Bharat
Coking Coal Ltd. Vs. M/S Annapurna Construction [2003] Insc 422 (29 August 2003)
Cji.
& S.B. Sinha. S.B. Sinha, J :
These
appeals are directed against the judgment and order dated 29.4.1997 passed by
the High Court of Patna, Ranchi Bench, Ranchi in Appeal from Original Order
No.169 of 1995 (R) whereby and whereunder the appeal preferred by the appellant
herein from a judgment and order dated 3.6.1995 passed by the Subordinate
Judge, 4th Court, Dhanbad in Title (Arbitration) Suit No.109 of 1994 was dismissed.
FACTS:
The
basic fact of the matter is not in dispute. The parties hereto entered into a
contract for construction of 140 numbers of temporary hutments, the estimated
cost of which was Rs.49,45,447.81.
A
formal work order was issued to the respondent herein. Entire work in terms of
the agreement was to be completed within a period of four months.
A
formal contract was entered into for the aforementioned work by and between the
parties. The said contract contained an arbitration agreement. The said
contractual job was not allegedly completed by the respondent within the
stipulated period wherefor a request was made for extension of time till
31.12.1986 to complete the work. Further extensions of time were sought for and
granted from time to time.
Disputes
and differences having arisen between the parties, the arbitration agreement
was invoked. The Chief Engineer of the appellant-Company was appointed as the
sole arbitrator. He was to give a reasoned award. Before the arbitrator the
respondent raised a claim of Rs.55,01,640.66. The appellant herein also raised
a counter claim for a sum of Rs.28,47,860.57. By reason of an award dated
13.7.1994, the sole arbitrator awarded a sum of Rs.18,97,729.37 with interest @
18% per annum in favour of the respondent. The counter claim of the appellant,
however, was rejected.
The
said award was filed before the learned Subordinate Judge, Dhanbad for being
made a rule of court in terms of Section 14 of the Arbitration Act, 1940 (for
short 'the Act'). The appellant herein in the said proceedings filed an
objection under Sections 15, 16, 30 and 33 of the Act. The learned trial Judge
by reason of a judgment dated 3.6.1995 rejected the said objection of the
appellant and made the award as rule of court, where-against an appeal was
preferred which by reason of the impugned judgment was dismissed.
However,
it may be noticed at this stage that the learned Subordinate Judge did not
grant any interest from the date of decree in favour of the respondent wherefor
an application purported to be under Section 152 of the Code of Civil Procedure
was filed. The said application was rejected on 12.12.1995 where-against the
respondent preferred a civil revision application before the High Court. Both
the appeal being M.A. No.169 of 1995 (R) filed by the appellant herein and
Civil Revision being C.R. No.12 of 1996 (R) filed by the respondent herein were
heard together. While disposing the appeal, the revison petition was allowed by
the High Court by reason of the impugned judgment.
SUBMISSIONS:
Mr. Ajit
Kumar Sinha, learned counsel appearing on behalf of the appellant, inter alia,
submitted that the respondent having accepted the final bill, a further claim
by it was inadmissible. The learned counsel pointed out that as a special case
the appellant granted 95% advance wherefor no interest was to be charged. The
said advance was to be adjusted from the running bills. In that view of the
matter, the learned counsel would contend that the arbitrator committed an
illegality in entertaining Claim Item Nos. 3 and 7. The learned counsel would
urge that the respondent having been granted extension, it was obligatory on
the part of the learned arbitrator to consider as to whether the respondent was
entitled to any compensation for the alleged loss occurred on the ground of
delay in completion of work, particularly when it was agreed that the extension
of time was granted subject to payment of penalty. The learned counsel would
further submit that in terms of the contract the appellant had been supplied
with all the essential raw materials, namely, cement, steel etc. which would
cover about 95% of the total cost to be incurred for the construction of the
hutments and in that view of the matter the respondent could not be held to be
entitled to any amount by way of escalation in the price.
Mr.
S.B. Upadhyay, learned counsel appearing on behalf of the respondent, per
contra would submit that the objections filed by the appellant herein have been
thoroughly considered by the learned Subordinate Judge and the High Court and
as such it is not a fit case wherein this Court should interfere. The learned
counsel would urge that it is not the case of the appellant that the learned
sole arbitrator did not pass a reasoned award and, thus, this court in exercise
of its jurisdiction under Section 30 of the Act would not interfere when two
views are possible. The learned counsel would submit that while exercising its
jurisdiction under Section 30 of the Act, the court does not reappraise
evidences brought on record. Strong reliance, in this connection, has been
placed on Ispat Engineering & Foundry Works, B.S. City, Bokaro vs. Steel
Authority of India Ltd., B.S. City, Bokaro [(2001) 6 SCC 347].
FINDINGS:
Only
because the respondent has accepted the final bill, the same would not mean
that it was not entitled to raise any claim. It is not the case of the
appellant that while accepting the final bill, the respondent had unequivocally
stated that he would not raise any further claim. In absence of such a
declaration, the respondent cannot be held to be estopped or precluded from
raising any claim. We, therefore, do not find any merit in the said submission
of Mr. Sinha.
The
submission of Mr. Sinha to the effect that the High Court committed an error in
granting interest from the date of the decree purported to be in terms of
Section 29 of the Arbitration Act appears to be correct. The learned
Subordinate Judge did not grant any interest in terms of Section 29 of the Act.
The same was not by way of a clerical or arithmetical mistake which could be
corrected by the court in exercise of its power under Section 152 of the Code
of Civil Procedure. The remedy of the respondent, therefore, was either to
prefer an appeal thereagaint or file a review petition. As the court could not
have exercised its jurisdiction under Section 152 of the Code of Civil
Procedure, the High Court in exercise of its revisional jurisdiction could not
have interfered therewith.
So far
as the question of late payment of the bills is concerned, the arbitrator has
arrived at a finding of fact that there had been an inordinate delay in respect
of 10th R/A bill for Rs.4,85,403.31 which was paid after a lapse of one year
from the date of completion of work on 15.1.1988 and a sum of Rs.54,737.53 was
awarded as damages @ 12% on the said amount for the period of 343 days to the
appellant.
So far
as Claim Item No.3 is concerned, the question which arose for consideration
before the arbitrator was as to whether any extra work had been done or not.
The case of the appellant was that the respondent had not done any extra work.
The arbitrator had considered the materials on record for the purpose of
arriving at a finding of fact that certain extra work had been done by the
respondent wherefor only a sum of Rs.84,942.02 was awarded in place and instead
of Rs.1,58,862.26.
However,
Mr. Sinha is correct in his submission that the learned arbitrator has not
taken into consideration the effect and purport of the following clause in the
contract:
"Provided
always that :
(a)
Contractor/Contractors shall not be entitled to any payment for any additional
work done unless he/they have received an order in writing from the
Superintending Engineer/Sr. Executive Engineer/Executive Engineer for such
additional work;
(b)
The contractor/contractors shall be bound to submit his/their claim for any
such additional work done during any month on or before the 15th day of the
following month accompanied by the additional work; and
(c)
The contractor/contractors shall not be entitled to any payment in respect of
such additional work if he/they fail to submit his/their claim within the
aforesaid period."
The
question is as to whether the claim of the contractor is de hors the rules or
not was a matter which fell for consideration before the arbitrator. He was
bound to consider the same. The jurisdiction of the arbitrator in such a matter
must be held to be confined to the four-corners of the contract. He could not
have ignored an important clause in the agreement; although it may be open to
the arbitrator to arrive at a finding on the materials on records that the
claimant's claim for additional work was otherwise justified.
Claim
Item No.4 was rejected.
The
award in respect of Claim Item No.5 is not in question.
Claim
Item No.6 was in relation to penalty amount of Rs.10,000/- which was deducted
by way of penalty and was not found to be justifiable, and as such the
appellant was directed to refund the said amount.
We are
furthermore concerned with Claim Item Nos.7 and 11 which are under the headings
of 'Losses due to prolongation of work' and 'Material Escalation'. It is not in
dispute that a secured advance of 95% of the cost of materials was given in
terms of the contract which is to the following effect :
"Secured
Advance will be paid @ 95% of the cost of materials as a special case to get
the work completed within 4(four) months as per latest price list of BCCL (copy
enclosed), subject to submissions of Indemnity Bond on non-Judicial stamp paper
of required value in the approved proforma of BCCL and also Insurance against
fire, theft and damages etc. The secured advance will be paid only on the items
on which it was payable in BCCL. The secured advance thus paid, will be
recovered in five equal instalments from the subsequent running account bills
or on the consumption of materials whichever is earlier." The appellant
does not dispute the same. It is also not in dispute that the appellant has not
charged any interest in respect of the said advance. It is further not in
dispute that cement @ Rs.51/- per bag, mild steel rounds @ Rs.5460/- per metric
tonne and tor steel @ Rs.5810/-per metric tonne were supplied by the appellant.
However, the claim relating to material escalation was confined to six articles
which were allegedly not supplied by the appellant, namely, bricks, AC sheets,
angles, doors, frames and shutters etc.
So far
as these items are concerned, in our opinion, the learned sole arbitrator
should have taken into consideration the relevant provisions contained in the
agreement as also the correspondences passed between the parties. The question
as to whether the work could not be completed within the period of four months
or the extension was sought for on one condition or the other was justifiable
or not, which are relevant facts which were required to be taken into
consideration by the arbitrator.
It is
now well settled that the Arbitrator cannot act arbitrarily, irrationally,
capriciously or independent of the contract.
In
Associated Engineering vs. Govt. of A.P. [(1991) 4 SCC 93], this Court clearly
held that the arbitrators cannot travel beyond the parameters of the contract. In
M/s. Sudarsan Trading Co. v. The Govt. of Kerala [(1989) 2
SCC 38], this Court has observed that an award may be remitted or set aside on
the ground that the arbitrator in making it had exceeded his jurisdiction and
evidence of matters not appearing on the face of it, will be admitted in order
to establish whether the jurisdiction had been exceeded or not, because the
nature of the dispute is something which has been determined outside the award,
whatever might be said about it in the award by the Arbitrator. This Court
further observed that an arbitrator acting beyond his jurisdiction is a
different ground from the error apparent on the face of the award.
There
lies a clear distinction between an error within the jurisdiction and error in
excess of jurisdiction. Thus, the role of the arbitrator is to arbitrate within
the terms of the contract. He has no power apart from what the parties have
given him under the contract. If he has travelled beyond the contract, he would
be acting without jurisdiction, whereas if he has remained inside the parameter
of the contract, his award cannot be questioned on the ground that it contains
an error apparent on the face of the records.
In
paragraph 577 of Halsbury's laws of England 4th Edition Vol 2, the law has been stated in the following terms:
"As
an arbitrator (and subsequently any umpire) obtains his jurisdiction solely
from the agreement for his appointment it is never open to him to reject any
part of that agreement, or to disregard any limitations placed on his
authority, as, for example, a limitation on his right to appoint an umpire. Nor
can he confer jurisdiction upon himself by deciding in his own favour some
preliminary point upon which his jurisdiction depends. Nevertheless he is
entitled to consider the question whether or not he has jurisdiction to act in
order to satisfy himself that it is worth while to proceed, and an award which
expressly or impliedly refers to such a finding is not thereby
invalidated." In 'Commercial Arbitration' by Mustill and Boyd at page 598
it is stated :
"in
the first place, it could be argued that an arbitrator who is appointed in
respect of a dispute arising under a contract expressly or impliedly governed
by English law is authorised by the parties to pronounce upon the issues in
accordance with that law, and in no other way.
Any
decision which proceeds, on a different basis lies outside the scope of the
arbitrator's mandate to bind the parties. The award is accordingly void for
want of jurisdiction, since the arbitrator has done something which the parties
never authorised him to do. Secondly, it would be possible to draw support from
a line of authority culminating in three important decisions during the past
decade which approach the question whether a tribunal can effectively decide
contrary to law by using the word 'jursdiction' in the first of the three
senses indicated above. Whilst a reconciliation of this decision is a matter
for a treatise on administrative law, there is no doubt that in relation to
certain kinds of tribunal the law has recognised a distinction between errors
of law which go to jurisdiction and those which do not, and that there is a
difference between tribunal which has arrived at a decision by asking itself
the wrong question, and one which has correctly identified the question, but
has supplied the wrong answer in terms of law.
Following
up this line of authority, it could be said that an arbitrator empowered to
decide the rights of the parties under a contract governed by English law, who
asks himself not what England law has to say about those right, but what the
rights ought to be if assessed in accordance with his own ideas of an extra-legal
concept of justice, is either asking himself the wrong question, or not really
asking a question at all." In Alopi Parshad & Sons Ltd. v. Union of
India [(1960) 2 SCR 793], this Court clearly held that if damages are awarded
ignoring the expressed terms of the contract, the arbitrator would commit
misconduct of the proceedings. Reference in this connection may also be made to
In Heyman v. Darwin [1942 (1) All ER 327], it was held that arbitrator as a
rule cannot clothe himself with the jurisdiction when it has none.
In
paragraph 622 at pages 330-331 Halsbury's Laws of England (4th Edn) Vol2 it has
been stated but misconduct occurs, for example;
(1) If
the arbitrator or umpire fails to decide all the matters which were referred to
him.
(2) If
by his award the arbitrator or umpire purports to decide matters which have not
in fact been included in the agreement of reference, for example, where the
arbitrator construed the lease (wrongly), instead of determining the rental and
the value of buildings to be maintained on the land; or where the award
contains unauthorised directions to the parties, or where the arbitrator, has
power to direct what shall be done but his directions affect the interest of
third persons; or where he decided to the parties rights, not under the
contract upon which the arbitration had proceeded but under another contract;
(3) If
the award is inconsistent, or is uncertain or ambiguous, or even if there is
some mistake of fact, although in that case the mistake must be either admitted
or at least clear beyond any reasonable doubt;" In Associated Engineering
(supra), it has been held:
"If
the arbitrator commits an error in the construction of the contract, that is an
error within his jurisdiction. But if he wanders outside the contract and deals
with matters not allotted to him, he commits a jurisdiction error. Such error
going to his jurisdiction can be established by looking into material outside
the award. Extrinsic evidence is admissible in such cases because the dispute
is not something which arises under or in relation to the contract or dependent
on the construction of the contract or to be determined within the award. The
dispute as to jurisdiction is a matter which is outside the award or outside
whatever may be said about it in the award. The ambiguity of the award can, in
such cases, be resolved by admitting extrinsic evidence. The rationale of this
rule is that the nature of the dispute is something which has to be determined
outside and independent of what appears in the award. Such jurisdictional error
needs to be proved by evidence extrinsic to the award.
In the
instant case, the umpire decided matters strikingly outside his jurisdiction.
He outstepped the confines of the contract. He wandered far outside the
designated area. He digressed far away from the allotted task. His error arose
not by misreading or misconstruing or misunderstanding the contract, but by
acting in excess of what was agreed. It was an error going to the root of his
jurisdiction because he asked himself the wrong question, disregarded the
contract and awarded in excess of his authority. In many respects, the award
flew in the face of provisions of the contract to the contrary.
The
umpire, in our view, acted unreasonably, irrationally and capriciously in
ignoring the limits and the clear provisions of the contract. In awarding
claims which are totally opposed to the provisions of the contract to which he
made specific reference in allowing them, he has misdirected and misconducted
himself by manifestly disregarding the limits of his jurisdiction and the
bounds of the contract from which he derived his authority thereby acting ultra
fines compromissi." In State of Orissa v. Dandasi Sahu [1988 (4) SCC 12],
this Court observed:
"In
our opinion, the evidence of such state of affairs should make this Court scrutinise
the award carefully in each particular case but that does not make the court
declare that all high amounts of award would be bad per se." In K.P. Poulose
v. State of Kerala [(1975) 2 SCC 236], this Court observed that the case of
legal misconduct would be complete if the arbitrator on the face of the award
arrives at an inconsistent conclusion even on his own finding or arrives at a
decision by ignoring the very material documents which throw abundant light on
the controversy to help a just and fair decision.
In
K.V. George v. The Secretary to Government, Water and Power Dept, Tri-vendrum
[1989 (4) SCC 595], this Court held :- "In the instant case, the contract
was terminated by the respondents on April 26, 1980, and as such all the issues
arose out of the termination of the contract and they could have been raised in
the first claim petition filed before the Arbitrator by the Appellant.
This
having not been done the second claim petition before the Arbitrator raising
the remaining disputes is clearly barred. With regard to the submission as to
the applicability of the principles of res judicata as provided in Section 11
of the Code of Civil Procedure to arbitration case, it is to be noted that Section
41 of the Arbitration Act provides that the provisions of the Code of Civil
Procedure will apply to the Arbitration proceedings. The provisions of res judicata
are based on the principles that there shall be no multiplicity of proceedings
and there shall be finality of proceedings. This is applicable to the
arbitration proceedings as well." This Court referred to the decision in Satish
Kumar v. Surinder Kumar [AIR 1970 SC 833] and held:
"The
true legal position in regard to the effect of an award is not in dispute. It
is well settled that as a general rule, all claims which are the subject-matter
of a reference to arbitration merge in the award which is pronounced in the
proceedings before the arbitrator and that after an award has been pronounced,
the rights and liabilities of the parties in respect of the said claims can be
determined only on the basis of the said award.
After
an award is pronounced, no action can be started on the original claim which
had been the subject-matter of the reference....... This conclusion, according
to the learned Judge, is based upon the elementary principle that, as between
the parties and their privies, an award is entitled to that respect which is
due to judgment of a court of last resort. Therefore, if the award which has
been pronounced-between the parties has in fact, or can in law, be deemed to
have dealt with the present dispute, the second reference would be incompetent.
This position also has not been and cannot be seriously disputed." In
Union of India vs. Jain Associates and Another [(1994) 4 SCC 665], this Court
upon following K.P. Poulose (supra) and Dandasi Sahu (supra) held :
"8.
The question, therefore, is whether the umpire had committed misconduct in
making the award.
It is
seen that claims 11 and 12 for damages and loss of profit are founded on the
breach of contract and Section 73 encompasses both the claims as damages.
The
umpire, it is held by the High Court, awarded mechanically, different amounts
on each claim. He also totally failed to consider the counter-claim on the
specious plea that it is belated counter- statement. These facts would show,
not only the state of mind of the umpire but also non-application of the mind,
as is demonstrable from the above facts. It would also show that he did not act
in a judicious manner objectively and dispassionately which would go to the
root of the competence of the arbitrator to decide the disputes." 629],
this Court held:
"It
would be difficult for the courts to either exhaustively define the word
"misconduct" or likewise enumerate the line of cases in which alone
interference either could or could not be made. Courts of law have a duty and
obligation in order to maintain purity of standards and preserve full faith and
credit as well as to inspire confidence in alternate dispute redressal method
of arbitration, when on the face of the award it is shown to be based upon a
proposition of law which is unsound or findings recorded which are absurd or so
unreasonable and irrational that no reasonable or right-thinking person or
authority could have reasonably come to such a conclusion on the basis of the
materials on record or the governing position of law to interfere."
(India) and Another [(2001) 8 SCC 482], it was observed:
"In
the light of this enunciation of law, we are of the view that unless the error
of law sought to be pointed out by the learned counsel for the petitioners in
the instant case is patent on the face of the award, neither the High Court nor
this Court can interfere with the award. The exercise to be done by examining
clause 14(ii) of the contract entered into between the parties, construing the
same properly and thereafter applying the law to it to come to a conclusion one
way or the other, is too involved a process and it cannot be stated that such
an error is apparent or patent on the face of the award. Whether under the
context of the terms and conditions of a contract, a stipulation in the form
and nature of clause 14(ii) operates as a special provision to the exclusion of
Section 73 of the Indian Contract Act is a matter of appreciation of facts in a
case, and when the decision thereon is not patently absurd or wholly
unreasonable, there is no scope for interference by courts dealing with a
challenge to the award." Kumar Kayan and Others [(2002) 5 SCC 679], this
Court opined:
"In
order to determine whether the arbitrator has acted in excess of his
jurisdiction what has to be seen is whether the claimant can raise a particular
claim before the arbitrator.
If
there is a specific term in the contract or the law which does not permit the
parties to raise a point before the arbitrator and if there is a specific bar
in the contract to the raising of the point, then the award passed by the
arbitrator in respect thereof would be in excess of his jurisdiction." The
High Court was, therefore, required to consider, the objections filed by the
Appellant herein from the aforementioned points of view.
Where upon
Mr. Sinha has placed strong reliance cannot be held to be applicable in this
case as therein the court was concerned with hybrid award. The court was not in
a position to ascertain as to whether escalation charges had been made against
the materials supplied by the principal or also other materials.
It is
no doubt true that the jurisdiction of this Court while considering the
validity of an award is limited as has been stated by this Court in Ispat
Engineering & Foundry Works (supra):
"4.
Needless to record that there exists a long catena of cases through which the
law seems to be rather well settled that the reappraisal of evidence by the
court is not permissible. This Court in one of its latest decisions (Arosan
Enterprises Ltd. v. Union of India ((1999) 9 SCC 449)) upon consideration of
decisions in Champsey Bhara & Co. v. Jivraj Balloo Spg. & Wvg. Co. Ltd.
(AIR 1923 PC 66 : 1923 AC 480), Union of India v. Bungo Steel Furniture (P)
Ltd. (AIR 1967 SC 1032 : (1967) 1 SCR 324), N. Chellappan v. Secy., Kerala SEB
((1975) 1 SCC 289), Sudarsan Trading Co. v. Govt. of Kerala ((1989) 2 SCC 38),
State of Rajasthan v. Puri Construction Co. Ltd. ((1994) 6 SCC 485) as also in
Olympus Superstructures (P) Ltd. v. Meena Vijay Khetan ((1999) 5 SCC 651) has
stated that reappraisal of evidence by the court is not permissible and as a
matter of fact, exercise of power to reappraise the evidence is unknown to a
proceeding under Section 30 of the Arbitration Act. This Court in Arosan
Enterprises ((1999) 9 SCC 449) categorically stated that in the event of there
being no reason in the award, question of interference of the court would not
arise at all. In the event, however, there are reasons, interference would
still be not available unless of course, there exist a total perversity in the
award or the judgment is based on a wrong proposition of law. This Court went on
to record that in the event, however, two views are possible on a question of
law, the court would not be justified in interfering with the award of the
arbitrator if the view taken recourse to is a possible view. The observations
of Lord Dunedin in Champsey Bhara (AIR 1923 PC 66 : 1923 AC 480) stand accepted
and adopted by this Court in Bungo Steel Furniture (AIR 1967 SC 1032 : (1967) 1
SCR 324) to the effect that the court had no jurisdiction to investigate into
the merits of the case or to examine the documentary and oral evidence in the
record for the purposes of finding out whether or not the arbitrator has
committed an error of law. The court as a matter of fact, cannot substitute its
own evaluation and come to the conclusion that the arbitrator had acted
contrary to the bargain between the parties." However, as noticed
hereinbefore, this case stands on a different footing, namely, that the
arbitrator while passing the award in relation to some items failed and/or
neglected to take into consideration the relevant clauses of the contract, nor
did he take into consideration the relevant materials for the purpose of
arriving at a correct fact. Such an order would amount to misdirection in law.
We
are, therefore, of the opinion that the matter requires reconsideration. Having
regard to the facts and circumstances of this case and particularly keeping in
view the fact that the matter relates to pure interpretation of document which
gives rise to question of law and instead and in place of remitting the matter
to the named arbitrator, we would direct that the disputes in relation to Claim
item Nos.3, 7 and 11 be referred to Hon'ble Mr. Justice D.N. Prasad, a retired
Judge of the Jharkhand High Court on such terms and conditions as may be
mutually agreed upon by the parties. The learned arbitrator is requested to
consider the desirability of making his award as expeditiously as possible
keeping in view the fact that the matter has been pending for a long time.
These
appeals are allowed to the aforementioned extent. No costs.
Back