M/S Konkan
Railway Corpn. Ltd. & ANR Vs. M/S Rani Construction Pvt. Ltd. [2000] INSC
512 (14 October 2000)
Appeal (civil) 713-714 of 1999 Appeal (civil) 715 of 1999
Appeal (civil) 716 of 1999 Appeal (civil) 2037-2040 of 1999 Appeal (civil) 2041
of 1999 Appeal (civil) 2042-2044 of 1999 Appeal (civil) 4311 of 1999 Appeal
(civil) 4312 of 1999 Appeal (civil) 4324 of 1999 Appeal (civil) 4356 of 1999
Appeal (civil) 7304 of 1999 Appeal (civil) 73066-09 of 1999
K.G.Balakrishnaan,
M.J.Rao
D E R
L.I.T.J M.JAGANNADHA RAO,J.
Learned
Solicitor General of India Sri Harish Salve, appearing for the appellants, has
submitted that the order dated 4.7.97 of the learned Chief Justice of the
Bombay High Court, under section 11 of the Arbitration and Conciliation Act,
1996 on the preliminary issues is a Judicial order and, on facts, is liable to
be set aside under Article 136 of the Constitution of India. It is contended
that, even if it is to be treated as administrative in nature, it is amenable
to Article 136.
The
learned Chief Justice in his order dated 4.7.97 held that inasmuch as the
appellant-company failed to appoint Arbitrators as required under the
arbitration clause, the appellants should be compelled to furnish a panel of
names of arbitrators to the respondent-contractors and one name should be
suggested by the appellants. The learned Chief Justice had also rejected the
plea of the appellants that no reference be made as the matters were 'excepted
matters' and held that the question whether the claims related to 'excepted
matters' or not was also to be decided by the arbitrators after recording
evidence and verifying the facts. Learned Solicitor General contends that such
an order of the Chief Justice deciding rights preliminary points cannot be characterised
as an administrative order.
Appellant
is confronted with the three Judge Bench in Konkan Railway Corporation Ltd. vs.
M/s Mehul Construction Co. [2000 (6) SCALE 71] which has held that no appeal is
maintainable under Article 136 against such an order passed by the Chief
Justice directing appointment of arbitrators under section 11 inasmuch as such
orders are administrative in nature even if they contain reasons and decision
on certain preliminary issues raised by the parties at the stage of appointment
of arbitrator.
It is
pointed out by the learned Solicitor General of India that the above judgment
requires reconsideration. Counsel pointed out that initially in Sundaram
Finance Ltd. vs. NEPC India Ltd. [1999 (2) SCC 479] in a case which arose under
section 9 (and not under section 11), a passing observation was made by Kirpal,
J. (in para 12) that under section 11 the Chief Justice or his nominee would
not be passing a judicial order. That was by way of obiter. Later on, in Ador Samia
Private Ltd. vs. Peekay Holdings Limited & Others [1999 (8) SCC 572], a
Bench consisting of Majmudar and Mohapatra, JJ. held that against an order
under section 11 passed by the Chief Justice, no application for special leave
could be filed under Article 136 inasmuch as the order was an administrative
order and the Bench relied upon the observations of Kirpal, J. in Sundaram
Finance Ltd.. The Bench also referred to the judgment of the Constitution Bench
in Indo-China Steam Navigation Co. Ltd. vs. Jasjit Singh [AIR 1964 SC 1140 :
1964 (6) SCR 594 (at 603) which held that a purely administrative order or
executive order was not amenable to Article 136. However, it appears that a
Bench presided over by Majmudar, J. referred the question as to the nature of
the order to a three Judge Bench in Konkan Railway Co.
Limited.
The three Judge Bench took the view (see 2000 (6) SCALE 71) that no special
leave petition could be filed under Article 136 against the order passed by the
Chief Justice or his nominee under section 11.
According
to the learned Solicitor General, this view of the three Judge Bench requires
reconsideration.
Learned
Solicitor General submits that, it is now well-settled in several countries,
where the UNCITRAL model has been adopted and where the arbitrator also is
permitted to decide questions as to the existence of the arbitration clause or
validity of the agreement - that the Court can decide certain preliminary
disputes which are raised before it at or before the appointment of arbitrators
- such as disputes relating to existence of the arbitration agreement or a
question as to the very existence of a 'dispute' or as to whether the items of
disputes fell within 'excepted' matters or whether an arbitrator could be
appointed where the invocation of the clause by one party was beyond the
prescribed period in which one has to ask the otherside to appoint an
arbitrator, etc. It is true that under section 16(1) of the new Act, the
arbitrator is now empowered to decide his own jurisdiction including any
objection as to the existence or validity of the agreement and for that purpose
the arbitration clause is deemed to be independent of the main contract (called
Kompetenz- Kompetenz principle). Counsel contends that, it may be that in situations
where the matter has straightway gone before an arbitrator by act of parties
without intervention of Court, the arbitrator is now statutorily empowered to
decide these basic questions also. But when a case comes before judicial
authority and the defendant pleads that there is an arbitration clause (see
section 8 of the new Act) or where, on account of the non-appointment of an
arbitrator, the Court is approached for appointment of an arbitrator (see
section 11), - the Court can decide these preliminary issues judicially and
need not mechanically appoint an arbitrator under section 11 in such cases.
The
power of the Court has not been taken away by the new Act. It is contended,
that this is still the law in all countries where the UNCITRAL model has been
adopted.
In all
such cases, the order of the court or the Chief Justice (or his nominee) will
be a 'judicial' one and not an administrative order. It is pointed out that the
UNCITRAL Model Law, in fact, uses the words 'Court or other authority' in Article
6 and Article 11. See in this connection Article II(3) of the New York
Convention, Article 4(1) Geneva Protocol, Article 8 of the Model Law and
section 9 of the English Act of 1996.
We may
note that in para 5.49 (pp.273-274) of 'Law and Practice of International
Commercial Arbitration' by Alan Redfern and Martin Hunter (3rd Ed.) (1999), it
is stated, in relation to the procedure adopted now in various countries
following the UNCITRAL model as follows:
"The
third course of action is for the respondent to ignore the arbitral tribunal
and to go to Court to resolve the issue of jurisdiction. There are various ways
in which this may be done. The respondent may, for example, seek an injunction
or similar remedy to restrain the arbitral tribunal from proceeding. Or the
respondent may seek a declaration to the effect that the arbitral tribunal does
not have jurisdiction in respect of the particular claim or claims put forward
by the claimant-for instance, on the basis that there was no valid arbitration
agreement. Or, again by way of example, the respondent may take the offensive
and commence litigation in respect of the matters in dispute. The claimant in
the arbitration would presumably defend such a challenge to the jurisdiction of
the arbitral tribunal by seeking to have the arbitration agreement enforced.
This would be a straightforward matter of reliance upon Article II of the New
York Convention (such as section 9 of the English 1996 Act) or a similar
provision of the law governing arbitration at the seat of the arbitration (as
in Article 8 of the Model Law). The relevant national Court must decide whether
the arbitration agreement is null and void, inoperative or incapable of being
performed; if it is not, the parties will be referred to arbitration." (See
also para 5.51 which deals with a 'combined approach').
In
several countries, the negative effects of the 'Kompetenz-Kompetenz' principle,
conferring powers on the arbitrator, has been considered.
In
this connection, there is an exhaustive and detailed discussion of this aspect
in 'Fouchard, Gaillard Goldman on International Arbitration) (1999) (para 672
to 682) (pages 407-413), referring to the post-UNCITRAL case-law in France,
Austria, Sweden, Belgium, Netherlands, USA etc. to the effect that if the Court
is first seized of these preliminary issues before appointment of arbitrator, -
even in cases where the arbitrator, under the statute, is empowered to decide
these questions - the Court can and will decide these issues first rather than
permit the arbitrator to decide them. The experience of the various Courts in
these countries where the UNCITRAL model had been adopted long ago is a matter
for consideration in India, where we have recently adopted the
model.
In France, in Caprodag vs. Dame Bohin (1995
Rev.
Arb.
617) the Court of Appeal has held recently that the arbitrators can decide
these questions in cases where the Court is not seized with these questions
earlier.
This
is also so under the 1961 European Convention.
Where,
however, the matter straightway goes before the arbitrator by act of parties
and the arbitrators are first seized of these problems, they can decide but
their decisions will still be subject to the decision of the Court. Reference
is made by the authors (Fouchard etc.) to the US cases in Comptek Telecom Inc
vs. IVD Corp. (1995 US Dist. Lexis 11876) (W.D.N.Y Aug. 1, 1995) (10. Intnl Arb.
Rep. 1) SMG Swedish Machine Group vs.
Swedish
Machine Group Inc (1991 US Dist. Lexis 780) holding that if
the Court is seized of these issues first, it had better decide them. The
position is the same under Swedish Law in the 1999 Arbitration Act (Sec 2, para
1). The authors (Fouchard etc.) refer (p.409) to the Belgium Law (Art. 1679, para
1 of the Judicial Code), the 1986 Netherlands Arbitration Act (Act 1022 (1) of
the Code of Civil Procedure), the 1987 Swiss Private International Law Statute
(Art 7) - all stating that the arbitrators shall decide these issues except
where the Court is seized of these issues at an earlier stage. The Swiss case
law, the 1996 English Arbitration Act are also referred to. In para 676, the
Authors say "As a result, and although it was at one time relatively
isolated, the rule found in French law and in the 1961 European Convention has
recently gained substantial acceptance." In para 678, under the heading
'Policy Considerations', it is stated that if matter has not gone straight to
the arbitrators but has come initially before the Court, the Court can decide
these preliminary issues and this saves (i) time and (ii) costs of arbitration.
It is said:
"The
approach whereby the Courts seized of the merits of the case are entitled to
rule immediately on the existence and validity of the arbitration agreement
arguably leads to a certain degree of time and cost avoidance. It may prevent
parties having to wait several months, or in some cases, years, before knowing
the final outcome of the dispute regarding jurisdiction - it will often take
long for the arbitrators and then the Courts to reach their decisions."
Baltic Shipping Co. ( 1999(1) LL LR 68), which arose under the 1996 Act, the
parties had first gone before the arbitrator on the preliminary question of
jurisdiction, the matter was argued for three days to ascertain whether or not
there was a contract with the respondent and the arbitrator held that the
respondent before him was a party to the contract. The matter then came under
Section 67 before the Court. The Court observed that this was perhaps a case
where the parties could have straight come first before the Court for determination
on this issue and that would have saved costs and time. ( The English Act
permits parties to take consent or by consent of the arbitrator, to go to Court
on jurisdictional issues). Rix J said (p.70):
"This
was perhaps a case where the parties might well have come to Court, either by
agreement or upon an application from the one side or the other, for the Court
to determine issues of jurisdiction, on the ground that it was likely to
produce substantial savings in cost and that there was good reason why the
matter should be decided by the Court." [ See also 'A Practical Approach
to Arbitration Law by Keren Tweeddale and Andrew Tweeddale'(1999)(at p.79)] It
is, therefore, contended that the Chief Justice or his nominee, is, therefore,
entitled to decide these issues notwithstanding the arbitrator's 'competence'
to decide these issues and if there is a decision, the order deciding rights of
parties cannot be 'administrative' but can only be a judicial order amenable to
Article 136.
As to
the nature of the order to be passed under section 7 of the International
Arbitration Act which deals with reference of disputes falling under the
Convention to arbitration, the Federal Court of Australia (New South Wales) in its judgment dated 30.6.97
held:
"Each
of these determinations which may arise under section 7 of the Act, calls for
the exercised by the Court of judicial power." (See Hi-Fert Pty. Ltd. vs. Kiukiang
Maritime Carriers reported in Vol. XXIII - 1998, Year Book of Commercial
Arbitration of ICCA p. 606 at p.612).
The
learned Solicitor General of India Sri
Salve has also contended that under section 11 the Chief Justice (or his
nominee) has now replaced the jurisdiction of the Court under section 8 of the
old Arbitration Act, 1940. More or less, the same powers are now conferred on
the Chief Justice and this has been done only to enthuse more confidence among
the litigants in the person who is appointed as arbitrator. The District Court
has been previously performing judicial functions under Section 8 of the Arbitration
Act, 1940 and even now the Chief Justice performs only judicial functions. The
UNCITRAL MODEL law, (on which the 1996 Act is modeled) and several statutes
passed in various countries on the UNCITRAL model use the word 'Court' and do
not use the word 'Chief Justice'. It is contended that merely because the word
'Chief Justice' (or his nominee) is now used in the new Indian Act, the order
of the Chief Justice (or his nominee) cannot be treated as an administrative
order. The order does not relate to administrative functions of the Chief
Justice of India or of the Chief Justice of the High Court -such as those
concerning the internal administration of the Supreme Court or High Court or of
the Subordinate Judiciary, as the case may be. On the other hand, the order
judicially decides preliminary issues raised by two contracting litigating
parties. Such an order cannot be said to be administrative in nature. That is
the contention.
It was
pointed out by the learned Solicitor General that in this very case, the
learned Chief Justice of the Bombay High Court had passed a judicial order on
the preliminary issues raised -and which could be raised at the stage anterior
to the appointment of the arbitrator. These issues had to be decided.
Other
examples are also referred to. The case in SLP(C) No.19549 of 1999 which was
heard by the three Judge Bench (from the order of the Chief Justice, Gauhati) alongwith
Konkan Railway Corporation's cases, (see para 8 at p.77) is one such. But the
three Judge Bench however characterised a detailed reasoned judicial order of
the Chief Justice, Gauhati in that SLP as an 'administrative order' though the
Chief Justice had decided a preliminary issue concerning the existence or
otherwise of an arbitration agreement. Learned Solicitor General argued that
the judgment of the three Judge Bench was not correct in stating that the Chief
Justice of Guwahati was "not functioning" as a Court when the said
order was passed. A similar question arose in Wellington Associates Ltd. vs.
Mr. Kirit Mehta [JT 2000 (4) SC 135] (before one of us, Jagannadha Rao, J.) as
to the existence of the arbitration clause and after deciding about the
competence of the Court and the Kompetenz-Kompetenz principle, the issue was
decided as a matter of law by assigning reasons and in fact, it was held that
there was no arbitration clause at all. (Of course, in Nimet Resources Inc.
& Anr. vs. Essar Steels Ltd. [JT 2000 (Suppl. 1) SC 95], Rajendra Babu, J.
while
dealing with the question of existence of the contract, referred to the above
case in Wellington Associates Ltd.
but
felt bound by the three Judge Bench in Konkan Railway case). In yet another
case, in M/s Datar Anr.(Civil Appeal arising out of SLP(C) No.13812 of 2000
disposed of on 18.10.2000), a question arose whether when one party had, on
demand by the other party, appointed an arbitrator - though beyond the period
stipulated in the contract, - the Chief Justice (or his nominee), could, when
approached by the other party, appoint another (sole) arbitrator. Such a
question, it would be obvious, had to be decided at that stage and could not be
left to be decided by one of the arbitrators because the question would be as
to who among them would then be the 'sole' arbitrator? It is pointed out that
there could be a variety of situations where preliminary issues arising at the
stage of Section 11 would have to be decided by the Chief Justice or his
nominee, by a judicial order and this would save time and expenditure and that
this view is not inconsistent with the UNCITRAL Model.
It was
pointed out that there is a more important aspect of a practical nature which
had to be borne in mind. If such an order of the Chief Justice (or his nominee)
was to be treated as an administrative order, it could be challenged before a
Single Judge of the High Court and then before a Division Bench and then in
this Court under Article 136, and such a procedure would only delay the
arbitration proceedings more than if the order was accepted as a Judicial order
and was permitted to be challenged directly under Article 136. In fact, if the
order was to be treated as administrative in nature, even the order of the
Chief Justice of India (or his nominee) could be challenged first before a
Single Judge of the High Court and then before a Division Bench and then under
Article 136 - rather than being treated as a final order of this Court. That
would only delay the proceedings further. Similarly, if the order of the Chief
Justice of the High Court or his nominee is treated as a judicial order, there
would be only one appeal to this Court under Article 136 of the Constitution.
It was contended that the reasoning of the three Judge Bench, that if the order
was to be treated as an administrative order, time would be saved, - could thus
be rendered nugatory. In practice, the defaulting party could drag on the
matter for years at the two stages of Article 226 proceedings even on the
preliminary issues, it is pointed out.
We are
of the view that in the light of the above contentions and material, which in
our opinion have a substantial bearing on the matter, and further inasmuch as
this question is one arising almost constantly in a large number of cases in
the various High Courts, it is desirable that this Court re-examines the
matter.
We,
therefore, direct the papers to be placed before the Hon'ble Chief Justice of
India for passing appropriate orders.
......................J.
[M.JAGANNADHA RAO] NEW
DELHI;
......................J. OCTOBER
19, 2000.
[K.G.BALAKRISHNAN] IN THE SURPEME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOS. 5880-5889 of 1997 M/s Konkan Railway Corpn.Ltd. and Anr.
..Appellants versus M/s Rani Construction Pvt.Ltd. ..Respondents Dear Brother,
A Revised draft order in the above-mentioned matter is being sent herewith for
your favourable consideration.
Back