Bharat
Coking Coal Ltd. Vs. M/S L.K.Ahuja & Company [2001] Insc 98 (21 February 2001)
S. Rajendra
Babu & S.N. Phukan. Rajendra Babu, J. :
L.T.J
Two
works were assigned by the appellant for construction of 108 and 72 units of B
Type quarters at Karmik Nagar, Dhanbad pursuant to a tender notice dated
4/13.7.1981. After certain negotiations between the parties, two work orders
were issued by the appellant to the respondent on certain terms and conditions
mentioned therein valuing at Rs.86,49,730/- and Rs.57,64,368/- for the said two
works on 14.3.1982 and two separate agreements were executed by the parties.
The schedule dates for completion of the respective works were fixed as
24.3.1983 and 19.3.1983. The respondent sought for extension of time which was
granted by the appellant. Disputes having arisen between the parties, the
matter was referred to the sole arbitrator, Shri M.P.Sharma, the then
Additional Chief Engineer. The arbitrator made two awards in respect of the two
contracts on 14.5.1989, which were filed in the court of the Civil Judge on
12.6.1990 in two Title [Arbitration] Suits Nos. 37/86 and 40/86. The learned
Civil Judge held that the notice for Title [Arbitration] Suit No.37/86 had been
served upon the appellant on 28.8.1990 and the objections filed on 14.9.1990
could be examined as they had been filed in time. So far as Title [Arbitration]
Suit No.40/86 is concerned it appears that the service of notice on the
respondent was made on 13.7.1990 of the filing of the award and the objections
in question were filed on 18.8.1990 and thus apparently there being a delay of
five days in filing the objections beyond the period of limitation prescribed
under Article 119 of the Schedule to the Limitation Act, 1963 were not
considered. On decrees being passed in terms of awards appeals filed in the
High Court having met with failure, these appeals have been preferred by
special leave.
The
parties filed elaborate pleadings before the arbitrator in respect of both the
agreements. The claim made in the first agreement is as follows:
1.
Claim for payment of the final bill amount Rs.3,10,000.00
2.
Claim for payment of PLO escalation Rs. 20,000.00
3.
Claim for compensation for making late Rs.8,00,000.00 payment of running
account bill
4.
Claim for payment for labour escalation Rs.4,12,000.00
5.
Claim for refund of sales tax Rs. 60,000.00
6.Claim
for payment of extra items Rs.10,31,350.00
7.
Claim for payment of material escalation Rs.40,00,000.00
8. Keep
Back Amount Rs. 8,000.00
9.
Claim for payment of compensation to loss Rs.10,00,000.00 arising out of
turnover due to prolongation of work
10.
Claim for payment on account of loss of Rs.2,00,000.00 reputation
etc.Rs.78,41,350.00
11.With
interest @ 18% per annum from Rs.20,000.00 31.5.84 till date of actual
payment of awarded J amount or court decree whichever is earlier.
12.
Arbitration Cost Rs.20,000.00 Claim made in the dispute arising out of second
agreement is as follows :
1.
Claim for payment of the final bill amount Rs.2,00,000.00
2.
Claim for payment of PLO escalation Rs. 15,000.00
3.
Claim for compensation for making late Rs.5,00,000.00 payment of running account
bill
4.
Claim for payment for labour escalation Rs.3,00,000.00
5. Claim
for refund of sales tax Rs. 40,000.00
6.
Claim for payment of extra items Rs. 6,54,000.00
7.
Payment of material escalation Rs.25,00,000.00
8.
Keep Back Amount Rs. 28,000.00
9.
Claim for payment of compensation to loss Rs. 7,00,000.00 arising out of
turnover due to prolongation of work
10.
Claim for payment on account of loss of Rs. 2,00,000.00 reputation etc. Rs.51,27,000.00
11.
With interest @ 18 % per annum from@ 30.4.84 till date of actual payment of
awarded amount or court decree whichever is earlier.
12.
Arbitration Cost Rs.20,000.00 He passed two separate awards.
In
addition to these pleadings, it appears that the arbitrator asked both the
parties to file certain joint statements and in this regard stated as follows:
.Before
going into the merits of the case the parties were advised to file joint
statement signed by them, showing the quantities, rates and the payments made
for various items and balance payment due to the claimant under various heads
and other particulars on 26.4.89. The parties submitted the joint statements
duly signed by them containing details of bricks and cement supply statements,
bill statements with details of delay in payment of R/A bills alongwith
relevant dates of measurements and other particulars, including payable amounts
under various heads and measurements for extra items, rolling margin etc.
The
arbitrator noticed in the course of his award that the joint statements signed
by both the parties is the backbone of the award. The arbitrator rather
strangely made the two awards after making elaborate reference to the pleadings
on either side but not deciding any one of the claims except the claim relating
to payment of material escalation in the two claims. On that aspect of the
matter, the arbitrator, after adverting to the pleadings, stated as follows:
Since
the prices of building materials and labour cost sky rocketting and the value
of rupee going down, the refusal to compensate increase in material cost on
some ground or the other would lead to total financial disaster to the
claimant. The payment of advances like mobilisation has been made against
rebate of 1½% claimed by the O.P. and was meant for mobilising resources before
commencing work.
On the
other hand very partly sum is payable against secured advance without hardly
giving any financial assistance. The planning of procurement of material is
linked with progress at site. Whereas during contract period the work hardly
progressed 50% and the payment for work done was restricted to 16% how could
the planned procurement availing secured advance could be made in such
solution. The payment of material escalation for the increase in cost during
the extended period of the contract would give some relief to disaster already
caused financially to the claimant.
On
examination of the contract provision I find that the claimant had undertaken
to complete the work at agreed rates within the stipulated period with the
provision for extension of time to execute at the agreed rates till completion.
This contention shall hold good provided the extended period is within a
reasonable limit. In this case the original stipulated period is 12 months and
actual completion is 26 months having extension element of 14 months which
cannot be termed reasonable by any yardstick.
The
grant of extension of time is a poor consolation. It is not remedy for losses
suffered on account of delay in supply of building materials committed to be
supplied by the O.P.
But
after setting out the other claims of the respondent and the rebuttals to them
by the appellant, the arbitrator concluded as follows:
NOW,
THEREFORE, I, the said M.P.Sharma, Sole Arbitrator after hearing the parties at
length examining and carefully considering the evidence adduced the arguments
advanced by them, the discussions made above, scrutinising the joint statement
signed by the parties and written arguments filed by O.P. DO HEREBY MAKE AND
PUBLISH MY AWARD AS FOLLOWS:
1. The
Opposite Party M/s Bharat Coking Coal Ltd., Dhanbad, shall pay the claimant
i.e. L.K.Ahuja & Co. a lump sum amount of Rs.24,27,686.12 (Rupees Twenty
four lacs twenty seven thousand six hundred eighty six and paise twelve only).
I am
dividing the period in three years for calculation and payments of interest.
a).
The aforesaid amount will carry interest @ 15% per annum for the following
periods:
I.
From 1.1.85 to 3.10.88 when the claimant submitted the claim.
II.
From 4.10.88 to 14.5.90 when the award is published.
III.
From 14.5.90 till the date of payment or court decrees whichever is earlier.
2. A
sum of Rs.15,000/- (Rupees fifteen thousand) only towards the cost of
arbitration proceedings along with the interest @ 15% p.a. w.e.f. 14.6.90 till
its date of payment or the date of court decree whichever is earlier.
It may
be made clear that the power to order award of interest on all above amounts
vests in the Honble Court from the date of decree till the decretal amount is
paid to the claimant as provided under S.29 of the Arbitration Act which
empowers the Honble Court deems reasonable from the date of decree till payment
of decretal amount to the claimant.
He
similarly awarded in respect of second agreement a lump sum of Rs. 16,74,197.29
with interest at certain rates and costs of the arbitration.
We
cannot but describe the arbitrators awards as hybrid which are neither speaking
awards nor non-speaking - partly speaking and partly non-speaking awards. The
law is well settled that if the award made by the arbitrator is a non-speaking
one the difficulty of showing that there is an error apparent on the face of the
award becomes insurmountable and ordinarily such award cannot be challenged at
all unless it is shown that the arbitrator has wholly travelled outside the
contract which gives him the jurisdiction. The law is equally well settled that
in cases of speaking awards the court can interfere if there is an error
apparent on the face of the award itself; it could also be shown that the
arbitrator has misconducted himself in arriving at certain conclusions which
are either plainly contrary to law or to the terms of the contract or ignored
the provisions of contract or the evidence on record and such other similar
matters. When a lumpsum award is made, it is all the more difficult to find out
as to what went into the mental process of the arbitrator in fixing the same
particularly when a part of the award is a speaking award and determines the
portion of the claim in a particular manner and in respect of other claims
merely refers to the pleadings but not decided the matter but gives the award.
The
position of the appellant before the court is unenviable and bristles with too
many complexities to get over the awards.
Realising
these difficulties, Shri M.L.Verma, learned senior Advocate and Shri Ajit Kumar
Sinha, learned Advocate for the appellant, very cautiously treaded their path
to put forth before us the difficulties in upholding the award.
Shri S.B.Upadhyay,
learned counsel for the respondent, with equal astuteness and competence
contended as to the manner in which the award made by the arbitrator could be
maintained though it is bristles with many difficulties.
We
have adverted in detail to the consideration of the claim on payment of
material escalation earlier. The terms of the contract in this regard indicate
as follows:
Clause
17: The contractor shall supply at his own cost all materials (except such
special materials, if any, as may be in accordance with the contract be
supplied from the Engineer-in-Chiefs stores), plants, tools, appliances,
implements, ladders, cordage, tackle, scaffolding, and tempers, works requisite
or proper for the proper execution of the work whether original, altered or
substituted and whether included in the specification or other documents
forming part of the contract or referred to in these conditions or not or which
may be necessary for the purpose of satisfying or complying with the
requirements of the Engineer-in- Chief as to any matter as to which under these
conditions he is entitled to be satisfied, which he is entitled to require
together with carriage therefore, to and from the work. The contractor shall
also supply without charge the requisite number of persons with the means and
materials necessary for the purpose of setting out works, and counting weighing
and assisting in the measurement or examination at any time and from time to
time of the work or materials. Failing his so doing, the same may be provided
by the Engineer-in-Chief at the expense of the contractor and the expenses may
be deducted from any money due to the contractor under the contract from his
security deposit or the proceeds of sale thereof, or of a sufficient portion
thereof. The contractor shall also provide all necessary fencing and lights
required to protect the public from accident, and shall be bound to bear the
expenses of defence of every suit, action or other proceeding at law that may
be brought by any person for injury sustained owing to neglect of the above
precautions, and to pay any damages and costs which may be awarded in any such
suit, action or proceeding to any such person or which may with the consent of
the contractor be paid to compromise any claim by any such person.
It is
not clear from the pleadings whether the claim made by the respondent is in
respect of escalation in the costs of material such as plant, tools,
appliances, implements, ladders, cordage, tackle, scaffolding, and tempers,
works, etc. inasmuch as the appellant has the obligation to supply the most
essential building materials such as cement, steel and such other building
material. It is also not clear either from the pleadings or from the award as
to whether the escalation claim is in respect of the materials provided by the
respondent or in respect of escalation arising from delay in non-supply of
materials which was due to be supplied by the appellant. So far as the plant
and other equipments are concerned, they had already been provided for the
purpose of the execution of the work and how the delay in non-supply of
building materials such as cement, steel, etc. caused escalation so far as the
building materials provided by the appellant is concerned is not clear. The
arbitrator has not applied his mind to this aspect of the matter at all. Having
lost sight of the importance of clause 17 and application of the same to the
circumstances of the case will clearly disclose that there is an error apparent
on the face of the award. The claim under this head is Rs.40 lacs with
reference to the first agreement and Rs. 25 lacs with reference to the second
agreement which is the major chunk being nearly half the claim made by the respondent.
In what manner this aspect has gone into in fixing the lumpsum by the
arbitrator is not discernible. Therefore, we have no option but to set aside
the entire award in respect of both the agreements made by the arbitrator and
remit the matter. We propose that a new arbitrator be appointed in place of the
old arbitrator because the arbitrator has dealt with the matter himself as an
officer who had correspondence with the contractor at the time when he was an
officer of the appellant. Therefore, it is fair neither to the appellant nor to
the respondent to continue him as an arbitrator in the proceedings.
In so
far as the other appeal is concerned, certain additional contentions have been
addressed by the respondent and they are based on Article 119 of the Schedule
to the Limitation Act which provides that an application for setting aside an
award or getting an award remitted for reconsideration, the period of
limitation is fixed as 30 days from the date of the service of the notice of
the making of the award. As stated earlier, the award had been filed in the
court and the notice of which had been served upon the appellant in Title
[Arbitration] Suit No.40/86 and the objection had been filed. Service of notice
has been made on the appellant on 13.7.1990 and the objection in question had
been filed on 18.8.1990, while it should have been filed on or before 12th August, 1990. The learned counsel for the
respondent in this regard relied on the following observations made by this
Court in Madan Lal vs. Sunderlal & Anr., 1967 (3) SCR 147:
It may
be conceded that there is no special form prescribed for making such an
application and in an appropriate case an objection of the type made in this
case may be treated as such an application, if it is filed within the period of
limitation. But if an objection like this has been filed after the period of
limitation it cannot be treated as an application to set aside the award, for
if it is so treated it will be barred by limitation. [p.151] It is obvious from
these observations that even an objection setting out the grounds specified in
Section 30 of the Arbitration Act would amount to an application as
contemplated under Article 119 of the Schedule to the Limitation Act and,
therefore, such objection will have to be filed within the period of
limitation. Courts have taken the view that inasmuch as agreement of reference
to arbitration is an instrument of solemn character, which is binding on the
parties, and so is the award; if, therefore, a party desires to avoid the effect
either of the agreement or the award, he must strictly comply with the
provisions of the law and an objection to the award must be filed within the
time which cannot be extended. In certain circumstances, courts have taken the
view that by granting time to file objection the Court had impliedly extended
the time even without a formal application under Section 5 of the Limitation
Act. An application for condonation of delay is permissible to file objections
under Section 30 of the Arbitration Act by resorting to Section 5 of the
Limitation Act. Section 5 of the Limitation Act, 1963 provides that any
application, other than those contemplated under Order XXI CPC could be
admitted after the prescribed period if the applicant satisfies the court that
he had sufficient cause for not preferring the appeal or making the application
within such period. It is clear that Section 5 of the Limitation Act is
applicable to all applications other than those under Order XXI C.P.C. Hence
scheme of an enactment cannot be availed of to defeat such a right conferred
under the statute of limitation in clear terms. In the instant case, it is set
out in the course of the order made by the Civil Judge that the award was filed
in the sealed cover and presented to the court and unless the same was made
available to the parties, they could not file the objections. The object of
filing the objections is to question the validity of the award on the grounds
mentioned in Section 30 of the Arbitration Act. If such a course is not possible
for want of copy in respect of award, certainly the circumstances, as arising
in the present case, should be taken note of. The objections filed on 18.8.1990
are in the nature of an application under Section 30 of the Arbitration Act to
set aside the award and is an application under Article 119 of the Schedule to
the Limitation Act.
Therefore,
Section 5 necessarily would get attracted to such a situation. In this case,
the notice of filing of award was served upon the appellant on 13.7.1990 and
the appellant filed objections on 18.8.1990 and those objections have been shut
out from the consideration on the ground that the same have been filed beyond
the period of limitation prescribed under the relevant provisions of the
Limitation Act. On the totality of the circumstances, we are satisfied that
there was a sufficient cause for delay in making the application and the time
should be extended till 18.8.1990 when the application was made. We condone the
delay in f iling such objections upto that date. case in neither There is a
clear lapse on the part of the Advocate appearing in the making a proper
application for enlargement of time in the civil court nor pursuing this aspect
of the matter in the High Court. In this Court too even, at the time of
arguments, no application was forthcoming. However, to meet the ends of
justice, we have adopted this course, but this indulgence shown by this Court
cannot be taken advantage of by the appellant without paying appropriate costs
to the respondent which we quantify to be a sum of Rs.40,000/- which shall be
paid before the new arbitrator commences the arbitration proceedings. This cost
shall not be the costs in the cause and are payable by way of penalty.
So far
as the main matter is concerned, there is no difference between the award
passed in Title [Arbitration] Suit No.37/86 and the proceedings in Title
[Arbitration] Suit No.40/86 and the same also deserves to be set aside for the
very reasons stated earlier and shall be governed by the same terms as to
remittal of the award for fresh consideration by a new arbitrator.
As
suggested by the learned counsel on both sides, we name Shri Justice Uday Sinha,
former Judge, High Court of Patna, as the new arbitrator who is at liberty to
fix his terms as he deems fit and proper to adjudicate the matter in dispute.
The new arbitrator shall consider the pleadings and evidence on record already
placed by the parties and shall not permit either of the party to raise further
or fresh pleas or evidence. It would be appropriate for the arbitrator to make
an award within a period of four months from the date of the receipt of this
judgment and submit the same to this Court after publishing the same to the
parties.
The
Registry of this Court is directed to transmit a copy of this judgment to Shri
Justice Uday Sinha, former Judge, High Court of Patna, 308, Patliputra Colony,
Patna-13 forthwith. The parties are directed to appear before Shri Justice Uday
Sinha for further directions, as may be deemed fit by him, within one week from
the date of this judgment.
In the
result, the appeals are disposed of accordingly.
In the
circumstances of this case, the appellant is directed to pay a sum of Rs.40,000/-
[Rupees forty thousand only] to the respondent as costs.
Back