M.D. Kerala State Bev. (M & M) Corpn. Ltd. & Anr
Vs. K.M.K. Salim & Ors [2001] Insc 26 (17 January 2001)
S.N.Phukan,
S.S.M.Quadri Syed Shah Mohammed Quadri, J.
Special Leave Petition (civil) 15881 of 1999 Special Leave
Petition (civil) 666 of 2001 Special Leave Petition (crl.) 1476 of 2000
L.J
Leave
is granted.
These
two appeals are between the same parties and arise out of the proceedings
relating to award of contract for handling loading and unloading operations in
the appellants Corporation. They can conveniently be disposed of together.
Civil
Appeal No.665 of 2001 @ S.L.P.(C) NO.15881 of 1999 is directed against the
order of a Division Bench of the High Court of Kerala at Ernakulam in O.P.NO.19616
of 1999 dated September
20, 1999. Civil Appeal
No.666 of 2001 @ S.L.P.(C)No.1476 of 2000 is directed against an interim order
passed by a learned Single Judge of the High Court of Kerala at Ernakulam on December 3, 1999 in O.P. No.30284 of 1999 which is
offshoot of the order impugned in the aforementioned Civil Appeal. The facts
giving rise to these appeals are as follows. The appellants invited tenders for
handling loading and unloading operations in the Kerala State Beverages (M
& M) Corporation Liquor Godown in Valanjavattom, Tiruvalla on September 14, 1998. In response to the said invitation
for tenders, 12 persons including respondent Nos.1 to 3 filed tenders.
Respondent Nos.1 & 2 filed a joint tender and quoted the lowest rates.
However, the appellants, after negotiations, awarded the contract to respondent
No.3 at the rate lower than that quoted by respondent Nos.1 & 2 on October 23, 1998. On October 26, 1998 respondent Nos.1 & 2 questioned the validity of order
of the appellant awarding the contract to respondent No.3 in the High Court in
O.P.No.20911 of 1998 which was dismissed by a learned Single Judge of that
court on November 26,
1998. But on appeal
(Writ Appeal No.2692 of 1998), a Division Bench of the High Court set aside the
order of the learned Single Judge and directed the appellants to reconsider the
tenders and pass appropriate orders within one month of the order; for
reporting compliance, the case was directed to come up on July 23, 1999. The writ appeal was thus allowed
on June 24, 1999. The appellants issued notice to
respondent Nos.1 to 3 and conducted interview on July 12, 1999. The contract was awarded to respondent No.3 by order
issued on July 21, 1999. It is that order which was quashed
by the Division Bench in O.P.No.19616 of 1999 by the order, impugned in the
first- mentioned civil appeal.
By the
said impugned order the Managing Director of the first appellant was directed
to consider the tenders afresh and pass appropriate orders within two weeks
from the date of that order keeping in view the observations of the High Court
in Writ Appeal No.2692 of 1998. On fresh consideration of the tenders, the
Managing Director awarded the contract to respondent Nos.1 & 2 on October 1, 1999.
Thereafter,
respondent Nos.1 & 2 filed O.P.NO.30284 of 1999 seeking a writ of mandamus
directing the appellants to enter into an agreement with them within ten days
without insisting on any licence from the District Labour Officer in terms of
award of the work. In the said O.P. a direction was sought in the above terms
in C.M.P. NO.51612 of 1999.
On December 3, 1999, a learned Single Judge of the High
Court issued an interim direction to the first appellant as prayed for. That
order is the subject matter of appeal in C.A.No.666 of 2001 @ S.L.P.(C) No.1476
of 2000. Pursuant thereto, respondent Nos.1 & 2 complied with all the
formalities and have been carrying on loading and unloading operations. Dr.
Rajeev Dhawan, the learned senior counsel appearing for the appellants,
contended that the High Court ought not to have interfered with the order of
the appellants awarding the contract to respondent No.3 on October 23, 1998. The reasons for awarding the
contract to respondent No.3, submitted the learned counsel, were neither
irrelevant nor arbitrary within the meaning of Wednesbury principle. So also,
the High Court ought not to have interfered with the award of contract to
respondent No.3 by quashing the order of the appellant dated June 24, 1999.
The
subsequent order of the Managing Director awarding the contract in favour of
respondent Nos.1 & 2, was under the threat of contempt. He argued that if
this Court were to set aside the impugned order of the Division Bench of the
High Court, the award of contract in favour of respondent Nos.1 & 2, would
consequently stand set aside. Mr. K. Sukumaran, the learned senior counsel
appearing for respondent Nos.1 & 2, contended that the High Court directed
fresh consideration of the tenders of respondent Nos.1 to 3 by the Managing
Director of the first appellant and he awarded the contract in favour of
respondent Nos.1 & 2. As the secretary of the first appellant did not
conduct himself properly in carrying out the directions of the High Court dated
June 24, 1999, the Managing Director was ordered
to consider afresh the question of awarding tenders. He submitted that after
award of contract in their favour, respondents executed an agreement with the
appellants, paid the security deposit and furnished the bank guarantee and that
respondent No.3, the affected party, did not challenge the order of award of
contract in their favour so this is not a fit case for interference by this
Court under Article 136 of the Constitution. We have considered the contentions
of the learned counsel of the parties. We are of the view that by the impugned
order the High Court did not direct the Managing Director of the first
appellant to award the contract in favour of respondent Nos.1 & 2 but
ordered him to consider afresh the competing claims of the tenderers and he, on
fresh consideration, awarded the contract in favour of respondent Nos.1 &
2. The choice of awarding the contract to respondent Nos.1 and 2 is that of the
Managing Director of the first appellant. Inasmuch as respondent Nos.1 & 2,
after award of contract, complied with all the formalities by entering into an
agreement, paying the security deposit and furnishing bank guarantee, it will
not be appropriate, having regard to the subsequent developments and the facts
of this case, to deal with the correctness or otherwise of the reasoning of the
High Court in the impugned orders. In this view of the matter, while leaving
the questions of law open, we decline to interfere with the orders under
challenge in these appeals. The appeals are accordingly disposed of. No costs.
Back