Konkan
Railway Corpn. Ltd. & Ors Vs. M/S. Mehul Construction Co [2000] INSC 437
(21 August 2000)
G.B.Pattanaik,
Doraswamy Raju, S.N.Variava
PATTANAIK,J.
In
this batch of cases an important question arises for consideration of this
Court, namely, under the provisions of Arbitration and Conciliation Act, 1996,
what should be the correct approach of the Chief Justice or his nominee in
relation to the matter of appointment of an arbitrator under Section 11(6) of
the Act, and what is the true nature of the said order and further if a person
is aggrieved by such order, can he file application in a Court and whether such
an application could be entertained and if so, in which forum? In Sundaram
Finance Ltd. vs. NEPC India Ltd. (1999) 2 Supreme Court Cases 479, while
deciding the question as to whether under Section 9 of the Arbitration and
Conciliation Act, 1996, the Court has jurisdiction to pass an interim order
even before commencement of arbitration proceeding and before an Arbitrator is
appointed, after analysing different provisions of Arbitration Act, 1940 and
the present Act of 1996 an observation has been made to the effect under the
1996 Act, appointment of Arbitrator is made as per the provisions of Section 11
which does not require the Court to pass a judicial order appointing
Arbitrator. In Ador Samia Private Ltd. vs. Peekay Holdings Limited and others -
(1999) 8 Supreme Court Cases, 572, this Court came to the conclusion that the
Chief Justice of the High Court or his designate under Section 11(6) of 1996
Act, acts in administrative capacity, and such, an order of the Chief Justice
is not passed by any court exercising any judicial function nor is it a
tribunal having the trappings of a judicial authority and it must, therefore,
be held that against such order, which is administrative in nature application
under Article 136 of the Constitution would not lie. Notwithstanding the
aforesaid decision of this Court in Ador Samia Pvt. Ltd. (supra) case when the
present batch of cases came up for consideration before the Bench presided over
by Majmudar, J. who was the author of Samias case (supra) it was contended that
the aforesaid decision requires consideration and having acceded to the request
of the petitioner, the Bench passed the order to place this batch of cases
before a Three Judge Bench and that is how these cases have come before us. Two
basic questions which really arise for consideration are, (1) what is the
nature of the order that is passed by the Chief Justice or his nominee in
exercise of power under sub-section (6) of Section 11 of the Act? and, (2) even
if said order is held to be administrative in nature what is the remedy open to
the person concerned if his request for appointment of an Arbitrator is turned
down by the learned Chief Justice or his nominee, for some reason or other? In
deciding the latter question it would be necessary to find out the true
intention of the legislature in substituting 1940 Act by the present Act and
bearing in mind the object of enactment of the new Act what should be the
approach of the learned Chief Justice or his nominee when an application for
appointment of an Arbitrator is made invoking the jurisdiction under Section
11(6) of the 1996 Act.
At the
outset, it must be borne in mind that prior to the 1996 Act, the Arbitration
Act of 1940, which was in force in India provided for domestic arbitration and no provision was there to deal
with the foreign awards. So far as the Foreign Awards are concerned, the same
were being dealt with by the Arbitration (Protocol and Convention) Act, 1937,
and the Foreign Awards (Recognition and Enforcement) Act, 1961. The increasing
growth of global trade and the delay in disposal of cases in Courts under the
normal system in several countries made it imperative to have the perception of
an alternative Dispute Resolution System, more particularly, in the matter of
commercial disputes. When the entire world was moving in favour of a speedy
resolution of commercial disputes, the United Nations Commission on
International Trade Law way back in 1985 adopted the Uncitral Model Law of
International Commercial Arbitration and since then, number of countries have
given recognition to that Model in their respective legislative system. With
the said Uncitral Model Law in view the present Arbitration and Conciliation
Act of 1996 has been enacted in India replacing the Indian Arbitration Act, 1940 , which was the principal
legislation on Arbitration in the country that had been enacted during the
British Rule. The Arbitration Act of 1996 provides not only for domestic
arbitration but spreads its sweep to International Commercial Arbitration too.
The Indian law relating to the enforcement of Foreign Arbitration Awards
provides for greater autonomy in the arbitral process and limits judicial intervention
to a narrower circumference than under the previous law. To attract the
confidence of International Mercantile community and the growing volume of
Indias trade and commercial relationship with the rest of the world after the
new liberalisation policy of the Government, Indian Parliament was persuaded to
enact the Arbitration and Conciliation Act of 1996 in Uncitral model and,
therefore, in interpreting any provisions of the 1996 Act Courts must not
ignore the objects and purpose of the enactment of 1996. A bare comparison of
different provisions of the Arbitration Act of 1940 with the provisions of the
Arbitration and Conciliation Act 1996 would unequivocally indicate that 1996
Act limits intervention of Court with an arbitral process to the minimum and it
is certainly not the legislative intent that each and every order passed by an
authority under the Act would be a subject matter of judicial scrutiny of a
Court of Law. Under the new law the grounds on which an award of an arbitrator
could be challenged before the Court have been severely cut down and such
challenge is now permitted on the basis of invalidity of the agreement, want of
jurisdiction on the part of the arbitrator or want of proper notice to a party
of the appointment of the arbitrator or of atbitral proceedings. The powers of
the arbitrator have been amplified by insertion of specific provisions of
several matters. Obstructive tactics adopted by the parties in arbitration
proceedings are sought to be thwarted by an express provision inasmuch as if a
party knowingly keeps silent and then suddenly raises a procedural objection
will not be allowed to do so. The role of institutions in promoting and
organising arbitration has been recognised.
The
power to nominate arbitrators has been given to the Chief Justice or to an
institution or person designated by him. The time limit for making awards has
been deleted.
The
existing provisions in 1940 Act relating to arbitration through intervention of
Court, when there is no suit pending or by order of the court when there is a
suit pending, have been removed. The importance of transnational commercial
arbitration has been recognised and it has been specifically provided that even
where the arbitration is held in India, the parties to the contract would be free to designate the law
applicable to the substance of the dispute. Under the new law unless the
agreement provides otherwise, the arbitrators are required to give reasons for
the award. The award itself has now been vested with status of a decree, inasmuch
as the award itself is made executable as a decree and it will no longer be
necessary to apply to the court for a decree in terms of the award. All these
aim at achieving the sole object to resolve the dispute as expeditiously as
possible with the minimum intervention of a Court of Law so that the trade and
commerce is not affected on account of litigations before a court. When United
Nations established the Commission on International Trade Law it is on account
of the fact that the General Assembly recognised that disparities in national
laws governing international trade created obstacles to the flow of trade. The
General Assembly regarded the Commission on International Trade Law as a medium
which could play a more active role in reducing or removing the obstacles. Such
Commission, therefore, was given a mandate for progressive harmonization and
unification of the law of International Trade. With that objective when
Uncitral Model has been prepared and the Parliament in our country enacted the
Arbitration and Conciliation Act of 1996 adopting Uncitral Model, it would be
appropriate to bear the said objective in mind while interpreting any provision
of the Act. The Statement of Objects and Reasons of the Act clearly enunciates
that the main objective of the legislation was to minimise the supervisory role
of Courts in the arbitral process. If a comparison is made between the language
of Section 11 of the Act and Article 11 of the Model Law it would be apparent
that the Act has designated the Chief Justice of a High Court in cases of
domestic arbitration and the Chief Justice of India in cases of international
commercial arbitration, to be the authority to perform the function of
appointment of arbitrator whereas under the Model Law the said power has been
vested with the Court. When the matter is placed before the Chief Justice or
his nominee under Section 11 of the Act it is imperative for the said Chief
Justice or his nominee to bear in mind the legislative intent that the arbitral
process should be set in motion without any delay whatsoever and all
contentious issues are left to be raised before the arbitral tribunal itself.
At that stage it would not be appropriate for the Chief Justice or his nominee
to entertain any contentious issue between the parties and decide the same. A
bare reading of Sections 13 and 16 of the Act makes it crystal clear that
questions with regard to the qualifications, independence and impartiality of
the arbitrator, and in respect of the jurisdiction of the arbitrator could be
raised before the arbitrator who would decide the same. Section 13(1) provides
that party would be free to agree on a procedure for challenging an arbitrator.
Sub-section
(2) of said Section provides that failing any such agreement, a party intending
to challenge an arbitrator, either on grounds of independence or impartiality
or on the grounds of lack of requisite qualifications, shall within 15 days of
becoming aware of the constitution of the Tribunal send a written statement for
the challenge to the Tribunal itself. Section 13(3) provides that unless the
arbitrator withdraws or the other party agrees to the challenge, the Tribunal
shall decide on the challenge itself. Sub-section (4) of Section 13 mandates an
arbitrator to continue the arbitral proceedings and to make an award. Section
16 empowers the arbitral tribunal to rule on its own as well as on objections
with respect to the existence or validity of the arbitration agreement.
Conferment of such power on the arbitrator under 1996 Act indicates the intention
of the legislature and its anxiety to see that the arbitral process is set in
motion.
This
being the legislative intent, it would be proper for the Chief Justice or his
nominee just to appoint an arbitrator without wasting any time or without entertaining
any contentious issues at that stage, by a party objecting to the appointment
of an arbitrator. If this approach is adhered to, then there would be no
grievance of any party and in the arbitral proceeding, it would be open to
raise any objection, as provided under the Act. But certain contingencies may
arise where the Chief Justice or his nominee refuses to make an appointment of
an arbitrator and in such a case a party seeking appointment of arbitrator
cannot be said to be without any remedy. Bearing in mind the purpose of
legislation, the language used in Section 11(6) conferring power on the Chief
Justice or his nominee to appoint an arbitrator, the curtailment of the powers
of the Court in the matter of interference, the expanding jurisdiction of the
arbitrator in course of the arbitral proceeding, and above all the main
objective, namely, the confidence of the international market for speedy
disposal of their disputes, the character and status of an order appointing
arbitrator by the Chief Justice or his nominee under Section 11(6) has to be
decided upon. If it is held that an order under Section 11(6) is a judicial or
quasi-judicial order then the said order would be amenable for judicial
intervention and any reluctant party may frustrate the entire purpose of the
Act by adopting dilatory tactics in approaching a court of law even against an
order of appointment of an arbitrator. Such an interpretation has to be avoided
in order to achieve the basic objective for which the country has enacted the
Act of 1996 adopting Uncitral Model. If on the other hand, it is held that the
order passed by the Chief Justice under Section 11(6) is administrative in
nature, then in such an event in a case where the learned Chief Justice or his
nominee refuses erroneously to make an appointment then an intervention could
be possible by a court in the same way as an intervention is possible against
an administrative order of the executive. In other words, it would be a case of
non- performance of the duty by the Chief Justice or his nominee, and
therefore, a mandamus would lie. If such an interpretation is given with regard
to the character of the order that has been passed under Section 11(6) then in
the event an order of refusal is passed under Section 11(6) it could be
remedied by issuance of a mandamus. We are persuaded to accept the second
alternative inasmuch as in such an event there would not be inordinate delay in
setting the arbitral process in motion. But, as has been explained earlier in
the earlier part of this judgment, the duty of the Chief Justice or his nominee
being to set the arbitral process in motion it is expected that invariably the
Chief Justice or his nominee would make an appointment of arbitrator so that
the arbitral proceeding would start as expeditiously as possible and the
dispute itself could be resolved and the objective of the Act can be achieved.
In fact a Bench of this Court in Sundaram Finance case (supra) while
considering the scope of Section 9 of the Act has approached the problem from
this perspective and incidental observation has been made that Section 11 does
not require the Court to pass a judicial order appointing arbitrator.
The
nature and function performed by the Chief Justice or his nominee under sub-
section (6) of Section 11 being essentially to aid the constitution of the
arbitral tribunal cannot be held to be a judicial function as otherwise the
legislature could have used the expression court or judicial authority instead
of choosing the expression the Chief Justice or his nominee. If a comparison is
made with the English Arbitration Act 1996 it would appear that under the
English Act it is the Court which has been vested with the function of
appointment of an arbitrator upon failure of the agreed appointment procedure and
an order made by the Court becomes appealable under Section 11(5) whereas under
the Arbitration and Conciliation Act of 1996 in India the power of appointment
is vested with the Chief Justice or his nominee.
An
analysis of different sub-sections of Section 11 would indicate the character
of the order, which the Chief Justice or his nominee passes under Sub-section
(6) of Section 11. Sub-section (3) and sub-section (4) deals with cases, in
which a party fails to appoint an arbitrator or the arbitrators fail to agree
on the third arbitrator and thus seeks to avoid frustration or unreasonable
delay in the matter of constitution of the arbitral tribunal. It authorises the
Chief Justice of India or the Chief Justice of a High Court concerned, or any
person or institution designated by him to make the appointment upon request of
a party, if the other party has failed to appoint an arbitrator within thirty
days from the receipt of a request to that end. Sub-sections 4, 5 and 6
designedly use the expression Chief Justice in preference to a Court or other
authority as in paragraphs (3) and (4) of Article 11 of the Model Law,
obviously for the reason that the Chief Justice acting in his administrative
capacity, is expected to act quickly without encroaching on the requirements
that only competent persons are appointed as arbitrators. Sub-section (4) does
not lay down any time limit within which the Chief Justice or his nominee,
designated by him, has to make the appointment. It however expects that these
functionaries would act promptly. While sub-sections (4) and (5) deal with
removal of obstacles arising in the absence of agreement between the parties on
a procedure for appointing the arbitrator or arbitrators, sub- section (6)
seeks to remove obstacles arising when there is an agreed appointment
procedure. These obstacles are identified in Clauses (a), (b) and (c) of
sub-section(6). Sub- section(6) provides a cure to these problems by permitting
the aggrieved party to request the Chief Justice or any person or institution
designated by him to take the necessary measure i.e. to make the appointment,
unless the agreement on the appointment procedure provides other means for
securing the appointment. Sub-section(6), therefore, aims at removing any
dead-lock or undue delay in the appointment process.
This
being the position, it is reasonable to hold that while discharging the
functions under sub-section(6), the Chief Justice or his nominee will be acting
in his administrative capacity and such a construction would subserve the very
object of the new Arbitration Law.
The
nature of the function performed by the Chief Justice being essentially to aid
the Constitution of the Arbitration Tribunal immediately and the legislature
having consciously chosen to confer the power on the Chief Justice and not a
Court, it is apparent that the order passed by the Chief Justice or his nominee
is an administrative order, as has been held by this Court in Ador Samias case
and the observations of this Court in Sundaram Finance Ltd. case also is quite
appropriate and neither of those decisions require any re-consideration. This
being the position even an order refusing to appoint an arbitrator will not be
amenable to the jurisdiction of this Court under Article 136 of the
Constitution. Needless to mention such an order refusing to appoint an
arbitrator after deciding the contentious issues would be an act of
non-performance of duty and in view of what has been stated earlier the
concerned authority could be directed by mandamus to perform its duty.
Having
answered the two basic questions raised, as above, let us now examine the
impugned orders in the different cases, which are before us. In S.L.P.(Civil)
No.
11522-11526
of 1999, the order of the learned Chief Justice of Bombay High Court in appointing
an arbitrator is the subject matter of challenge. Since the order of
appointment passed by the learned Chief Justice, is administrative in nature
and the learned Chief Justice does not function as a Court or a tribunal, the
said order is not amenable to the jurisdiction of this Court under Article 136
of the Constitution. The special leave petitions, are accordingly dismissed.
Special
Leave Petition(Civil) No.19549/99 is directed against the order of the learned
Chief Justice of Gauhati High Court, refusing to appoint an arbitrator, after
entertaining contentious issues and deciding the said issues by elaborate
consideration, on a finding that there is no valid agreement for arbitration.
Even if, it was not open for the learned Chief Justice to entertain the
contentious issues and deciding the same, but since the ultimate order is
administrative in nature, as has been held by us and since the learned Chief
Justice does not function as a Court or Tribunal, the order, cannot be subject
to judicial scrutiny of this Court under Article 136 of the Constitution. The
aggrieved party however, has a remedy to approach the High Court for issuance
of a writ of mandamus, if so advised, in accordance with law. It is clarified
that the learned Chief Justice not having functioned as a Court or Tribunal and
the order being administrative in nature, the observations and findings are not
binding and will not be taken into consideration by the Arbitral Tribunal, if
an objection to validity or existence of Arbitration Agreement is taken before
it. Such objection, if taken, shall be decided on its own merits. The special
leave petition stands rejected.
Writ
Petition(Civil) No. 81/2000 is a petition under Article 32 of the Constitution,
against the very order of the learned Chief Justice of Gauhati High Court,
which was the subject matter of challenge in Special Leave Petition(c) No.
19549/99. We fail to understand how a petition under Article 32, at all is
entertainable against the order of the learned Chief Justice, refusing to appoint
an arbitrator under Section 11 of the Arbitration and Conciliation Act, 1996.
This petition under Article 32, accordingly stands dismissed.
Special
Leave Petition(Civil) No. 11317/99 is directed against the order of the nominee
of learned Chief Justice of Andhra Pradesh High Court, appointing an arbitrator
under Section 11(6) of the Act. The order in question being administrative in
nature and the nominee of the learned Chief Justice, not being a Court or a
Tribunal, as held by us, this special leave petition stands dismissed.
Special
Leave Petition(Civil) No. 12323 of 1999 is by the Union of India, against the
order of the nominee of the learned Chief Justice of Andhra Pradesh High Court,
appointing an arbitrator under Section 11(6) of the Act.
For the
reasons, already indicated in SLP(C) No. 11317/99, this special leave petition
stands dismissed.
Special
Leave Petition(Civil) No. 8563/99 is directed against the order of the nominee
of the learned Chief Justice of Madras High Court, appointing an arbitrator
under Section 11(6) of the Act. For the reasons, already indicated, the said
order of appointment being administrative in nature and the nominee of the
learned Chief Justice , not being a Court or a Tribunal, the order in question
is not amenable to the jurisdiction of this Court under Article 136 of the
Constitution and consequently, the special leave petition stands dismissed.
Special
Leave Petition(Civil) No. 8581/99 is directed against the order of the nominee
of the learned Chief Justice of Madras High Court, appointing an arbitrator
under Section 11(6) of the Act. For the self same reasons, indicated in SLP (C)
No. 8563/99, this special leave petition stands dismissed.
Back