M/S N.S. Nayak & Sons Vs. State of
Goa [2003] Insc 270
(8 May 2003)
Appeal (civil) 98 of 2002 Appeal
(civil) 99 of 2002 Appeal (civil) 100 of 2002 Appeal (civil) 101 of 2002 M/s
Heera Constructions M/s Rani Constructions Pvt. Ltd. M/s Rani Constructions Pvt. Ltd. M/s Pioneer Engineering Syndicate
State of Goa State of Goa & Another State of Goa & Another Board of
Trustees of Port Mormugao M.B. SHAH & ARUN KUMAR. Shah, J.
These appeals are directed against
the judgment and order dated 27th April, 2000 passed by the High Court of Bombay, Goa Bench, in
Arbitration Appeal No.1 of 1993 etc. etc.
In pending appeals, a contention
was raised by the appellant that appeals filed by the respondents under Section
37 of the Arbitration Act, 1940 (hereinafter referred to as the 'Old Act'), are
required to be decided on the basis of the Arbitration and Conciliation Act,
1996 (hereinafter referred to as the 'New Act') because the arbitration
agreement provides as under:
"Subject as aforesaid the
provisions of the Arbitration
Act, 1940, or any statutory modification or re-enactment thereof and the
Rules made thereunder and for the time being in force shall apply to the
arbitration proceedings under this clause." That contention was rejected
by the High Court. Hence, these appeals.
In support of aforesaid
contention, learned senior counsel Mr.
Desai for the appellant relied
upon the decision in Thyssen Stahlunion GMBH v. Steel Authority of India Ltd. [(1999)
9 SCC 334].
Before referring to the decision
in Thyssen's case, we would first refer to Section 85 of the New Act, which
reads as under:
"85. Repeal and saving. (1)
The Arbitration (Protocol and Convention) Act, 1937 (6 of 1937), the
Arbitration Act, 1940 (10 of 1940) and the Foreign Awards (Recognition and
Enforcement) Act, 1961 (45 of 1961) are hereby repealed.
(2) Notwithstanding such repeal,
(a) the provisions of the said enactments shall apply in relation to arbitral
proceedings which commenced before this Act came into force unless otherwise
agreed by the parties but this Act shall apply in relation to arbitral
proceedings which commenced on or after this Act comes into force;
(b) all rules made and
notifications published, under the said enactments shall, to the extent to
which they are not repugnant to this Act, be deemed respectively to have been
made or issued under this Act." Section 85 (2) (a) specifically provides
that (1) the provisions of the Old Act shall apply in relation to arbitral
proceedings which commenced on or before the New Act came into force, unless
otherwise agreed by the parties; (2) it also provides that the New Act shall
apply in relation to arbitral proceedings which commenced on or after the New
Act came into force.
In all these matters arbitrators
were appointed prior to 25th January 1996. Arbitral proceedings started before
that date and the awards in CA No.97/2002, CA No.99/2002, C.A. No.100/2002 and
C.A. No.101/2002 were passed on 20.12.1991, 17.5.1994, 7.5.1992, 3.2.1989
respectively, i.e. prior to 25th January, 1996, and in CA No.98/2002, the award
was passed on 30.9.1996, i.e. after 25th January, 1996. On the basis of
sub-section 2(a), the provisions of the Old Act would apply to the arbitral
proceedings which commenced on or before the New Act came into force.
Further, the part of the
arbitration clause which is quoted above also provides that the provisions of Arbitration Act,
1940 which were for time being in force were to apply to the arbitral
proceedings between the parties. It nowhere provides that once the arbitral
proceedings have commenced under the Old Act, they should be conducted under
the New Act as soon as the New Act comes into operation. Hence, in the
proceedings where the award is passed under the Old Act, the remedy of filing
appeal or petition for setting aside the said award would be as per the
provisions of the Old Act.
Further, the complete answer to
the contention of the learned counsel for the appellant is in the following
paragraph (para 32) of Thyssen's case wherein the Court has specifically held
that once the arbitral proceedings commenced under the Old Act, it would be Old
Act which would apply in arbitral proceedings and also for enforcing the award:
32. Principles enunciated in the
judgments show as to when a right accrues to a party under the repealed Act. It
is not necessary that for the right to accrue legal proceedings must be pending
when the new Act comes into force. To have the award enforced when arbitral
proceedings commenced under the old Act under that very Act is certainly an
accrued right. Consequences for the party against whom award is given after
arbitral proceedings have been held under the old Act though given after the
coming into force of the new Act, would be quite grave if it is debarred from
challenging the award under the provisions of the old Act. Structure of both
the Acts is different. When arbitral proceedings commenced under the old Act it
would be in the mind of everybody, i.e., the arbitrators and the parties that
the award given should not fall foul of Sections 30 and 32 of the old Act.
Nobody at that time could have thought that Section 30 of the old Act could be
substituted by Section 34 of the new Act. As a matter of fact appellant Thyssen
in Civil Appeal No.6036 of 1998 itself understood that the old Act would apply
when it approached the High Court under Sections 14 and 17 of the old Act for
making the award rule of the court. It was only later on that it changed the
stand and now took the position that the new Act would apply and for that
purpose filed an application for execution of the award. By that time
limitation to set aside the award under the new Act had elapsed. The appellant
itself led the respondent SAIL in believing that the old Act would apply. SAIL
had filed objections to the award under Section 30 of the old Act after notice
for filing the award was received by it on the application filed by Thyssen
under Sections 14 and 17 of the old Act.
We have been informed that
numerous such matters are pending all over the country where the award in
similar circumstances is sought to be enforced or set aside under the
provisions of the old Act. We, therefore, cannot adopt a construction which
would lead to such anomalous situations where the party seeking to have the
award set aside finds himself without any remedy.
We are, therefore, of the opinion
that it would be the provisions of the old Act that would apply to the
enforcement of the award in the case of Civil Appeal No.6036 of 1998. Any other
construction on Section 85(2)(a) would only lead to confusion and hardship.
This construction put by us is consistent with the wording of Section 85(2)(a)
using the terms "provision" and "in relation to arbitral
proceedings" which would mean that once the arbitral proceedings commenced
under the old Act it would be the old Act which would apply for enforcing the
award as well." The highlighted portion in terms emphasizes that in such
cases where the arbitral proceedings commenced under the Old Act, it is an
accrued right to proceed in accordance with that law and it would be the Old
Act which would apply even for enforcing the award.
Learned senior counsel Mr. Desai
submitted that in Thyssen's case, the phrase 'in relation to arbitral
proceedings' is given wider meaning so as to include arbitral proceedings
before the arbitrator as well as the proceedings before the Court and once New
Act came into force, further proceedings including appeals are required to be
dealt with and decided in accordance with the New Act as per the agreement. For
this purpose, he placed reliance on paragraph 22 of the said judgment.
In our view, paragraph 22 nowhere
lays down that after the New Act came into force, even appeals filed under the
provisions of Old Act are to be decided on the basis of the provisions
contained in the New Act. Paragraphs 22 and 23 are as under:
"The Conclusions 22. For the
reasons to follow, we hold:
1. The provisions of the old Act (Arbitration
Act, 1940) shall apply in relation to arbitral proceedings which have commenced
before the coming into force of the new Act (the Arbitration and
Conciliation Act, 1996).
2. The phrase "in relation to
arbitral proceedings" cannot be given a narrow meaning to mean only
pendency of the arbitration proceedings before the arbitrator. It would cover
not only proceedings pending before the arbitrator but would also cover the
proceedings before the court and any proceedings which are required to be taken
under the old Act for the award becoming a decree under Section 17 thereof and
also appeal arising thereunder.
3. In cases where arbitral
proceedings have commenced before the coming into force of the new Act and are
pending before the arbitrator, it is open to the parties to agree that the new
Act be applicable to such arbitral proceedings and they can so agree even
before the coming into force of the new Act.
4. The new Act would be applicable
in relation to arbitral proceedings which commenced on or after the new Act
comes into force.
5. Once the arbitral proceedings
have commenced, it cannot be stated that the right to be governed by the old
Act for enforcement of the award was an inchoate right. It was certainly a
right accrued. It is not imperative that for right to accrue to have the award
enforced under the old Act some legal proceedings for its enforcement must be
pending under that Act at the time the new Act came into force.
6. If a narrow meaning of the
phrase "in relation to arbitral proceedings" is to be accepted, it is
likely to create a great deal of confusion with regard to the matters where
award is made under the old Act.
Provisions for the conduct of
arbitral proceedings are vastly different in both the old and the new Act.
Challenge of award can be with
reference to the conduct of arbitral proceedings. An interpretation which leads
to unjust and inconvenient results cannot be accepted.
7. A foreign award given after the
commencement of the new Act can be enforced only under the new Act. There is no
vested right to have the foreign award enforced under the Foreign Awards Act
[Foreign Awards (Recognition and Enforcement) Act, 1961].
23. Section 85(2)(a) of the new
Act is in two limbs: (1) provisions of the old Act shall apply in relation to
arbitral proceedings which commenced before the new Act came into force unless
otherwise agreed by the parties and (2) the new Act shall apply in relation to
arbitral proceedings which commenced on or after the new Act came into force.
The first limb can further be bifurcated into two: (a) provisions of the old
Act shall apply in relation to arbitral proceedings commenced before the new
Act came into force, and (b) the old Act will not apply in such cases where the
parties agree that it will not apply in relation to arbitral proceedings which
commenced before the new Act came into force. The expression "in relation
to" is of the widest import as held by various decisions of this Court in
Doypack Systems (P) Ltd., Mansukhlal Dhanraj Jain, Dhanrajamal Gobindram and
Navin Chemicals Mfg. This expression "in relation to" has to be given
full effect to, particularly when read in conjunction with the words "the
provisions" of the old Act. That would mean that the old Act will apply to
the whole gambit of arbitration culminating in the enforcement of the award. If
it was not so, only the word "to" could have sufficed and when the
legislature has used the expression "in relation to", a proper
meaning has to be given. This expression does not admit of restrictive meaning.
The first limb of Section 85(2)(a) is not a limited saving clause. It saves not
only the proceedings pending at the time of commencement of the new Act but
also the provisions of the old Act for enforcement of the award under that
Act." As stated in paragraph 22, Conclusion1 without any reservation
provides that the provisions of Old Act shall apply in relation to arbitral
proceedings which have commenced before coming into force of the New Act.
Conclusion2, in our view, is required to be read in context with Conclusion1,
that is to say, the phrase 'in relation to arbitral proceedings' cannot be
given a narrow meaning to mean only pendency of the proceedings before the arbitrator.
It would cover not only proceedings pending before the arbitrator but would
also cover the proceedings before the court and any proceedings which are
required to be taken under the old Act for the award becoming a decree under
Section 17 thereof and also appeal arising thereunder. Hence, conclusions1 and
2 are to be read together which unambiguously reiterate that once the arbitral
proceedings have started under the Old Act, the Old Act would apply for the
award becoming decree and also for appeal arising thereunder.
Conclusion3 only reiterates what
is provided in various Sections of the Arbitration Act,
which gives option to the parties to opt for the procedure as per their
agreement during the arbitral proceedings before the arbitrator. The phrase
'unless otherwise agreed by the parties' used in various Sections namely, 17,
21, 23(3), 24(1), 25, 26, 29, 31, 85(2)(a) etc. indicates that it is open to
the parties to agree otherwise. During the arbitral proceedings, right is given
to the parties to decide their own procedure. So if there is an agreement
between the parties with regard to the procedure to be followed by the
arbitrator, arbitrator is required to follow the said procedure. Reason being,
arbitrator is appointed on the basis of the contract between the parties and is
required to act as per the contract.
However, this would not mean that
in appeal parties can contend that appellate procedure should be as per their
agreement. Appellate procedure would be governed as per the statutory
provisions and parties have no right to change the same. It is also settled law
that the right to file an appeal is accrued right that cannot be taken away
unless there is specific provision to the contrary. There is no such provision
in the New Act. In the present cases, the appeals were pending before the High
Court under the provisions of the Old Act and, therefore, appeals are required
to be decided on the basis of the statutory provisions under the said Act.
Hence, there is no substance in the submission made by the learned counsel for
the appellant.
Learned counsel for the appellant
however relied upon paragraph 35 of Thyssen's case. In our view, it nowhere
lays down anything contrary to what we have stated above. Relevant portion of
the said discussion is as under:
" The expression "unless
otherwise agreed" as appearing in Section 85(2)(a) of the new Act would
clearly apply in the case of Rani Constructions in Civil Appeal No.61 of 1999.
Parties were clear in their minds that it would be the old Act or any statutory
modification or re-enactment of that Act which would govern the arbitration. We
accept the submission of the appellant Rani Constructions that parties could
anticipate that the new enactment may come into operation at the time the
disputes arise. We have seen Section 28 of the Contract Act. It is difficult
for us to comprehend that arbitration agreement could be said to be in
restraint of legal proceedings. There is no substance in the submission of the
respondent that parties could not have agreed to the application of the new Act
till they knew the provisions thereof and that would mean that any such
agreement as mentioned in the arbitration clause could be entered into only
after the new Act had come into force. When the agreement uses the expressions
"unless otherwise agreed" and "law in force" it does give
an option to the parties to agree that the new Act would apply to the pending
arbitration proceedings. That agreement can be entered into even before the new
Act comes into force and it cannot be said that agreement has to be entered
into only after the coming into force of the new Act." The aforesaid
discussion only deals with the contention that parties could not have agreed to
the application of the New Act till they had the knowledge about the provisions
thereof and, therefore, the agreement to the effect that to the arbitral
proceedings, the provisions of the Arbitration Act,
1940 or any statutory modification or re-enactment thereof would be
applicable, is not valid. The Court negatived the said contention by
interpreting the expression 'unless otherwise agreed'. The Court held that such
agreement could be entered into even before coming into force of the New Act.
However, it nowhere lays down that in a pending arbitral proceeding, which was
being conducted as per the procedure prescribed under the Old Act, the parties
have option of changing the procedure.
In this view of the matter, there
is no substance in these appeals and they are accordingly dismissed. The
appellant in each case shall pay the costs of Rs.10,000/- to the respondent
within a period of three months from today.
Back