Bishandayal
And Sons Vs. State of Orissa & Ors [2000] INSC 627 (7 December 2000)
V.N.Khare,
S.N.Variava
L.I.T.J
This
Appeal is against a Judgment dated 15th May, 1992. Briefly stated the facts are as follows:
In an auction sale held by the Court Receiver, the 1st Respondent purchased,
for a sum of Rs. 2.32 lacs, all the assets of one Mayurbhanj Spinning and
Weaving Mills including plant and machinery and land measuring Ac. 419.14,. The
1st Respondent then proposed to sell off the Mill. The Appellant by a letter
dated 14th November,
1992 offered to
purchase the Mill with all its assets for consideration of a sum of Rs. 2.31 lacs.
During this period the State of Orissa was under the President's Rule. The Appellants thus had a meeting with
the Governor of Orissa wherein they were asked to enhance the consideration to
Rs. 2.32 lacs. The Appellants by the letter dated 17th Marcy, 1973, addressed
to the Governor, conveyed their acceptance to purchase the Mill with all its
assets for Rs. 2.32 lacs. By a letter dated 9th April, 1973, addressed by the Deputy Secretary
to the Government to the Director of Industries, the Director of Industries was
informed that the Government had decided to sell the Mill to the Appellants for
a sum of Rs. 2.32 lacs. It was, however, stated that the Director of Industries
was to ensure that correct assessment, of the land required to run the unit by
the Appellants, was made.
This
was an internal communication, not addressed to the Appellants yet the
Appellants came to know of it. The Appellants, obviously with a view to
pressurize, address a letter dated 18th April, 1973 to the Governor stating
that they had accepted the offer to purchase the Mill at the cost of Rs. 2.32 lacs
and purported to forward a Demand Draft in a sum of Rs. 1,32,000/-. The 2nd
Respondent by his letter dated 21st April, 1973, addressed to the Appellants,
informed them that the Government had approved the proposal to sell the Mill to
the Appellant for a cost of Rs. 2.32 lacs and that they would be allotted land
actually required for running the Mill. By their letter dated 23rd April, 1973, the Appellants informed the 2nd
Respondent that they were surprised to learn that the land was to be allotted
to the extent actually required. They insisted that the entire assets including
the entire land was to be sold to them for a sum of Rs. 2.32 lacs. The 2nd
Respondent by the letter dated 5th July, 1973 informed the Appellants that the
Government was willing to sell the entire land provided they paid the full
market value of the land and entered into a lease and paid the premium and
abided by the terms and conditions of that lease. The Appellants on 17th July, 1973 gave an undertaking to apply to the
local Tehsildar. On 2nd
August, 1973 the
Appellants undertook to pay full value of land and other charges and to abide
by terms and conditions of lease. As till date no agreement had been finalised
by letter dated 22nd
October, 1973 the 2nd
Respondent returned the Demand Draft of Rs. 1.32 lacs to the Appellants.
Thereafter
some correspondence was carried on between the parties. Ultimately the
Appellants gave a notice dated 26th October, 1974, purporting to be a notice under Section 80 of the Civil Procedure Code
where under they claimed that a complete contract had been arrived at to sell
the Mill with all lands to the Appellants for a sum of Rs. 2.32 lacs.
The
Appellant then filed Suit No. 108 of 1976 in the Court of Sub-Judge, Cuttack, claiming that a concluded contract
had been arrived at to sell the Mill and all its assets, including Ac. 419.14
of land to the Appellants for a price of Rs. 2.32 lacs. The Appellants claimed
that they had acquired valid right and title to the properties of the Mill. The
Appellants also claimed that the undertakings given by them were void as they
were obtained by misrepresentation, fraud, undue influence and coercion. The
Appellants also sought an injunction against the Respondents from selling away
the Mill and its properties. At this stage itself it is to be seen that the
Appellants and the Respondents were at cross purposes. Whilst the Appellant was
insisting on purchasing the Mill with all its land for a price of Rs. 2.32 lacs
only, the Government was only offering the mill with such land as would be
required for running the Mill. Thus upto this stage there had been no concluded
contract or agreement. At the Appellate stage counsel for Appellants fairly
conceded that the prayers in the Original Suit could not have been granted and
that he was not pressing for the same. This is recorded in paras 8 & 9 of
the impugned Judgment. Thus we are not now concerned with the Original Suit but
with events which took place thereafter. After the suit was filed a meeting was
held in the Chamber of Minister of Industries on 29th December, 1978. Minutes of the meeting of 29th December, 1978, inter alia, records as follows :
"3. After discussion the following decision were taken :
(a)
M/s. Bishandayal & Sons would pay the previously fixed price of Rs. 2.32 lakhs
towards plant, machinery & building.
(b)
They will be leased out an area of Ac. 40 of land.
(c)
They would pay premium @ 1/3rd of the market value of land as prevailing in
1972.
(d)
The suit will be withdrawn by the firm.
(e)
After sale, the unit will be revived by the party." Copy of those minutes
were given to the Appellants.
The
Appellants applied for and were allowed to amend the plaint on 11th September, 1981. It was now claimed that a fresh
agreement to sell had been arrived at on the basis of the decision taken in the
meeting of 29th
December, 1978.
The
Appellants now sought Specific Performance of this agreement. The Respondents
filed an additional Written Statement wherein they denied that there was any
such agreement. On 19th
March, 1982 this suit
was decreed by the trial court. It was held by the trial court that there was a
completed contract between the Appellants and the Respondents and that the
Appellants had acquired rights over the mill and its lands. Having come to that
conclusion the trial court still directed the Appellants to pay for 40 acres of
land at the rate of Rs. 300 per acre. The trial Court concluded that the
Appellant was ready and willing to perform its part of the contract and that
the decision in agreement arrived at on the meeting of 29th December, 1978 were
mere confirmations of the previous contract. The trial court also held that the
condition regarding withdrawal of suit was not a condition precedent and that
there was valid notice under Section 80 of the Code of Civil Procedure. The
Respondents then filed First Appeal No. 261 of 1992 in the High Court of Orissa.
This Appeal has been allowed by the impugned Judgment dated 15th May, 1992. As has been set out herein above,
before the Appellate Court counsel for the Appellant fairly and correctly
conceded that the prayers in the original plaint were not maintainable and
could not have been granted. As stated above counsel for the Appellants fairly
conceded that he was not pressing the prayers in the original plaint. Thus
clearly the decree of the trial court holding that there was a concluded
contract was wrong and unsustainable, not only in law, but also on facts.
Before the Appellate Court the question was whether the Appellants were
entitled to specific performance of the agreement alleged to have been arrived
at in the meeting of 29th
December, 1978. The
Respondents herein contended that there was no agreement. They also contended
that even if there was an agreement the same was unenforceable in law as the
provisions of Article 299 of the Constitution of India had not been complied
with. It was also contended that by the amendment of the plaint, an entirely
new case had been incorporated and no fresh notice under 80 of the Code of
Civil Procedure having been given the amended suit was not maintainable. It was
also contended that even if there was an agreement one of the pre-conditions
was that the suit should be withdrawn and as the Appellants had not withdrawn
the suit, it could not be said that they were ready and willing to perform
their part of the contract and no relief should have been granted to them on
this count also. The Appellate Court has, in the impugned Judgment held that an
agreement was arrived at. The Appellate Court has however held that the
agreement is not enforceable in law as it does not comply with the provisions
of Article 299 of the Constitution of India. The Appellate Court has also
upheld the contentions of the Respondents herein, on Section 80 Code of Civil
Procedure and on precondition of withdrawal of Suit. Before us the Respondents
have not disputed that, at the meeting of 29th December, 1978, an agreement as reflected in the
minutes had been arrived at. Thus there is no challenge to the findings in this
behalf. However, it has been contended that this is an agreement, which is
unenforceable in law as the provisions of Article 299 of the Constitution of
India have not been complied with. The contentions regarding Section 80, Code
of Civil Procedure and precondition of withdrawal of suit have been pressed.
On
behalf of the Appellants it is contended that it is not open to the Respondents
to take up the plea of non compliance with Article 299, Constitution of India
as no such plea was taken in the written statement. In support of this reliance
was placed on the case of Kalyanpur Lime Works Ltd. v. State of Bihar and other
reported in AIR 1954 S.
C.
165. In this case the question was whether the concerned contract conformed
with the provision of Section 30 of the Government of India Act, 1915 Such a
plea had not been raised in the pleadings or in the memorandum of appeal to the
High Court but was taken for the first time during arguments in this Court.
This Court held that such a question could not be allowed to be raised at the
time of the arguments, as it was a mixed question of law and fact and no
opportunity to adduce evidence was given to the other side. Reliance was also
placed upon the case of Union of India vs. Surjit Singh Atwal reported in 1979
(1) S.C.C.
520.
In this case there was a concluded contract for the construction of a hard
runway, taxi tracks and dispersal roads The work under the contract had been
completed and the dispute between the parties was whether the Contractor was
entitled to special rates in respect of certain stone, which were not available
at the site. It was claimed that at a meeting it had been agreed that the
Plaintiff (therein) would be entitled to extra price. The plea regarding
illegality of the contract had not been raised in the written statement. In the
written statement there was total denial regarding the agreement to make
payment of special price. Thereafter an application for amendment of the
written statement was made to plead that there was failure to comply with the
provisions of Section 175(3) of the Government of India Act, 1935. That
application was dismissed but it was observed that the plea could be raised
even without an amendment. The suit then went to trial.
The
trial court dismissed the suit on the ground that there was a new agreement in
November 1947 and that this agreement did not comply with the requirements of
Section 175(3) of the Government of India Act, 1935. In Appeal the Division
Bench held that there was no new agreement. The Appellate Court held that the
trial court was wrong in entertaining a plea which had not been taken in the
written statement. The Appeal was accordingly allowed. This Court dismissed the
appeal to this Court on the ground that such a plea not having been taken in
the written statement could not be raised after several years after the
institution of the suit as it would greatly prejudice the plaintiff. This Court
held if such a plea had been taken at the earlier stage, the plaintiff could
have come out with a certain alternate case or raised certain other pleas,
which right he had now lost.
This
Court also held that such a plea was a mixed plea of fact and law. Reliance was
also placed upon the case of Nirod Baran Banerjee vs. Dy. Commissioner of Hazaribagh
reported in 1980 (3) S.C.C. 5. In this case it was held that the question whether
Article 299 of the Constitution of India was complied with is not a pure
question of law but a question depending on facts and since the point was not
pleaded either before the trial court or the High Court, it cannot be raised in
this Court for the first time. There can be no dispute with the preposition of
law. The question whether a contract complies with Article 299 of the
Constitution of India or not is a mixed question of law and fact. Undoubtedly
in this case the plea has not been taken in the written statement and not been
urged before the trial court. However, it was squarely urged before the
Appellate Court. At the stage i.e. when it was urged before the Appellate
Court, a contention could have been taken that such a plea cannot be raised. Instead
the Appellants took out an application under Order 41, Rule 27, Code of Civil
Procedure, for a direction to the Respondents to produce the original minutes
in Court. That application was allowed by the Appellate Court and the
Respondents were directed to produce the original minutes in Court. Thus the
Appellate Court made sure that no prejudice was being caused to the Appellants.
The Appellate Court made sure that Appellants were not deprived of an
opportunity to lay all facts before the Court. The minutes were then produced
in Court. It was found that the original minutes did not contain the signatures
of either of the parties. The original minutes were shown to the counsel for
the Appellants and they were satisfied that the minutes had not been signed by
the parties. Thus the Appellants themselves, on such a plea being raised,
called for the additional evidence and the Appellate Court permitted it. The
original minutes clearly indicated that the provisions of Article 299 had not
been complied with. Further the witness of the Appellant had, during his cross
examination, admitted that apart from the minutes there was no other written
agreement between the parties. It is not the case of the Appellants that the
agreement arrived at in the meeting of 29th December, 1978 had thereafter been approved or
sanctioned either by the President or the Governor. It is, therefore, clear
that even though there may have been some agreement the same was not in
compliance with the constitutional requirement under Article 299 of the
Constitution of India and is therefore unenforceable in law. In a case such as
this there is no alternate plea that could be taken. None has been taken.
For
this reason the Appellants would not be entitled to specific performance of
such an agreement. It must be seen that all the cases relied upon by the
Appellants were cases where such a plea was not allowed to raised, for the
first time in this Court or in the Appeal Court on the ground that the concerned party did not have an
opportunity to meet such a case. In this case the Appellants, on their
application, were permitted to have brought in Court the original minutes.
Unfortunately this did not assist them. Now they can not be permitted to argue
that such a plea could not be raised. The next question for consideration is
whether the amended suit was not maintainable for want of notice under Section
80 of the Code of Civil Procedure. In this behalf the Appellants have relied
upon the cases of Amar Nath Dogra vs. Union of India reported in AIR 1963 S.C.
424, State of Punjab vs. M/s. Geeta Iron & Brass Works Ltd. reported in
1978 (1) S.C.R. 746, Ghanshyam Dass and others vs.
Dominion
of India and others reported in 1984 (3) S.C.C. 46 and Vasant Ambadas Pandit
vs. Bombay Municipal Corporation and others reported in AIR 1981 Bombay 394. In
these cases it has been held that a notice under Section 80 C.P.C. or
equivalent notices under Section 527 of the Bombay Municipal Corporation Act
are for the benefit of the Respondents and the same can be waived as they do
not go to the root of jurisdiction in a true sense of the term. There can be no
dispute to the proposition that a notice under Section 80 can be waived. But
the question is whether merely because in the amended written statement such a
plea is not taken it amounts to waiver. This contention was argued before the
Appellate Court. Even otherwise we find that in the suit itself Issue No. 4 had
been raised as to whether or not there was a valid and appropriate notice under
Section 80.
Such a
point having been taken in the original written statement and an issue having
been raised, it was not necessary that in the amended written statement such a
plea be again taken. On behalf of the Respondents, reliance has been placed on
the case of Gangappa Gurupadappa Gugwad vs.
Rachawwa
and others reported in AIR 1971 S.C. 442, wherein it has been held that where
the plaintiff's cause of action is against a Government and the plaint does not
show that notice under Section 80 was served, it would be duty of the Court to
reject the plaint. In this case the original notice was only in respect of a
claim under the plaint as it originally stood. That claim was on the basis that
there was a concluded contract and that the Appellants had already acquired
rights in the mill and the lands. As has been fairly conceded those reliefs
were not maintainable and were given up before the Appellate Court. The amended
plaint was on an entirely new cause of action. It was based on facts and events
which took place after the filing of the original plant. It was a fresh case.
Now the claim was for specific performance of the agreement alleged to have
been entered into on 29th
December, 1978.
Admittedly no notice under Section 80 CPC was given for this case. As there was
an Issue pertaining to Notice under Section 80, the trial court should have
dealt with this aspect. The trial court failed to do so. It was then pressed
before the Appellate Court.
In our
view the finding in the impugned Judgment that the suit based on this claim was
not maintainable is correct and requires no interference. If a new cause of
action is being introduced a fresh notice under Section 80 CPC would be
required to be given. The same not having been given, the suit on this cause of
action was not maintainable. We also find ourselves in agreement with the
findings in the impugned judgment that the condition regarding withdrawal of
the suit was a condition precedent. As the Appellants did not withdraw the suit
they could not be said to be ready and willing to perform their part of the
agreement arrived at on 29th
December, 1978. For
this reason also the claim for specific performance could not have been
enforced. In this view of the matter, we see no reason to interfere with the
impugned Judgment. The Appeal stands dismissed. There will, however, be no
order as to costs.
Back