Nirmala
Anand Vs. Advent Corporation (Pvt.) Ltd. & Ors [2002] Insc 416 (30 September 2002)
G.B.
Pattanaik, Y.K.Sabharwal & H.K. Sema. Y.K. Sabharwal, J.
The
appellant, who was plaintiff No.4 in the suit, entered into an agreement dated
8th September, 1966 with Respondent No.1 and 2 for the purchase of Flat No.71,
on the 7th Floor of the building known as 'Divya Prabha' situated at 12-A,
Foreshore Road, Bombay.
The
sale consideration payable under the agreement is Rs.60,000/-. The agreement
stipulated that the building was to be completed and possession of the flat
delivered to the appellant by 30th June, 1969 up to which time, the appellant
had already paid Rs.35,000/- out of the sale consideration leaving a balance of
Rs.25,000/-. Just a few days before the date fixed for completion and delivery
of possession, the lease of the plot of land on which the flats were being
constructed was cancelled by the Bombay Municipal Corporation. At that stage,
the building was incomplete. Admittedly, it is incomplete till date.
Similar
agreements in respect of different flats were also entered into by the sellers
with other flat purchasers. On 30th July, 1969,
a suit, out of which the present appeal has arisen, was filed seeking specific
performance of the flat purchase agreements. The plaintiffs other than
plaintiff Nos.4 and 7 settled their case with sellers during the pendency of
the suit and plaintiff No.7 also settled during pendency of the appeal before
the Division Bench of the High Court. There was, however, no settlement between
the plaintiff-appellant and respondents 1 and 2. In the decision of the suit,
learned Single Judge of the High Court held that the appellant was always ready
and willing to perform her part of the contract and it was the sellers who
committed breach in not carrying out the terms of the agreement. Learned Single
Judge was, however, of the view that the grant of specific performance being
discretionary remedy in equity, taking into account several and serious imponderabilities
and further considering that huge sums may be required to complete the
building, which amount cannot be properly assessed, the appellant was not
entitled to the relief of specific performance and instead it was directed that
the seller shall pay to the appellant damages as assessed by the Commissioner
for taking accounts with interest at 6% per annum from the date of the decree
till the date of payment/realization, in addition to the repayment of
Rs.35,000/- with interest thereon at 9% per annum from 4th October, 1967 till the
date of decree and for the subsequent period, at 6% per annum till the date of
payment/realization. The judgment and decree of the learned Single Judge was
affirmed by a Division Bench of the High Court in appeal. Aggrieved therefrom,
the present appeal was filed on grant of leave.
The
appeal was heard by a two Judge Bench. The learned Judges have concurred that
the appellant is entitled to the specific performance of the agreement dated 8th September, 1966. There has, however, been
difference of opinion between learned Judges on the condition in respect of
additional amount that may be paid by the appellant to respondent Nos.1 and 2
and, therefore, the matter has been placed before this three Judge Bench. The
opinions of the learned Judges are reported in Nirmala Anand v. Advent
Corporation (P) Ltd. & Ors. [(2002) 5 SCC 481]. In the opinion expressed by
brother Justice Doraiswamy Raju, the appellant has been directed to pay a sum
of Rs.40,00,000/- in addition to the sum already paid to respondents 1 and 2
and in the view of brother Justice Ashok Bhan, it would be unfair to impose the
condition of payment of Rs.40,00,000/- and the appellant is entitled to
specific performance of agreement to sell on the price mentioned in the
agreement.
We
have heard learned counsel for the parties. The only question to determine is
as to whether the appellant shall be directed to pay to respondents 1 and 2 any
additional sum and if so what amount.
The
appellant is prepared and willing to take possession of the incomplete flat
without claiming any reduction in the purchase price and would not hold
respondent Nos.1 and 2 responsible for anything incomplete in the building. It
has been concurrently held that she did not commit breach of the agreement to
sell. She has always been ready and willing to perform her part of the
agreement. The appellant is ready and willing to pay to respondents 1 and 2
interest on sum of Rs.25,000/-. The breach was committed by respondents 1 and 2
as noticed hereinbefore. It is evident that the appellant is ready to take
incomplete flat and pay further sum as noticed, most likely on account of
phenomenal increase in the market price of the flat during the pendency of this
litigation for over three decades. We see no reason why the appellant cannot be
allowed to have, for her alone, the entire benefit of manifold mega increase of
the value of real estate property in the locality. In our view, it would not be
unreasonable and inequitable to make the appellant the sole beneficiary of the
escalation of real estate prices and the enhanced value of the flat in
question. There is no reason why the appellant, who is not a defaulting party,
should not be allowed to reap to herself the fruits of increase in value.
It is
true that grant of decree of specific performance lies in the discretion of the
court and it is also well settled that it is not always necessary to grant
specific performance simply for the reason that it is legal to do so. It is
further well settled that the court in its discretion can impose any reasonable
condition including payment of an additional amount by one party to the other
while granting or refusing decree of specific performance. Whether the
purchaser shall be directed to pay an additional amount to the seller or
converse would depend upon the facts and circumstances of a case. Ordinarily,
the plaintiff is not to be denied the relief of specific performance only on
account of the phenomenal increase of price during the pendency of litigation.
That may be, in a given case, one of the consideration besides many others to
be taken into consideration for refusing the decree of specific performance. As
a general rule, it cannot be held that ordinarily the plaintiff cannot be
allowed to have, for her alone, the entire benefit of phenomenal increase of
the value of the property during the pendency of the litigation. While
balancing the equities, one of the consideration to be kept in view is as to
who is the defaulting party. It is also to be borne in mind whether a party is
trying to take undue advantage over the other as also the hardship that may be
caused to the defendant by directing the specific performance. There may be
other circumstances on which parties may not have any control. The totality of
the circumstances is required to be seen.
In the
present case, the suit was filed by the plaintiff within a month of the date
when the possession under the agreement was to be delivered to her. By that
time, she had already paid more than 50% of the sale consideration. There was
no occasion for her to pay the balance consideration to the seller. The courts
have concurrently found that the appellant has always been ready and willing to
perform her part of the contract and the seller committed breach in not
carrying out the terms of the agreement. While others left, the appellant has
been single handedly fighting for her rights under the agreement. She has
agreed to take the flat on as-is-where-is basis without claiming any reduction
in purchase price and without making the seller liable for anything incomplete
in the building. Further the building except the flat in question has been sold
by respondents 1 and 2 to the 7th respondent. For the revival of the building
plans, revival of lease and other such steps, the sellers and/or their
assignees may have to take steps as per agreement between them but to ask the
appellant to pay to respondent Nos. 1 and 2, a sum of Rs.40,00,000/- would be
too onerous and would almost amount to denying her specific performance. It
would also amount to putting a premium on the breach committed by respondents 1
and 2. Along with the remaining amount of the sale consideration, the appellant
can also be directed to pay to respondents 1 and 2 some reasonable additional
amount, they having been deprived of that amount of Rs.25,000/- during all
these years.
Having
regard to the totality of circumstances, we would direct the appellant to pay
to respondents 1 and 2 a sum of Rs.6,25,000/- instead of Rs.25,000/-. The
amount of Rs.40,00,000/-, wherever it appears in the opinion of Justice Doraiswamy
Raju, would be read as Rs.6,25,000/-. All other conditions will remain.
The
appeal is accordingly allowed and the impugned judgment and decree of the High
Court shall stand modified and altered and there shall be a decree in Suit
No.744 of 1969 on the file of the original side of the High Court, Bombay in the following terms :
(i)
There shall be conditional decree for specific performance of the agreement
dated 8-9-1966 entered into between the 4th plaintiff and Defendants 1 and 2
and Defendants 1 and 2 shall execute a sale deed as envisaged in the agreement
for sale of Flat No.71 on 7th Floor of the building known as "Divya Prabha"
situated at No.12-A, Foreshore Road, Bombay, on "as-is-where-is
condition".
(ii)
That the appellant-plaintiff 4, within a period of six weeks, shall pay the
defendants-respondents 1 and 2, a sum of Rs.6,25,000/- (Rupees six lakh and
twenty five thousand only) in addition to the sum already paid by her. The
appellant shall be entitled to have the sale deed executed in her favour only
on prior compliance and satisfaction of this condition.
(iii)
The rights and interest in the land shall be as agreed to between parties and
as per scheme and arrangement contained in the agreement dated 8-9-1966.
(iv)
Defendants 1 and 2 and/or the 7th respondent in this appeal viz. Gaurav
Overseas Private Ltd., 92, Maker Chambers, Nariman Point Bombay - 400 020, as
and when they secure the necessary renewal of the lease and revalidation of the
building plan, the same shall be for the benefit of the appellant-Plaintiff 4
also, subject to the condition that she shall contribute her share of the
monetary commitments and expenses incurred therefor, on being intimated by any
of them in writing within four weeks from the date of such receipt of the
intimation. In case of dispute about the quantum, the same shall be got
determined and settled before the Commissioner for taking accounts, on being
moved by either of them. The sum so determined shall be a charge on the
property comprised in Flat No.71, till it is paid and shall be entitled to be
recovered, accordingly.
(v)
The appellant and the 7th respondent shall be at liberty to mutually agree for
completion of the incomplete building at such prevailing market rates as would
be applicable for the work and manner of its completion and the mode of
payment. If there can be no such mutual agreement among the appellant and the
7th respondent in this regard, as and when the sale deed is executed by the 1st
and 2nd defendants, as per this decree, the appellant shall be at liberty to
make her own arrangement to have her flat completed through approved and
licensed architects.
(vi)
The sale/conveyance pursuant to the decree in the suit shall be subject to all
such rights and liabilities and obligations of respective parties (the
appellant, respondents 1, 2 and 7) under the suit agreement, as are available
to each of them against the others, had the sale been effected even without the
intervention of this Court, by mutual agreement of parties.
(vii)
The appellant failing to comply with the terms of the conditional decree passed
as above, shall stand denied and lose her right and entitlement to get specific
performance of the agreement dated 8-9-1966 in her favour and consequently, the
appeal shall stand dismissed with the appellant's rights secured as per the
judgments and decrees dated 23-3-1981 and 15-7-1087 firmly affirmed and
settled, and the rights to have them executed in the manner known to law, alone
surviving to the appellant.
(viii)
Each party shall bear their respective costs in this Court.
The
appeal is allowed in above terms.