCB). Unless both the Boards grant no objection certificate, the mining
leases in the said area shall not be renewed. (M.C. Mehta v. Union of India & Ors. [(1996) 8 SCC 462]).
Present
Issues The aspects to be examined include the compliance of the conditions
imposed by the Pollution Boards while granting no objection certificate for
mining and also compliance of various statutory provisions and notifications as
also obtaining of the requisite clearances and permissions from the concerned
authorities before starting the mining operations.
In
matters under consideration, the areas of mining fall within the districts of Faridabad and Gurgaon in the Haryana State. I.A. No.1785/01 has been filed by the Delhi Ridge
Management Board praying that the Government of Haryana be directed to stop all
mining activities and pumping of ground water in and from area upto 5 kms from
Delhi-Haryana border in the Haryana side of the Ridge, inter alia, stating that
in the larger interest of maintaining the ecological balance of the environment
and protecting the Asola Bhatti Wildlife Sanctuary and the ridge located in
Delhi and adjoining Haryana, it is necessary to stop mining. In the
application, it has been averred that the Asola Bhatti Wildlife Sanctuary is
located on the southern ridge which is one of the oldest mountain ranges of the
world and represents the biogeographical outer layer of the Aravalli mountain
range which is one of the most protected areas in the country. The sanctuary is
significant as it is instrumental in protecting the green lung of National
Capital of Delhi and acts as a carbon sink for the industrial and vehicular
emissions of the country's capital which is witnessing rapid growth in its
pollution level each year. The ridge, it is averred, is a potential shelter
belt against advancing desertification and has been notified a wildlife
sanctuary and reserve forest by the Government of National Capital Territory of
Delhi. Regarding the mining activities, it is averred that for extraction of Badarpur
(Silica sand), there is large scale mining activity on the Haryana side just
adjacent to the wildlife sanctuary of the ridge which activities threaten the
sanctuaries habitat and also pumping of large quantity of ground water from
mining pits. It was also stated that the ground water level was being depleted
as a result of the mining activity. Further, the query dust that comes out of
mining pits is a serious health hazard for human population living nearby and
also the wild animals inhabiting the sanctuary pointing out that the mining and
extraction of ground water had been banned in National Capital Territory of
Delhi and the ridge being protected as per the order of this Court, it is
necessary, that the ridge on the Haryana side is also protected - that being
the extension of the range and, therefore, mining, withdrawal of ground water
and destruction of flora, etc. should also be restricted outside Delhi or at
least upto 5 kms. from Delhi-Haryana border towards Haryana.
On 6th May, 2002, this Court directed the Chief
Secretary, Government of Haryana to stop, within 48 hours, all mining
activities and pumping of ground water in and from an area upto 5kms. from Delhi- Haryana border in the Haryana side
of the ridge and also in the Aravalli Hills. The question to be considered is
whether the order shall be made absolute or vacated or modified.
Our
examination of the issues is confined to the effect on ecology of the mining
activity carried on within an area of 5 Kms. of Delhi-Haryana Border on Haryana side in areas falling within the
district of Faridabad and Gurgaon and in Aravalli Hills within Gurgaon
District. The question is whether the mining activity deserves to be absolutely
banned or permitted on compliance of stringent conditions and by monitoring it
to prevent the environmental pollution.
EPCA
Visits In terms of the order passed by this Court on 22nd July, 2002, Environmental Pollution Central Authority (EPCA) was
directed to give a report with regard to environment in the area preferably
after a personal visit to the area in question without any advance notice. It
may be noted that EPCA was constituted by the Government of India under
notification dated 29th January, 1998 issued in exercise of power under Section
3(1) & (3) of the Environment (Protection) Act, 1986 (for short, 'the EP
Act') Mr.
Bhure Lal
was appointed its Chairman. The EPCA was constituted with a view to protect and
improve the quality of environment and preventing, controlling and abetting
environmental pollution. EPCA has also the power to deal with environment
issues pertaining to National Capital Region which may be referred to it by the
Central Government. The EPCA has jurisdiction over the National Capital Region
as defined in clause (f) of Section 2 of the National Capital Region Planning
Board Act, 1985. The Districts of Gurgaon and Faridabad are part of the National Capital Region, under Section 2(f)
read with the Schedule of the said Act.
The
Chairman of the CPCB is a convenor member of EPCA. EPCA made a surprise visit
to the area to see the mining sites. The mining sites visited are located in
the villages of Anangpur, Pali, Mohabatabad and Mangar, which fall within the
notified area of 5 km radius from the Delhi border in the Faridabad district. EPCA also visited mining
sites that are located outside the notified zone in Kot area, EPCA also held
consultation with the officials of the Central Groundwater Board and obtained
their opinion on this matter. On August 7, 2002, members of the EPCA visited the mining sites located
within five km radius from Delhi border.
The objectives of the visit, as per EPCA, were as follows :
1.
Assessment of the level of compliance with the conditions laid down in the
regulatory procedures like the No Objection Certificate (NOC) granted by
authorities to the mine owners;
2.
Evidence of land and habitat degradation in and around the mining sites;
3.
Evidence of misuse and shortage of ground water in the area;
4.
Assessment of the implication of such activities for the local ecology and
drinking water sources in the area.
During
the visit, prima facie, EPCA found evidence of clear violation of some of the
key conditions of order of this court dated May 10, 1996.
EPCA Ist
Report and Recommendations The EPCA gave its report dated 9th August, 2002. It
would be useful to reproduce the said report in extenso as under:
"Anangpur
area and its vicinity : EPCA inspected the mining sites owned by Mohan Ram and
Company as well as at least 5 other mining sites in this area, which EPCA is
not clear who owns.
At the
time of visit there was no mining taking place. So EPCA members assessed level
of compliance with some of the key conditions laid down in the NOCs. There was
clear evidence of violation of the following conditions.
i. The
excavated pits should be filled with fly ash or municipal solid waste in the
bottom layers. The top soil should be used as a top layer while filling the
pit. Land reclamation and tree plantation should be done in a planned manner
over the reclaimed mine pits.
ii.
The applicant shall not discharge any effluent or groundwater outside their
lease premises and shall take appropriate measures for rainwater harvesting and
reuse of water so as not to affect adversely the ground water table of the
area. No mining operation shall be carried out in the water table area.
iii.
The green belt proposed in the environment management plan around the proposed
mining lease area and along the road side shall be developed.
The
most serious violation noticed by the EPCA was the continuation of mining even
after reaching the ground water level which has been disallowed by the
regulatory agencies. Photographs taken by EPCA, which show deep mining pits
have turned into large lakes of ground water. In this mining lease area EPCA
members saw extensive and deep water bodies. The water was blue, indicating
that this was groundwater and not surface water runoff collected in the pits.
Even
more serious violation noticed was configuration of water pipes laid out to
draw water out of the pits to throw them over hills and let the water flow out.
This is a grave misuse of precious ground water in an area where ground water
is the only source of water for the local population - both urban and rural.
EPCA
members talked to local villagers who complained that water table in the area has
gone down over a period of time and that the village is facing water shortage.
While earlier ground water could be tracked at the depth of 30-35 ft. now deep
bore wells have been dug to get drinking water, in addition, noise and dust
pollution from the mining sites are a problem.
Goodwill
mine in Pali village : EPCA found similar violation of conditions and evidence
of mining sites reaching the level of ground water in deep pits and pipes
fitted to drain out water here as well.
During
the long drive to various mining sites, EPCA could not see any credible sign of
green belt along the roads. Moreover, one important condition of NOCs is that
"a safe distance should be maintained from the road to overburden dumps
and the mine pits in accordance with the directions/notifications of the
department of environment, Haryana and bureau of mines." But EPCA noticed
mining sites very close to the roads and also very close to the ecologically
sensitive area of Asola sanctuary near the Goodwill mines.
Stone
crushing sites in Pali : EPCA has inspected the stone crushing sites in the
area. All sites had a lot of material and trucks being loaded. It is difficult
to establish if these are the left over material from the past or were products
from banned sites or from sites from outside the notified area. EPCA was
informed that after the Hon'ble Supreme Court directive of May 2002, the stone
crushers were not being operated, except between the hours of 5 am to 9 am.
EPCA was, therefore, unable to verify the working conditions of these crushers.
But it did not find any evidence of afforestation as stipulated by the NEERI
directive or any evidence of dust minimizing equipment.
Mining
around Mangar village : Again the same situation was found around Anangpur. The
villagers interviewed here were caught between the devastation of the mines,
desperate shortage of drinking water and the only livelihood option that these
manual stone quarries provided.
Legal
mining in Kot area : As mining is banned along the 5 km radius from the Delhi
border, EPCA also visited some mines that are outside the notified area to
ascertain the state of the environment. In this area, surface mining is being
done and not deep mining. Therefore, as yet, the groundwater reserves are not
being touched in this region. The entire area was like a giant dust field. We
saw no evidence of any afforestation or even dust minimising efforts being
undertaken in the areas that are being mined. We did see one tanker of water,
which was sprinkling the roads, unable to stop the dust from swirling. EPCA
could not see any protection for the workers from dust.
As
this area will clearly emerge as a major mining in the future, it is important
that the mining area is properly demarcated and environment management plan
implemented to enable scientific mining to minimize degradation of the
environment.
Faridabad-Gurgaon
road : EPCA saw mining alongside the road. Though the mines were closed because
of the Hon'ble court directive, EPCA saw vast pits and mining activity in this
area. This is the road for the proposed bypass from Delhi.
3. The
present laws and regulations in the area We have assessed the current
applicable laws and regulations in the area, which govern land use and mining
so as to understand what efforts have been made by different agencies to ensure
compliance.
? In may
1992, parts of the Aravalli range were declared ecologically sensitive under
the Environment (Protection) Act. Under this notification, certain activities -
including all new mining operations, including renewals of mining leases - are
restricted and permission has to be sought from the Ministry of Environment and
Forests. This notification is valid for reserved forests in the districts of Gurgaon
in Haryana and Alwar in Rajasthan.
? In
August 1992, the Forest Department of Haryana had issued a notification under
the Punjab Land Preservation Act 1900, banning the clearing and breaking up the
land not under cultivation, quarrying of stone... in the Badkal area without
prior permission of the forest department. This ban was for 30 years. Earlier
it had already issued a similar notification for the Pali area for 25 years.
? In
1996, the Hon'ble Supreme Court banned all mining activity within 2 kms of the Badkal
and Surajkund tourist resorts.
? In
the same order, it ordered that mining leases within the area from 2 km to 5 km
radius shall not be renewed without obtaining no-objection certificates from
the Haryana Pollution Control Board as also the Central Pollution Control Board
(CPCB). It stipulated that "unless both the boards grant no objection
certificate, the mining leases in the said area shall not be renewed".
?
Mining in the 2-5 kms was allowed under condition that there would be strict
adherence to the environment management plan laid down by the NEERI. It has to
be noted here that the CPCB had in its report to the Hon'ble Court in 1996
stated that the "deep mining for silica is causing an ecological
disaster". CPCB has recommended that mining activity "should be
stopped within a radius of 5 kms from Badkal and Surajkund. The subsequent
report of NEERI dated 20.4.1996, recommended green belt at 1 km radius all
around the boundaries of the two lakes. On this basis, the Hon'ble Court
directed that radius be extended to 2 kms for a green belt and to cushion the
impacts of air and noise pollution.
? The Hon'ble
Court in its order asked the agencies to ensure enforcement of the
recommendations of NEERI. It directed that "failure to comply with the
recommendations may result in the closure of the mining operations."
4.
Compliance and enforcement : absent and missing To discuss the future strategy
for this area, it would be important to assess the track-record of the
different agencies in ensuring that the previous orders and directives are
enforced and complied with.
1. No
mining within 2 kms of Badkal and Surajkund : Probably enforced. But difficult
to assess as the area is hilly.
2.
Mining within 2-5 kms should get permission from Haryana Pollution Control
Board and CPCB. The CPCB has issued 2 NOCs, dated December 20, 2001 and May 6,
2002.
No
further record has been found of NOCs given for mining in this area. EPCA has
not been able to find the NOCs granted by the Haryana Pollution Control Board.
Compliance
with the environmental management plans recommended by NEERI as directed by the
Hon'ble Supreme Court.
S. No.
Directive
Enforced or not
1. 200
mts wide green belt along Surajkund and Badkal Shrubs and wild growth. No real
evidence of good afforestation.
2. 100
mts wide green belt outside mining lease boundary Definitely not done. EPCA did
not see afforestation, except for some recent plantation of dying and dead
trees in one or two places. The sign boards were more prominent than the trees
they were supposed to show.
3. 100
mts open peripheral area around stone crusher zone with green belt Not done
4.
Green belt on either side of the road between Surajkund and Badkal. We saw
large scale construction on this road - from schools to management colleges and
housing colonies.
5.
Mining should commence only after the environmental management plan (EMP) is
approved by a designated authority There is no evidence of an environmental
management plan being adhered to in this region.
Adherence
to the conditions of the No-objection Certificate granted by CPCB for mining S.
No.
Directive
Enforced or not
1.
Mining to be done with approved mining plan No evidence
2.
Excavated pit to be filled by fly ash or municipal solid waste in the bottom
layers.
Overburden
should be used in the middle layer. Top soil on top layer and afforestation.
EPCA
saw no evidence that this recommendation had even been attempted to be
followed. All abandoned mines were left open and degraded.
The
entire region was pockmarked with deep holes and overburdens.
3. No
discharge of effluent or groundwater outside lease premises. Must take measures
for rain water harvesting and reuse of water so as not to affect the
groundwater table in the areas. No mining operations shall be carried out in
the water table area. Not done. Gross violation. See section on water for
details.
4.
Ambient air quality standards to be complied with. No evidence. Mine was
closed.
5.
Noise level at the boundary shall conform with noise standards No evidence.
Mine was closed.
6.
Green belt around lease area and roadside Not done.
7.
Clearance of groundwater board for the usage of the groundwater will be
obtained, for the conservation of groundwater and to ascertain that there will
be no impacts on the groundwater table of the area.
No
evidence.
Groundwater
board has not given any clearance that we could ascertain.
From
the above, it is clear that little or nothing has been done to seriously comply
with the directives of the Hon'ble Supreme Court as well as to enforce the
regulations and conditions laid down by the authorities for environmental
management of the mining areas.
5.
Impact on groundwater reserves It has been argued by the Government of Haryana
in its IA no.1785 of 2001 that the expert committee constituted by it under the
Chairmanship of the principal conservator of forests has submitted that there
is a water divide between the two boundaries of the two states which prevents
the flow of water from Delhi side to Haryana side. It has, therefore, argued
that the mining on the Haryana side is not affecting the water balance in the
Delhi side of the ridge.
It has
further said that only in four pits the groundwater was pumped regularly and in
two pits occasionally. Therefore, it has argued that little or no impact on
groundwater reserves is possible.
5.1
Groundwater Board EPCA requested the Central Ground Water Board (CGWB) for its
opinion. The Board has based its recommendations on the data available with it
as well as a field survey.
The
key issues are :
1. On
the issue of the ridge providing a water divide between the two states, the
CGWB has maintained that while the surface water divide follows the Delhi-Haryana
border, except in the catchment of Bhuria Nala, `the surface water divide may
not be the groundwater divide in the strict sense due to secondary porosity and
also flat topped nature of the hills.' It also states that the Aravalli hills
are highly fractured, jointed and weathered making the major recharge zone for
the surrounding areas.
2. On
the impact on the groundwater reserves due to mining, the Board has found that
its observation wells have shown an increase in groundwater levels in Anangpur,
Mangar, after the mining has been stopped in May.
Therefore,
in spite of monsoon failure and continued abstraction of water, the observation
wells have noted increased water levels within just 2 months of the mining
being closed.
The
groundwater levels in a tube well monitored in Mewla Maharajpur during mid July
and first week of August showed a rise of 0.18 metres, A higher rise - 0.71 to
0.78 metres was observed in the two tube wells near the Mangar mines and Pali
mines in the two months since the mines were closed. This clearly points to the
impact of mining on groundwater reserves.
This
fact was also confirmed in the interviews done by EPCA at site.
3.
CGWB also notes that contrary to what has been claimed, the mined water is not
being pumped into abandoned pits to recharge the groundwater. Instead the
groundwater pumped is discharged into the surrounding nalas, leading to
"wastage" of groundwater.
For
instance, in the case of Anangpur mines, the water was pumped into the Bhuria Nala
and in the case of Pali, the groundwater was discharged into a nala to the Badkal
lake and from Manger mine towards Dhauj lake causing "enormous losses to
groundwater resources of the area". The mined water is also full of silt,
which reduces recharge as well.
4.
Furthermore, CGWB notes that the large surface lakes in the mines are leading
to huge losses of groundwater through evaporation.
5. The
Central Ground Water Authority (CGWA) has notified these areas - South district
of NCT Delhi, Faridabad, Ballabhgarh Municipal Corporation area, Gurgaon town
as water stressed areas and has put regulatory measures on ground water development
in these areas.
Given
all this, CGWB concludes that the "dewartering of mines in the Aravalli
hills has affected groundwater regimes of the mine area as well as buffer zone
resulting in the depletion of ground water resources."
5.2
Compliance with groundwater related regulations The NOC given by the Central
Pollution Control Board, includes an explicit condition regarding ground water
:
That
the mine owner will ensure that there is no discharge of effluent of ground
water outside lease premises. They must take measures for rain water harvesting
and reuse of water so as not to affect the groundwater table in the areas. Most
importantly, it stipulates that no mining operations shall be carried out in
the water table area.
This
condition has been grossly violated. Even the Haryana government's affidavit in
court accepts that pumping of ground water is taking place, though it attempts
to soften the issue by arguing that it is only being done in a few cases.
Under
this condition, mining is not allowed in the water table area. EPCA saw deep
and extensive pits of mines with vast water bodies. EPCA also saw evidence of
pumps and pipes being used to drain out the ground water so that mining could
continue. Therefore, the miners are mining for silica, but also in the process,
mining and destroying the ground water reserves of the areas.
In
times of such water stress and desperation, this water mining is nothing less
than a gross act of wastage of a key resource. This time the stress has been
further aggravated by the failure of monsoon. Notices have been issued in the
nearby housing colonies stating that fall in groundwater table due to lack of
rains is responsible for water shortage in the area this season. This only
indicates how important it is to conserve ground water in the region for long
term sustainability of drinking water sources. Ground water is the only source
of drinking water here." On the basis of study and visit as well as the
report of the Central Ground Water Board, EPCA made the following recommendations
:
"1.
The ban on the mining activities and pumping of ground water in and from an
area upto 5 kms. from the Delhi-Haryana border in the Haryana side of the ridge
and also in the Aravalli Hill must be maintained.
2. Not
only must further degradation be halted but, all efforts must be made to ensure
that the local economy is rejuvenated, with the use of plantations and local
water harvesting based opportunities. It is indeed sad to note the plight of
people living in these hills who are caught between losing their water
dependent livelihood and between losing their only desperate livelihood to
break stones in the quarries. It is essential that the Government of Haryana
seriously implements programmes to enhance the land based livelihood of people
? agriculture, animal care and forestry.
Local
people must not be thrown into making false choices, which may secure their
present but will destroy their future.
Already,
all the villages visited by EPCA complained of dire and desperate shortages of
drinking water. Women talked about long queues before taps to collect water.
Clearly,
water resources of the region are critical inputs to development and cannot be
wasted and destroyed like this. The state government must come up with
strategies to involve local communities in the future development of this
region.
We
have been given to understand that under the mining lease, 10 per cent of the
royalty is to be given to local villagers. We have also understood that the
turnover is of the mining operations in this area is substantial ? between
Rs.50 lakhs to Rs. 1 crore a day were the gross estimates provided to us.
However, we do not have any estimate of the money that has been given to
villagers from this revenue. But there was little evidence in these poor and
destitute villages that any effort had been made to share the proceeds with
them.
3. The
Central Ground Water Board must be consulted urgently about what should be done
with the huge standing water in the area. This is a valuable national resource
and the Board should be asked if the water is best conserved by covering it to
stop evaporation or should it be used for recharge and storage with further
water harvesting efforts.
4. The
Ministry of Environment and Forests (MOEF) should be asked to extend the
notification under the Environment (Protection) Act to the Faridabad part of
the Aravalli and ridge as well. Currently, the notification is only for Gurgaon
district. This notification declaring it an ecologically sensitive area will
help to regulate the activities in this region.
5. It
is not clear to us if adequate planning for water is being done in the large
scale construction activities being undertaken in this area. This aspect is
outside the purview of this report but needs to be examined carefully.
6. It
must also be noted that Gurgaon- Faridabad road is being proposed as the major
bypass for the city of Delhi. The Hon'ble Court will note its directives on the
air pollution case in this regard. It has been said to the court in that matter
that the Government of Haryana is intending to widen the road and bids have
even been issued to this effect. Therefore, it is all the more important that
the mining activity along the road must not be allowed. The 5 kms. ban from the
border of Delhi will take care of this requirement.
7.
EPCA would also recommend that the mining area outside the 5 kms. area must be
demarcated and regulated. In this context, EPCA would like to draw the
attention of the court to the violations and gross disregard for regulations
found in the present mines. It is not out of place to mention that these mines
are owned by very powerful and highly placed individuals in the establishment.
In a related case the High Court of Punjab and Haryana has directed on
20.4.2001 a CBI enquiry on the basis of a public interest litigation filed by a
journalist. In its order the Hon'ble Court maintained that its examination has
found evidence that illegal mining operations are going on in the area. The Hon'ble
Court also noted the bias of the State Government to shield the offenders and
has said that because there is prima facie evidence of the involvement of a
`person who holds the high position of the cabinet minister in the state', the
enquiry should be done by CBI. This enquiry is still ongoing.
During
the examination of the case, EPCA was told of other persons involved in the
mining activity who are highly influential and part of the ruling political
parties in the state and Centre.
In
this respect, EPCA would recommend that tighter and constant monitoring of the
area must be done by a Central Government agency. To increase accountability,
EPCA would also recommend that the environment management plan (EMP) for the
mining area as well as the conditions of the NOC should be made a public document.
All other subsequent monitoring reports of this region must be available
publicly, preferably on the website of the monitoring agency." With the
report, a note given by the Chairmen, Central Ground Water Board on impact of
pumping of ground water from mines and ground water regime in mining area and
its buffer zone in Aravalli hills of NCT Delhi, Faridabad and Gurgaon Districts
of Haryana was also annexed. The said note reads as under :
Based
on available data with Central Ground Water Board and a quick survey in and
around mining area in Aravalli hills, following observations are made –
"1.
The area under consideration forms part of Aravalli range from where mining of
silica- sand and other construction material was being carried out. The mining
of silica sand was mainly carried out below water table by dewatering the mines
whereas mining for other construction material is carried out above water
table. The major mining areas are Anangpur, Pali, Manger and Mohabbatabad.
2. The
surface water divide in the area approximately follows Delhi-Haryana boarder
except the catchment of Bhuria Nala flowing in Haryana State, which extends in Asola area of Delhi State also.
The
formations in the Aravalli hills are highly fractured, jointed and weathered
making it the major recharge zone for the surrounding areas. The surface water
divide may not be ground water divide in strict sense due to secondary porosity
and also flat-topped nature of the hills.
3. The
pumping of ground water during mining of Silica sand affects ground water
regime of surrounding area. During the field visit, it was reported by local
people that during the dewatering of mines there was decline in ground water
levels and reduction in discharge in surrounding wells whereas after stoppage
of pumping the rise in water levels and increase in discharge has been
reported. In few observation wells on down stream side of mines rise in ground
water levels has been observed in Anangpur, Manger and villages after stoppage
of abstraction of ground water from deep mines. The ground water levels in a
tube well monitored in Mewla Maharajpur during mid July 2002 and first week of
August 2002 were 24.39 and 24.57 m. below ground level respectively, showing a
rise of 0.18 m.
Ground
water levels in tube well located at temple near Manger mine in second week of
July 2002 and first week of August, 2002 were 51.70 and 49.99. m. below ground
level respectively showing a rise of 0.71 m.
Similarly,
ground water level in a tube well at Indernagar in Delhi area near Pali mine in third week
of June 2002 and first week of August 2002 were 59.68 and 58.90 m. below ground
level respectively showing a rise of 0.78 m. The stoppage of dewatering of
mines has resulted in rise of ground water levels in surrounding areas.
4. It
has been observed that drainage pattern of the area has been modified due to
haphazard mining and dumping of waste material which has bearing on natural
path of ground water flow in the area.
5. It
is claimed that abandoned pits act as recharge pits and in some cases the
pumped ground water is put in these pits so there may not be substantial
modification in the conditions of ground water regime. All the ground water
pumped out from Anangpur mine has not been put into abandoned adjoining pits
resulting in wastage of ground water by discharge into Bhuria Nala. Observation
have indicated that Bhuria Nala which was ephemeral stream became a perennial
stream during mining operations and now flow has stopped after closure of
mining activity.
Similarly,
pumped out ground water from Pali mine was being discharged in a easterly
flowing nala to Badkal Lane and from Manger mine in a south westerly flowing nala
towards Dhauj lake causing enormous losses to ground water resources of the
area. Further, the pumped out water cannot be recharged effectively due to its
high silt content. In silica sand mines the water table has been intersected
and in presently exposed to the atmosphere causing huge losses to ground water
through evaporation.
6.
Studies conducted by Central Ground Water Board have revealed that water levels
in Faridabad new town which falls in buffer zone
of mine area have declined by 1.44 m/year. The decline of ground water level in
the towns has been attributed to over development of ground water for domestic
and industrial uses which is totally dependent on ground water. The pumping out
of ground water for mining of silica sand in recharge zone might have
aggravated the declining trend of ground water levels which otherwise would
have contributed to the buffer zone.
7.
Central Ground Water Authority has notified South district of NCT Delhi and Faridabad
and Ballabhgarh Municipal Corporation area and Gurgaon town and adjoining
industrial area in August 2000, October 1998 and December 2000 respectively
mainly on consideration of over development of ground water resources resulting
in substantial decline in ground water levels. Regulatory measures on ground
water development have been imposed in these areas.
8.
Therefore, it is observed that dewatering of mines in Aravalli hills has
affected ground water regime of the mine area as well as buffer zone resulting
in depletion of ground water resources." When the aforesaid report came up
for consideration, some of the mine owners submitted that their mines had not been
inspected by Bhure Lal Committee. Particulars of the mines that were stated to
have not been inspected were filed on 23rd September, 2002. Bhure Lal Committee was requested
to carry out the inspection of the said areas/mines. The Committee was also permitted
to associate such other organizations or persons as it may deem fit and proper
for the purpose of inspection.
EPCA
2nd Report and Recommendations In terms of the aforesaid order, 26 mines were
inspected and report dated 21st October, 2002 was submitted. The observations made as a request of inspection in
regard to each mine are as follows :
"The
numbers indicated in parenthesis are serial number of mines given in the list
of mines furnished by Kailash Vasudev, senior advocate to the Hon'ble Supreme
Court that was forwarded to EPCA.
1.
(no.9) Name of Mine/Area : New Anangpur Silica Sand Mines M/s S.P. Sethi,
Location : Village New Anangpur, Distt. Faridabad.
Total
Area of Land on lease/Actual area under mining activity : 186.52 hec.
Mineral
Extracted: Silica Sand Mines Status of Mining : Above groundwater level Whether
groundwater is extracted : No.
Status
of environmental clearances : No clearance given. No environmental management
plan.
This
mine is located very close to the Delhi border (in close proximity to the Asola sanctuary). EPCA members were
shown two pits, which were not being worked currently. There was no groundwater
exploitation seen in these pits. Only brown stagnant rain water was seen. But
what was very clear was that this mining lease was adjoining the boundary of Delhi. Only recent plantation of sapling
was noticed along the path.
2.
(13) Name of Mine/Area: Anangpur Silica Sand Mines M/s. Mohan Ram and Co.
Location
: Village Anangpur, Distt. Faridabad.
Total
Area of Land on lease/Actual area under mining activity : 175.00 Hec.
Mineral
Extracted: Silica Sand Mines.
Status
of Mining : Below groundwater level Whether ground water is extracted : Yes
Status of environmental clearances : NOC granted by state pollution control
board for renewal of lease in 1999. No environmental management plan.
This
mine has large pits where sand and silica was being extracted. This was a
working mine and had large amount of water in the two pits.
EPCA
members also saw a pipe, which was currently unused, meant for pumping out the
water from the pits. The pits were at least 100-150 feet deep and the
groundwater had been clearly exploited for some time. Large amount of
overburden were also seen in the area.
3.
(12) Name of Mine/Area: Anangpur Silica sand mines, M/s. S.P. Sethi, Anangpur.
Location:
Village Anangpur Distt. Faridabad.
Total
Area of Land on lease/Actual area under mining activity: 489.34 hec.
Mineral
Extracted : Silica sand, China clay, ordinary sand, stone road material (RM)
and masonry stone (MS) Status of Mining : Below groundwater table Whether
ground water is extracted : Yes.
Status
of environmental clearances: No clearance given. No environmental management
plan.
The
mining pit here has tuned into a huge groundwater lake, Groundwater is fully
exposed.
Extensive
oberburden could be seen near the pits.
It was
very evident that no major efforts were made to create plantation in the area.
Some new and young saplings could be seen along side the paths leading to the
pits. Clearly these were planted very recently.
4. (8)
Name of Mine/Area: Anangpur Silica sand mines, M/s. Rajdhani Minerals
Corporation.
Location:
Village Anangpur Distt. Faridabad.
Total
Area of Land on lease/Actual area under mining activity: 188.47 hec. Mineral Extracted
: Silica sand, China clay, ordinary sand, stone RM and MS Status: seen one
closed pit. Did not see any water.
Status
of environmental clearances: NOC granted by State Pollution Control Board.
5. (7)
Name of Mine/Area: Mewla maharajpur Silica sand mines, M/s K.C. Ahuja & Co.
Location:
Village Mewla Maharajpur Distt.. Faridabad.
Total
Area of Land on lease/Actual area under mining activity: 162.905 hec. Mineral Extracted
: Silica sand, China clay, ordinary sand, stone road material (RM) and masonry
stone (MS) Status : surface mining from the rocks Whether ground water is
extracted : No.
Status
of environmental clearances: No clearance given. No environmental management
plan.
One
pit seen, Mostly stone being quarried. Some water seen. No evidence of tree
plantation seen in the area. But mine pits are ajoining road.
6.
(19) Name of Mine/Area: M/s. Ramkrishna Purni Devi..
Location:
Village Badkal Distt. Faridabad.
Total
Area of Land on lease/Actual area under mining activity: 369.4 hec. (Of this 121
hec. Falls within 2 km of Badkal Tourist Complex where mining has been banned)
Mineral Extracted : Silica sand, ordinary sand, road metal, masonry stone and
minor mineral Status: mining above groundwater table Whether ground water is
extracted : No.
Status
of environmental clearances: No clearance given. No environmental management
plan.
EPCA
members saw one pit located next to the border of Delhi. The mining area is hard rock and
the pit was being worked for stone. The mining site was at the boundary of Delhi and the Asola sanctuary was seen at
a close distance. This mine is also adjoining the road.
7. (2)
Name of Mine/Area: Mohan Ram & Co. Proprietor Kartar Singh.
Location:
Village Pali Distt. Faridabad.
Mineral
extracted : Ordinary stone, road metal, masonry stone Under litigation in High
Court of Delhi.
8.
(11) Name of Mine/Area: Pali Silica Sand Mines, M/s Goodwill Mineral
Corporation.
Location:
Village Pali, Distt. Faridabad.
Total
Area of Land on lease/Actual area under mining activity: 50.5 hec.
Mineral
Extracted : Silica sand, China clay, sand Status of Mining : Below water table.
Whether
ground water is extracted : Yes.
Status
of environmental clearances: NOC granted by State Pollution Control Board in
1999 for renewal of lease. Asked to comply with conditions laid down by CPCB as
well. No environmental management plan as yet.
A deep
pit with extensive water body. Pipes pumps and generators could be seen at the
site.
Water
is extracted from the pit. Very little plantation could be seen at the site.
The pit is contiguous to other mines in the area and the extent of groundwater
being exploited is massive and the expanse is vast. Some trees have been
planted along the roadside. This mine is adjoining the main Delhi bypass of Faridabad-Gurgaon,
which is being tendered for a four-lane highway.
9.
(17) Name of Mine/Area: M/s. Sheeshpal Singh Location: Village Pali, Distt. Faridabad.
Total
Area of Land on lease/Actual area under mining activity: 127.95 hec.
Mineral
Extracted : Silica, China clay, sand, quartzite Status: Below groundwater
table.
Whether
ground water is extracted : Yes.
Status
of environmental clearances: No clearance given. No environmental management
plan.
Large
lake of ground water could be seen at the site. The lake apparently covers a
few contiguous mining pits. No efforts to create plantation in the area except
a few young saplings which seemed to have been planted very recently. Huge
overburden could be seen near the pits. This mine is adjoining the main Delhi
bypass of Faridabad-Gurgaon, which is being tendered for a four lane highway.
10.
(20) Name of Mine/Area: M/s. Ram Chandar Location: Village Gothra, Mohatabad, Distt.
Faridabad.
Total
Area of Land on lease/Actual area under mining activity: 296 hec.
Mineral
Extracted : Silica sand, ordinary sand, road metal and masonry stone.
Status:
Below groundwater table Whether ground water is extracted : Yes.
Status
of environmental clearances: No clearance given. No environmental management
plan.
Deep
mining pits with large water bodies could be seen. The mine is also contiguous
to the other mines so the amount of water that is being exploited is massive
and uncontrolled. Huge amounts of overburden were also seen in the area. In
this mine some efforts have been made to create plantations and the trees,
unlike those seen in other areas, were more mature. This mine is adjoining the
main bypass of Faridabad- Gurgaon, which is being tendered for a four-lane
highway.
11.
(22) Name of Mine/Area: M/s. Maruti Minerals.
Location:
Plot No.1 Village Manger, Distt. Faridabad.
Total
Area of Land on lease/Actual area under mining activity: 63.225 hec.
Mineral
Extracted : Silica sand, China clay, ordinary sand, road metal and masonry
stone.
Status:
above groundwater.
Whether
ground water is extracted :No .
Status
of environmental clearances: clearance given. No environmental management plan.
Observed
surface stone mining. No water seen.
New
lease and so the mines have not reached ground water levels as yet. But mine
ear Delhi bypass of Faridabad-Gurgaon road.
12A.
(1) Name of Mine/Area: M/s. Seven Mines and Minerals Pvt. Ltd.
Location:
Plot No.6, Village Manger, Distt.
Faridabad.
Total
Area of Land on lease/Actual area under mining activity: 59.3875 hec.
Mineral
Extracted : Ordinary sand, road metal and masonry stone.
Status:
Above groundwater table Whether ground water is extracted : No.
Status
of environmental clearances: Clearance given. No environmental management plan.
Observed
surface stone mining. No water seen.
New
lease and so the mines have not reached groundwater levels as yet. But mine
near Delhi bypass of Faridabad-Gurgaon Road. 12B.
Name
of Mine/Area: M/s. Seven Mines & Minerals Pvt. Ltd.
Location:
Plot No.8, Village Manger, Distt. Faridabad.
Total
Area of Land on lease/Actual area under mining activity: 63.75 hec.
Mineral
Extracted : Ordinary sand, road metal and masonry stone.
Status:
Above groundwater table Whether ground water is extracted : No.
Status
of environmental clearances: Clearance given. No environmental management plan.
Observed
surface stone mining. No water seen.
New
lease and so the mines have not reached groundwater levels as yet. But mine
near Delhi bypass of Faridabad-Gurgaon road.
13.
(25) Name of Mine/Area: M/s. Ashok Minerals industry Location: Plot No.7,
Village Manger, Distt. Faridabad.
Total
Area of Land on lease/Actual area under mining activity:67.00 hec.
Status:
Above groundwater table Whether ground water is extracted : No.
Status
of environmental clearances: No clearance given. No environmental management
plan.
Observed
surface stone mining. No water seen.
New
lease and so the mines have not reached groundwater levels as yet. But mine is
on the Delhi bypass of Faridabad-Gurgaon road.
14.
(23) Name of Mine/Area: M/s. Jaikrishan Impex Pvt. Ltd.
Location:
Plot No.2 & 3, Village Manger, Distt. Faridabad.
Total
Area of Land on lease/Actual area under mining activity: 44.785 hec and 56.4375
hec.
Mineral
Extracted : Stone mining Status: Below groundwater table Whether ground water
is extracted : Yes.
Status
of environmental clearances: No clearance given. No environmental management
plan.
Was
shown one pit with small water collection.
But at
a distance seen another pit with large amount of groundwater collected. This
mine is being worked and clearly water must have been pumped from the mine. Deep
pits seen. But mine is near Delhi bypass
of Faridabad-Gurgaon road.
15.
(10) Name of Mine/Area: M/s. Faridabad Gurgaon
Minerals.
Location:
Plot No.5 Village Manger, Distt. Faridabad.
Total
Area of Land on lease/Actual area under mining activity:33.0375 hec.
Mineral
Extracted : Ordinary sand, road metal and masonry stone Status: Below
groundwater table Whether ground water is extracted : Yes.
Status
of environmental clearances: No clearance given. No environmental management
plan.
Exposed
groundwater could be seen. This mine was also been worked. Deep pits seen in
this mine.
16.
(24) Name of Mine/Area: M/s. Patram Mines and Minerals Pvt. Ltd.
Location:
Plot No.11, Village Manger, Distt. Faridabad.
Total
Area of Land on lease/Actual area under mining activity: 126.75 hec.
Mineral
Extracted : Silica sand and stone Status: Above groundwater table.
Whether
ground water is extracted : No.
Status
of environmental clearances: No clearance given. No environmental management
plan.
Stone
quarry. No water seen. Some efforts have been made to create plantation.
17.
(18) Name of Mine/Area: M/s. Sheeshpal Singh Location: Village Pali, Distt. Faridabad.
Total
Area of Land on lease/Actual area under mining activity: 44.48 hec.
Mineral
Extracted : Solica/Ord. Sand & stone, road metal and masonry stone Status:
Above groundwater table Whether ground water is extracted : No.
Status
of environmental clearances: No clearance given. No environmental management
plan.
Recent
lease. Mining activity had recently started.
New
pit seen and as yet only stone was being quarried.
18.
(4) Name of Mine/Area: Pali Silica Sand Mines, M/s. S.P. Sethi.
Location:
Village Pali, Distt. Faridabad.
Total
Area of Land on lease/Actual area under mining activity: 82.20 hec.
Mineral
Extracted : Silica/Ord. Sand, china clay stone (road metal and masonry) Status:
Below groundwater table Whether ground water is extracted : Yes.
Status
of environmental clearances: NOC given by State Pollution Control Board in 1999
for renewal of lease. No environmental management plan.
Pit
with little water seen. Being worked. Large amount of overburden was seen close
to mine. 1 hec of plantation created near mine.
19.
(3) Name of Mine/Area: Pali Silica Sand Mines, M/s. P.K. Sethi Location: Pali, Distt.
Faridabad.
Total
Area of Land on lease/Actual area under mining activity: 162 hec.
Mineral
Extracted : Sand china clay, stone (road and masonry) Status: Above groundwater
table Whether ground water is extracted : No.
Status
of environmental clearances: No clearance given. No environmental management
plan.
Pit
with no water seen. Being worked. Large amount of overburden was seen close to
mine.
20.
(5) Name of Mine/Area: Pali Silica Sand Mines, M/s. Lucky Minerals Location:
Village Pali, Distt. Faridabad.
Total
Area of Land on lease/Actual area under mining activity: 261.36 hec.
Mineral
Extracted : Sand, china clay stone (road metal and masonry) Status: Above
groundwater table Whether ground water is extracted : No.
Status
of environmental clearances: No clearance given. No environmental management
plan.
Pit
with no water seen. Being worked. Large amount of overburden was seen close to
mine.
Nominal
plantation seen. But area with lessee is very large over - 261 ha - and no idea
if other mines in the area have reached water levels.
21.
(6) Name of Mine/Area: Mohabatabad Silica sand mines, M/s. P.K. Sethi Location:
Village Mohtabad, Distt. Faridabad.
Total
Area of Land on lease/Actual area under mining activity: 399.59 hec.
Mineral
Extracted : Sand, china clay, stone (road metal and masonry) Status: Above
groundwater table Whether ground water is extracted : No.
Status
of environmental clearances: No clearance given. No environmental management
plan.
Shown
pit where stone is being quarried. But area with lessee is very large over -
almost 400 hec. - and no idea if other mines in the area have reached water
level as yet.
22.
(14) Name of Mine/Area: M/s. Tejvir Singh and Co.
Location:
Village Bandhwari, Distt. Gurgaon.
Total
Area of Land on lease/Actual area under mining activity: 91.20 hec.
Mineral
Extracted : Silica Sand, Ord. Sand, china clay, quartz & stone mine.
Status:
Above groundwater table Whether ground water is extracted : No.
Status
of environmental clearances: Clearance given. No environmental management plan.
Stone
quarry. Very recent lease granted and clearance has only been done in April
2002.
Large
seemingly abandoned, pits seen on road.
Labourer
colony near on road near mine and a number of trucks seen on this road carrying
material. No plantation seen.
23.
(15) Name of Mine/Area: Mr. Ashok Gupta Location: Village Balola, Distt. Gurgaon.
Total
Area of Land on lease/Actual area under mining activity: 19.15 hec.
Mineral
Extracted : Silica Sand and china clay.
Status:
Above groundwater table Whether ground water is extracted : No.
Status
of environmental clearances: Clearance given. No environmental management plan.
Stone
quarry Recent lease and clearance of January 2002. No plantation seen. The mine
is on the main Delhi bypass - Gurgaon-Faridabad road,
which is being developed as a four-lane bypass.
24.
(16) Name of Mine/Area: Mr. Ashok Gupta Location: Plot No.3, Village Behrampur,
Distt. Gurgaon.
Total
Area of Land on lease/Actual area under mining activity: 94.05 hec.
Mineral
Extracted : Silica sand quartzites.
Status:
Above groundwater table Whether ground water is extracted : No.
Status
of environmental clearances: No clearance given. No environmental management
plan.
Stone
quarry. Recent lease. No plantation seen.
But
near village. As this mine is near the five km radius, other mines with
crushers and blasting seen at close distance.
(11B -
22) Name of Mine/Area: M/s. Maruti Minerals Location: Village Haidpur, Distt. Gurgaon.
Total
Area of Land on lease/Actual area under mining activity: 18.125 hec.
Mineral
Extracted : Stone Status: Above groundwater table Whether ground water is
extracted : No.
Status
of environmental clearances: No clearance given. No environmental management
plan.
Stone
quarry. No plantation seen. Near habitation of Gurgaon town.
25.
(21) Name of Mine/Area: Mr. Karan Singh Location: Village Nathpur, Distt. Gurgaon.
Total
Area of Land on lease/Actual area under mining activity: 5.996 hec.
Mineral
Extracted : Silica Sand .
Status:
Above groundwater level (surface mining) Whether ground water is extracted :
No.
Status
of environmental clearances: No Clearance given. No environmental management
plan.
Stone
quarry. No plantation seen. Mine on main Delhi-Gurgaon road at the border of Delhi. Mine lease recently awarded at the
edge of the DLF residential colony. Allegations that illegal mining is being
done at the Delhi side of this mine. Next to the
protected area of Delhi forest.
In
respect of the ground water regime the report states that :
"The
key issue to examine is the impact of mining on the ground water regime in the
region. It is evident from the inspection done by EPCA that ground water
reserves are being exploited and destroyed, it must be stressed that it is not
a matter of individual mines reaching ground water levels or not, the issue to
examine is the water regime of the entire area." The report further states
that "during its inspection to the mines, Kartar Singh Badana, Minister of
Cooperatives in the State and also a mine owner told EPCA members that the
impact of ground water abstraction is minimal. He maintained that the miners
were harvesting the water and not allowing it to flow to the Yamuna, where it would
be lost to the State. A perusal of the reports of the ground water regime shows
that this contention cannot be upheld." It is also stated in the report
that "the geology and geomorphology of the area comprises oldest exposed lithology
with upland units. The rock type is mainly quartzite and these rise 150-200 metres
above ground level in the quartzite's the ground water aquifers occur in the
weathered zones and interspaces within interconnected joints and fractures.
According to the CGWB, the unconfined aquifer is about 50 metres thick. But between
the 50-110 metre below ground level (bgi) a thick clay layer ranging in
thickness from 25-60 metres separates the top unconfined aquifer from the
confined aquifer.
The
mines inspected by EPCA were below 150 feet (45 metres) and on checking it was
found that most mines were further operating at 20-100 feet (6-30 metres) below
water levels. This means that the mines are abstracting water from the confined
aquifer. As annual rainfall mostly replenishes the unconfined or top aquifer
levels, the mining activity is destroying a non-renewable resource. EPCA saw
deep and extensive pits of mines with vast waterbodies ? stretching at times to
a kilometer and more. EPCA also saw evidence of pumps and pipes being used to
drain out the ground water so that mining could continue. Therefore, the miners
are mining for silica, but also in the process mining and destroying the ground
water reserves of the areas.
The
NOC given by the Central Pollution Control Board includes an explicit condition
regarding ground water :
"That
the mine owner will ensure that there is no discharge of effluent or ground
water outside lease premises. They must take measures for rain water harvesting
and reuse of water so as not to affect the ground water table in the areas.
Most importantly, it stipulates that there should be no mining operations shall
be carried out in the water table area." The report of the Central Ground
Water Board states very categorically that the ground water table is already at
a critical stage in Faridabad. It states, `The stage of ground
water development of Faridabad block is 89.02 percent in dark category and no
further abstraction of ground water should be carried out to avoid any adverse
environment impact on ground water regimes. Thus no additional tube wells are
advisable to be constructed for community water supply scheme even though they
may not affect the storage in Badkhal lake.' The report further states that
`The domestic water supply to Faridabad town
has to be catered and there are no surface water source which can be tapped.'
EPCA further observes that most of the mining is happening inside the municipal
area of Faridabad. In fact, Department of Mines and
Geology states in the letter dated October 12, 2002, `it is submitted that the
mineral rights of the mines vests with the State Government....The surface
rights of villages Badkhal, Pali, Gothra, Mohabtabad, Anangpur, Mewla Maharajpur
are with municipal corporation, Faridabad, and Manager revenue estate are with
gram panchayat.' Sensitivity of this region is further accentuated by its close
proximity to the reserved forests of Asola sanctuary located at the border of Delhi and Haryana and other ecologically
sensitive areas like Surajkund and Badkhal lake.
Even
in Gurgaon, the CGWB report indicates that the ground water scenario is grim.
According to CGWB, the `ground water development of Guirgaon block is 124 per
cent, indicating that the entire block in which Gurgaon town is situated is
over exploited.' The ground water levels are also falling dangerously according
to the report of CGWB which recommends strict regulatory measures for ground
water use.
The
EPCA, while reaffirming the recommendations that had been made in its earlier
report dated 9th
August, 2002, made the
following recommendations :
"The
overall assessment of the environmental impact of the mining activities in the
area especially its implication for ground water level in the region reaffirms EPCA's
assessment presented in its earlier report. EPCA upholds its earlier
recommendations made vide the report submitted to the Hon'ble Supreme Court on August 9, 2002.
EPCA
is concerned that if mining is allowed to continue in this area, it will have
serious implications for the groundwater reserve which is the only source of
drinking water in the area.
EPCA
has also noticed uncontrolled construction activities that will expand urban
habitation considerably in future. Unless immediate measures are taken to
conserve and augment water resources in the area acute survival crisis is
expected. Interviews with local villagers in the vicinity of mines confirm that
water shortage is already a serious problem in the region.
The
extent of degradation in and around mines is the evidence of failure to enforce
basic rules for ecological safeguards. Recent attempts at planting trees are
cosmetic. Exposed ground water lakes observed in mining sites only reconfirms
the worst fears. If mining could not be stopped in so many pits even after
reaching groundwater level there is no guarantee that even some of those mines
still at the surface level will abide by the stipulated norms when they reach
the water table." Submissions for Confirming or varying Order dated 6th
May, 2002 Having regard to the ground realities as reflected in the aforesaid
reports, should the order passed on 6th May, 2002 be varied is the question?
The continuance of the order has been strenuously objected to by the mining
lease holders and also by the Government of Haryana.
Various
applications have been filed seeking vacation of the order and in support
thereof, submissions have been made mainly by Mr. Shanti Bhushan, Dr. Rajeev Dhawan,
Mr. Kapil Sibbal, Mr. K.B. Rohtagi and Mr. Dhruv Mehta representing the lease
holders and Mr. Mukul Rohtagi, learned Additional Solicitor General
representing the Government of Haryana. We have also heard Mr. Raju Ramachandran
and Mr.Altaf Ahmad, learned Additional Solicitor Generals for the Ministry of
Environment and Forest, Government of India, Mr. C.S. Vaidyanathan and Mr. Kaushik
(in support of IA No.1825/2002 filed by the villagers). Mr. Ranjit Kumar,
learned Amicus and Mr. M.C. Mehta, Advocate/petitioner-in- person and Mr. Kailash
Vasudeva for Government of Delhi have made submissions in support of closure of
mining activity and for making the order dated 6th May, 2002 absolute by
prohibiting all mining activities and pumping of ground water in and from an
area upto 5 kms. from Delhi- Haryana Border in the Haryana side of the Ridge
and also in the Aravalli Hills.
Notifications
Regarding Mining on Aravalli Hills The notification dated 7th May, 1992 issued
by the Ministry of Environment and Forest, Government of India under Section
3(2)(v) of the EP Act read with Rule 5 of the Rules made under the said Act has
considerable bearing on the aspect of mining in Aravalli Hills. The
notification, inter alia, bans all new mining operations including renewals of
mining leases and sets out the procedure for taking prior permission before
undertaking such an activity. The notification, in so far as material for the
present purposes, reads :
"S.O.319(E)
- Whereas a Notification under Section 3(1) and Section 3(2) (v) of the
Environment (Protection) Act, 1986 (29 of 1986) inviting objections against
restricting certain activities in specified area of Aravalli Range which are
causing Environmental Degradation in the Region was published in the Gazette of
India Part II-Section 3 sub-section (ii) vide S.O. 25 (E) dated 9th January
1992;
And
whereas all objections received have been duly considered by the Central
Government;
Now,
therefore, in exercise of the powers conferred by sub-section (1) and clause
(v) of sub- section (2), of Section 3 of the Environment (Protection) Act, 1986
(29 of 1986), read with rule 5 of the Environment (Protection) Rules, 1986 the
Central Government hereby prohibits the carrying on the following process and
operations, except with its prior permission, in the areas specified in the
Table appended to this Notification :
(i)
......
(ii)
(a) All new mining operations including renewals of mining leases (b) Existing
mining leases in sanctuaries/national Park and areas covered under Project
Tiger and/or (c) Mining is being done without permission of the competent
authority (iii) Cutting of trees;
(iv)
Construction of any clusters of dwelling units, farmhouses, sheds, community
centers, information centers and any other activity connected with such
construction (including roads a part of any infrastructure relating thereto);
(v)
......
2. Any
person who desires to undertake any of the above mentioned processes or
operations in the said areas, shall submit an application to the Secretary,
Ministry of Environment and Forests, New Delhi, in the attached application
form (annexure) specifying, inter alia, details of the area and proposed
process or operation. He shall also furnish an Environment Impact Statement and
an Environmental Management Plan along with the application and such other
information as may be required by the Central Government for considering the
application.
(3)
The Central Government in the Ministry of Environment and Forests shall, having
regard to the guidelines issued by it from time to time for giving effect to
the provisions of the said Act, grant permission within a period of three
months from the date of receipt of the application or where further information
has been asked for from the applicant, within a period of three months from the
date of the receipt of such information, or refuse permission within the said
time on the basis of the impact of the proposed process or operation on the
environment in the said area.
4. For
seeking permission under this Notification, an application in the prescribed
form (see Annexure), duly filled in, may be submitted to the Secretary,
ministry of Environment and Forests, Paryavaran Bhavan, CGO Complex, Lodi Road,
New Delhi.
XXX
XXXX XXXX 3.(b)(ii) Erodability classification of the proposed land.
5.(a)
Water balance at site surface and ground water availability and demand.
XXX
XXXX XXXX 12.(a) Environmental Impact Assessment Report:
(b)
Environmental Management Plan : prepared as per Guidelines of MEF issued from
time to time.
(c)
Detailed Feasibility Report.
(d)
Proposal for diversion of forest land under Forest (Conservation) Act, 1980 including benefit cost analysis.
13.
Recommendations of the State Pollution Control Board and/or the State
Department of Environment and Forests." The aforesaid notification,
restricting mining activities in Aravalli range is relevant for mining
operation in Gurgaon district wherein part of Aravalli hills range exist.
The
powers vested in the Central Government in terms of the aforesaid notification
dated 7th May, 1992 were delegated to the State
Governments concerned, namely, Rajasthan and Haryana by issue of notification
dated November 29, 1999 by the Central Government, Ministry
of Environment and Forest. The said notification reads thus :
MINISTRY
OF ENVIRONMENT AND FORESTS NOTIFICATION New Delhi, the 29th November, 1999
S.O.1189(E).-In exercise of the powers conferred by section 23 of the
Environment (Protection) Act, 1986 (29 of 1986), (hereinafter referred to as
the said Act), read with sub-rule (4) of rule 5 of the Environment (Protection)
Rules, 1986, the Central Government hereby delegates the powers conferred on it
to take measures for protecting and improving the quality of the environment
and preventing, controlling and abating environmental pollution, to be
exercised also by the State Governments as notified in the Notification of the
Government of India in the Ministry of Environment and Forests S.O. NO.319(E)
dated 7th May, 1992 subject to certain conditions which are as follows :
(i) the
State Governments concerned, namely, Haryana and Rajasthan shall constitute an
Expert Committee for each state as per the composition given in the Schedule-I
annexed to this Notification;
(ii)
each State Government shall also constitute a Monitoring Committee, under the
chairmanship of the District Collector concerned (Gurgaon in Haryana and Alwar
in Rajasthan) as given in the Schedule-II annexed to this Notification which
shall inter alia monitor the compliance of the conditions stipulated while
according environmental clearance by such State Governments and report to such
State Government about the violations, if any, and the action taken thereon;
(iii)
The District Collectors of Gurgaon in Haryana and Alwar in Rajasthan shall be authorised
by the respective State Governments to take necessary action under section 5 of
the said Act in respect of cases where the project proponents fail to implement
the conditions.
2. The
State Government concerned shall initiate steps to prepare a Master Plan for
the development of the area covered by the Notification S.O. 319(E) dated 7th May, 1992 integrating environmental concerns and
keeping in view the future land use of the area. This Master Plan shall be
prepared by the concerned state agency, approved by the competent authority and
finally published within two years from the date of issue of this Notification,
in accordance with the procedure laid down in the Town and Country Planning Act
or any other similar Act of the respective State Government. The State
Government concerned shall implement the Master Plan forthwith after its final
publication.
3. Any
person desirous of undertaking any of the activities mentioned in the
Notification No.319(E) dated 7th May, 1992
shall submit an application to the Secretary, Department of Environment of the
Government of Haryana/Rajasthan, as the case may be. The applicant shall also
furnish environment impact statement and an environment management plan and
such other information as may be prescribed by such State Governments. The
application after due scrutiny shall be placed before the Expert Committee for
its recommendations. Based on the recommendations of the Expert Committee, the
Department of Environment in the State Government concerned shall take a final
decision and convey the same to the applicant within three months from the date
of receipt of application or when further information has been asked for from
the applicant within three months from the date of receipt of such information.
4. The
Ministry of Environment and Forests retains appellate power against rejection
of any proposal and the National Environmental Appellate Authority constituted
under the National Environment Appellate Authority Act, 1997 (22 of 1997) shall
continue as an Appellate Authority against approval." Schedule I and II of
the notification sets out the composition of the Expert Committee and of the Monitoring
Committee. Some controversy and confusion in respect of constitution of
committees insofar as it relates to appointment of an expert from
non-government organization, was brought to our notice but the delegation in favour
of State Governments having been withdrawn now, it is not necessary to examine
this aspect.
The
Central Government, in terms of notification dated 28th February, 2003, has withdrawn the delegation in favour of State
Governments.
Notification
of 27th January, 1994 Regarding Environment Impact
Assessment (EIA) Another notification which is of considerable importance on
aspect of mining is dated 27th January, 1994, as amended on 4th
May, 1994. The
notification has been issued by Ministry of Environment and Forest, Government
of India, in exercise of powers conferred by sub-section (1) and clause (5) of
sub-section (2) of Section 3 of the EP Act read with clause (d) of sub-rule (3)
of Rule 6 of the EP Rules stipulating that expansion or modernization of any
activity (if the pollution load is to exceed the existing one) or a new project
listed in Schedule I of the notification shall not be undertaken in any part of
India unless it has been accorded environmental clearance by the Central
Government in accordance with the procedure specified in the notification.
The
issue in these matters is about the interpretation of the notification, its
applicability also to mining leases granted earlier to the issue of the
notification i.e. at the time of the renewal of such mining lease.
The
notification dated 27th
January, 1994, to the
extent material for the present purpose, reads as under :
"S.O.60(E)
Whereas a notification under clause (a) of sub-rule (3) of rule 5 of the
Environment (Protection) Rules, 1986 inviting objections from the public within
sixty days from the date of publication of the said notification, against the
intention of the Central Government to impose restrictions and prohibitions on
the expansion and modernization of any activity or new projects being
undertaken in any part of India unless environmental clearance has been
accorded by the Central Government or the State Government in accordance with
the procedure specified in that notification was published as S.O. No.80(E)
dated 28th January, 1993:
And
whereas all objections received have been duly considered;
Now,
therefore, in exercise of the powers conferred by sub-section (1) and clause
(v) of sub- section (2) of section 3 of the Environment (Protection) Act, 1986
(29 of 1986) read with clause (d) of sub-rule (3) of rule 5 of the Environment
(Protection) Rules, 1986, the Central Government hereby directs that on and
from the date of publication of this notification in the Official Gazette
expansion or modernization of any activity (if pollution load is to exceed the
existing one) or a new project listed in Schedule I of this notification shall
not be undertaken in any part of India unless it has been accorded
environmental clearance by the Central Government in accordance with the
procedure hereinafter specified in this notification.
2.
Requirements and procedure for seeking environmental clearance of projects:
1.(a)
Any person who desires to undertake any new project or the expansion or
modernization of any existing industry or project listed in Schedule I shall
submit an application to the Secretary, Ministry of Environment and Forests, New Delhi.
The
application shall be made in the proforma specified in Schedule II of this
notification and shall be accompanied by a project report which shall, inter alia,
include an Environmental Impact Assessment Report/Environment Management Plan
prepared in accordance with the guidelines issued by the Central Government in
the Ministry of Environment and Forests from time to time.
(b)
Cases rejected due to submission of insufficient or inadequate data and plans
may be reviewed as and when submitted with complete data and plans. Submission
of incomplete data or plans for the second time would itself be a sufficient
reason for the Impact Assessment Agency to reject the case summarily.
II. In
case of the following site specific projects:
(a) mining;
(b) to
(d) ...
(e)
prospecting and exploration of major minerals in areas above 500 ha., The
project authorities will intimate the location of the project site to the
Central Government in the Ministry of Environment and Forests while initiating
any investigation and surveys. The Central Government in the Ministry of
Environment and Forests will convey a decision regarding suitability or
otherwise of the proposed site within a maximum period of thirty days. The said
site clearance shall be granted for a sanctioned capacity and shall be valid
for a period of five years for commencing the construction, operation or
mining.
III.(a)
The reports submitted with the application shall be evaluated and assessed by
the Impact Assessment Agency, and if deemed necessary it may consult a
Committee of Experts, having a composition as specified in Schedule-III of this
Notification. The Impact Assessment Agency (IAA) would be the Union Ministry of
Environment and Forests. The Committee of Experts mentioned above shall be
constituted by the IAA or such other body under the Central Government authorised
by the IAA in this regard.
(b)
The said Committee of Experts shall have full right of entry and inspection of
the site or, as the case may be, factory premises at any time prior to, during
or after the commencement of the operations relating to the project.
(c)
The Impact Assessment Agency shall prepare a set of recommendations based on
technical assessment of documents and data, furnished by the project
authorities, supplemented by data collected during visits to sites or
factories, if undertaken, and interaction with affected population and
environmental groups, if necessary.
Summary
of the reports, the recommendation and the conditions, subject to which
environmental clearance is given, shall be made available subject to the public
interest to the concerned parties or environmental groups on request.
Comments
of the public may be solicited, if so decided by Impact Assessment Agency,
within thirty days of receipt of proposal, in public hearings arranged for the
purpose after giving thirty days notice of such hearings in at least two
newspapers.
Public
shall be provided access, subject to the public interest, to the summary of the
reports/Environmental Management Plans at the Headquarters of the Impact
Assessment Agency.
The
assessment shall be completed within a period of ninety days from receipt of
the requisite documents and data from the project authorities and completion of
public hearing where required, and decision conveyed within thirty days
thereafter.
The
clearance granted shall be valid for a period of five years for commencement of
the construction or operation.
No
construction work preliminary or otherwise, relating to the setting up of the
project may be undertaken till the environmental and/or site clearance is
obtained.
IV. In
order to enable the Impact Assessment Agency to monitor effectively the
implementation of the recommendations and conditions subject to which the
environmental clearance has been given the project authorities concerned shall
submit a half-yearly report to the Impact Assessment Agency. Subject to the
public interest, the Impact Assessment Agency, shall make compliance reports publicly
available.
V. If
no comments from the Impact Assessment Agency are received within the time
limit, the project would be deemed to have been approved as proposed by project
authorities.
3.
Nothing contained in this Notification shall apply to :
(a)
any item falling under entry nos.3, 18 and 20 of the Schedule I to be located
or proposed to be located in the areas covered by the Notifications S.O.
No.102(E) dated 1st February, 1989; S.O. 114(E) dated 20th February, 1991, S.O.
No.416(E) dated 20th June, 1991 and S.O. No.319(E) dated 7th May, 1992.
(b)
any item falling under entry Nos.1, 2, 3, 4, 5, 7, 9, 10, 12, 13, 14, 16, 17,
19, 21, 25 and 27 of Schedule-I if the investment is less than Rs.50 crores.
(c) any
item reserved for Small Scale Industrial sector with investments less than Rs.1
crore.
4.
Concealing factual data or submission of false, misleading data/reports,
decisions or recommendations would lead to the project being rejected.
Approval, if granted earlier on the basis of false data would also be to be
revoked.
Misleading
and wrong information will cover the following :
--
False information;
--
False data.
--
Engineered reports.
--
Concealing of factual data.
--
False recommendations of decisions.
SCHEDULE-I
(See paras 1 and 2) LIST OF PROJECTS REQUIRING ENVIRONMENTAL CLEARANCE FROM THE
CENTRAL GOVERNMENT.
1.
Nuclear Power and related projects such as Heavy Water Plants, nuclear fuel
complex, rare earths.
2 to 19
...
20.
Mining projects (major minerals) with leases more than 5 hectares.
21 to 29
...
XXX
XXXX XXXX SCHEDULE III (See sub-para III(a) of Para 2) COMPOSITION OF THE EXPERT COMMITTEES
FOR
ENVIRONMENTAL IMPACT ASSESSMENT
1. The
Committee will consist of experts in the following disciplines :
(i)
Eco-System Management
(ii)
Air/Water Pollution Control
(iii)
Water Resource Management
(iv)
Flora/Fauna Conservation and Management
(v)
Land Use Planning
(vi)
Social Sciences/Rehabilitation
(vii)
Project Appraisal
(viii)
Ecology
(ix)
Environmental Health
(x)
Subject Area Specialists.
(xi)
Representatives of NGOs/Persons Concerned With Environmental Issues.
2. The
Chairman will be an outstanding and experienced ecologist or environmentalist
or technical professional with wide managerial experience.
3. The
representative of IAA will act as Member-Secretary
4.
Chairman and members will serve in their individual capacities except those
specifically nominated as representatives.
5. The
membership of a Committee shall not exceed 15.
EXPLANATORY
NOTE REGARDING THE IMPACT ASSESSMENT NOTIFICATION DATED 27TH JANUARY, 1994 1 to 3. ...
4.
Public Hearing Public hearings could be called for in case of projects
involving large displacement or having severe environmental ramifications.
5 to
7. ...
8.
Exemption for projects already initiated For projects listed in Schedule-I to
the notification in respect of which the required land has been acquired and
all relevant clearances of the State Government including NOC from the
respective State Pollution Control Boards have been obtained before 27th
January, 1994, a project proponent will not be required to seek environmental
clearance from the IAA. However, those units who have not as yet commenced
production will inform the IAA." Reference may also be made to a
notification issued by the Haryana Government on November 28, 2001 with a view
to enforce the recommendations of NEERI contained in para 6.1 of its report so
far as mining operations in the State of Haryana are concerned. In terms of the
notification, the Designated Authority and the Monitoring Committee were
directed to impose the conditions mentioned in the notification while according
environmental clearance. This notification, it seems, was issued in the
purported attempt to comply with the directions of this Court as contained in
the order dated 10th
May, 1996 as reported
in M.C. Mehta's case (supra).
We may
also refer to the circular dated May 14, 2002 issued by the Ministry of Environment and Forest noticing that in the past several
units had come up in violation of the notification dated 27th January, 1994 and a view had been taken earlier
that such units are permitted to apply for environment clearance by 31st March, 1999. For period of five years, there
was no circular or notification granting any time to apply for EIA under
notification dated 27th
January, 1994. The
period to apply for environment clearance was extended upto 30th June, 2001 which deadline was extended upto 31st March, 2003, stating that it was to give
opportunity to defaulting units to avail of the last and final opportunity to
obtain ex post facto environment clearance. The notification dated 27th January, 1994 is applicable also to construction
activity. It seems that this circular was issued to give opportunity to those
who had undertaken constructions after issue of notification without compliance
of stipulations therein. We are, however, not concerned in these matters with
the construction which may have come up in breach of the notification. It does
not appear that MOEF intended to legalise the commencement or continuance of
mining activity without compliance of stipulations of the notification. In any
case, a statutory notification cannot be notified by issue of circular.
Further, if MOEF intended to apply this circular also to mining activity commenced
and continued in violation of this notification, it would also show total non-
sensitivity of MOEF to the principles of sustainable development and the object
behind the issue of notification. The circular has no applicability to the
mining activity.
Central
Empowered Committee (CEC) - Its Suggestions The notification dated 27th January, 1994 is mandatory. The compliance of the
notification before commencement of any mining operation is essential and
cannot be dispensed with. The MOEF has not so far conducted Environment Impact
Assessment in respect of any of the mining lease under the notification dated 27th January, 1994.
Before
the order dated 6th
May, 2002 was passed,
the lease holders had not made any application before the Ministry for grant of
EIA. The applications were filed during the pendency of these matters under the
order of this Court. The EIA applications of the lease holders are lying with
CEC. CEC was constituted in terms of notification dated 17th September, 2002,
issued by the Government of India, Ministry of Environment and Forest in
exercise of power conferred by Section 3(3) of the EP Act for the purposes of
monitoring and ensuring compliance of the order of this Court covering the
subject matter of forest and wildlife and related issues arising out of the
said order and one of the functions of the Committee in terms of the
notification is to monitor the implementation of the orders of this Court and
place reports of non-compliance before the Court including in respect of encroachment
and removals, working plans, compensatory afforestation, plantations and other
conservation issues.
In the
order dated 31st October, 2002, this Court has observed that no mining activity
can be carried out without remedial measures taking place and for this purpose,
it is necessary that environment impact assessment is done and the applications
dealt with before any mining activity can be permitted. It was also observed
that the application of lease holders for environmental clearance can be
disposed of them of within a period to be specified by this Court. In terms of
order dated 25th
November, 2002, the
Central Empowered Committee was asked to file its suggestions in regard to the
time for considering the applications for grant of EIA. The CEC had received
large number of voluminous Environment Impact Assessment plans only in the last
few days which are being examined further stating that the process of
examination and formulation of suggestions is likely to take some more time. On
24th January, 2003, the CEC was granted time to file
its report upto 8th
February, 2003. CEC
has filed three reports, the last having been filed on 7th February, 2003.
In an
interim report dated 22nd
June, 2003 CEC stated
that the complete information had not been supplied to it by the State of Haryana.
The
report states that as per the information provided by the Haryana State, in Faridabad district there are 21 sanctioned
major mineral mines with the varying size from 44.48 hectare to 516.518
hectare. In Gurgaon districts 54 mining leases have been sanctioned varying in
size from 5.96 hectare to 802.322 hectare. All the mines of major minerals were
operating in Faridabad district without obtaining
statutory environmental clearance under the EP Act. It also noticed that in respect
of the Aravalli Hills range being an acknowledged as eco friendly area under
the Aravalli notification, clearances were being granted on the basis of
examination of an expert group without any public hearing or participation of
NGOs or the affected people. As already noticed, the delegation in favour of
the State has been now withdrawn. The report further observes that most of the
mines are operating in violation of approved plans. Instead of doing section
wise mining (bench mining) the mining operations are carried on
unscientifically with the sole aim to make maximum profits which has resulted
in number of fatal accidents involving labourers, hazards to the adjoining
population, indiscriminate scattering of the over burden, wasteful manner of
mining with complete disregard to mineral conservation aspect, rendering
reclamation of mined area impossible. Further it points out that several mining
leases have been granted in areas where plantations were undertaken with the
financial assistance provided by international donor agencies. Mining
activities are permitted in a manner which is destroying the ground water table
and also the deep aquifers thereby causing irreparable damage to the critical
ground water reserves. There is no effective mechanism to ensure compliance of
various conditions stipulated while granting statutory approvals. No deterrent
action was taken against mines even in those cases where during monitoring
serious violations and non compliance of conditions were found. The CEC has
made the following suggestions :
"I)
For major mineral mines above 5 hectare in Faridabad district, mining activity
may be allowed to be undertaken only after the required environmental
clearances are accorded by the Ministry of Environment and Forest (MOEF);
ii)
the powers delegated to the State Government by notification dated 27.1.1997 to
grant environmental clearances in respect of areas of Gurgaon district falling
within Aravalli notification dated 7.5.1992 requires to be reconsidered as the
presumptions on the basis of which powers were delegated to the State
Government have been found to be incorrect;
iii)
mining activity may be allowed in respect of areas notified under Section 4 and
5 of the PLP Act, which for the purpose of FC Act are `forest' even as per the
State Government records, only after obtaining prior approval under the said
Act from the MOEF;
iv) all
mining leases granted in respect of areas where plantations have been raised
under the financial assistance received from any international donor agencies
may be cancelled forthwith. The concerned authorities may be prohibited from
allowing any mining operations, allowing renewals or grants of fresh leases in
such areas;
v) mining
activity may be allowed only as per the approved Mining Plans. Mines which are
found to be operating at variance with the approved Mining Plans may be made
liable for cancellation of lease and payment of exemplary compensation;
vi) in
view of rampant and indiscriminate mining, which was being done, a high level
monitoring committee may be constituted comprising representatives of the State
Government, MOEF, Indian Bureau of Mines, Director General of Mine Safety and
reputed NGOs. This Committee may be empowered to monitor the implementation of
the conditions imposed while approving Mining Plans, grants of environmental
clearances and other approvals/clearances.
Whenever
any violation is detected, the Committee should have the powers to direct
closure of the defaulting mines and also to impose fines commensurate with the
seriousness of the violation;
vii) in
addition to the above
(vi),
the Officials of the State Government, Indian Bureau of Mines, MOEF, Director
General of Mine Safety may independently monitor, at least once in three
months, to ensure compliance of all statutory conditions;
viii) the
State Government may identify and notify officials, who would ensure
enforcement of the directions given by the Monitoring Committee and or the
above mentioned officials;
ix) no
mining activity may be allowed without obtaining `No Objection Certificate'
from the Central Groundwater Board to ensure that the water table and the
underground aquifers are not adversely affected;
x) before
allowing resumption of mining activity in any approved mining lease, the status
of compliance of the conditions of the approved Mining Plans, approved
Environmental Management Plans, environmental clearances and other statutory
conditions/clearances may be ascertained. Suitable and adequate
compensation/penalty for non-compliance of stipulations may be recovered,
otherwise such stipulations would remain only on paper;
xi) in
respect of forest area, including areas notified under Section 4 and 5, net
present value of the land leased out for mining may be recovered as per the Hon'ble
Supreme Court order dated 30.10.2002 in I.A. No.566 in Writ Petition (Civil)
No.202/95 (forest matter);
xii) a
suitable system of securing adequate bank guarantee, bank deposit or other
personal guarantee from the mine owner may be worked out to ensure compliance
of all statutory and other conditions;
xiii)
after considering the annual approved rate of mining and mineral deposits in
the area, optimum size of the mines may be determined in respect of approved
mines to ensure optimum utilization of the mineral resources;
xiv) presently,
the over burden is not stacked as per approved Minining Plan, which makes it
practically impossible to carry out any reclamation work. The over burden
dumping may be allowed only at identified sites within the mining lease area as
per approved Mining Plans;
xv) for
the purpose of afforestation, the funds may be recovered from the mine owners
and deposited with the forest department for undertaking afforestation in a
planned manner;
xvi) the
identification of the consultants for preparation of the EIA's should be done
by the regulating agency instead of by the mine owners to ensure good and
credible reports.
It is
important that payment to the consultants should also be routed through the
regulating agency and not directly by the mine owners." The report of CEC
dated 7th February,
2003 mentions that the
State Government, despite letters, had not made available to the Committee the
following information :
i) mine
wise details of stipulated conditions, which have been fulfilled and those
which have not been fulfilled
ii)
details of five major mineral mines in Faridabad and Gurgaon Districts which
have fulfilled all the conditions stated in the approved mining plans,
environmental and other clearances;
iii) details
of the mines where mining activity has been undertaken without obtaining
requisite environmental clearance.
In the
absence of the information as aforesaid the CEC gave its suggestions on the
basis of information available to it which are as under:
i) the
ban on mining activity may continue up to 2 km from Surajkund and Badkal Lakes, as per the Hon'ble Court's order dated 10.5.1996;
(ii) each
of the existing mines may be physically inspected by Inspection Team(s)
comprising officials of the State Government, Indian Bureau of Mines, Director
General of Mines Safety and the Ministry of Environment and Forest to report the specific conditions
which have not been fulfilled/violated especially in respect of :
a. sectionwise
(benchwise) mining to be done as per approved mining plan;
b.
storage of top soil as per approved mining plan;
c.
dumping of over-burden in identified area as per the approval mining plan;
d.
plantations as per Environmental Management Plan;
e.
observance of mines safety Rules and Regulations;
f.
damage to the plantations raised under externally aided projects (foreign
funding);
g.
damage if any to the water table/underground acquifers; and
h.
compliance of environmental clearance stipulations;
The
Inspection Team(s) may submit the reports to the State Government and the
Ministry of Environment & Forest (MOEF) with copies to the Central
Empowered Committee (CEC) for their comments and for carrying out verification,
if found necessary.
(iii) suitable
penalties for non- compliance/violation of various conditions, as found by the
above Inspection Team(s) or by the CEC may be imposed. Norms for quantifying
the penalties for violation of various conditions may be formulated by the
State Government with the concurrence of the CEC. No mine may be allowed to
resume mining activity without first paying the penalty imposed on it.
(iv) mining
activity may completely be prohibited in area where plantations have been
undertaken with the foreign assistance/funding (externally aided projects).
Mining leases already granted/approved in all such areas may be cancelled;
(v) yearwise
requirement of funds for implementation of various conditions under which
mining has been approved may be computed for each mine. To ensure compliance of
these conditions, adequate safeguards by way of bank guarantee, mortgage of
immovable assets, pledge of movable assets, personnel guarantee of the lessee
or others (supported by adequate assets) may be put in place;
(vi)
MOEF may examine the Environment Impact Assessment Report/Environment Management
Plan of individual major mineral mines and proposals for approval under the FC
Act, if the mining lease is in 'forest' as per the Hon'ble Supreme Courts order
dated 12.12.1996 in Writ Petition (C) No.206/95, and take decision(s) thereon,
including regarding measures for protecting the water table and underground acquifers,
in a time bound manner; and
(vii) regular
inspection of the mines may be undertaken by the identified officials of the
State Government, Indian Bureau of Mines and Director General of Mines Safety.
Mines
which are found to have violated the conditions may be made liable to pay stiff
penalties including closure of the mines." Some mining leases were granted
prior to notification dated 27th January, 1994 and some after the issue of that notification. Even in respect of the
leases granted prior to 27th
January, 1994, the
renewal of most of the leases has come up after issue of notification. Some of
the leases are for extraction of major mineral, some for extraction of minor
mineral and some for extraction of both major and minor mineral. In respect of
none of the leases, before commencement of mining activity, EIA was obtained
from the MOEF. In respect of mining in Aravalli Hills in Gurgaon, the relevant
notifications dated 7th
May, 1992, 29th November, 1999 and 28th January, 2003 have been noticed earlier. Under the notification
dated 7th May, 1992, no permission was granted by the
MOEF though some applications were pending before it when power was delegated
to the State Government. Permissions were granted by the State Government after
the powers were delegated to it. The delegation in favour of the State has
since been withdrawn.
Legal
Parameters The natural sources of air, water and soil cannot be utilized if the
utilization results in irreversible damage to environments. There has been
accelerated degradation of environment primarily on account of lack of
effective enforcement of environmental laws and non-compliance of the statutory
norms. This Court has repeatedly said that the right to live is a fundamental
right under Article 21 of the Constitution and it includes the right to of
enjoyment of pollution-free water and air for full enjoyment of life. (See Subhash
Kumar v. State of Bihar [AIR 1991 SC 420].
Further,
by 42nd Constitutional Amendment, Article 48-A was inserted in the Constitution
in Part IV stipulating that the State shall endeavour to protect and improve
the environment and to safeguard the forest and wildlife of the country.
Article 51A, inter alia, provides that it shall be the duty of every citizen of
India to protect and improve the natural
environment including forest, lakes, rivers and wildlife and to have compassion
for living creatures. Article 47 which provides that it shall be the duty of
the State to raise the level of nutrition and the standard of living and to
improve public health is also relevant in this connection. The most vital
necessities, namely, air, water and soil, having regard to right of life under
Article 21 cannot be permitted to be misused and polluted so as to reduce the
quality of life of others. Having regard to the right of the community at large
it is permissible to encourage the participation of Amicus Curiae, the
appointment of experts and the appointments of monitory committees. The approach
of the Court has to be liberal towards ensuring social justice and protection
of human rights. In M.C. Mehta v. Union of India [(1987) 4 SCC 463], this Court
held that life, public health and ecology has priority over unemployment and
loss of revenue. The definition of 'sustainable development' which Brundtland
gave more than 3 decades back still holds good. The phrase covers the
development that meets the needs of the present without compromising the
ability of the future generation to meet their own needs. In Narmada Bachao Andolan v. Union of India & Ors. [(2000) 10 SCC 664], this Court
observed that sustainable development means the type or extent of development
that can take place and which can be sustained by nature/ecology with or
without mitigation. In these matters, the required standard now is that the
risk of harm to the environment or to human health is to be decided in public
interest, according to a "reasonable person's " test. [See Chairman Barton
: The Status of the Precautionary Principle in Australia : (Vol. 22) (1998) (Harv. Envtt. Law Review, p. 509 at
p.549-A) as in AP Pollution Control Board vs. Prof. M.V. Nayuder (Retd) &
Ors. [(1999) 2 SCC 718].
The
mining operation is hazardous in nature. It impairs ecology and people's right
of natural resources. The entire process of setting up and functioning of
mining operation require utmost good faith and honesty on the part of the
intending entrepreneur. For carrying on any mining activity close to township
which has tendency to degrade environment and are likely to effect air, water
and soil and impair the quality of life of inhabitants of the area, there would
be greater responsibility on the part of the entrepreneur. The fullest
disclosures including the potential for increased burdens on the environment
consequent upon possible increase in the quantum and degree of pollution, has
to be made at the outset so that public and all those concerned including
authorities may decide whether the permission can at all be granted for
carrying on mining activity. The regulatory authorities have to act with utmost
care in ensuring compliance of safeguards, norms and standards to be observed
by such entrepreneurs. When questioned, the regulatory authorities have to show
that the said authorities acted in the manner enjoined upon them. Where the
regulatory authorities, either connive or act negligently by not taking prompt
action to prevent, avoid or control the damage to environment, natural
resources and peoples' life, health and property, the principles of
accountability for restoration and compensation have to be applied.
The
development and the protection of environments are not enemies. If without
degrading the environment or minimising adverse effects thereupon by applying
stringent safeguards, it is possible to carry on development activity applying
the principles of sustainable development, in that eventuality, the development
has to go on because one cannot lose sight of the need for development of
industries, irrigation resources and power projects etc. including the need to
improve employment opportunities and the generation of revenue. A balance has
to be struck. We may note that to stall fast the depletion of forest, series of
orders have been passed by this Court in T.N. Godavarman's case regulating the
felling of trees in all the forests in the country. Principle 15 of Rio
Conference of 1992 relating to the applicability of precautionary principle
which stipulates that where there are threats of serious or irreversible
damage, lack of full scientific certainty shall not be used as a reason for
proposing effective measures to prevent environmental degradation is also
required to be kept in view. In such matters, many a times, the option to be
adopted is not very easy or in a straight jacket. If an activity is allowed to
go ahead, there may be irreparable damage to the environment and if it is
stopped, there may be irreparable damage to economic interest. In case of
doubt, however, protection of environment would have precedence over the economic
interest. Precautionary principle requires anticipatory action to be taken to
prevent harm. The harm can be prevented even on a reasonable suspicion. It is
not always necessary that there should be direct evidence of harm to the
environment.
Bearing
in mind the aforesaid principles, we have to consider the main question: should
the mining activity in areas in question be banned altogether or permitted and,
if so, conditions to be provided therefor? The reports and suggestions of
NEERI, EPCA and CEC have already been extensively noted. The effect of mining
activity in area upto 5 km. from Delhi-Haryana border on Haryana side of the
ridge and also in the Aravalli Hills is to be seen in light of these reports
and another report dealt later.
One of
the aspect stated in these reports is about carrying on of mining activity in
close proximity to the residential area and/or main roads carrying traffic.
Mines
and Minerals (Regulation and Development) Act and Rules thereunder The grant of
mining lease is governed by the Mines and Minerals (Regulation and Development)
Act, 1957 (for short, 'the MMRD Act) which was enacted to provide for the
development and regulation of mines and minerals under the control of the
Union. Section 13 is the rule making power of the Central Government. The
Central Government is empowered to make rules to provide for the manner in
which rehabilitation of flora and other vegetation, such as trees, shrubs and
the like destroyed by reason of any mining operation shall be made in the same area
or in any other area selected by the Central Government (whether by way of
reimbursement of the cost of rehabilitation or otherwise) by the person holding
the mining lease. Section 18, inter alia, casts a duty upon the Central
Government to take all such steps as may be necessary for the conservation and
systematic development of minerals in India and for the protection of
environment by preventing or controlling any pollution which may be caused by
mining operations and for such purposes, the Central Government may, by
notification in the official gazette, make such rules as it thinks fit.
The
Mineral Concession Rules, 1960 have been framed by the Central Government in
exercise of the powers conferred by Section 13 of the MMRD Act. Chapter IV of
these Rules relate to grant of mining leases in respect of land in which the
minerals vest in the Government. Rule 22(4), inter alia, provides that on
receipt of the communication from the State Government of the precise areas to
be granted for mining purpose, the applicant shall submit a mining plan, within
the period stipulated in the Rules, to the Central Government for its approval.
The applicant, on approval of the mining plan by the Central Government, shall
submit the same to the State Government to grant mining lease over that area.
Rule 4A, inter alia, provides that notwithstanding anything contained in Sub-
rule(4), the State Government shall be competent to approve mining plan of open
cost mines (mines other than underground mines) in respect of now metallic or
industrial minerals, named therein, one of it being Silica sand. The mining
plan, as provided in sub-rule (5) of Rule 22, shall, inter alia, incorporate
the mineral reserves of the area and the plan of area showing, inter alia,
water courses, limit of reserves and other forest areas and density of trees,
if any, assessment of impact of mining activity on forest, land surface and
environment including air and water pollution; details of the scheme of
restoration of the area by afforestation, land reclamation, use of pollution
control devices and such other measures as may be directed by the Central
Government or the State Government from time to time. A tentative scheme of
mining and annual programme and plan for excavation from year to year for five years
is also required to be incorporated in the mining plan. Rule 22(5) was inserted
in the Rules by notification dated 27th September, 1994 to which certain amendments were
made in terms of notification dated 17th January, 2000 also inserting by same notification
Rule 22(4A). Sub-rule(4) to Rule 22 ad been earlier inserted by notification
dated 27th September,
1994.
The
grant of permission for mining and approving mining plan and the scheme by the
Ministry of Mines, Government of India by itself does not mean that mining
operation can commence. It cannot be accepted that by approving Mining Plan and
Scheme by Ministry of Mines, Central Government is deemed to have approved
mining and it can commence forthwith on such approval. Section 13 of the MMRD
Act and the Rules made in exercise of powers under the said section, deal,
inter alia, with the aspect of grant of mining of lease and not commencement of
mining operations. Rules made under Section 18, however, deal with commencement
of mining operations and steps required to be taken for protection of
environment by proventing or controlling any pollution which may be caused by
mining operation. A mining lease holder is also required to comply with other
statutory provisions such as Environment (protection) Act, 1986, Air
(Prevention and control of Pollution) Act, 1981, The Water (Prevention and
Control of Pollution) Act, 1974, Forest (Conservation) Act, 1980. Mere approval
of the mining plan by Government of India, Ministry of Mines would not absolve
the lease holder from complying with the other provisions.
Rules
31 to 41 contained in Chapter V of the Mineral Conservation and Development
Rules, 1988 framed under Section 18 of the MMRD Act deal with the measures
required to be taken by the lessee for the protection of environment from any
adverse effect of mining or irreversible consequences thereof. These Rules,
inter alia, provide that every holder of a mining lease shall take all possible
precautions for the protection of environment and control of pollution while
conducting mining operations in the area; shall, wherever top soil exists and
is to be excavated for mining operations, remove it separately and utilize for
restoration or rehabilitation of the land which is no longer required for
mining operations. The holder is also required to take steps so that the
overburden, waste rock, rejects and fines generated during prospecting and
mining operations or tailings, slims and fines produced during sizing salting
and benefication or metallurgical operations shall be stored in separate dumps
which shall be properly secured to prevent escape of material therefrom in
harmful quantities which may cause degradation of environment. Wherever
possible, the waste rock, overburden etc. shall be back-filled into the mines excavation
with a view to restoring the land for its original use as far as possible and
wherever it is not feasible during mining operation, the waste dumps shall be
suitably tarraced and stabilized through vegetation or otherwise. It is also
required that the phased restoration, reclamation and rehabilitation of lands
affected by mining operation shall be undertaken which work shall be completed
before the conclusion of mining operations and the abandonment of mine. Air
pollution due to fines, dust and smoke or gaseous emissions during mining
operations and related activities shall be controlled and kept within
'permissible limits' specified under various environmental laws of the country
including the Air (Prevention and Control of Pollution) Act, 1981 and the
Environment (Protection) Act, 1986 by the holder of mining lease. Further,
noise arising out of such operations shall be abated or controlled by the
lessee at the source so as to keep it within the permissible limit. The mining
operations shall be carried out in such a manner so as to cause least damage to
the flora of the area and nearby areas. Every holder of mining lease shall take
immediate measures for planting in the same area or any other area as selected
by the authorized officer and not less than twice the number of trees destroyed
by reason of any mining operation and look after them during the subsistence of
the licence/lease and restore, to the extent possible, other flora destroyed by
mining operations.
The
aforesaid measures are not required to remain only on paper but strictly
complied for the protection of environment and control of pollution as a result
and consequence of mining operations.
National
Forest Policy In respect of mining in the forest area, we may also refer to the
National Forest Policy, 1988 issued by Ministry of Environment and Forest, Government of India which, inter alia,
notices that over the years, forests in the country have suffered serious
depletion. One of the reason of it is inadequacy of protection measure and
diversion of forest land to non- forest uses. Without ensuring compensatory afforestation
and essential environmental safeguards; and the tendency to look upon forests
as revenue earning resource. The basic objectives of the policy, inter alia,
are maintenance of environment stability through preservation and, where
necessary, restoration of the ecological balance that has been adversely
disturbed by serious depletion of the forests of the country and checking the
soil erosion and water conservation and increasing substantially the
forest/tree cover through massive afforestation and social forestry programmes.
It provides that the National goal should be to have a minimum of 1/3rd of the
total land area of the country under forest or tree cover. In the hills and in
mountains regions, the aim should be to maintain 2/3rd of the area under such
cover in order to prevent erosion and land degradation and to ensure the
stability of the fragile eco-system. It also provides that a massive need based
and time bound programme of afforestation and tree planting, with particular
emphasis on fuel wood and fodder development, on all degraded and denuded lands
in the country, whether forest or non-forest land, is a national imperative.
Mining
in Forest Area The question of permitting mining in the area where large scale
of afforestation with foreign funding has taken place is required to be
examined keeping in view the National Forest Policy which also provides that
forest land or land with tree cover should not be treated merely as a resource
readily available to be utilized for various projects and programmes but as a
national asset which requires to be properly sasfeguarded for providing
sustained benefits to the entire community.
Diversion
of forest land for any non-forest purpose should be subject to the most careful
examinations by specialists from the standpoint of social and environmental
costs and benefits. The mining and industrial development should be consistent
with the needs for conservation of trees in forest. It provides that no mining
should be granted to any party, private or public, without a proper mine
management plan appraised from the environmental angle and enforced by adequate
machinery.
Our
attention was drawn by learned counsel appearing for lease- holders to the part
of national policy which provides that beneficiaries who are allowed mining and
quarrying in forest land and in land covered by trees should be required to
repair and re-vegetate the area in accordance with established forestry practices
to submit that the policy itself contemplates mining operations in the forest
area. For present, we are not suggesting a complete ban of mining operations on
forest land so long as it is possible to undertake the said operation on the
sustainable development principles and after obtaining due approvals under
various statutory provisions including Section 2 of the Forest (Conservation)
Act, 1980. At the same time, we are unable to appreciate the commencement and
continuation of mining over areas on which crores of the foreign funds have
been spent for afforestation and plantation. Further, it is also not possible
to accept the contention urged on behalf of the lease holders that only that
part of such leased land where allegedly damage has been caused to plantation
as a result of mining operations, be excluded from mining and not the entire
area of the lease. For example, if the mining area is 5 hectare and damages as
a result of mining is to plantation in an area of 1 hectare, it is not
practicable or reasonable to exclude only that 1 hectare and permit the mining
operation on the rest of the mining area.
Reference
can also be usefully made to the part of the State of Forest Report, 1999 issued by Forest Survey of
India in relation to Haryana. It, inter alia, provides that large scale
plantations were carried out under Aravalli project since 1992. The document
claims increase of the forest cover in the State as a result of plantation
under the Aravalli project. It, inter alia, mentions that forest cover increase
in Gurgaon and Faridabad is mainly due to plantation raised
under the Aravalli project which was started in early 1990s. In these matters,
neither the State nor the leaseholders can be permitted to turn round and now
take a stand that the areas covered under the Aravalli project is not forest.
The National Forestry Action Programme of December 2000 issued by the Ministry
of Environment and Forest, Government giving project profile
also makes detailed reference to the institution building and integrated
national resource development in the Aravalli region, Haryana under the project
implementing agency of Forest Department, Government of Haryana. The project
profile, inter alia, states that the Central to such a policy is rehabilitation
of common lands to meet the needs of the rural poor and to reduce soil and
water erosion and the proposed programme was envisaged to bring the benefit of
integrated development of the Aravalli eco-system to the whole community,
particularly, to the poorer sections.
The project,
it is stated, has been implemented in Aravalli hills situated in the five
districts of Haryana including Gurgaon. One of the expected outcome of the
project is the reduced soil erosion and improved water regime in the
rehabilitated area will be drastically reduce and run-off leading to recharge
of constantly depleting ground water resources. It records that Haryana Forest
Department has implemented a project on the eco-restoration of common lands in
the Aravalli hills, from June 1990 to October 1999. The project is being funded
by Delegation of European Communities. The total cost was 28.8 million ECU in
which external assistance was to the extent of 23.2 million EUC.
Aravallis
Hill Range The Aravallis, most distinctive and ancient mountain chain of peninsular
India, mark the site of one of the oldest
geological formations in the world. Heavily eroded and with exposed outcrops of
the slate rock and granite, it has summits reaching 4950 feet above sea level.
Due to its geological location, the Aravalli range harbours a mix of Saharan,
Ethiopian, Peninsular, oriental and even Malayan elements of flora and fauna.
In the early part of this century, the Aravallis were well wooded.
There
were dense forests with waterfalls and one could encounter a large number of
wild animals. Today, the changes in the environment at Aravalli are severe.
Though one finds a number of tree species in the hills, timber quality trees
have almost disappeared. Despite the increase of population resulting in
increase of demand from the forest, It cannot be questioned nor has been
questioned that to save the ecology of the Aravalli mountain, the laws have to
be strictly implemented. The notification dated 7th May, 1992 was passed with a view to strictly implement the measures
to protect the ecology of the Aravalli range. The notification was followed
more in its breach.
In the
aforesaid background, any mining activity on the area under plantation under Aravalli
project cannot be permitted. The grant of leases for mining operation over such
an area would be wholly arbitrary, unreasonable and illogical.
Report
of CMPDI on Aravalli The Central Mine Planning & Design Institute Limited
(CMPDI) on being asked by the Central Pollution Control Board to conduct a
study of environmental problems of Aravalli hills and preparation of action
plan for restoration of environmental quality in Gurgaon district, after
extensive examination, has submitted to CPCB its final report in July 2003.
CMPDI is a subsidiary of Coal India Limited (Government of India Enterprise).
The report in respect of Aravalli range in Gurgaon district has been prepared
by CMPDI with the following objectives :
1. To
prepare status report of the pollution problems in the Aravalli Hills.
2. To
prepare environmental management plan to abate various environmental problems
3. To
prepare action plan for restoration of environmental quality.
The
environmental problems in the Aravalli Range in Gurgaon district have been
identified and remedial measures including the pollution control guidelines and
action plan for various stakeholders have been suggested by CMPDI. It has been
noticed that in large scale mining projects what is still required is a
proposal on district level as to what will be mined, how it will be mined and
with what method and many such areas of environmental concern which had not
been adequately addressed keeping in view the environmental degradation of the Aravalli
Hills. It has also been noticed that the Aravalli notification restricts
process and operations under certain categories of the land in district. Though
the records of such lands are available at every village level map, there is no
record available in the district level in respect of these areas to undertake
realistic appraisal and effective monitoring of mining and other projects at
the macro level on such lands. While noticing that, notification dated 29th
November, 1999, inter alia, made provision for preparing a master plan
integrating the environmental concerns and the future land use of the area, but
the master plan prepared on 28th August, 2002 does not, inter alia, address the
issue of natural resource assessment and water Resource status; the areas near
crushing zone and active mining zone remain a matter of concern and concerted
efforts have not been given to the quality of roads and the dust suppression
measures to maintain the air quality within safe limits. The guidelines of
operation in an eco-friendly manner have been issued by the State Government
but the compliance is only partial, inasmuch as wind breaking walls are not
proper, pollution control devices are not operating and the green belt around
the crushing zones are not maintained. Identification of mines in the district
is difficult. There does not seem to be mechanism to upgrade the mining
technologies and methodologies to minimize the impact due to mining in the
eco-sensitive zones in the district. There is no identified land where
overburden could be temporarily dumped prior to being utilized for void filling
and for other purposes. There does not seem to adequate awareness among the
people in respect of the environmental problems. In some parts of the district,
the ground water potential is already in the dark category. Lack of water
conservation measures and rainwater harvesting may ultimately lead to water
scarcity in the near future.
Having
identified the environmental problems, various actions have been recommended by
CMPDI for the eco restoration in the Aravalli Range in Gurgaon district. It has been,
inter alia, recommended that it is imperative on the part of the State
Government to improve inter- departmental co-ordination among various
Government departments to achieve the common objective, i.e., ecological
restoration of Aravalli Hills in the district. The master plan should indicate
the proposed eco- restoration plan to compensate the environmental degradation
by the proposed activities in the master plan. Rehabilitation programmes for
the abandoned mines areas either to convert these to water reservoirs and
eco-parks or reclamation by filling by rural waste, urban waste or fly ash.
The
master plan should be detailed to show the areas where overburden could be
dumped, areas where waste material could be stocked, areas where plantation
could be carried out, etc.etc. The planning should, inter alia, include
environmental impact and concerns of activities of one sector on the other
sectors in the district, e.g., afforestation should be planned not only with a
view to increase vegetation on the hills but also to be supplement for fuel,
fodder etc. in the district. All efforts should be made to preserve the ground
water resources. Water shed management and rainwater harvesting to be
implemented in the Aravalli hills regions on war footing. In the areas where
mining deeper than the ground water table of the area is to be carried out,
adequate provision of pollution control and conservation of water resources
should be made. There should be frequent inspections of the mining operations
to ensure that these are in line with the requirement for sustainable
development. The inspections may be carried out at an interval of three months.
There should be continual source of revenue from the mining operations to the
fund, recommended to be created, for the eco-restoration of the Aravalli hills.
The
minimum period of lease should be for 15-20 years. This will induce the mine
operators to take environmental protection measures more seriously. The State
Pollution Control Board shall undertake regular monitoring to check compliance
and to assess the ambient air quality, water quality and other environmental
protection measures. The Ministry of Environment and Forest should take initiative to appoint a
Central Agency to monitor the eco-restoration efforts and to provide technical
support to the implementing organizations. The renewal of mining lease and
granting new leases should be effected after examining the environmental
protection measures taken by the lessee. Requisite data should be displayed on
the internet to arouse awareness in public and for further usage. Stringent
action should be taken for water conservation.
The
Forest Department may even carry out the afforestation on behalf of mine
operators. Expenses should, however, be borne by the mine operators. The afforestation
shall be carried out keeping in view, inter alia, the consideration of checking
the soil erosion. The mine lessee should implement the environmental management
plan and mining plan approved by the concerned authority. In future, efforts in
respect of search for sustainable development should broadly take into
consideration resource potential in the region, the demand of the products and
the supply options.
Though
the demand for the niche products existing in the Aravalli range which is one
of the oldest mountain ranges in India will continue to grow, the supply options need to be given a closer
look due to eco-sensitivity of the region. The environmental cost needs to be
internalized in the cost of the product and there is need to limit the supply
options. Noticing that the Aravalli range prevents the desert from spreading
into Indo-Gangetic plains, it has been suggested that all future planning
should not only concentrate to meet the ever growing demand of the products but
due consideration should also be given to protect the chain. All the
developmental activities should, therefore, be planned in a coherent manner and
there should be integrated approach for sustainable development.
CMPDI
has noticed that in the Aravalli Hills, a large number of activities,
operations of stone crushers and deforestation besides other activities are
causing environmental degradation. These mines are usually located in the
clusters in remote mineral rich districts/areas where living standards is lower
and understanding of people towards environmental impact is also poor. In the
past, the mine operators took no note of environmental damage. In fact, they
were not even conscious about it.
The
attitude of mining community is to ignore the environmental concerns.
In
majority of the cases, the environmental concerns are ignored for making quick
profits. The small mines (less than 5 hectares) and the mining of minor
minerals which are no doubt small individually but have damaging
characteristics when in clusters, e.g. the mines of granite, marble, slates,
quartzite etc. (falling under minor minerals) are no less damaging than the
others, especially when the processing is taken into consideration. The mining
activities results in disturbance of land surface, altering drainage pattern
and land use, besides the pollution problems, which may lead to the
environmental problems of air, water and noise pollution and solid waste
pollution.
It has
been suggested that the short term and long term action plan for the
restoration of environmental quality of the area shall be prepared separately.
The action plan shall be prepared in such a way that it should be a guiding
tool also in the hands of the state pollution control boards and Government
agencies for enforcement of the environmental laws for the restoration of
environmental quality of the area. Monitoring programme shall include frequency
of monitoring for air quality, water quality, ground water, solid wastes, noise
level etc.
In
respect of water resources, it has been, inter alia, suggested that in order to
draw water resource management plan, it is essential to assess the water
quality of the various components of the hydrologic cycle, i.e., stream, ground
water, surface water etc. It has been pointed out that since the surface water
potential is not promising in the district, there is increased dependence on
the ground water for meeting the agricultural, domestic and industrial
requirement resulting in depletion of ground water resources in the district.
It has been suggested that utmost care is required for further development of
ground water in the areas where the recharge of the ground water is low.
Dealing
with the flora and fauna, it has been pointed out that the earliest account
shows that at one time the Aravalli hills were well covered with dhauk (Anogeissus
pendula). Now, except in few places, viz., the Jhir Forest in Firozpur Jhirka
(dedicated to Mahadeo Temple) and near Bhondsi recently regenerated with dhauk,
the Aravallis are by and large, bereft of vegetation in the district.
It has
been noticed that in order to take stock of the environmental problems, CPCB
and CMPDI team made several visits to Aravalli hills and held discussion with
the mine operators, State officials and local people.
There
are number of mining projects etc. which are already existing and there is also
tremendous potential to further increase the industrial and the other
development activities. The environmental impact due to mining projects on air
quality, water quality, noise level, overburden etc. have been noticed and it
has been pointed out that the opening of new projects will further affect some
of the environmental attributes.
The
report notices that the environmental degradation has taken place due to mining
activities. The existing crusher units are also not functioning on the
environmental sound systems. The situation warrants closer look on various
components of the systems affecting the environmental attributes in the area,
devising pragmatic approaches to facilitate eco-restoration of the Aravalli
hills and offering broad framework to the industrial units to function under
environmentally sustainable framework. The suggestions also include the
enactment of rules for grant of mine leases to levy a separate charge for dump
removal, ecological restoration in the area, the technology to be used for
mining operations and post mining land use and mine decommissioning. As far as
environmental protection in the Aravalli hills is concerned, planning and
provisions must start from the stage of grant of mine lease and what all it
should include have been set out. It has been, inter alia, suggested that the
environmental framework shall include the framework for environmental clearance
such as depth of cutting, area of plantation and the type of plantation, which
are attributes related to closure planning as also framework for monitoring and
for forestry besides air quality, land use pattern etc. In nutshell, it has
been suggested that it is imperative on the part of the mine operators to carry
out the mine operations in such a fashion that it has least impact on the
ecology of the area. The pollution prevention guidelines have been suggested in
para 7.1.1.2 Having regard to the detailed study, the recommendations and
action plan has been dealt with in Chapter VIII of the report, inter alia,
suggesting that concerted efforts from various departments are needed.
The
report states that though the environmental upgradation measures need to be
taken more seriously by the mine and other industrial operators, there is need
on the part of the State Government to immediately start these measures in the
areas where degradation has already taken place. The other recommendations have
already been broadly noticed.
No one
has raised any objection to the recommendations contained in the report of
CMPDI. We accept the recommendations in principle.
Modification
of Order dated 6th May, 2002 Regarding Mining in Aravalli Now, the question is
should mining activities in the Aravalli range in Gurgaon district be permitted
to restart and, to that extent, the order dated 6th May, 2002 be modified,
meanwhile directing implementation of recommendations in the report of CMPDI
and earlier referred reports. The other option is to first constitute a
monitoring committee directing it to individually examine and inspect mines
from environmental angle in the light of the said recommendations and file a
report in this Court in respect of individual mines with its recommendations
for restart or otherwise as also recommendation, if any, for the payment by the
mine operators and/or by State Government towards environmental fund having
regard to the precautionary principles and polluter pays principle and on
consideration of that report, to decide the aspect of modification of the order
dated 6th May, 2002, partially or entirely. We are of the view that the second
option is more appropriate. We are conscious of observations in CMPDI that
measures for protecting the environment can be undertaken without stopping mine
operations and also the suggestions of MOEF to permit mining subject to the
mine lease holders undertaking to comply with such conditions which remain to
be complied, but, having regard to the enormous degradation of the environment,
in our view, the safer and the proper course is to first constitute a Monitoring
Committee, get a report from it and only thereafter consider, on individual
mine to mine basis, lifting of ban imposed in terms of order dated 6th May,
2002. Before concluding this aspect, we may note that assuming there was any
ambiguity about the applicability of order dated 6th May, 2002 to mining in Aravalli Range, it is clarified that the said
order would be applicable to all the mines in Aravalli hill range in Gurgaon
district.
Applicability
of notification dated 27th
January, 1994 The
notification has been reproduced in the earlier part of the judgment. It, inter
alia, applies to mining projects (major minerals) with leases of more than 5
hectares. It can neither be disputed nor has been disputed that the
notification is mandatory. It, inter alia, provides that on and from the date
of its publication in official Gazette expansion or modernization of any
activity (if pollution load is to exceed the existing one) or a new project
listed in Schedule A of this notification shall not be undertaken in any part
of India unless it has been accorded environmental clearance by the Central
Government in accordance with the procedure specified therein. The contention
urged on behalf of the lease-holders is that the leases in question do not
relate to expansion or modernization of any activity as postulated by the
notification. Further, it is contended, that the notification applies to 'a new
project' which means that it will apply to mining lease granted after issue of
notification. It has been strenuously contended that the renewal of existing
mining lease is neither 'an expansion' nor 'modernization' nor is it a 'new
project' and, therefore, the notification will have no applicability at the
time of consideration of the renewal of the lease. Reliance has been placed on
a decision of this Court in Narmada's case
(supra) holding that the notification is clearly prospective and, inter alia,
prohibits the undertaking of a new project listed in Schedule I without prior
environmental clearance from the Central Government. The contention urged was
that since in Narmada's case, where construction had
commenced nearly 8 years prior to the notification, same very notification was
not held applicable. On the same analogy, it cannot have any applicability to
the leases granted prior to the issue of notification.
No
doubt, the notification is prospective but the question here is whether it
would be applicable when the aspect of renewal comes up for consideration after
the issue of the notification. In Narmada's case, it was not held that this notification will not apply at the
stage of renewal. The observations made in para 129 of the said decision and
relied upon by learned counsel for the lease holders have no relevance to
determine the applicability of the notification at the stage of renewal. In Narmada's
case, the environmental clearance had been granted in the year 1987 and this
Court noticing that when it was granted by the Prime Minister, whatever studies
were available were taken into consideration, it was known that the
construction of the dam would result in submergence and the consequent effect
which the reservoir will have on the ecology of the surrounding areas and
various studies relating to environmental impact had been taken into
consideration and that there was no obligation to obtain the statutory
clearance under 1994 notification.
In the
present case, regarding the manner of grant of no objection certificate from
environmental angle for proposed mining activity, by way of illustration, we
may refer to the order dated 18th January, 1999 issued by Haryana State
Pollution Control Board whereby no objection certificate for renewal of lease
was granted stipulating that the applicant Som Prakash Sethi in respect of
mining activity at village Anangpur, district Faridabad shall also seeking
environmental clearance of its mining project in compliance with this
notification without even mentioning any time limit for it and admittedly till
date that had not been done. None bothered to find out whether conditions in the
order has been complied or not. Further the letter dated 25th January, 2003, sent to Principal Secretary of
Central Empowered Committee by Director Mines and Ecology, Haryana shows how
the State Government has been circumventing the legal requirements and
permitting mining. In that letter, it has been stated that pending approval of
the environmental plan, the mining lessees undertook the mining operation of
the minor mineral on issue of short term permit, in cases where the fresh
mining leases were granted and in case of renewal of mining leases, the mining
activities were going on. This is despite conditions in the judgment dated 10th May, 1996 by this Court that the Director Mining
and Ecology Haryana would be responsible for mining in the State of Haryana.
Be
that as it may and reverting to legal position, in Ambica Quarry Works v. State
of Gujarat & Ors. [(1987) 1 SCC 213], though a case under Forest
(Conservation) Act, 1980 rejecting the contention that approval at the stage of
renewal was not necessary and also the plea that since the leaseholders had
invested sum of money in mining operation, it was the duty of the authorities
to renew the lease, it was held that having regard to the awareness that
deforestation and ecological imbalances as a result of deforestation have
become social menaces and the same should be prevented and that the concept
that power coupled with the duty enjoined upon the respondents to renew the
lease stood eroded by the mandate of the FC Act. It was held that The primary duty
was to the community and that duty took precedence. In such cases, the
obligation to the society must predominate over the obligation to the
individuals. It would be apposite to reproduce what was said by Justice Mukherjee
(as he then was) in paras 14 and 15 which read thus :
"14.
Here the case of the appellants is that they have invested large sums of money
in mining operations. Therefore, it was the duty of the authorities that the
power of granting permission should have been so exercised that the appellants
had the full benefits of their investments. It was emphasized that none of the
appellants had committed any breach of the terms of grant nor were there any
other factors disentitling them to such renewal. While there was power to grant
renewal and in these cases there were clauses permitting renewals, it might
have cast a duty to grant such renewal in the facts and circumstances of the
cases specially in view of the investments made by the appellants in the areas
covered by the quarrying leases, but renewals cannot be claimed as a matter of
right for the following reasons.
15.
The rules dealt with a situation prior to the coming into operation of 1980
Act. '1980 Act' was an Act in recognition of the awareness that deforestation
and ecological imbalances as a result of deforestation have become social
menaces and further deforestation and ecological imbalances should be
prevented. That was the primary purpose writ large in the Act of 1980.
Therefore
the concept that power coupled with the duty enjoined upon the respondents to
renew the lease stands eroded by the mandate of the legislation as manifest in
1980 Act in the facts and circumstances of these cases. The primary duty was to
the community and that duty took precedence, in our opinion, in these cases.
The obligation to the society must predominate over the obligation to the
individuals." In Rural Litigation and Entitlement Kendra v. State of U.P.
[1989 Supp.(1) SCC 504], agreeing with views expressed in Ambica Quarry
Workers, it was held that the FC Act applies to renewals as well and even if
there was a provision for renewal in the lease agreement on exercise of
lessee's option, the requirement of the Act had to be satisfied before such
renewal could be granted. In State of M.P.
& Ors. v. Krishnadas Tikaram [1995 Supp.(1) SCC 587], these two decisions
were relied upon and it was held that even the renewal of lease cannot be
granted without the prior concurrence of the Central Government. It is settled
law that the grant of renewal is a fresh grant and must be consistent with law.
We are
unable to accept the contention that the notification dated 27th January, 1994 would not apply to leases which
come up for consideration for renewal after issue of the notification. The
notification mandates that the mining operation shall not be undertaken in any
part of India unless environmental clearance by
the Central Government has been accorded. The clearance under the notification
is valid for a period of five years. In none of the leases the requirement of
notification was complied with either at the stage of initial grant of the
mining lease or at the stage of renewal. Some of the leases were fresh leases
granted after issue of the notification. Some were cases of renewal. No mining
operation can commence without obtaining environmental impact assessment in
terms of the notification.
The
Applicability of Forest (Conservation) Act, 1980 to areas treated as forest by
State Forest Department The provisions of the Act provide for the conservations
of forest and for matters connected therewith or ancillary or incidental
thereto. Any forest land or portion thereof cannot be used for any non-forest
purposes or assigned by way of leases or otherwise to any private person or to
any authority, corporation, agency or any other organization not owned, managed
or controlled by the Government, except with the prior approval of the Central
Government. Mining activity within forest area cannot be permitted in
contravention of the provisions of the Act. The Act makes the contravention of
any of the provisions of Section 2 as an offence punishable in the manner
provided in the Act.
The
controversy is in respect of certain leases where area under the lease is
covered under notification issued under Section 4 and/or 5 of the Punjab Land
Preservation Act, 1900. The question is whether such area is 'forest' of any
kind.
Under
Section 3 of the aforesaid Act, whenever it appears to the State Government
that it is desirable to provide for the conservation of sub-soil water or the prevention
of erosion in any area subject to erosion or likely to become liable to
erosion, such Government may by notification make a direction accordingly.
Under Section 4(b), the State Government has power to regulate, restrict or
prohibit the quarrying of stone or the burning of lime at placed where such
stone or lime had not ordinarily been so quarried or burnt prior to the
publication of the notification under section
3.
Section 5(b) in respect of any specified village or villages, or part or parts
thereof, comprised within the limits of any area notified under section 3, the
State Government may, by special order, temporarily regulate, restrict or
prohibit the quarrying of any stone or the burning of any lime at places where
such stone or lime had ordinarily been so quarried or burnt prior to the
publication of the notification under section 3. In respect of some mining
areas notifications have been issued under Section 4 and in respect of some
notifications have been issued both under Sections 4 and
5. The
submission is that invoking of Sections 3, 4 and 5 is only to conserve sub-soil
water and prevention of the area from erosion of land and is not to create any
forest. It has been pointed out that in cases where the notifications have been
issued, only felling of trees had been prohibited and not quarrying of stone.
It
cannot be disputed that the State Forest Department has been treating and
showing the aforesaid areas as 'forest'. The contention urged on behalf of the
State Government is that it was on account of erroneous view point of Forest
Department. In fact and law, such area is not 'forest' and mining is not
prohibited and, therefore the question of seeking permission under Section 2 of
the FC Act does not arise.
In the
instant case, it is not necessary to decide the legal effect of issue of the
notification under Section 4 and/or 5 of the Act. Not only in their record the
area has been shown as forest but the affidavits have been filed in this Court
stating the area to be 'forest'. In T.N. Godavarman Thirumulkpad v. Union of India & Ors. [(1997) 2 SCC 267] , this Court
held that the term 'forest' is to be understood in the dictionary sense and
also that any area regarded as a forest in Government record irrespective of
ownership would be a forest. The State of Haryana, besides having filed affidavits in the forest matters treating such
areas as forest for the purposes of the FC Act has been seeking prior approval
from the Central Government for diversion of such land for non-forestry
purpose.
Reference
in this connection may also be made to the affidavit dated 8th December, 1996 filed by Banarsi Das, Principal
Chief Conservator of Forest, Chandigarh, Haryana in Civil Writ No.171 of 1996 Environmental
Awareness Forum v. State of Jammu & Kashmir and Ors. Our attention has also
been drawn to letter dated 26th November, 2002 addressed by Divisional Forest
Officer, Faridabad to Mining Officer, Faridabad forwarding to him a list of
blocked forest areas of Faridabad district and requesting him to ensure that
the said forest areas are not affected by any mining operations as also to a
letter dated 17th September, 2001 sent by Principal Chief Conservator of
Forest, Haryana (Panchkula) to Director of Environment, Haryana stating therein
that no mining activity can be permitted in the area. On the facts and
circumstances of the case, we cannot permit the State Government to take a
compete summersault in these proceedings and contend that the earlier stand
that the area is 'forest was under some erroneous impressions. In the present
case, for the purposes of the FC Act, these areas shall be treated as forest
and for use of it for non-forestry purpose, it would be necessary to comply
with the provisions of the FC Act.
We may
also note that assuming that there was any confusion or erroneous impression,
it ought to have been first sorted out at appropriate level and where
affidavits had been filed in this Court, clarifications/orders sought before
issue of the mining lease in respect of such area.
Impact
of Mining on Ground Water Where during mining water level is touched, the
Monitoring Committee shall carve out that area and it was agreed on behalf of
the leaseholders that they would co-operate and not undertake any mining in
such an area.
Non-payment
of royalty to the villagers A controversy has been raised about non-payment of
royalty by the leaseholders to villagers on whose behalf it was contended that
the order dated 6th May, 2002 prohibiting mining should not be varied till the
leaseholders discharge their liability to pay royalty to the villagers. On the
other hand, mine leaseholders dispute the claim put-forth on behalf of the
villagers and it has been submitted that no amount is payable by them and the
villagers can make their claim, if any, from the State Government.
The
dispute of this nature cannot be properly adjudicated in these proceedings. We
leave it open to be adjudicated before appropriate forum in accordance with
law.
Leases
in respect of minor mineral Though notification dated 27th January, 1994 is not
applicable to minor minerals, but having regard to what we have discussed above
in regard to degradation of environment and the required standard about the
risk of harm to the environment or to human health to be decided in public
interest according to 'reasonable person's test', and the report of CMPDI, we
direct the Monitoring Committee to examine the leases granted for extraction of
minor mineral in light thereof and file its report. The Committee would,
however, bear in mind that the notification dated 27th January, 1994 as such is not applicable to these leases.
Mining
in Faridabad District Having examined the matter, we are of the view that
though the study conducted by CMPDI relates to mining activity in Aravalli
Hills in Gurgaon district, in public interest the general safeguards and
suggestions in that report deserve to be implemented in respect of mining in Faridabad district as well.
We
have already extracted the recommendations of NEERI, as also violations noticed
in the reports submitted by EPCA and the suggestions of EPCA, CEC and CMPDI.
The Monitoring Committee shall inspect the leases in question in Faridabad
District as well in the light of these recommendations and file its report
containing suggestions on recommencement or otherwise of the mining activity
therein.
It may
be reiterated that if, despite stringent conditions, the degradation of
environment continues and reaches a stage of no return, this Court may have to
consider, at a later date, the closure of mining activity in areas where there
is such a risk.
As
earlier noticed as well, it would not be expedient to lift the ban on mining
imposed in terms of the order of this Court dated 6th May, 2002 before ensuring
implementation of suggestions of CMPDI and other recommendations of experts
(NEERI, EPCA and CEC). The safer course is to consider this question, on
individual basis after receipt of report of the Monitoring Committee.
Environment
Impact assessment applications During the course of hearing environment
assessment applications in terms of notification dated 27th January, 1994 have been filed by some of the
leaseholders. In case, those applications are presently with Central Empowered
Committee, the same shall be forthwith forwarded by CEC to MOEF. The adverse
effect, if any, and extent thereof on human health and ecology shall be
examined while deciding impact of these activities.
There
is also the desirability of transparency in such matter. The MOEF is directed
to consider the said applications within a period of 10 weeks.
Monitoring
Committee With a view to monitor the overall eco-restoration efforts in the Aravalli
Hills and to provide technical support to the implementing organizations and
also to monitor implementation of recommendations contained in reports referred
herein, it is necessary to constitute a Monitoring Committee. The heads of the
following departments would be members of the Monitoring Committee :
1.
Regional Officer of State Pollution Control Board.
2.
Forest Department
3.
District Administration
4.
Department of Mining & Geology
5.
Irrigation Department
6.
Regional Officer of CGWB
7.
Agriculture Department
8.
District Industry Department.
9.
Chairman - CPCB.
Besides
above, MOEF is directed to appoint an officer from Central Ground Water Board
to be a member of the Monitoring Committee. The following persons as
representatives of public shall also be members of the said Committee :
1.
Prof. Dilip Biswas, Ex Chairman, CPCB.
2. Mr.
Valmiki Thapar,
3. Mr.
Bhure Lal.
The
MOEF would act as a nodal agency of the Monitoring Committee. The Secretary of
MOEF is directed to appoint an officer not below the rank of a Joint Secretary
in the Ministry for the said purpose.
The
Monitoring Committee is directed to inspect the mines in question and file a
report within a period of three months, inter alia, containing suggestions for
recommencement of mining in individual cases.
All
concerned individuals and departments are directed to render full co- operation
to the Monitoring Committee.
Conclusions
1. The
order dated 6th May,
2002 as clarified
hereinbefore cannot be vacated or varied before consideration of the report of
the Monitoring Committee constituted by this judgment.
2. The
notification of environment assessment clearance dated 27th January, 1994 is
applicable also when renewal of mining lease is considered after issue of the
notification.
3. On
the facts of the case, the mining activity on areas covered under Section 4
and/or 5 of Punjab Land Preservation Act, 1900 cannot be undertaken without
approval under the Forest (Conservation) Act, 1980.
4. No
mining activity can be carried out on area over which plantation has been
undertaken under Aravalli project by utilization of foreign funds.
5. The
mining activity can be permitted only on the basis of sustainable development
and on compliance of stringent conditions.
6. The
Aravalli hill range has to be protected at any cost. In case despite stringent
condition, there is an adverse irreversible effect on the ecology in the Aravalli
hill range area, at a later date, the total stoppage of mining activity in the
area may have to be considered.
For
similar reasons such step may have to be considered in respect of mining in Faridabad
District as well.
7.
MOEF is directed to prepare a short term and long term action plan for the
restoration of environmental quality of Aravalli hills in Gurgaon district
having regard to what is stated in final report of CMPDI within four months.
8.
Violation of any of the conditions would entail the risk of cancellation of
mining lease. The mining activity shall continue only on strict compliance of
the stipulated conditions.
The
matters are directed to be listed after reopening of courts after summer
vacation on receipt of the report from the Monitoring Committee.
Back