The
TATA Hydro-Electric Power Supply Co. Ltd. & Ors Vs. Union of India [2003] Insc
52 (5 February 2003)
M.B.
Shah, B.P. Singh & H.K. Sema.
Arising
Out of S.L.P.( C) NO.4123 OF 2001 B.P.SINGH, J.
Special
leave granted.
This
appeal is directed against the judgment and order of the High Court of
Judicature at Bombay dated 5.10.2000 in Appeal No.144 of 2000 whereby the
Division Bench of the High Court affirmed the judgment of the learned Single
Judge allowing the Arbitration Petition filed by the respondent under Section
34 of the Arbitration and Conciliation Act, 1996 challenging the award of the
Umpire dated 30th March, 1998 on the ground of an error of law apparent on the
face of the Award.
The
appellant-companies are licensees under the Indian Electricity Act, 1910
(hereinafter referred to as "the Act"). A Power Supply Agreement was
executed on 7th July
1971 between the
aforesaid companies and President of India represented by Central Railways and Western Railways. Under the
agreement electric power is supplied to the railways at a number of points on
the railways electrified track route for the operation of the railways electric
trains services. Clause 20 of the said agreement contains an arbitration clause
which reads as under:- "20.0: In the event of any dispute or difference at
any time arising between the Government and the Companies in regard to any
matter arising out of or in connection with this Agreement such dispute or
difference shall be referred to arbitration of two arbitrators one to be appointed
by each party hereto and an Umpire to be appointed by the Arbitrators before
entering upon the reference and decision or award of the said Arbitrators or
Umpire shall be final and binding on the parties hereto and any reference made
under this clause shall be deemed to be a submission to arbitration under the
Arbitration Act, 1940, or any statutory modification thereof for the time being
in force.
The
venue of arbitration shall be Bombay".
The
facts of the case are that on 7th June, 1993 the appellants found that Western
Railways Feeder No.36 Red phase current was lower (0.4 amps.) than Blue phase
current (14 amps.). The respondent was accordingly advised by message dated 9th June, 1993 indicating that the appellants
would be carrying out further investigation. On 13th June, 1993 further investigation was carried out in the presence of
representative of Western Railways and it was confirmed that in Feeder No.36,
the main Current Transformer (CT) in Red phase had developed inter-turn short
resulting in lower output from its secondary windings. The appellants,
therefore, replaced the defective CT and installed a new CT after showing the
test results on the defective CT to the representative of the Western Railways.
The meter was checked and found satisfactory.
Subsequent
to the replacement of the defective CT on 13th June, 1993 the off take of the Trivector
Meter and the sum of the energy recorded on the two energy meters at Dharavi
were found to be higher by 28.7 per cent.
On
22.6.1993 the appellants informed the Western Railways about the defect that
had been detected and rectified and also that they shall advise the Railways
the exact period of under registration and the estimation of the quantum of
energy that had not been registered by the tariff meter due to the defective
CT. By their subsequent letter of 16th July, 1993, they informed the respondent
that the Western Railway's off take recorded at Dharavi between October, 91 and
June, 1993 was lower by about 34 per cent compared to the off take prior to
October, 1991 and that the recorded off take of Western Railways after
replacement of the defective CT on 13th June, 1993 had come back to the level
prevailing before October, 1991. The appellants, therefore, expressed the need
to make an adjustment of about 20.20 per cent of the total monthly energy off
take of Railways at Dharavi billed since October, 1991 up to 13th June, 1993.
On
26th July, 1993, the appellants submitted a supplementary bill to the
respondent dated 26th July, 1993 for Rs.8,89,32,367.50 for the period of under
registration i.e. from 20th October, 1991 to 13th June, 1993 giving inter-alia
the extent of adjustment in energy off take and M.D. Fuel, Adjustment charges
etc. A request was made for early payment of the bill. The respondent vide its
letter of 6th August, 1993 drew the attention of the appellants to paras 10.1
and 10.3 of the contract agreement between the parties and stated that the
metering responsibility as a whole lay with the appellants and that there is no
interference by the Railways in this regard. Moreover, para 10.3 of the
contract agreement provided a period of three months as a corrective period
during which the defective meter should have been put back to the required
accuracy level. Considering the date of the bill as 26.7.1993, the respondent
expressed its readiness to consider the period of under registration for a
maximum period of three preceding months i.e. w.e.f. May, 1993. If so advised,
the appellants were required to submit a revised bill.
It
appears that several meetings took place between the parties, but they could
not come to an agreement. On 2nd June, 1995,
the appellants wrote to the respondent referring to its supplementary bill and
the discussions which the parties had on the subject. However, since the issue
remained unresolved the appellants informed the respondent that they were
resorting to Clause 20 of the Power Supply Agreement and refer the matter to
two arbitrators, one each to be appointed by the parties. This was followed by
letter dated 27th July,
1995 informing the
respondent that the appellants had appointed Mr. A.D. Limaye, (Retd.) Asstt.
General Manager (Supply) BEST as their arbitrator in terms of Clause 20 of the
Agreement. The respondent was requested to name its arbitrator and advise the
appellants. Accordingly by letter dated 2nd February, 1996, the respondent appointed Shri R.K.
Sinha, Financial Advisor and Chief Accounts Officer, Western Railways as its
arbitrator and endorsed a copy of this letter to the appellants for information.
The arbitrators entered upon the arbitration but since they failed to agree,
they referred the dispute to the Umpire by their letter dated 29th November, 1996.
Thereafter
the Umpire received the documents from both the arbitrators in January, 1997.
The claim was filed by the appellants before the Umpire and a reply filed
thereto by the respondent in the months of March and April, 1997. The Umpire
entered upon the reference on 15th April, 1997
and ultimately passed an award on 30th March, 1998 awarding a lump sum of Rs. 4 crores
to the appellants with interest @ 12 per cent per annum from August, 1993 till
the passing of the decree.
The
respondent filed an Arbitration Petition 210 of 1998 under Section 34 of the
Arbitration and Conciliation Act, 1996 challenging the award on the ground of
error of law apparent on the face of the award contending that the decision of
the arbitrator was clearly contrary to the law laid down by the Supreme Court
by its Judgment and Order dated 17th December, 1999. A learned Single Judge of
the High Court set aside the award on the ground that it was contrary to the
law as declared by the Supreme Court in also held that the Umpire had no
jurisdiction in the matter since the dispute could be resolved only under
Section 26 of the Indian Electricity Act, 1910, which precluded private
arbitration. The dispute, therefore, could be resolved only by the Electrical
Inspector as provided in Section 26 of the Act.
The
appellants preferred an appeal against the judgment and order of the learned
Single Judge setting aside the award but the said appeal was dismissed by the
Division Bench of the High Court in Appeal No. 144 of 2000 by judgment and
order dated 5th
October, 2000
affirming the judgment and order of the learned Single Judge. The judgment and
order of the Division Bench is the subject matter of challenge in this appeal.
Section
26 of the Indian Electricity Act provides inter-alia that in the absence of an
agreement to the contrary, the amount of energy supplied to a consumer or the
electrical quantity contained in the supply shall be ascertained by means of a
correct meter, and the licensee shall, if required by the consumer, cause the
consumer to be supplied with such a meter. Sub-sections (6) & (7) of
Section 26 of the Act are relevant and read thus:-
"(6)
Where any difference or dispute arises as to whether any meter referred to in
sub-section (1) is or is not correct, the matter shall be decided, upon the
application of either party, by an Electrical Inspector; and where the meter
has, in the opinion of such Inspector ceased to be correct, such Inspector
shall estimate the amount of the energy supplied to the consumer or the
electrical quantity contained in the supply, during such time, not exceeding
six months, as the meter shall not, in the opinion of such Inspector, have been
correct; but save as aforesaid, the register of the meter shall, in the absence
of fraud, be conclusive proof of such amount or quantity:
Provided
that before either a licensee or a consumer applies to the Electrical Inspector
under this sub-section, he shall give to the other party not less than seven
days' notice of his intention so to do.
(7) In
addition to any meter which may be placed upon the premises of a consumer in
pursuance of the provisions of sub-section (1), the licensee may place upon
such premises such meter, maximum demand indicator or other apparatus as he may
think fit for the purpose of ascertaining or regulating either the amount of
energy supplied to the consumer, or the number of hours during which the supply
is given, or the rate per unit of time at which energy is supplied to the
consumer, or any other quantity or time connected with the supply:
Provided
that the meter, indicator or apparatus shall not, in the absence of an agreement
to the contrary be placed otherwise than between the distributing mains of the
licensee and any meter referred to in sub-section (1);
Provided
also that, where the charges for the supply of energy depend wholly or partly
upon the reading or indication of any such meter, indicator or apparatus as
aforesaid, the licensee shall, in the absence of an agreement to the contrary,
keep the meter, indicator or apparatus correct; and the provisions of
sub-sections (4), (5) and (6) shall in that case apply as though the meter,
indicator or apparatus were a meter referred to in sub-section (1).
Explanation. A meter shall be deemed to be
"correct" if it registers the amount of energy supplied, or the
electrical quantity contained in the supply, within the prescribed limits of
error, and a maximum demand indicator or other apparatus referred to in
sub-section (7) shall be deemed to be "correct" if it complies with
such conditions as may be prescribed in the case of any such indicator or other
apparatus".
Two
issues were highlighted before the High Court by the parties. While it was
contended on behalf of the appellants that a Current Transformer (C.T.) is not
a "meter" within the meaning of Section 26 of the Act, the respondent
contended that a Current Transformer being an "apparatus" for the
purpose of ascertaining or regulating the amount of energy supplied to the
consumer, it was an apparatus contemplated by Section 26(7) of the Act, and for
this, reliance was placed on the decision of the Supreme Court in Atma Steels
(supra). Secondly, the respondents contended that the dispute, since it related
to a defective meter and consequent under registering of electricity supplied,
was a dispute within the contemplation of Section 26(6) of the Act and,
therefore, such a dispute could be resolved only by the Electrical Inspector as
provided in sub-section (6) of Section 26. A statutory arbitration provided in
the aforesaid sub-section ruled out any private arbitration and therefore the
Umpire had no jurisdiction to pass an award in respect of such a dispute even
if referred to it by the parties.
The
appellants sought to sustain the award contending that since the parties had
submitted a specific question to the arbitrator for his decision viz whether a
CT was an "apparatus" within the meaning of the proviso to Section
26(7) of the Act which could confer exclusive jurisdiction on the Electrical
Inspector to decide the dispute, even if the specific question was decided
erroneously by the arbitrator, the award could not be set aside on that ground.
On
these questions the learned Single Judge as well as Appellate Bench have held
in favour of the respondents.
A
perusal of the award of the Umpire would disclose that he has noticed in detail
the submissions urged before him by the parties. The Umpire had also before him
the statements of monthly energy consumption as recorded by the appellants
billed figures and the Western Railways aggregate figures of the energy
recorded by Western Railways own meters at Railway's end of the 5 Western
Railway feeders. These were furnished by the Western Railways in Annexure 12 of
their letter dated 28.4.1997. The chart which is incorporated in the award
itself is as follows :- "Col.1 Col.2 Col.3 Col.4 Month & Total energy Energy
con- Col.3 & Col.4 Year consumed by summed by Ratio of consum- Railways as
per W.Rly 5 as per ption per TEC Summation TEC's in Vector meter vis--vis of KMhr
readings Meter Rly's aggregate as at Rly's end of 5 per Rly's Meters feeders
July'91 6,271,200 7,364,763 1.174 Aug.'91 6,371,260 7,503,409 1.178 Sept.'91
6,339,740 7,349,398 1.159 Oct.'91 7,145,300 6,251,070 0.875 Nov.'91 6,802,400
4,944,667 0.727 Dec.'91 6,792,860 4,977,564 0.734 Jan.'92 7,068,760 5,183,124
0.731 Feb.'92 6,508,380 4,769,028 0.733 March'92 6,492,100 4,813,383 0.741
April'92 6,878,300 5,010,531 0.729 May'92 6,695,240 5,001,012 0.747 June'92
6,551,360 4,799,810 0.798 July,92 6,896,000 5,028,104 0,729 Aug.'92 6,637,300
4,722,777 0.712 Sept.'92 6,203,700 4,713,970 0.780 Oct.'92 7,066,000 5,169,855
0.782 Nov.'92 7,264,480 5,019,352 0.691 Dec.'92 7,822,600 5,229,249 0.668
Jan.'93 7,255,200 5,034,874 0.694 Feb.'93 7,112,540 4,930,264 0.693 March'93
7,639,460 5,481,025 0.715 April'93 7,399,900 5,267,613 0.712 May'93 7,443,700
5,096,903 0.688 June'93 7,450,500 7,396,796 0.992 July'93 9,046,800 8,563,222
0.947 Aug.'93 7,847,400 8.490,753 1.082 Sept.'93 7,156,600 7,592,191 1.061 It
is observed from Col. 4 of the table that the ratio of energy consumption as
recorded by W. Rly's meter to that recorded by Rly's meters at the receiving
end which was around 1.159 to 1.178 dropped to 0.875 in June 91 and from July
91 to May 93 remained in the range of 0.685 to 0.760.
The
ratio changed to 0.993 in June'93 and picked upto 1.061 in Sept.'93.
Notwithstanding W. Rly's foot note that Railway's meters are not periodically
calibrated and therefore could not be relied upon (though there was a
contradiction on this front in the remarks of Mr. P.P. Sharma Sr.
Sec.
Engineer (S/S) of W. Rly's observation that the KWhr. Elements of TVMs were
being calibrated once in 5 years) and Mr. Jain of W. Rly later clarifying in W.
Rly's letter of 23.12.97 that this practice was not being rigidly adhered to
and the further fact that aggregation of readings also results in aggregation
of errors of individual meters, some positive and some negative is worth noting
that this comparison corroborates the fact of the meter registration at Dharavi
RS dropped down from October 1991 onwards till in June 1993 when the defective
CT was replaced".
It is
no doubt true that before the Umpire it was seriously urged on behalf of the
Railways that CT was an "apparatus" within the meaning of the proviso
to section 26(7) of the Indian Electricity Act, 1910 while on the other hand it
was contended on behalf of the appellant that CT is not such an apparatus and,
therefore, any defect in the CT will not amount to a defect in the meter. The
Umpire in his award upheld the contention of the appellant.
It was
urged before the High Court as also before us that having regard to the
judgment of this Court in U.P.S.E.B. vs. Atma Steel (supra) it is no longer
open to the appellant to contend that CT was not an apparatus within the
meaning of section 26(7) of the Act. Having perused the judgment of this Court
in Atma Steel's case (supra), we also entertain no doubt that CT is an
apparatus within the meaning of section 26(7) of the Act.
The
question that still survives consideration is whether the dispute before the
Umpire was in fact a dispute contemplated by section 26(6) of the Act.
Sub-section 6 of section 26 begins with the words "where any difference or
dispute arises as to whether any meter referred to in sub-section (1) is or is
not correct, the matter shall be decided, upon the application of either party,
by an Electrical Inspector; .". Sub-section 6 contemplates a difference or
dispute, where one party contends that the meter has rightly recorded the
energy supplied while the other controverts that position and contends that it
has not correctly recorded the supply of electrical energy. If such a dispute
arises between the parties, the matter is required to be decided by an
electrical inspector and it is he who can pronounce upon the question as to
whether the meter was or was not correct. Based upon his finding, he is authorized
to estimate the amount of the energy supplied during such time, not exceeding
six months, as the meter shall not in his opinion have been correct. A dispute
as to whether CT is an apparatus within the meaning of sub-section 7 of section
26 is not such a dispute, unless it is further contended that the CT which is
an "apparatus" within the meaning of sub-section 7 of section 26 was
in fact defective, and, therefore, the meter had incorrectly recorded the
supply of electrical energy. In short, before an electrical inspector can be
called upon to decide a dispute under sub-section 6 of section 26, it must be
shown that while one party contends that the meter, including the CT, is
defective the other contends to the contrary. In the facts of this case we find
that there was in fact no dispute that the CT was defective and it had,
therefore, to be replaced. In fact when the supplementary bill was submitted by
the appellant, the Western Railways did not dispute the position that the CT
was defective, but only denied their liability to pay the amount of Rs.8.89 crores
demanded in the supplementary bill and contended that at best they were liable
to pay only Rs.12,20,740/- since demand for under registration by the meter
could be permitted for a maximum period of 3 months of the demand as per the
Power Supply Agreement. Considering the date of the bill as 26th July, 1993,
the respondent expressed its readiness to consider the period of under
registration for a maximum period of three preceding months i.e. with effect
from May, 1993 and wrote to the appellant that if so advised it may submit a
revised bill. It, therefore, appears that there was really no dispute between
the parties that the meter was defective. Even if we proceed on the basis that
CT is a meter/apparatus within the meaning of sub- section 7 of section 26 of
the Act, the only dispute was whether the respondent was liable to pay the
entire supplementary bill as claimed by the appellant or whether their
liability was limited to a period of three months preceding the date of the
bill.
Where
there is no dispute that the meter is defective, such a dispute is not one
contemplated by sub-section (6) of section 26 of the Act. It is no doubt true
that if a dispute as contemplated by sub-section (6) of section 26 of the Act
arises, the matter has to be referred to the Electrical Inspector, and in view
of the statutory provisions, private arbitration in the case of such a dispute
is not permissible in law. However, if there is no dispute as to whether the
meter is defective or not, there is nothing which prevents the parties from
referring their other disputes to arbitration for determining the liability of
the consumer in such cases. It is only where any difference or dispute arises
as to whether any meter referred to in sub-section (1) of Section 26 is or is
not correct, that dispute has mandatorily to be resolved by the Electrical
Inspector.
In
resolving the dispute, the Electrical Inspector can make an estimate of the
electrical energy supplied during such time, not exceeding six months, as the
meter shall not in his opinion have been correct. For the remaining period, the
register of the meter is deemed to be conclusive proof of such amount or
quantity, in the absence of fraud. All this pre-supposes the existence of a
dispute contemplated by Section 26(6) of the Act which has to be resolved by
the Electrical Inspector.
The
Umpire no doubt held that CT was not an "apparatus" within the
meaning of sub-section (7) of section 26 of the Act.
Since
an argument was raised before him that CT is such an apparatus within the
meaning of sub-section (7) of section 26, he expressed his opinion in the
matter and may be, he decided wrongly. But that by itself will not bring the
dispute under sub- section (6) of section 26 of the Act. It was neither
contended before the Umpire nor was it decided by the Umpire, that the CT was
not defective. This was so because the parties were agreed that the CT was
defective. In any event that is not the basis of the award. All that the Umpire
had to decide was whether there was under registration of supply of electrical
energy to the respondent and if so, the extent thereof and the liability of the
respondent to pay for such electrical energy supplied but not recorded. From a
perusal of the award it appears that that is precisely what the Umpire has
done. Having noticed all the facts and circumstances of the case the Umpire
recorded his finding in the following words:- "In the event, taking into
account the facts
1)
That it is nobody's case that the Railway has not been paying regularly
according to the bills preferred by TEC based on the energy consumption and MD
recorded by their meter, the maintenance of whose accuracy is entirely the
responsibility of TEC in terms of the power supply agreement as well as the
I.E. Act and which meter incidentally had been tested to be working properly in
the tests carried out by TEC in Nov.,91 and March 93 in the presence of
Railway's representative.
2)
That the traffic level handled by the W. Rly.
During
the dispute period had not decreased or remained static but had on the contrary
increased, while the aggregate energy consumed had dropped despite the Railway
not having undertaken any improved methods of operation or implementation of
any energy saving techniques and further that after the disputed period the
level of energy consumed had attained higher levels in the consonance with the
traffic levels obtaining in these later periods, establishes the fact that
during the disputed period there has been some part of the energy consumed that
has escaped metering.
3)
That the time taken by TEC to discover the defect that had arisen in their
metering CT was an abnormally long one and that the consumer cannot be
penalized for TEC's failure to discover this defect, for whatever reasons they
be, in a reasonable time, particularly when they had the obligation to maintain
the meter and metering system in a state of good repair as well as accuracy
level and that the customer cannot be penalized for the failure of the Ct
attributable to probable manufacturing defect, if any, and with a view to
answering that the ends of natural justice, equity and fairplay are properly
met with, with respect to both the parties I pronounce my lumpsum award of Rs.
4 crores only (Rupees Four Crores only) in favour of the claimant, payable by
the Railway, I hold that the payment becomes due w.e.f. Aug. 93. I also award
interest charges of 12% p.a. w.e.f. Aug. 93 till the passing of the court
decree".
As
noticed earlier the Umpire took into account the readings of the meters
maintained by the Railways themselves, but did not give to the appellant the
full benefit thereof, otherwise the amount would have been much higher. Only a lumpsum
award of Rs. 4 crores was made.
In
fact, during the pendency of the special leave petition before this Court as
well, the Court had noticed the fact that the Western Railways was also
maintaining meters at their end and the said meters revealed the total energy
consumed at the railways end at 5 feeder stations. This was noticed by the
Umpire as well.
There
appeared to be no reason why the railways should not pay the amount as per
their own meters. It appeared unfair and inequitable that the Union Government
should deny to pay the amount for the electricity consumed as per their own
record.
Counsel
for the Union of India was given time to consider the matter and obtain
necessary instructions. It, however, appears that the Union of India was not
inclined to settle the dispute and, therefore, the matter had to be heard.
We,
therefore, hold that the High Court erred in setting aside the award of the
Umpire on a finding that the dispute before him was one contemplated by
sub-section (6) of section 26 of the Act and, therefore, not arbitrable. We
hold that the parties never disputed the fact that the CT, which is an
"apparatus" within the meaning of sub-section (7) of section 26 of
the Act, was in fact defective. There being therefore, no dispute as to whether
the meter had ceased to be correct, the dispute was not one contemplated by
sub-section 6 of section 26 of the Act. In fact none of the parties even raised
a contention before the Umpire that the CT was not defective, and therefore the
Umpire was not required to give his finding on the question, which in a dispute
under Section 26(6) of the Act is the primary question to be decided. The
dispute related only to the claim of the appellant who had submitted a
supplementary bill for the electrical energy supplied but not recorded. In the
absence of a dispute as to whether the meter was or was not correct, such a
dispute was arbitrable. The Umpire on the basis of the material before him
particularly total energy consumed by the Railways as per summation of KWhr
readings at Railways end of 5 feeders for which there is no dispute, made an
Award, which in our view, he was entitled to make. However, on one aspect of
the matter we feel that the award requires to be modified. The Umpire has
awarded interest @ 12% per annum with effect from August, 1993 till the passing
of the court decree. In the facts and circumstances of the case the award is
required to be modified to the extent that interest be awarded at the same
rate, but with effect from the date of the award i.e. 30th March, 1998 instead
of August, 1993. The impugned judgment and order of the High Court is set
aside. The appeal is accordingly allowed with the said modification. Let a
decree be drawn up accordingly. There shall be no order as to costs.
Back