M/S
Raymond Limited & ANR Vs. Madhya Pradesh Electricity Board & Ors [2000]
INSC 575 (16
November 2000)
B.N.Kirpal,
Doraiswamy Raju, K.G.Balakrishna RAJU, J.
L.I.T.J
The above batch of appeals arise out of a common judgment rendered in a batch
of Writ Petitions by a Full Bench of the Madhya Pradesh High Court, since
reported in AIR 1999 Madhya Pradesh 143 and also the consequential separate
orders passed subsequently by the Division Bench dismissing the Writ Petitions.
The Writ Petitioner - Industries filed appeals against that portion of the
opinion of the Full Bench confining the declaration of law made for prospective
application only and the dismissal of the Writ Petitions, whereas, the
Electricity Board had filed appeals against that portion of the opinion of the
Full Bench declaring the position of law that whenever the contracted supply
falls short of 40% of the contract load then the Board shall be entitled to
charge only for the reduced energy actually supplied and not for 40% of the
contract load as minimum charges and thereby overruling an earlier decision of
a Division Bench of the said High Court reported in M/s Gwalior Steels Private
Ltd. vs M.P. Electricity Board (AIR 1993 M.P. 118). For the purpose of
appreciating the points raised, we would advert to the facts in one of these
appeals, particularly those in M/s Raymond Ltd. in C.A. Nos. 4218-4219 of 1998.
The
appellant M/s Raymond Ltd., a company registered under the Companies Act, 1956
and having its cement manufacturing division within the State of Madhya Pradesh, entered into an agreement with the
Madhya Pradesh Electricity Board on 27.3.1979 renewed periodically for supply
and purchase of high tension electric energy for use in the manufacture of
cement. The minimum contractual demand was for 33 MW (38,822 KVA) per day and
clause 19 provided for the Tariff, while clause 21 stipulated the term relating
to minimum guarantee in the following terms:
21(a)
The consumer shall from the date of utilisation of electrical energy, or from
the date of expiry of the three months notice mentioned in clause 2 hereof
guarantee such minimum consumption as when calculated at the tariff (excluding
charges due to fuel adjustment clause, meter rent and miscellaneous charges)
will yield an annual revenue of Rs.5,40,000/- (Rupees Five Lakhs Forty Thousand
Only) or pay this sum as a minimum. The deficit, if any, between the guaranteed
minimum charges and the actual charges shall be payable by the Consumer.
(b)
The minimum guarantee specified in Clause 21(a) above shall at all times be
without prejudice to realisation by the Board of the minimum prescribed under
the tariff referred to in Clause 19 hereof.
(c) It
hereby agreed further that the Board shall be entitled to fix and charge
enhanced amount of annual revenue if the Board, on completion of all works for
supply to the Consumer, finds it has incurred higher expenditure than the pre-
estimated cost and in that case the Consumer shall pay to the Board the enhanced
annual revenue so fixed by the Board without any objection and will not raise
any dispute regarding the same.
Clause
19 of the agreement read as follows:
The
Consumer shall pay to the Board every month, charges for the electrical energy
supplied to the Consumer during the preceding month, at the Boards tariff
applicable to the class of service and in force from time to time. A copy of
the current H.T. tariff No.1-A of notification No.5/GA/147-A dated 11.03.1976
as amended applicable to the Consumer is set out in the Schedule attached to
this Agreement.
Under
the notification issued for High Tension for 132 KV/220 KV supply, the minimum
tariff prescribed for cement factories is said to be as hereunder:
The
consumer will guarantee a minimum monthly consumption (KWH) equivalent to 40%
load factor of the contract demand. The consumer will be required to pay the
energy charges on the said minimum monthly consumption plus the demand charges
on the billing demand for the month as minimum monthly payment irrespective of
whether any energy is consumed or not during the month. An average power factor
of 0.9 will be applied for the calculation of corresponding unit of 40% load
factor on contractual demand.
The
Senior Account Officer concerned of the Electricity Board issued a bill dated
18.10.1995 raising a demand of Rs.2,83,18.581/- for the consumption period from
15.9.1995 to 15.10.1995. While recording the actual consumption in units of the
electrical energy and the charges therefor, the ultimate bill and demand came to
be raised on the basis of the minimum guarantee charges equivalent to 40% load
factor of contract demand. This, according to the appellant, resulted in a
demand of Rs.87,45,685/- in addition to the charges really due on the actual
consumption of energy during the period in question.
Challenging
the same, Writ Petition No. 3616 of 1995 came to be filed, claiming either for
refund or adjustment of the said excess amount against future demands, the said
sum being for electrical energy not really consumed by them.
During
the pendency of the said Writ Petition, another bill dated 18.10.96 for the
consumption period from 1.12.95 to 15.12.95 was said to have been issued for
Rs.10,24,867/- towards minimum guarantee charges equivalent to 40% load factor
of contract demand. As against this, Writ Petition No. 4711 of 1996 came to be
filed challenging the demand and seeking for either refund of the same or for
adjustment thereof against future demands. The Electricity Board contested the
claim of the appellants and others contending that as per the terms of the
agreement entered into governing the supply of electrical energy, the sum
demanded is quite, in accordance with law, justified and cannot be avoided by
any of the appellants, and the details of their defence will be adverted to
hereinafter, at the appropriate stage.
The
batch of Writ Petitions initially came up before a Division Bench and keeping
in view the earlier decision of a Division Bench reported in AIR 1993 M.P. 118
(Supra), by an order dated 11.9.97, the matter was placed before a Full Bench
with the following observations:
After
reviewing all these cases on the subject we are impressed with the arguments
that the matter requires consideration by the larger Bench because
notwithstanding the fact that as per the terms of the agreement, an obligation
has been cast on the consumer 40% load factor of the contract demand and pay
for the same every month. But there is no corresponding obligation on the
Electricity Board to supply 40% load factor of the contract demand.
When
there is no corresponding duty on the part of the Electricity Board to supply
minimum 40% of the contract demand load every month still the consumer is under
an obligation to 40% of the contract demand load. This prima-facie sound in
equitable. Therefore, we think it proper that since this is a larger issue
which involve serious interpretation of the aforesaid tariff clause of the
Electricity Board as much, yet the matter may be referred to a Larger Bench so
that the matter can be placed beyond the pale of any further controversy in the
matter. Papers maybe placed before the Chief Justice for constituting a Larger
Bench.
The
Full Bench, which heard the matter, by its opinion dated 5.3.98 held as follows:@@
JJJJJJJJJJJJJJJJJJJJJJJ
25.
After considering all aspects of the matter, we are of the opinion that the
view taken by the learned Division bench of this Court in the case of M/s Gwalior
Steels Private Limited v M.P.Electricity Board, AIR 1993 Madh Pra 118, does not
lay down a correct law and we hold with reference to Clause 23(b) of the
Agreement read with Tariff, that whenever contracted supply falls short of 40%
of the contract load, then the Board shall be entitled to charge for the
reduced energy (actually supplied) and will not be entitled to charge 40% of
the contract load. This interpretation which appears to us to be more
equitable, just and reasonable shall be applicable only prospectively that is
from the date of the order and will not have any retrospective operation. This
is being done keeping in view that the Division Bench judgment of this Court
has held the field since 1993 and the Board has been billing the consumers in
the State on that basis and now since we are taking a different view from that
of the Division Bench of this Court and we are interpreting the provision
contrary to the view taken by the Division Bench in the above case of M/s Gwalior
Steel Private Limited it would be more just and equitable to give this
interpretation a prospective effect and not retrospective. Similar course of
action was adopted by the Hon. Supreme Court in the case of L.Chandra Kumar v.
Union of India, AIR 1997 SC 1125. Therefore, we hold that the present
interpretation will be prospective in nature and not retrospective.
Thereupon,
the Writ Petitions came to be posted before the Division Bench, and apparently
on account of the prospective declaration of law, no relief as prayed for in
respect of particular demands for the earlier period could be granted and the
Writ Petitions came to be dismissed.
Hence,
the appeals by the Writ Petitioners before the High Court. So far as the
Electricity Board is concerned, they filed appeals, felt aggrieved by the
judgment of the Full Bench insofar as it overruled the earlier judgment
reported in AIR 1993 M.P. 118 (Supra). This Court, while granting leave in the
Special Leave Petitions filed, on 24.8.98 directed the appeals to be placed
before a Bench of three judges in view of the decision of this Court in Orissa
State Electricity Board & Another vs IPI Steel Ltd. & Others reported
in 1995 (4) SCC 320.
Heard
the learned counsel appearing on either side.
Shri
C.S. Vaidyanathan, learned senior counsel for the Electricity Board, took us at
length through the various clauses in the agreements and contended that the minimum
charges expressly guaranteed in favour of the Board is not subject to either
actual supply by the Board or consumption by the consumer and the payment of
such minimum guarantee at a rate equivalent to 40% load factor of the contract
demand is in substance a partial return for various investments in the various
installations and to meet recurring expenses for maintenance and the consumers,
having specifically undertaken to do so with no provision for any reduction or
deduction in the contract as such for such reasons or grounds, cannot go back
upon the solemn commitments and undertaking under clause 19. In reinforcing the
said stand it is further contended that whenever the State Government pass
orders under Section 22 B imposing power cuts/reduction/staggering in supply
both parties are obliged to carry out the same and it would be futile for the
consumers to read into the word consumption, the element of supply too. The
load factor envisaged is said to be a measure of liability for minimum
guarantee and not to cast any obligation on the Board to effect supply of
energy to that extent so as to make it a condition precedent for casting
liability on the consumer to pay the minimum guaranteed charges. It is further
contended that the minimum guarantee has been fixed for various industries such
as cement, steel etc. depending upon the different minimum load factors having
regard to the investments on establishments and recurring maintenance
expenditure and it is never considered to be part of the tariff but really
relate to the realm of mechanics of price fixation, exclusively within the
discretion of the Board and consequently the High Court could not have
interfered with the same.
On
behalf of the consumer industries Shri G.L.Sanghi, learned senior Advocate,
made the leading arguments followed by Sarvashri A.K. Chitale, Bhimrao Naik, Ravindra
Srivastava, Senior Advocates, and S.Ganesh, U.A.Rana, A.K.Sanghi and others.
Adverting to clauses 1(a), 3(a), (b), 8, 11, 12, 18, 19, 21 and 23, it was
strenuously contended that the contract must be construed as a whole in the
context of the object underlying the same and the basic contract being for
supply continuously 33 KV electrical energy on day to day basis, it should
really be meaningful and really useful and possible of consumption for the
purposes of the industries concerned. It is further stated that the quality,
the quantity and manner of supply has also to be taken into account in
assessing the usefulness of the energy for industrial purposes and if it is shown
that the supply actually made did not conform to these vital aspects of supply
then the undertaking to pay the minimum guaranteed amount should itself have to
go and any other construction would result in grave injustice besides being
also inequitable and unconscionable. The further plea is that the Board during
the period in dispute did not supply even the bare minimum quality of energy
required to run the essential machineries to keep the manufacturing process
going and continuous and the supply actually made was of poor quality, not
really useful, erratic and non- continuous, fluctuating and accentuated with
frequent trippings and in effect not only dislocating the normal working of the
industries but also damaging the machineries and retarding production and
therefore, no exception could be taken to the manner of construction placed on
the clauses in the contract as well as the conclusions arrived at in respect of
the statutory and other liabilities of the consumers, by the High Court. The
learned counsel appearing also endeavoured to highlight some of the individual
factual details pertaining to their cases and also invited our attention to
some of the correspondence exchanged between parties regarding their grievances
about the quality as well as the quantity of supply made to them. We may make
it clear even at this stage that we do not propose to undertake an enquiry into
or adjudication of such factual claims in these proceedings, particularly in
the teeth of the manner of disposal given by the Division Bench after the
opinion of the Full Bench and the desire of the learned counsel themselves to
relegate to the High Court the matters, if need be, for determination of such
claims.
Though
there was an attempt for the consumers to contend that any shortfall in the
supply of the total quantity of contract demand agreed to be made would relieve
them of all liabilities from payment of the minimum guaranteed sum undertaken,
we are unable to countenance any such claim, particularly in view of the very
question that was actually referred to and decided by the Full Bench of the
High Court and which on the face of it merely pertained to the liability or
otherwise of the consumer industries to pay the minimum guaranteed charges even
when the minimum 40% of the contract demand energy is not supplied during the
relevant period by the Board. As a matter of fact, we find, in the light of the
decision in AIR 1993 M.P. 118 (Supra) the correctness of which was taken up for
consideration by the Full Bench, the question referred to the Full Bench itself
is as to whether the consumer is required to pay minimum tariff of 40% of the
contract load irrespective of the fact that even 40% of the contract load
energy has been supplied or not to the consumer. Therefore, it is not permissible
for the consumer industries in these appeals to invite a decision as to the
liability or otherwise of the consumers to pay the minimum guaranteed charges
undertaken, notwithstanding the factual position that the supply made was
actually 40% or even more though not of the extent of total contract demand
agreed to between the parties under the respective contracts. That apart,
countenancing such claims to be agitated in proceedings under Article 226 of
the Constitution would amount to the extraordinary jurisdiction being permitted
to be availed to rewrite the contract and read just contractual liabilities and
thereby undertaking an adjudication of rights of parties flowing under a
contract - a function normally assigned to the ordinary civil courts of the
land.
Apart
from making such submissions on the merits of their claim, on the basis of the
very decision of the High Court and drawing sustenance to substantiate such
claims, the consumer industries also attacked that portion of the judgment
which purported to confine the declaration of law made for future application
only by applying the principle of prospective overruling, contending that such
principles cannot be invoked by the High Courts exercising jurisdiction under
Article 226 of the Constitution of India and that the High Court, in any event,
committed an error in not affording an opportunity to them to make their
submissions on the applicability or otherwise of the principle of prospective
overruling to the cases on hand.
Claims
similar to the one sought to be now asserted, have come up for consideration
before this Court, though in somewhat different background of facts and pattern
of contracts between consumers and Electricity Boards, and either of the
parties before us tried to lay their hands on some or the other of the
observations made in those cases, to justify their respective stand. In M/s Northern India Iron and Steel Co. vs. State of Haryana
& Anr. (1976 (2) SCC 877) the dispute arose between the parties as to
whether in a situation where there were substantial power cuts and the Board
was not able to supply the energy required by the consumer in terms of the
contract entered into, the Board was entitled to get any demand charge and if
so, to what extent and whether the State could demand any duty on such demand
charge. This Court adverted to the existence of two well-known systems of
tariff - one the flat rate system in which a flat rate on units of energy
consumed and the other known as the two-part tariff system, meant for big
consumers of electricity comprising of (i) what is known as `demand charges to
cover investment, installation and the standing charges to some extent and (ii)
energy charges for the actual amount of energy consumed. The Court ultimately
decided the question on the basis of the specific stipulation contained in
clause 4(f) of the contract therein, which entitled the consumer to a
proportionate reduction of demand charges/minimum charges, if the consumer was
not able to consume any part of the electrical energy due to any circumstance
beyond its control and for that purpose the circumstance of power cut which
disabled the Board to give the full supply to the consumer because of the
government order made under Section 22 B of the Electricity Act, 1910, was
considered to be a circumstance which disabled the consumer from consuming
electricity as per the contract.
In Bihar State Electricity Board & Anr. vs M/s Dhanawat Rice & Oil
Mills (1989 (1) SCC 452), this Court while applying the decision in 1976 (2)
SCC 877 (supra) construed clause 13 of the contract between parties in that
case which specifically provided for the proportionate reduction of the annual
minimum guarantee bills, as merely entitling the consumer to a proportionate
reduction only and not completely avoid payment of annual minimum guarantee
bills, even in cases where there was failure on the part of the Board to supply
electrical energy as per demand of the consumer under the contract. In Bihar
State Electricity Board, Patna & Others vs M/s Green Rubber Industries
& Others (1990 (1) SCC 731, this Court, while repelling a challenge to the
clause in the agreement which provided for payment of minimum guaranteed
charges irrespective of whether energy was consumed or not, observed that the
same was reasonable and valid for the reason that the supply of electricity to
a consumer involves incurring of overhead installation expenses by the Board
which do not vary with the quantity of electricity consumed and also for the
reason that those installations have to be continued and must be maintained
until the agreement itself comes to an end. Such a stipulation was also
considered to be not by way of penalty for not consuming the specified quantity
of energy but more for the obligation of the Board to keep the energy available
to the consumer at his end. Again in Andhra Steel Corporation Ltd. & Others
vs Andhra Pradesh State Electricity Board & Others (1991 (3) SCC 263) this
Court held that the purpose of prescribing minimum charges is to ensure that no
undue loss is caused to the Electricity Board due to the tendency of the
consumer to have connection for inflated requirement and the Boards agreement
to meet such requirement and the readiness to maintain the supply up to that
requirement, even if no or very little energy is consumed. The decision of the
State Government under Section 78 A of the Supply Act, 1948, to fix concessional
tariff was also held not sufficient to absolve the consumer from the liability
undertaken to pay the minimum guaranteed charges. In coming to such a
conclusion, reliance has also been placed upon the decisions reported in 1990
(1) SCC 731 (Supra) and The Amalgamated Electricity Company Ltd. vs The Jalgaon
Borough Municipality (1975 (2) SCC 508) wherein this Court observed as follows:
9.
Moreover it is obvious that if the plaintiff company was to give bulk supply of
electricity at a concessional rate 0.5 anna per unit it had to lay down lines
and to keep the power ready for being supplied as and when required. The
consumers could put their switches on whenever they liked and therefore the
plaintiff had to keep everything ready so that power is supplied the moment the
switch was put on. In these circumstances it was absolutely essential that the
plaintiff should have been ensured the payment of the minimum charges for the
supply of electrical energy whether consumed or not so that it may be able to
meet the bare maintenance expenses.
In Orissa
State Electricity Board & Another vs IPI Steel Ltd. & Others (1995 (4)
SCC 320) this Court had an occasion once again to deal with these issues in the
light of the earlier case law on the subject. This Court explained therein the
meaning of the expressions maximum demand charges, consumption charges and
dealt with the role as well as purpose of installing two meters - the normal
meter meant for recording the total quantity of energy consumed over a given
period, in variably a month and trivector meter meant for recording the highest
level/ load at which the energy is drawn over any thirty minute period in a
month. While explaining the two part tariff system meant for big/bulk consumers
of electricity, this Court has emphasised and reiterated the justification and
reasonableness of the same, observing the following:
Normally
speaking, a factory utilises energy at a broadly constant level. May be, on
certain occasions, whether on account of breakdowns, strikes or shutdowns or
for other reasons, the factory may not utilise energy at the requisite level
over certain periods, but these are exceptions. Every factory expects to work
normally. So does the Electricity Board expect - and accordingly produces
energy required by the factory and keeps it in readiness for that factory -
keeping it ready on tap, so to speak. As already emphasised, electricity once
generated cannot be stored for future use. This is the reason and the
justification for the demand charges and the manner of charging for it. There
is yet another justification for this type of levy and it is this: demand
charges and consumption charges are intended to defray different items.
Broadly
speaking, while demand charges are meant to defray the capital costs,
consumption charges are supposed to meet the running charges. Every Electricity
Board requires machinery, plant, equipment, sub-stations, transmission lines and
so on, all of which require a huge capital outlay.
The
Board like any other corporation has to raise funds for the purpose which means
it has to obtain loans. The loans have to be repaid, and with interest.
Provision has to be made for depreciation of machinery, equipment and
buildings.
Plants,
machines, stations and transmission lines have to be maintained, all of which
require a huge staff. It is to meet the capital outlay that demand charges are
levied and collected whereas the consumption charges are levied and collected
to meet the running charges.
Adverting
to the actual grievance of the consumer in that case that where the cut in
supply, be it even for the reason of an order passed by the Government under
Section 22 B of the 1910 Act, is only to the extent of half of the contract
demand, it was held that during such periods of restricted supply the consumer
had to pay the energy charges for the actual consumption plus maximum demand
charges for the maximum demand availed of by him at the rate prescribed in the
agreement. As in the cases before us, it seems to have been projected there
also that even during the periods of restricted supply there were frequent cuts
and break downs as well as irregular supply and the Board cannot levy full
demand charges merely because in any thirty minute period in a given month, the
power is availed at the maximum demand level, and that except the actual
consumption charges nothing further, particularly the full demand charges could
be collected. After referring to the decisions reported in 1990 (1) SCC 731
(Supra), and the other decisions which were quoted with approval therein such
as AIR 1936 Cal.265 (Saila Bala Roy vs Chairman, Darjeeling Municipality and
1969 (1) Madras Law Journal 69 (M.G.Natesa Chettiar vs Mad. SEB) which were
quoted with approval earlier by this Court, the challenge by the consumer came
to be rejected. It was also observed that breakdowns and trippings etc. which
are not confined to periods of restricted supply alone but may occur during
normal times also does not affect the liability of the consumer and only if
there is no supply at all for considerable periods, the situation would be
different, whether it happens during the period of normal supply or restricted
supply, though on facts the case considered by the Court was not found to be
one such.
We
have carefully considered the submissions of the learned counsel appearing on
either side, in the light of the provisions of the 1910 Act and 1948 Act, the
contract entered into between the parties, the general conditions for supply
and the tariff rates prescribed as well as the governing principles as laid
down by this Court. The terms and conditions of supply, as envisaged in the
contract and the statutory provisions and general conditions have been standardised
for uniform application among consumers with variations merely necessitated by
the different class or categories of consumers and there is no scope otherwise
for expecting any scope for individual or free bargaining right in this regard
by each consumer with the Board. Therefore, it is futile for a consumer to
contend that the Board was at the dictating end and the parties were not
equally positioned in settling the terms of the contract. The further attempt
made to contend that the failure on the part of the Board to effect supply up
to the contract demand level relieved the consumers from the obligation
undertaken to pay a minimum guaranteed sum per month, as though the contract
demand is the minimum guaranteed for supply, not only lack any basis in law or
on the terms of the contract governing the supply but also directly runs
counter to the terms in the contract which makes different stipulations
relating to contract demand and the minimum guarantee in the form of a portion
or percentage of the contract demand, only. The question of exonerating the
consumer from the liability undertaken to pay minimum guaranteed charges for a
month and billing only for the actual consumption of energy or allowing a
consumer to pay the rates on the actual consumption of electricity measured in
units will and can arise and has also been considered for determination only in
case the supply by the Board itself fell short of the minimum of energy, the
consumption of which go to make up the minimum guaranteed sum. It is well
settled and there could be no controversy over the position that if only the
supply was available for consumption but the consumer did not consume so much
of energy up to the extent of the obligation cast upon him to pay the minimum
charge, there is no escape from the payment of the minimum guaranteed charges,
except in very exceptional cases envisaged under clause 23 of the contract, and
that too subject to the stipulations and restrictions contained therein.
In the
light of the serious controversies raised as to the duration, quantity, manner
and quality of supply of electrical energy expected to be made by the Board, it
becomes inevitably necessary to decide first the question relating to the unit
or standard of measurement, which invariably must have relevance, in our view,
only to the billing cycle envisaged in the contract and the tariff which is
only a month. The payment by the consumer is to be on the electrical energy
supplied during the preceding month.
The
parties have also agreed that the maximum demand of the supply is to be
measured with reference to the month at the point of supply of the consumer and
will be determined on the basis of the supply during any consecutive thirty
minutes in that month as recorded by the trivector meter.
The
power factor, according to the statutory conditions of supply which form part
and parcel of the supply of energy to a consumer, is also to be determined with
reference to the supply of energy to a consumer, and that factor is also to be
determined with reference to the supply of electrical energy made during a
month. The minimum consumption of energy guaranteed, as per the tariff
notification, is also in terms of a monthly minimum. While that be the
position, it is futile for the consumers to contend that they will not be
liable to abide by the minimum guaranteed charges undertaken, unless on every
day of the month/year and during the twenty four hours or round the clock the
load factor and power supply agreed to be made, at one and is the same level
without any shortfall, tripping or low voltage. The provisions of Section 56 of
the Contract Act, 1872 sought to be relied upon have no relevance or
application to the cases on hand. Countenancing of such claims would not only
defeat the very purpose, object and aim of providing for a minimum charges
guarantee clause but would ultimately result in mutilation of the very fabric
of tariff structure rendering thereby the schemes of generation and supply of
power at the agreed concessional rates uneconomical and non-viable for the
Board. This would also result in the re-writing of many of the clauses in the
contract and rendering nugatory the tariff pattern and system itself throwing
into disarray and disharmony the efficient execution of the power supply
schemes.
The
further claim asserted on behalf of the consumers that since what was agreed to
between the parties was to make the supply available continuously except during
situations envisaged in clause 11 of the contract, the failure to effect such
supply by the Board renders the very contract relating to the payment of
minimum guaranteed charges unenforceable against them, does not merit
acceptance in our hands. It cannot legitimately be contended that the word
continuously has one definite meaning only to convey uninterruptedness in time
sequence or essence and on the other hand the very word would also mean
`recurring at repeated intervals so as to be of repeated occurrence`. That
apart, used as an adjective it draws colour from the context too, and in the
light of the texture of clause 11 as well as clause 12 and clause 23 (b) and
also Section 22 B of the 1948 Act and orders passed therein which are binding
with equal force upon both the consumer and the Board, the word is incapable of
being construed in such absolute terms as endeavoured by the learned counsel
for the consumers.
The
High Court was of the view that it would be more just, equitable and reasonable
to hold whenever the contracted supply fell short of 40% of the contract load
which alone accounts for the minimum guaranteed sum, then the Board shall be
entitled to charge for the reduced energy actually supplied and not the minimum
of 40% of the contract demand. As noticed supra, on behalf of the consumers,
not only inspiration is drawn to support their claim in this regard but an
extreme stand is also sought to be taken by contending that in such cases as
also in cases where the supply is not of the contracted load and to the extent
of the agreed load factor without interruptions so as to cause any disturbance
or dislocation of the smooth functioning of their industry concerned, the
obligation under the clause in the agreement providing for the payment of the
minimum guaranteed charges to the tune of 40% of the contract load also would
automatically stand snapped and not only that the consumers will be relieved of
their liability but they can be made answerable only to the extent of energy
actually supplied and which has been consumed. There is no justification for
countenancing this extreme stand either under any of the provisions of the Act
or the regulations made thereunder or under the provisions of the contract
entered into between the parties and tariff schedule notified and made binding
upon the consumers. This would, if accepted, give credence to the plea vaguely
and indirectly projected as though the contract demand is the minimum supply
undertaken to be made by the Board, whereas in contrast clause 23 of the
general conditions for supply of electrical energy by the Board applicable to
all consumers in unmistakable terms stipulate that the maximum demand agreed to
be supplied and taken under the agreement shall be the consumers contract
demand and that if as a matter of fact in any given case the consumption
exceeds this level, then only the contract provides for additional charges to
be paid by the consumers.
As a
matter of general principle, any stipulation for payment of minimum guarantee
charges is unexceptionable, in a contract of this nature wherein, the Board
which undertakes generation, transmission and supply of electrical energy has
to, in order to fulfil its obligation lay down lines and install the required
equipment and gadgets and constantly keep them in a state of good repair and
condition to render it possible for the consumer to draw the supply required at
any and all times. These commitments are irrespective of the capacity of the
Board to generate at a given point of time or during a relevant period the
total quantum required for the consumption of all consumers of various
categories or even during the days of breakdown envisaged or staggering
necessitated on account of orders of Government regulating the distribution and
consumption of energy as well as during periods when for reasons personal or
peculiar to the consumers or even beyond their control the consumption is not
and could not be of the mutually agreed extent. The Board undertakes to
generate and supply energy, in public interest also at concessional rates of
varying nature and it cannot be stated that the rates so fixed invariably are
to meet the expenditure incurred by the Board for generation and supply of
energy, to the last pie.
Consequently,
if either in the general conditions and terms of supply or the contract or the
tariff rates as the case may there be any stipulation, in clear and
unmistakable terms that the liability relating to the payment of guaranteed
minimum charge could or will be enforced irrespective of the actual consumption
rate of the consumer or even dehors the capacity or otherwise of the Board to
supply even the minimum of the contract demanded energy, there could be no
valid objection in law for any such stipulation being made and the consumer
will be bound to honour such commitment. The contract for the supply of
electrical energy cannot be treated on par with any other contacts of mutual
rights and obligations, having regard to the peculiar problems involved in the
generation, transmission and supply which invariably depend upon the vagaries
of monsoon as well short supply to them of the required coal and oil in time
and similar other problems over which the Board cannot have any absolute
control. The recurring commitments relating to constant and periodical
maintenance of supply lines and other installations cannot be anytheless even
during such times and such onerous liabilities cannot be left to fall
exclusively upon the Board and it is only keeping in view all these aspects,
payment of minimum guaranteed charges is necessarily in built in the tariff
system of the Board and the reasonableness or legality of the same cannot be
considered either in the abstract or in isolation of all these aspects.
It is
for this reason that all over and the consumer is also made to share the
constraints on Boards economy even during such periods. In fact the tariff
inclusive of such a provision for payment of a minimum guaranteed sum
irrespective of the supply/consumption factor appears to be the consideration
for the commitments undertaken by the Board as a package deal and it is not
possible or permissible to allow the consumer to wriggle out of such
commitments merely on the ground that the Board is not able to supply at any
point of time or period the required or agreed quantum of supply or even supply
up to the level of the minimum guaranteed rate of charges. Tinkering with
portions of contracts for any such reasons, merely on considerations of equity
or reasonableness pleaded for and vis-a-vis one party alone will amount to
mutilation of the whole scheme underlying the contract and render thereby the
very generation and supply of electrical energy economically unviable for the
Board. Consumers, who enter into such commitments openly and knowing fully well
all these hazards involved in the generation, transmission and supply, will be estopped
from going behind the solemn commitment and undertaking on their/its part under
the contract. The High Court does not seem to have properly appreciated the
ratio of the several decisions noticed except merely referring to them in extenso,
and yet ultimately just, arrived at a conclusion merely for the reason that the
court considered it to be `more equitable, just and reasonable to do so.
So far
as the cases under consideration and the liability of the consumers relating to
minimum guarantee are concerned, the relevant clause relating to minimum
guarantee charges as well as the tariff notification relied upon, would go to
show that what was guaranteed was not the payment of a flat sum or amount of
money to be calculated with reference to a particular number or percentage of
units, dehors the quantum of electrical energy distributed and supplied by the
Board. In other words, the guarantee was of such minimum consumption as when
calculated at the tariff.. will yield a particular monthly/annual sum to the
Board. Even going by the tariff notification which prescribes also a minimum
entitling the Board to collect it [vide clause 21 (b)] it merely casts
liability on the consumer to guarantee a minimum monthly consumption equivalent
to 40% load factor of the contract demand.
Consequently,
for the consumer to honour his/its commitment so undertaken to give a minimum
consumption there should essentially be corresponding supply by the Board at
least to that extent, without which the consumption of the agreed minimum is
rendered impossible by the very lapse of the Board. The minimum guarantee,
thus, appears to be not in terms of any fixed or stipulated amount but in terms
of merely the energy to be consumed. The right, therefore, of the Board to
demand the minimum guaranteed charges, by the very terms of the language in the
contract as well as the one used in the tariff notification is made enforceable
depending upon a corresponding duty, impliedly undertaken to supply electrical
energy at least to that extent, and not otherwise. It is for this and only
reason we find that the ultimate conclusion arrived at by the Full Bench of the
High Court does not call for any interference in these appeals.
Shri
C. S. Vaidyanathan, learned senior counsel for the Board, further contended
that the High Court committed an error in overlooking the facts placed on
record in the form of statements showing the units which were made available to
the consumers during the periods in question and the units determined on which
the minimum charges became payable and that those statements sufficiently
substantiated the position that the units made available were more than
sufficient to cover the payment of minimum charges and the contentions to the
contrary that the Board had not been able to supply even 40% of the contract
demand to insist upon the payment of minimum guaranteed charges has no basis or
merit of acceptance. In this connection, our attention has been drawn by the
counsel on either side to those materials and particulars placed along with the
counter affidavits/Return of the Board filed before the High Court, the annexures
thereto and some of the correspondence between the officers of the Board and
the consumers concerned. Unfortunately, even the Division Bench, before which
the matters were posted for further hearing and disposal pursuant to the
opinion given by the Division Bench, did not undertake to adjudicate this vital
aspect of the issues involved which, in our view, became very much relevant and
essential in the light of the opinion of the Full Bench. Apparently, on account
of the fact that the Full Bench confined the operation of its decision for
future application only, and the liability for the periods under challenge
therefore stood governed by the position of law as declared by the decision in
AIR 1993 MP 118 (supra) which held the field, the Division Bench might have
thought such an exercise to be superfluous. But, in the light of our conclusion
that, as the matter stands, on the basis of the existing clauses in the
contract as well as the Tariff notification the minimum guarantee assured was
of the monthly consumption equivalent to 40% load factor of the contract demand
which obligated the Board also to ensure supply at least to that extent to
insist upon the payment of the minimum charges, it becomes necessary to
undertake an exercise, to decide in individual cases, the question of actual
supply said to have been made in order to find out whether the units of energy
to the extent of minimum of 40% of the contract demand has been made available
for consumption. For this purpose, these cases have to be necessarily and are
hereby remitted to the High Court, for being restored to their original number
to find out the actual position about claim/dispute relating to the supply of
energy equivalent to 40% load factor of the contract demand. Wherever the High
Court finds this fact in favour of the Board, the consumer has to pay the
minimum guaranteed consumption charges as claimed, without any further
challenge to the said liability. Both parties shall be at liberty to
substantiate their respective stand in the light of the materials already on
record or that may be produced further before the High Court in the relegated
proceedings.
So far
as the challenge made to the judgment of the Full Bench of the High Court, in confining
its operation and applicability only for future period, Shri G.L. Sanghi,
learned counsel, followed by the others have strongly contended that the High
Court as such cannot apply the principle of prospective over ruling. Reliance
in this regard has been placed upon the decision reported in State of H.P.
& Others vs Nurpur Private Bus Operators Union & Others [1999 (9) SCC
559] to which one of us (B.N.Kirpal, J.) was a party. Passing reference has
been made to the decision in Golak Nath vs State of Punjab (AIR 1967 SC 1643) and the
observation contained therein that the doctrine of prospective overruling can
be invoked only in matters arising under the Constitution and that it can be
applied by the Supreme Court of India. The decision in Golak Naths case as such
was subsequently overruled by the decision reported in Kesavananda Bharati vs
State of Kerala (AIR 1973 SC 1461) though not
specifically on this point. Reliance has also been placed upon the decision
reported in M/s K.S.Venkataraman & Co. vs State of Madras (AIR 1966 SC
1089) even to contend that if the High Court had no such power, this Court
while hearing an appeal from such judgment of the High Court, will equally
cannot exercise such powers.
This
submission of the learned counsel overlooks the vital fact in that case that
not only the High Court was found to exercise under Section 66 of the Income
Tax Act, 1922, a special advisory jurisdiction the scope of which stood limited
by the section conferring such jurisdiction but even the appeal to the Supreme
Court having been made only under Section 66 A (2) of the said Act was noticed
to hold that the jurisdiction of this Court also does not get enlarged and that
the Supreme Court can also only do what the High Court could do. Apart from the
fact that the writ jurisdiction conferred upon High Courts under Article 226 of
the Constitution does not carry any restriction in the quality and content of
such the powers, this Court could always have recourse to the said doctrine or
principle or even dehors the necessity to fall back upon the said principle
pass such orders under powers which are inherent in its being the highest court
in the country whose dictates, declaration and mandate runs throughout the
country and binds all Courts and every authority or persons therein and having
regard to Articles 141 and 142 of the Constitution of India. The Appellate
powers under Article 136 of the Constitution itself would also be sufficient to
pass any such orders. This Court has been from time to time exercising such
powers whenever found to be necessary in balancing the rights of parties and in
the interests of justice. [vide: Union
of India vs Mohd. Ramzan Khan 1991 (1) SCC
588; Managing Director ECIL vs B. Karunakar & Others 1993 (4) SCC 727;
India Cement Ltd. vs State of Tamil Nadu AIR
1990 S.C.85.] The decision reported in 1999(9) SCC 559 (Supra) at any rate is
no authority for any contra position to deny such powers to this Court.
The
peculiar facts and circumstances of these cases and the interests of justice,
in our view, necessitate the application of the Law declared therein only
prospectively.
The
electricity Board is a public authority of the State engaged in the generation
and supply of electrical energy at concessional rates to different class and category
of consumers in the State. The construction placed by us is likely to have
serious and adverse impact upon the finances and the economic viability of the
scheme underlying tariff and minimum guarantee charges already determined. It
is impossible for the Board, at this point of time to make up or change the
pattern of tariff retrospectively to retrieve itself in this regard for the
past period. The construction and execution of various developmental schemes
and works are likely to suffer thereby a serious set back also. Keeping in view
all these aspects we will be justified in declaring that the law declared in
these cases shall be for future application only and not for the earlier
period.
For
all the reasons stated above, the appeals are disposed of in the light of the
directions and observations contained herein and the High Court shall restore
the proceedings to its original file and dispose of the same in accordance with
the directions contained in this judgment.
The
parties will bear their respective costs.
Back