West Bengal State Electricity Board Vs. Patel
Engineering Co. Ltd. & Ors [2001] Insc 21 (15 January 2001)
S.S.M.Quadri,
S.N.Phukan Syed Shah Mohammed Quadri, J.
L.J
This
appeal by the West Bengal State Electricity Board is from the common judgment
of a Division Bench of the High Court at Calcutta in M.A.T. No.398 of 2000,
C.A.N. No.1089 of 2000 and M.A.T. No.523 of 2000 with cross objections (C.O.T.
No.522 of 2000) dated April 4, 2000 dismissing the appeals and cross objections
and confirming the order of the learned Single Judge in W.P.No.22458(W) of 1999
dated February 3, 2000. To appreciate the controversy in this case narration of
the following relevant facts will be necessary. As a pragmatic solution to meet
the peak demand of the energy/power by the West Bengal and also to cater to the
requirements of the entire Eastern Region, the West Bengal State Electricity
Board (for short, the appellant) formulated Purulia Pumped Storage Project (for
short, the Project), at an estimated cost of about Rs.3,188.9 crores with an
installed capacity of 900 M.W. For funding that project the Central Government
entered into a loan agreement with the Overseas Economic Cooperative Fund now
Japan Bank of International Cooperation (for short, the J.B.I.C.). The Project
is proposed to be completed in six Lots of which Lot No.4 relates to main civil
works. For carrying out the work of Lot No.4, the appellant, after complying
with the formalities and after satisfying itself of the pre- qualification of
the bidders, invited revised tenders (hereinafter referred to as, the tenders).
The bids were to be submitted on or before April 27, 1998.
Three
bidders are now in fray. The first is a consortium of four companies
(respondent Nos.1 to 4), the second is M/s. Taisei Corporation (respondent
No.10) and the third is M/s. Skanska International (respondent No.11). They
submitted their bids along with the summary sheets thereof. On September 8, 1999 the bids were opened in the presence
of the representatives of the bidders and they were read out;
the
bid of respondent Nos.1 to 4 was Rs.647.90 crores, of respondent No.11 was
Rs.691.22 crores and of respondent No.10 was 726.50 crores. While the details
of the bid were under scrutiny, by letter dated October 25, 1999, respondent Nos.1 to 4 informed the appellant that there
was a repetitive systematic computer typographical transmission failure and
requested that it be corrected. On December 17, 1999 they sent another letter
stating that they had reason to believe that the appellant was evaluating their
price bid by an illogical and incorrect application of the Instructions To
Bidders (for short, the ITB) and pointed out that the mistake indicated in
their letter of October 25, 1999 was that Indian Rupee unit rate stated in the
first line Item 0.2 was repeated in the next two succeeding lines, which is
clerical in nature and not an arithmetic error.
They emphasised
that their bid was the lowest at Rs.647.90 crores and assured that they would maintain
the said bid price. Under the ITB, the appellant evaluated their bid and on December 18, 1999 informed them that during checking
of their bid documents a good number of arithmetic errors was discovered.
Copies of duly corrected documents were communicated to the said respondents
for their response to be sent in writing to the appellant before December 27, 1999 (1700 IST). A caveat was also
entered that the said letter did not provide any confirmation towards
acceptance of their bid and subsequent award of contract by the appellant.
Challenging
the validity of the said letter of the appellant dated December 18, 1999, respondent Nos.1 to 4 filed the
aforementioned writ petition in the High Court at Calcutta.
On December 21, 1999 a learned Single Judge of the High
Court granted an interim direction to the appellant to consider the
representation which would be made to it by the writ petitioners (respondent
Nos.1 to 4). A representation was accordingly made to the appellant on December 23, 1999, which was decided by the
Evaluation Committee of the appellant on January 6, 2000. The decision taken by the
appellant pursuant to the order of the High Court dated December 21, 1999 did not meet with the approval of
the High Court. On February
3, 2000, while disposing
of the writ petition, a learned Single Judge of the High Court directed the
appellant to reconsider the representation of respondent Nos.1 to 4, after
giving hearing to them, and to pass and communicate a reasoned order within one
week from the date of the order. Against the said order of the learned Single
Judge, the aforementioned appeals and cross-objections were filed both by the
appellant as well as by respondent Nos.1 to 4. A Division Bench of the High
Court at Calcutta, by the impugned common judgment, dismissed the appeals and
the cross-objections upholding the order of the learned Single Judge, directed
the appellant to permit respondent Nos.1 to 4 to correct the errors in the bid
documents and then consider their bid along with the other bids and take a
decision objectively and rationally. Mr. Altaf Ahmed, the learned Additional
Solicitor General, appearing for the appellant, has submitted that the
appellant is bound by the ITB and it acted accordingly. The letter dated October 25, 1999 of respondent Nos.1 to 4 did not
indicate the errors in the bid documents and the correction sought by them.
Even their letter of December
17, 1999 did not
specify in any detail the desired corrections, therefore, the appellant
proceeded to evaluate the bid in terms of ITB. The actual scope of correction
sought by respondent Nos.1 to 4 came to light in their representation dated December 23, 1999, filed after approaching the High
Court. The appellant, submitted the learned Additional Solicitor General,
committed no wrong in rejecting the representation as the same was not
acceptable in terms of Clause 29 of the ITB because neither the unit rate can
be changed nor the price bid can be altered at the request of the bidder; the
unit rate quoted is final and the appellant can correct only arithmetic
mistakes in the line total on the basis of the quoted unit rate. Mr.Ashok H.Desai,
the learned senior counsel appearing for respondent No.11, argued that the
resolution of the appellant rejecting the representation on January 6, 2000 was
in accordance with Clause 29.1(b) of the ITB and that there was no case for
interference by the High Court.
The
decision of the appellant in evaluating the bid documents in terms of ITB,
submitted the learned counsel, could not be termed as arbitrary or illegal; in
the example: A x B = C; B being the quantity for which the bid is offered; A
and C being the unit rate and the result of the multiplication respectively,
are unalterable at the instance of the bidder. If any arithmetic error in arriving
at the line total is noticed by the appellant, that alone could be corrected by
it. But, the correction sought by respondent Nos.1 to 4, was in effect a change
in the unit rate which was impermissible and, therefore, the decision of the
appellant could not have been interfered with by the High Court. Mr.Bhaskar P.Gupta,
the learned senior counsel appearing for respondent No.10, submitted that the
unit rate given by respondent Nos.1 to 4 was an essential term which would be
evident from Clauses 14, 27 and 29 of the ITB, so permitting them to correct
the bid would tantamount to modifying the essential term of the bid and as such
the High Court ought not to have directed the appellant to permit correction of
bid documents and further to consider their bid along with the other bids. Mr.P.Chidambaram,
the learned senior counsel appearing for respondent Nos.1 to 4, argued that in Annexures
1 to 9 which comprised of 749 items there were mistakes in only 37 items due to
the fault of the computer; the nature of mistake was not arithmetic (which
would mean in multiplication or addition) but mechanical, attributable to the
computer and that such mistakes are not covered by Clause 29 of the ITB; in a
case of an unintended mistake, a court of equity would not be a silent
spectator and the High Court, being both a court of law and equity, had rightly
directed the appellant to permit correction of the mistakes by respondent Nos.1
to 4. It was submitted that having regard to the nature of the mistakes, the
appellant itself ought to have sought clarification from the said respondents
under Clause 27 of ITB instead of evaluating the bid on the basis of an
unintended unit rate to reach an astonishing figure which was wholly
disproportionate to the cost of the Project. His contention is that once the
total bid price is maintained, the unit rate is a matter of arithmetic exercise
which should have been corrected by the appellant; further the mode of payment
by the appellant for the work done is not on the basis of each unit but on the
basis of bid price. Accepting that the bid price is unalterable, the unit rate
should be regarded as adjustable. It was also argued by Mr.
Chidambaram
that there was no mistake in giving the unit rate as such; the mistake was in
giving the conversion equivalent in US Dollars and, therefore, the correction
not being the one falling under Clause 29 of the ITB was rightly permitted to
be corrected by the High Court. Finally, he contended that their bid being less
than the bids of respondent Nos.11 and 10 by Rs.40 crores and Rs.80 crores
respectively, the High Court rightly directed consideration of the bid of
respondent Nos.1 to 4 after due correction of the bid documents in public
interest which did not warrant interference by this Court. In the light of the
above contentions, we have to examine as to what is the permissible course of
action under ITB. A reference to the relevant clauses of the ITB will be
apposite here. Clause
14.1
says that unless stated otherwise in the bid documents, the Contract shall be
for the whole Works as described in sub-clause 1.1 thereof based on the
schedule of unit rates and prices submitted by the bidder. Clause 14.2 enjoins
all the bidders to fill in rates and prices for all items of the Works
described in the Bill of Quantities both in figures and words and cautions that
items against which no rate or price is entered by the bidder will not be paid
for by the Employer (the appellant herein) on the execution of items of those
works and the same shall be deemed covered by the other rates and prices in the
Bill of Quantities. With regard to the currencies of the bid, Clause 15.1
directs that unit rates and prices shall be quoted by the bidder in Indian
Rupee (INR) and either in U.S. Dollar or Japanese Yen. The bidders are given
option to assess the component of currency requirements as follows:
(a) for
those inputs to the Works which the bidder expects to supply from within the
Employers country (the appellants country - India) in Indian Rupee; and
(b) for
those inputs to the Works which the bidder expects to supply from outside the
Employers i.e. outside India in U.S. Dollar or Japanese Yen.
In
regard to modification and withdrawal of bids, Clause 24.1 provides that the
bidder may modify or withdraw his bid after bid submission but before the
deadline for submission of bids. The mandate of Clause 24.3 of the ITB is that
no bid shall be modified by the bidder after the deadline for submission of
bids. Inasmuch as Clauses 27 and 29 of the ITB deal with clarification of bids
and correction of errors respectively and their true interpretation has a
bearing on the decision in this case, it will be apt to quote them here : 27.
Clarification of Bids 27.1 To assist in the examination, evaluation and
comparison of bids, the Employers authorised representative may, at his
discretion, ask any or all bidders for clarification of his/their Bids,
including breakdowns of unit rates, technical information, documents and
materials after opening of the Bid. The request for clarification and the
response shall be in writing or by cable, but no change in the price or
substance of the Bid after opening the Price Bid shall be sought, offered or
permitted except as required to confirm the correction of arithmetic errors
discovered by the Employers authorised representative in the evaluation of the
bids in accordance with Clause 29 of ITB.
29.
Correction of Errors
29.1
Bids determined to be substantially responsive will be checked by the Employers
authorised representative for any arithmetic errors. Errors will be corrected
by the Employers authorised representative as follows:
(a) where
there is a discrepancy between the amounts in figures and in words, the amount
in words will govern; and
(b) where
there is a discrepancy between the unit rate and the line item total resulting
from multiplying the unit rate by the quantity, the unit rate as quoted will
govern.
(c)
Where there is a discrepancy between figures and in words of an unit rate, the
unit rate as quoted in words will govern. 29.2 The amount stated in the Form of
Bid will be adjusted by the Employers authorised representative in accordance
with the above procedure for the correction of errors and shall be communicated
to the Bidder in writing for his acceptance in writing within seven (7) days from
the date of issue of such communication. Such corrections however shall be
binding upon the Bidder. If the Bidder does not accept the corrected amount of
bid, his bid will be rejected, and the bid security shall be forfeited in
accordance with sub-clause 17.6(b) of ITB. It may be seen that Clause 27.1
enables the appellant or its authorised representative to ask any or all
bidders for clarification of his/their bids, including breakdowns of unit
rates, technical information, documents and materials after opening of the bid.
The request for such clarification is required to be made in writing or by
cable, so also the response to such request. It is important to note that the
said clause prohibits seeking, offering or permitting any change in the price or
substance of the bid after opening of the price bid. The exception provided to
that mandate is correction of arithmetic errors discovered by the appellant's authorised
representative in the evaluation of the bids in accordance with Clause 29
thereof. A plain reading of Clause 29.1 shows it has two limbs; the first limb
imposes a duty on the appellants authorised representative to check bids
determined to be substantially responsive for any arithmetic errors and the
second postulates correction of such errors by the authorised representative in
the manner laid down in sub-clauses (a) to (c) thereof. Sub-clause (a) says
that in the event of discrepancy between the amounts in figures and in words,
the amount in words will govern;
sub-clause
(b), which is germane for our discussion, provides that in case of a
discrepancy between the unit rate and the line item total resulting from
multiplying the unit rate by the quantity, the unit rate as quoted will govern;
and
the import of sub-clause (c) is that in case of a discrepancy between figures
and in words of any unit rate, the unit rate as quoted in words will govern.
Where errors are corrected in accordance with the above guidelines by the appellants
authorised representative, Clause 29.2 specifies the procedure to adjust the
amount stated in the Form of Bid. The authorised representative has to
communicate the correction of errors to the bidder in writing for his written
acceptance within seven days from the date of issue of such communication. It
also provides that such corrections shall be binding upon the bidder and in the
event of the bidder not accepting the corrected amount of bid, his bid will be
rejected and the bid security is liable to be forfeited in accordance with sub-
clause 17.6 (b) of the ITB. Now adverting to the Annexures, the statement of B.Upper
Dam price bid submitted by respondents 1 to 4 discloses that with reference to
each work item the quantity thereof is mentioned. The bidder is expected to
give the unit price in Indian Rupee as well as in U.S. Dollar both in figures
as well as in words and enter the line item total resulting from multiplying
the unit rate by the quantity. A plain reading of sub-clause (b) of Clause
29.1, referred to above, leaves no room for doubt that once the unit rate and
line item total are filled in by the bidder, both the quoted unit rate and item
total are treated as unalterable at the instance of the bidder though
arithmetic errors in arriving at line item total by multiplication are
permitted to be corrected by the appellants authorised representative.
This
being the intendment of the ITB, we shall now examine :
(i) whether
the correction made by the appellant in the bid documents of respondent Nos.1
to 4 and consequential evaluation of their bid communicated with letter dated December 18, 1999 are valid in law; and
(ii) whether
respondents 1 to 4 are entitled to seek correction in their bid documents
either under ITB or in equity and the direction given by the High Court to the
appellant to permit the correction of errors, is sustainable. Before proceeding
to ascertain answers to the above questions, it will be useful to bear in mind
the principles governing the exercise of power of judicial review by the High
Courts.
We
consider it unnecessary to refer to cases on the scope of the power of judicial
review of administrative action by the High Court as a three Judge Bench of
this Court has, after exhaustive consideration of long line of authorities,
succinctly summarised the position and laid down the [1994 (6) SCC 651] :
(1)
The modern trend points to judicial restraint in administrative action.
(2)
The court does not sit as a court of appeal but merely reviews the manner in
which the decision was made.
(3)
The court does not have the expertise to correct the administrative decision.
If a review of the administrative decision is permitted it will be substituting
its own decision, without the necessary expertise which itself may be fallible.
(4)
The terms of the invitation to tender cannot be open to judicial scrutiny
because the invitation to tender is in the realm of contract. Normally
speaking, the decision to accept the tender or award the contract is reached by
process of negotiations through several tiers. More often than not, such
decisions are made qualitatively by experts.
(5)
The Government must have freedom of contract. In other words, a fair play in
the joints is a necessary concomitant for an administrative body functioning in
an administrative sphere or quasi-administrative sphere. However, the decision must
not only be tested by the application of Wednesbury principle of reasonableness
(including its other facts pointed out above) but must be free from
arbitrariness not affected by bias or actuated by mala fides.
(6)
Quashing decisions may impose heavy administrative burden on the administration
and lead to increased and unbudgeted expenditure. In the light of these
principles, we shall determine the aforementioned points. Taking up the first
question first, it will be necessary to understand the nature of errors,
correction made by the appellant and the relief sought by respondent Nos.1 to 4
in respect of 37 items in the bid documents. We shall extract here, as a sample
of errors in 37 items, the price bid submitted by respondent Nos.1 to 4
relating to B. Upper Dam found on page No.70 of Vol.IV of the documents (marked
A). It reads thus: Annexure B. Upper Dam A Price Bid as Submitted Item Work
Item Esc. Coeff.
Remarks
Unit Quantity Unit Price Amount Clause In Specifica- tions INR US$ Figure Words
1.Care of river 02 Rock Excavation I Cum 1000 148.08 One hundred forty-eight
point nil eight 148,077.97 7.4 148.08 One hundred forty-eight point nil eight
3,384.64 03 Impervious Core Embankment I Cum 148.08 One hundred forty-eight
point nil eight 328,418.53 9.5 1.92 One point ninety-two 7,506.71 According to
respondents 1 to 4, the above price bid should be corrected to read as given in
the following statement (marked B):
B Item
Work Item Esc. Coeff.
Remarks
Unit Quantity Unit Price Amount Clause In Specifica- tions INR US$ Figure Words
1.Care of river 02 Rock Excavation I Cum 1000 148.08 One hundred forty-eight
point nil eight 148,077.97 7.4 3.38 Three point thirty eight 3,384.64 03
Impervious Core Embankment I Cum 3,900 84..21 Eight four point twenty one
328,418.53 9.5 1.92 One point ninety-two 7,506.71 A perusal of the price bid
statement A shows that the unit price filled in by the bidder in the first line
against Item (02) - Work Item -, Rock Excavation is repeated in two lines - in
the second line of the same item and in the first line of Item (03) - Work item
- Impervious Core Embankment. In the quantity column, 1000 is noted by the
appellant. The unit rate for Rock Excavation is given by respondent Nos.1 to 4
in the first line in Indian Rupee as Rs.148.08 both in figures as well as in
words. In the amount column Rs.148,077.97 is entered which is arrived at by
multiplying quantity, 1000, by unit rate, Rs.148.08.
It
contains an arithmetic error; instead of Rs.148,080.00, it is noted as
Rs.148,077.97. It has been noticed above that under Clause 29.1(b) of the ITB,
such an error in the line total in the amount column is amenable for correction
and not the unit rate noted by the bidder in the figure column. In the second
line, the same entry is repeated though that line should contain unit rate in U.S.Dollar
which is rupee equivalent of the unit rate mentioned in the first line.
Respondent Nos.1 to 4 seek correction of 148.08 in the second line as 3.38 in
the figure column and also in words to conform to 3,384.64 which is noted in
the amount column, to wit as US Dollar equivalent of 148,077.97 Indian Rupee in
the first line. This appears to be the import of their letter of December 17, 1999.
Respondent
Nos.1 to 4 seek correction of the entries in the third line also which is the
first line against work item Impervious Core Embankment. It is plain that
against this Work Item the entries in the first line are quite different.
The
quantity column is blank, though 3900 should have been noted therein. In that
line also the entries in the first line are repeated. There the correction
sought is that the figure column should read as 84.21 both in figure and words.
It is
stated that in the second line the unit rate 1.92 both in figures and words,
represents U.S. Dollar equivalent of 84.21 Indian Rupee which is now sought to
be inserted. The errors in other 36 items are said to be similar. Had the
errors been confined to these aspects, it would not have resulted in material
change in the unit rate because the unit rate in one of the permissible
currencies is correctly given and there will be no discrepancy as envisaged in
sub-clause (b) of Clause 29.1. It would not really be a case of incorporating a
new unit rate but a case of either recording U.S. Dollar equivalent of the unit
rate already noted in Indian Rupee or vice versa as given in statement B above.
In such a case, perhaps, they would have been entitled to equitable relief of
rectification of mistake.
But
here, as would be shown presently, the position is different. With regards to
the mistakes in the bid documents, for the first time respondent Nos.1 to 4
informed the appellant in their letter of October 25, 1999 which runs as follows :
Re : Purulia
Pumped Storage Project Lot 4 - Main Civil Works - Resubmittal Price Bid. Dear Sirs, We regret that certain
repetitive systematic computer typographical data transmission failure have
occurred in items as per attached annexure in our bid submitted to you on
08.09.99.
In
order to dispel any doubts, we hereby unconditionally declare that we stand by
the amounts (both INRs and US $) against the affected schedules A to I,
announced at the opening of the revised price bid on the 8th of September at
WBSEB and reiterate that there is no change in the price or substance of our
bid. Our unit bid prices should be computed accordingly for the aforesaid
items. This letter is strictly without prejudice to our rights and contentions.
It may be noticed that in this letter they informed that certain mistakes had
crept in the items mentioned in the annexure to the letter and declared that no
change in the price or substance of the bid was asked for and that they stood
by the amounts announced at the time of the bids on September 8, 1999. However,
the actual mistakes are not pointed out. In their letter of December 17, 1999
they attempted to clarify the position. The relevant excerpt of that letter may
be quoted here: West Bengal State Electricity Board Office of the Project
Manager, Mr. S.K. Roy Choudhury, The Project Manager, Purulia Pumped Storage
Project, Vidyut Bhawan, 5th Floor, Salt Lake City, Calcutta - 700 091, India,
Fax No.0091 33 3591854 / 3581533 1999-12-17 Purulia Pumped Storage Project Dear
Sir, We refer to our telefax dated 25th October 1999. A copy thereof is again
enclosed for your convenience.
We
request that the systematic computer typographical transmission failure pointed
out in the said telefax is merely clerical in nature and not arithmetical and
do not in any way affect the validity of our bid. Its nature is fully explained
below.
I. The
computer has unfortunately systematically copied, in the first page (Serial
items 2 & 3) of the BOQ (Schedule A to I), the INR unit rates stated in
line 1 Serial Item 2 to the next two succeeding lines i.e. the computer has
overwritten the unit rates in US$ terms for the serial item no.2 and the INR
unit rates for the immediately succeeding serial item.
However,
the figures appearing the amount column of the BOQ for the said lines/items in
which the above mentioned errors have occurred are the correct tendered figures
both in US$ terms as well as INR terms.
II.
Further the BOQ quantities stated in the quantity column of serial item no.3 on
each and every page has been erased.
Enclosed
is an attachment which would show the applicable unit rates (in the lower half)
and the unit rates which were overwritten due to computer failure (in the upper
half).
It is
an admitted position that at the time of opening of the tender on 8th September
1999, our bid was the lowest at Rs.647.90 crores. The bid of Skanska was
Rs.691.22 crores and that of Taisei was Rs.726.50. We confirm that we have all
along maintained and still maintain the said bid price of Rs.647.90 crores.
However,
we have reasons to believe that you have chosen to ignore our said letter and
have proceeded to evaluate our price bid by an illogical and mis-application of
the rules for the evaluation of the bids set down in the ITB.
We,
therefore, once again call upon you to evaluate our bid after taking into
consideration the applicable unit rates. As already mentioned in our earlier
fax there is no change in the price or substance of our bid as mentioned in the
amount column of the BOQ. (Emphasis supplied) Here, though the nature of
mistakes are pointed out yet the scope of the correction sought is not indicated.
The
appellant could not have ignored these letters. Had the appellant taken note of
these letters and the mistakes occurring due to repetition of entries in 37
items in the bid documents, it would not have proceeded with correction of such
mistakes and evaluation of their bid without first seeking clarification from
respondents 1 to 4 under Clause 27.1. We have already referred to the gist of
that clause.
The
only prohibition contained therein is that no change in the price or substance
of the bid after its opening can be sought, offered or permitted. In that
regard they had made their position clear. The prohibition is, therefore, not
attracted. In these circumstances any reasonable person in the position of the
appellant would have sought clarification from respondent Nos.1 to 4 under
Clause 27.1.
Even
assuming that after the letter of December 17, 1999, no further clarification
was required to be sought by the appellant, we cannot but hold that correction
of the errors taking note of the unit rates which are mere repetition of the
unit rates quoted for a different work item is mechanical and without
application of mind by the appellant.
In our
view such a correction is far beyond the scope of Clause 29. From the
description of the mistakes, noted above, and the correction and evaluation
made by the appellant, it is evident that except the error in the first line
against the work item Rock Excavation and Schedule N day work, all other
mistakes/errors are beyond the scope of Clause 29.1, so Clause 29.2 will not be
attracted. It follows that the corrections in the bid documents of respondent
Nos.1 to 4 carried out by the appellant, evaluation of bid under Clause 29.2
and the impugned communication of the appellant dated December 18, 1999 are
unsustainable and of no consequence. Now, reverting to the relief of correction
of errors, Mr. Chidambaram has argued that in the two lines against each of the
Work Items, the first line denotes 50 per cent of the quoted unit rate in
Indian Rupee and the second line represents the other 50 per cent of the unit
rate in U.S. Dollar. According to him the actual rate quoted for quantity 1000
is the sum total of two lines i.e. 148.08 in Indian Rupee plus 3.38 in U.S. Dollar.
This is not noted either in statement A or in statement B. Be that as it may, quoting
the unit rate 50 per cent in Indian Rupee and 50 per cent in U.S. Dollar is not
provided in the ITB. Nothing is brought to our notice to justify splitting of
unit rate in that ratio. There is no indication of this fact in the price bid
documents submitted by the said respondents to explain that the unit rate has
been so quoted. This is also not in conformity with Clause 15 of ITB which, as
noted above, requires a bidder to quote unit rates and prices in Indian Rupee and
either in U.S.Dollar or Japanese Yen. The learned Additional Solicitor General,
in our view, is right in his submission that till the representation was made
by the said respondents on December 23, 1999, after the interim direction of
the High Court, the appellant was unaware of the quoted unit rate being in such
proportion. A combined reading of ITB and the annexure, extracted above, makes
it clear that the second line against each work item is meant for writing U.S.
Dollar or Japanese Yen equivalent of the unit rate and line total in the amount
column entered in the first line and not for writing bifurcated unit price in
different currencies in the ratio of 50 : 50. On these facts, the errors cannot
be termed as mere clerical or mechanical. Permitting correction of such errors,
if they can be so called, would result in not only re-writing unit rates in 37
entries in which such errors are said to have been committed but also appending
an explanation thereto regarding splitting of unit rates in terms of representation
dated 23.12.1999 of respondent Nos.1 to 4. Neither Clauses 27 and 29 nor any
other clause in the ITB permits such corrections. The mistakes/errors in
question, it is stated, are unintentional and occurred due to the fault of
computer termed as a repetitive systematic computer typographical transmission
failure. It is difficult to accept this contention. A mistake may be unilateral
or mutual but it is always unintentional. If it is intentional it ceases to be
a mistake. Here the mistakes may be unintentional but it was not beyond the
control of respondent Nos.1 to 4 to correct the same before submission of the
bid. Had they been vigil in checking the bid documents before their submission,
the mistakes would have been avoided. Further, correction of such mistakes
after one and a half month of opening of the bids will also be violative of
Clauses 24.1, 24.3 and 29.1 of ITB. The controversy in this case has arisen at
the threshold. It cannot be disputed that this is an international competitive
bidding which postulates keen competition and high efficiency. The bidders have
or should have assistance of technical experts. The degree of care required in
such a bidding is greater than in ordinary local bids for small works. It is
essential to maintain the sanctity and integrity of process of tender/bid and
also award of a contract. The appellant, respondent Nos.1 to 4 and respondent
Nos.10 & 11 are all bound by the ITB which should be complied with
scrupulously. In a work of this nature and magnitude where bidders who fulfil
pre- qualification alone are invited to bid, adherence to the instructions
cannot be given a go-bye by branding it as a pedantic approach otherwise it
will encourage and provide scope for discrimination, arbitrarinessand favouritism
which are totally opposed to the Rule of law and our Constitutional values. The
very purpose of issuing Rules/instructions is to ensure their enforcement lest
the Rule of law should be a casuality. Relaxation or waiver of a rule or
condition, unless so provided under ITB, by the State or its agencies (the
appellant) in favour of one bidder would create justifiable doubts in the minds
of other bidders, would impair the rule of transparency and fairness and
provide room for manipulation to suit the whims of the State agencies in
picking and choosing a bidder for awarding contracts as in the case of
distributing bounty or charity.
In our
view such approach should always be avoided. Where power to relax or waive a
rule or a condition exists under the Rules, it has to be done strictly in
compliance with the Rules. We have, therefore, no hesitation in concluding that
adherence to ITB or Rules is the best principle to be followed, which is also
in the best public interest. For all these reason, in such a highly competitive
bid of global tender, the appellant was justified in not permitting respondent
Nos. 1 to 4 to correct the errors of the nature and the magnitude which, if
permitted, will give a different complexion to the bid. The High Court erred in
directing the appellant to permit respondent Nos.1 to 4 to correct the errors
in the bid documents. Mr.Chidambram, however, submitted that in equity
respondent Nos.1 to 4 would be entitled to relief of correction of mistakes. He
invited our attention to para 84 of the American Jurisprudence (Second Edition,
Volume 64, Page No.944). It will be useful to quote the relevant part of that para
here: As a general rule, equitable relief will be granted to a bidder for a
public contract where he has made a material mistake of fact in the bid which
he submitted, and where, upon the discovery of that mistake, he acts promptly
in informing the public authorities and requesting withdrawal of his bid or
opportunity to rectify his mistake particularly where he does so before any
formal contract is entered into. The principle is based on the judgment of the
Supreme Court of 373; 44 L Ed 1108, 20 S Ct 957. There the plaintiff gave
proposals by way of bid for two works of excavation of earth, quoting the unit
rate 1.5 Dollar instead of 15 Dollars and 50 cents instead of 70 cents per
cubic yard.
The
City of Rochester which called for tenders, was promptly informed of the
mistake by the plaintiffs agent as soon as it was discovered but before
entering into contract.
However,
the proposal of the plaintiff was accepted by the City of Rochester in regard
to one work and the other work was allotted to another bidder. The plaintiff
declined to enter into a contract with the City of Rochester which took steps
to enforce execution of the contract. The plaintiff filed the suit for
correction of proposals to conform to the asserted intention in making them and
for execution of the contract on corrected rates or alternatively for the recission
of the proposals. It also sought injunction against the officers of the City of
Rochester declaring it to be defaulter, its bond forfeited or enforced. It was
found that the price noted was grossly inadequate and far below what would be
the actual cost of the work under the most favourable circumstances. The trial
court decreed the suit holding that the proposals of the bidder be rescinded,
cancelled and declared null, void, and of no effect and granting the injunction
prayed for. But on appeal the decree was reversed by the circuit court of
appeals. On further appeal to the Supreme Court of U.S.A., it was observed that
both the courts below found that there was a mistake and while the trial court
opined it was clear, explicit and undisputed, the court of appeal was of the
view that it was not a mistake in any legal sense but was a negligent omission
arising from an inadequate calculation of the cost of the work and held that
the mistake was not sufficient to preclude a claim for relief if the mistake
justified it. The Supreme Court relied on the following observation in an
earlier judgment of that Court in Hearne side may be a ground for rescinding,
but not for reforming, a contract. Where the minds of the parties have not met
there is no contract, and hence none to be rectified. And it was concluded that
the last two propositions might be claimed to be pertinent to that case even
though the transactions between the parties be considered as a completed
contract and held that the action of the City of Rochester in awarding one
contract to another bidder and forcing the plaintiff to enter into the second
contract after it had declared there was a mistake in its proposal was
inequitable. Exceptions to the above general principle of seeking relief in
equity on the ground of mistake, as can be culled out from the same para, are :
(1)
where the mistake might have been avoided by the exercise of ordinary care and
diligence on the part of the bidder; but where the offeree of the bid has or is
deemed to have knowledge of the mistake, he cannot be permitted to take
advantage of such a mistake.
(2) where
the bidder on discovery of the mistake fails to act promptly in informing to
the concerned authority and request for rectification, withdrawal or
cancellation of bid on the ground of clerical mistake is not made before
opening of all the bids,
(3) where
the bidder fails to follow the rules and regulations set forth in the
advertisement for bids as to the time when bidders may withdraw their offer;
however where the mistake is discovered after opening of bids, the bidder may
be permitted to withdraw the bid. In the instant case, we have also noted that
the mistakes in the bid documents of respondent Nos.1 to 4 even though caused
on account of faulty functioning of computer, could have been discovered and
notified by the said respondents with exercise of ordinary care and diligence.
Here,
the mistakes remained in the documents due to gross negligence in not checking
the same before the submission of bid. Further Clauses 24 and 27 of ITB permit
modification or withdrawal of bids after bid submission but before the dead
line for submissions of the bids and not thereafter. And equity follows the
law. Having submitted the bid they did not promptly act in discovering the
errors and informing the same to the appellant. Though letters were written on
October 25, 1999, and December 17, 1999, yet the real nature of errors/mistakes
and corrections sought were not pointed out till December 23, 1999 when
representation was made after interim direction of the High Court was given on
December 21, 1999. Indeed it appears to us that they improved their claim in
the representation. In our view the said respondents are not entitled to
rectification of mistakes/error for being considered along with the other
bidders. Mr. Chidambaram relied upon a decision of the Superior Court of New
Jersey in Spina Asphalt Paving N.J. Super 425] to justify the claim for
rectification of mistakes. In that case, the Borough of Fairview invited
tenders. Spina and one Tomaro participated in the bid. The bid was on a unit
price basis and the proposals were submitted on Forms supplied by the Borough.
The bid specifications provided, inter alia : in the event there is a
discrepancy between the unit price and the extended total, the unit price shall
prevail. The Borough reserved the right to waive any informality if deemed in
the best interests of the owner. On the evening when the bids were opened, Spina
discovered that its secretary had erroneously indicated the unit price for one
of the items as 400 dollars per square yard though it should have been 4
dollars per square yard as reflected in the total bid for that work.
Spina
faxed the Borough indicating that the intended unit price was 4 dollars per
square yard. On the basis of 400 dollars per square yard Spinas bid was
calculated which obviously worked out far higher than the intended bid amount.
Taking note of that amount the Borough awarded the contract to Tomaro. Spina
instituted action claiming that the Borough arbitrarily failed to recognise
that its bid was lower than that of Tomaro. The Law Division held that the
error in the bid was non-material and subject to waiver.
The
Superior Court while agreeing with the Law Division observed that they did not
hold that generally an error in the statement of a price could be treated as immaterial
and it was only when as in that case the error was patent and the true intent
of the bidder obvious that such an error might be disregarded. The Superior
Court held that when as in that case the failure to waive the deviation would
thwart the aims of the public bidding laws, the municipality was obliged to
grant the waiver. (Emphasis supplied) Though Clause 29 in this case appears to
be similarly worded as in the bid documents in Spinas case (supra), a close
reading of these clauses shows that no power of waiver is reserved in the case
on hand. That apart, the nature of the error in these two cases is entirely
different. There, the error was apparent $ 400 for $ 4, non-material and waiveable
by the Corporation; in the present case the errors pointed out above are not
simply arithmetic and clerical mistake but a deliberate mode of splitting the
bid which would amount to re-writing the entries in the bid document and cannot
be treated as non-material. Therefore, the judgment in Spinas case (supra) does
not help respondent Nos.1 to 4. The submission that remains to be considered is
that as the price bid of respondent Nos.1 to 4 is lesser by 40 crores and 80 crores
than that of respondent Nos.11 and 10 respectively, public interest demands
that the bid of respondent Nos.1 to 4 should be considered. The project
undertaken by the appellant is undoubtedly for the benefit of public. The mode
of execution of the work of the project should also ensure that the public
interest is best served.
Tenders
are invited on the basis of competitive bidding for execution of the work of
the project as it serves dual purposes. On the one hand it offers a fair
opportunity to all those who are interested in competing for the contract
relating to execution of the work and on the other hand it affords the
appellant a choice to select the best of the competitors on competitive price
without prejudice to the quality of the work. Above all it eliminates favouritism
and discrimination in awarding public works to contractors.
The
contract is, therefore, awarded normally to the lowest tenderer which is in
public interest. The principle of awarding contract to the lowest tenderer
applies when all things are equal. It is equally in public interest to adhere
to the rules and conditions subject to which bids are invited. Merely because a
bid is the lowest the requirements of compliance of rules and conditions cannot
be ignored. It is obvious that the bid of respondent Nos.1 to 4 is the lowest
of bids offered. As the bid documents of respondent Nos.1 to 4 stands without
correction there will be inherent inconsistency between the particulars given
in the annexure and the total bid amount, it cannot be directed to be
considered along with other bid on the sole ground of being the lowest. We find
no force in the submission that as under Clause 14.2 items against which no
rate or price is entered by the bidder will not be paid by the employer when
executed and shall be deemed covered by the other rates and prices in the bill
of quantities, the unit price in items containing errors be ignored and the bid
be considered on the basis of total price bid which is the lowest. In our view,
there is a basic distinction between a case where against some items no rates
or prices are quoted and a case where some rate is quoted. Whereas in the
former case the bidder will not be entitled to claim any specific amount for
the work done by him in the absence of any rate for that work, because in the
aforementioned clause it is clarified that the bidders will not be paid by the
employer and that the execution of the work shall be deemed covered by other
rates and prices in the bill of quantities but in the latter case the bidder
will be entitled to claim for the work executed on the basis of quoted
price/rate. We may, however, clarify that the appellant is not obliged to award
contract to any of the bidders at their quoted price bid.
It is
always open to the appellant to negotiate with the next lowest bidder for
awarding the contract on economically viable price bid. For the reasons
abovementioned, though the impugned order of the High Court insofar as it
relates to quashing of letter of the appellant dated December 18, 1999, falls
within the purview of judicial review, yet the direction to the appellant to
permit correction of errors by respondents 1 to 4 in their bid documents and
consider their bid along with other bid, goes far beyond the scope of judicial
review, as elucidated by this Court in Tata Cellular (supra). In the result, we
uphold the impugned order of the Division Bench insofar as it relates to
quashing of communication and letter dated December 18, 1999 and set aside that
part of the impugned order giving direction to the appellant to permit
respondent Nos.1 to 4 to correct bid documents and to consider their bid after
correction along with other bids. The appeal is thus allowed in part. On the
facts and in the circumstances of this case we leave the parties to bear their
own costs.
Back