Delhi Development Authority Vs. Mr. Ravindra
Mohan Aggarwal & ANR [1999] INSC 85 (19 March 1999)
Sujata
V.Manohar, R C Lahoti R.C. Lahoti, J.
A plot
bearing number 13 of site no.58 on Kalkaji Road, Delhi admeasuring 162 sq.mtrs. with two
sides open was put to auction on 5.2.1985 holding it out to be a developed plot
by Delhi Development Authority. The respondents made a bid of Rs.3,25,000/-
which was the highest. The officer conducting the sale knocked down the bid in favour
of the respondents. With the fall of hammer, the respondents deposited an
amount of Rs.81,250/- being 25 per cent of the bid amount.
The
authority competent to accept or not the bid was the Vice-Chairman of the DDA
before whom the papers were placed. It appears that a public interest litigation
was filed by a third party laying challenge to the auction complaining that the
plot was situated in green-belt and therefore could neither have been treated
as a developed plot nor put to auction for any purpose other than use as a
green-belt. The High Court had issued an ad-interim writ staying the auction.
The interim order though passed earlier was brought to the knowledge of the
Vice-Chairman, DDA after the authority had signed its approval of the bid on
the file. The authority then stayed its hands in view of the High Court's
order.
The
respondents filed a writ petition before the High Court of Delhi seeking a
direction to the DDA to conclude the auction sale proceedings and handover
possession of the plot to the respondents. The High Court found that the plot
being situated in the green-belt, could not have been put to auction at all.
The High Court by its order dated 1.8.1991 refused to grant any relief to the
respondents so far as plot number 13 is concerned. However, it held that the
respondents could not be faulted for having made a bid at the auction and
inasmuch as an expectation has been built up in their favour of having a plot
in face of acute shortage of land in Delhi, the DDA was directed to give a plot
to the respondents of equivalent measurement at the same price in the same area
adjoining the area in question, i.e., Kalkaji within a period of two months
from the date of the order.
Aggrieved
by the abovesaid direction of the High Court, the DDA has filed this petition
for special leave to appeal before this Court. Leave granted. The facts
relevant and material for the disposal of this appeal are :-
(i)
that the plot on
the date of the auction was situated within the green-belt and hence could not
have been put to auction by the DDA;
(ii)
that the sale
was not finalised inasmuch as the same was stayed by the High Court in a public
interest litigation;
(iii)
that the
authority competent to accept the bid recorded its acceptance at a point of
time when the High Court had already stayed the same though the order of the
High court was not till that point of time brought to the notice of the
authority;
(iv)
that the
acceptance of the bid was never communicated by the DDA to the respondents;
(v)
that the
tendered amount was 25 per cent only of the bid amount. The balance 75 per cent
was yet to be paid by the respondents to the petitioner; and
(vi)
that it was only
in the year 1994 that the zonal plan was modified to alter the use of the plot
to residential purpose.
It is
submitted by the learned counsel for the appellant that the auction never
achieved a finality. No right much less a vested right had accrued in favour of
the respondents. The High Court was therefore not justified in directing an
alternate plot to be given to the respondents.
On the
other hand, it is submitted by the learned counsel for the respondents that a
bid having been finalised and also accepted by the competent authority, a right
had accrued in favour of the respondents. In the year 1994 the disability
attached with the plot has ceased to exist and therefore on the doctrine of
feeding the grant by estoppel enunciated in Section 43 of the Transfer of
Property Act, the DDA should be compelled to finalise the sale and deliver
possession over the plot to the respondents. Alternatively, the DDA must
compensate the respondents by allotting an alternate plot as directed by the
High Court and they should not be made to suffer for no fault of theirs. The
learned counsel for the respondents insisted that both in law and equity the
respondents are entitled to some relief.
Having
heard the learned counsel for the parties, we are of the opinion that there is
merit in the appeal and the same deserves to be allowed. On the date of the
auction the plot being in the green-belt, could not and should not have been
put to auction. There is no estoppel against statute and when the
considerations of public interest are involved.
The
acceptance of the bid recorded by the Vice-Chairman, DDA on the file was bad
for two reasons. Firstly, it was so recorded after the passing of the interim
order of stay by the High Court though it was in the process of being
communicated. Secondly, the acceptance was not communicated by the DDA to the
respondents and therefore the acceptance was not complete. Merely because the
respondents gathered knowledge of the acceptance having been recorded on the
file would not make any difference. Reliance on Section 43 of the Transfer of
Property Act is entirely misconceived inasmuch as there was no transfer or
grant ever made by the DDA in favour of the respondents. Acceptance of bid at a
public auction and deposit of 25% of bid amount do not constitute a transfer of
property. The respondents have no basis in law to support their claim. Even the
equitable considerations would not justify a public authority like DDA being
directed today to provide an alternate plot to the respondents in the same
locality and at the same price after a lapse of 14 years from the date of the
auction.
We may
place on record that according to the appellant, the auction having been stayed
by the High Court, the amount of Rs.81,250/- was sent by cheque to respondents,
but they did not accept the same. The amount has remained with the DDA for all
these 14 years.
The
appeal is allowed, the impugned order of the High Court directing the DDA to
allot an alternate plot to the respondents is set aside. The writ petition
filed by the respondents is directed to be dismissed. However, in the facts and
circumstances of this case the amount of Rs.81,250/- which has remained with
the DDA is directed to be returned to the respondents with interest calculated
at the rate of 9 per cent per annum from 5.2.1985 till the date of return. No
order as to the costs.
Back