M/S.
Lokmat Newspapers Pvt. Ltd. Vs. Shankarprasad [1999] INSC 222 (19 July 1999)
S.B.Majumdar,
Syed Shah Mohammed Quadri S.B.Majmudar, J.
Leave
granted.
L.I.T.A
We have heard learned counsel for the parties finally in this appeal. It is
being disposed of by this judgment.
The
question involved in this appeal at the instance of the appellant-management
pertains to the legality and validity of the discharge of the
respondent-employee and also calls for the decision as to whether the said
discharge order amounted to `unfair labour practice' on the part of the
management. A few relevant facts are required to be noted at the outset.
Introductory facts: The respondent was working in the composing department of
the appellant at Nagpur in Maharashtra State when his services were terminated.
He was a foreman in the composing department of the appellant. The appellant is
a company engaged in the publication of a Marathi daily named `Lokmat'. The
appellant has its registered office at Nagpur and Lokmat is being published therefrom. In the year 1976, the
appellant-company decided to start publication of Jalgaon Edition of the said
paper and for that purpose set up an establishment at Jalgaon in the eastern
district of Maharashtra State. The Jalgaon Edition was composed and printed at Nagpur and was taken to Jalgaon. The
composing of both the Editions was done by hand composing and printing was done
on rotary printing machine. In 1978, the appellant decided to have composed and
printed part of the Jalgaon Edition at Jalgaon. Since then the Jalgaon Edition
was composed and printed partly at Jalgaon and partly at Nagpur.
Then
in 1981, the appellant installed two photo type composing machines at Nagpur. According to the appellant, it was
a new technique of rationalisation, standardisation and improvement of plant or
technique. It appears that the said machine was operated on experimental basis
for sometime but by October 1981 it became fully operative.
Consequently,
the respondent along with 24 other employees, who were working in the hand
composing department became redundant. Therefore, they were sought to be
transferred to Jalgaon District in the State of Maharashtra where another establishment of the appellant was located.
The said orders of transfer were challenged by the respodent and other
employees before the Industrial
Court under the
provisions of The Maharashtra [Recognition of Trade Unions & Prevention of
Unfair Labour Practices] Act, 1971 (hereinafter referred to as `the Maharashtra
Act'). The Industrial
Court, after hearing
the parties, took the view that the said transfer orders amounted to change in
the conditions of service of the complainants which resulted into `unfair
labour practice' on the part of the appellant. The said decision of the Industrial Court was rendered on 12th February, 1982.
The
order of the Industrial
Court was challenged
by the appellant before the High Court by filing Writ Petition No.
630/82.
It appears that subsequently the said Writ Petition was withdrawn.
Consequently, the order of the Industrial Tribunal calling upon the appellant
to withdraw the illegal transfers of the respondent and others remained a final
order. Having realised that the respondent and other workmen could not be transferred
out of Nagpur even though they had become surplus on account of introduction of
the aforesaid photo composing machine, the appellant issued a notice on 25th
March, 1982 under Section 9-A of the Industrial Disputes Act, 1947 (for short
the `I.D. Act') to the respondent inter alia, stating that as a result of the
installation of photo composing machine, there was no work available with the
appellant so as to provide the same to the respondent and other employees.
The
respondent and other employees opposed the said notice and consequently the
Conciliation Officer held conciliation proceedings under Section 12 of the I.D.
Act.
Parties
were heard and efforts were made in conciliation to enable them to amicably
settle the dispute but those proceedings ultimately failed. The Conciliation
Officer closed the proceedings on 22.6.1982 and subsequently sent failure
report to the State Government. The said report reached the State Government on
13th August, 1982. In the meantime, once the
conciliation proceedings were closed, the appellant issued the impugned
discharge order dated 22nd
June,1982 terminating
the services of the respondent. As a consequence thereof, the services of the
respondent and other employees were terminated by following the provisions of
Section 25-F of the I.D. Act.
Immediately
after the discharge order was served on the respondent, he filed a complaint on
25.6.1982 before the Labour Court under Section 28 of the Maharashtra Act
alleging that the respondent indulged in `unfair labour practice' which falls
within the provisions of Schedule -IV item no. 1 (a), (b), (d) and (f) of the
Maharashtra Act.
The
appellant resisted the said proceedings and contended that it has not resorted
to any `unfair labour practice' against the respondent. During the pendency of
this complaint, the State Government, acting on the failure report of the
Conciliation Officer, made a reference of the Industrial dispute under Section
10 of the I.D. Act. The appellant raised an objection before the Industrial Court, Nagpur, that the reference proceedings under Section 10 of the
I.D. Act were incompetent and barred by Section 59 of the Maharashtra Act. As
the respondent had already filed complaint under the Maharashtra Act
challenging the very same discharge order, these objections were upheld by the Industrial Court, Nagpur and reference under Section 10 of the I.D. Act was disposed
of.
The
complaint filed by the respondent was dismissed by the Labour Court by its order dated 30.1.1990. It
was held that the impugned retrenchment order did not attract any of the
provisions of Schedule IV, item no.1 of the Maharashtra Act and that the
respondent was not guilty of any `unfair labour practice' when it passed the
impugned retrenchment order against the respondent.
The
respondent filed a Revision Petition before the Industrial Tribunal, Nagpur. The said Revision Petition was
dismissed by the Tribunal on 22nd November, 1990 upholding the findings of the Labour Court that the respondent had not engaged in any `unfair labour
practice'.
The
respondent then filed Writ Petition No. 70 of 1991 under Articles 226 and 227
of the Constitution of India challenging the decision rendered by both the
Courts below.
The
said Writ Petition was also rejected by the learned Single Judge on 25th April, 1991. Respondent thereafter preferred
Letters Patent Appeal No. 24 of 1991 before the Division Bench of the High
Court at Nagpur under Clause 15 of the Letters
Patent. The said appeal was heard by the Division Bench on merits. The Division
Bench, by its orders dated 6.11.1996, held that the appellant had engaged in
`unfair labour practice' under item 1 (a), (b), (d) and (f) of Schedule IV of
the Maharashtra Act and hence it was directed to pay back-wages and other
benefits to the respondent from the date of the order of retrenchment i.e. 22.6.1982
till the date of his retirement as he had also got superannuated in the
meantime. This order of the Division Bench of the High Court has been brought
in challenge by the appellant- management by way of present appeal on special
leave under Article 136 of the Constitution of India.
Learned
counsel appearing for the appellant, at the outset, submitted that the Writ
Petition filed by the respondent before the High Court was in substance under
Article 227 of the Constitution of India and hence was not maintainable under
Clause 15 of the Letters Patent Appeal.
In
order to support this contention, he took us to the relevant averments in the
Writ Petition as well as the order of the learned Single Judge. He also relied
on judgments of this Court to which we will refer hereinafter. His submission
was that the learned Single Judge had exercised his jurisdiction under Article
227 of the Constitution only and, therefore, the Letters Patent Appeal was not
maintainable. On merits, it was submitted that even if the appeal was
maintainable the Division Bench had patently erred in taking the view that
notice under Section 9-A of the I.D. Act was illegal and inoperative. It was
also contended that the decision of the Division Bench that respondent's
complaint was maintainable and that by passing the impugned order of the
retrenchment, the appellant had resorted to `unfair labour practice', was
erroneous. It was further submitted that the Division Bench had erred in
holding that the impugned discharge order was violative of Section 33 of the
I.D. Act and that in any case pure finding of fact of courts below that the
appellant was not guilty of any `unfair labour practice' ought not to have been
interfered with by the Division Bench in the Letters Patent Appeal.
On the
other hand, learned counsel for the respondent tried to support the decision
rendered by the Division Bench of the High Court on the points on which the
Bench decided in favour of the respondent. He also submitted that the appeal
under Clause 15 of the Letters Patent was maintainable before the Division
Bench.
Learned
Counsel for the respondent invited our attention to a number of decisions of
this Court in support of the respondent's case on merits. We shall refer to
them in latter part of this judgment when we shall consider these contentions
on merits.
In the
light of the aforesaid rival contentions, the following points arise for our
consideration : 1. Whether the respondent's Letters Patent Appeal was
maintainable; 2.
If
yes, whether the Division Bench was right in taking the view that the impugned
retrenchment order was violative of Section 33 (1) of the I.D. Act; 3. Whether
the appellant, in issuing the said order, had violated the provisions of
Section 9-A of the I.D. Act; 4. Whether the impugned retrenchment order
amounted to the commission of `unfair labour practice' by the appellant as per
Schedule IV items 1 (a), (b), (d) and (f) of the Maharashtra Act; 5. Whether
the Division Bench was justified in interfering with the findings of fact
arrived at by the authorities below and as confirmed by the learned Single
Judge while deciding the aforesaid question of `unfair labour practice'; and 6.
What
final order ? We shall deal with these points seriatim. Point No.1: So far as
the question of maintainability of Letters Patent appeal is concerned, it has
to be noted that the Revisional Order was passed by the Labour Court on respondent's complaint under
Section 28 of the Maharashtra Act. The said order was confirmed by the Industrial
Tribunal under Section 44 of the same Act. Both the courts held that
retrenchment of the respondent does not amount to any `unfair labour practice'
on the part of the appellant. These orders were challenged by the respondent by
filing Writ Petition under Articles 226 and 227 of the Constitution of India
before the High Court of Judicature at Bombay, Nagpur Bench. The learned Single Judge dismissed the said Writ
Petition, but his order itself shows that he was considering the Writ Petition
of the respondent which was moved before him invoking the High Court's
Jurisdiction under Articles 226 and 227 of the Constitution of India. In the
said Writ Petition under Articles 226 and 227 of the Constitution, the
respondent requested the High Court to call for the record and proceedings of
Revision Petition No. 70 of 1990 and after perusal thereof to be further
pleased to quash and set aside the Order dated 30.1.1990 passed by the Second
Labour Court, Nagpur in Complaint No. 262 of 1982 and order dated 20.11.1990
passed in Revision by the Industrial Court.
When
we turn to the relevant paragraph of the Writ Petition, we find averments to
the effect that the Courts below, while interpreting the provisions contained
in Sections 9-A, 20 and 33 and other provisions of the I.D. Act, 1947 and the
rules framed thereunder, had totally lost sight of the object and purpose of
these provisions and had put an interpretation alien to industrial
jurisprudence and had thus committed serious error of law apparent on the face
of the record which resulted in serious miscarriage of justice and also in
failure to exercise the jurisdiction vested in the courts below under the
provisions of the Maharashtra Act. In para 9 of the Writ Petition, it was
averred that the impugned orders of the Courts below had further resulted in
infraction of his fundamental rights guaranteed to him under Articles 14, 21
and other Articles as enshrined in the Constitution of India.
It is,
therefore, obvious that the Writ Petition invoking jurisdiction of the High
Court both under Articles 226 and 227 of the Constitution had tried to make out
a case for High Court's interference seeking issuance of an appropriate Writ of
Certiorari under Article 226 of the Constitution of India. Basic averments for
invoking such jurisdiction were already pleaded in the Writ Petition for High
Court's consideration. It is true, as submitted by learned counsel for the
appellant, that the order of the learned Single Judge nowhere stated that the
Court was considering the Writ Petition under Article 226 of the Constitution
of India. It is equally true that the learned Single Judge dismissed the Writ
Petition by observing that the Courts below had appreciated the contentions and
rejected the complaint. But the said observation of the learned Single Judge
did not necessarily mean that the learned Judge did not inclined to interfere
under article 227 of the Constitution of India only. The said observation
equally supports the conclusion that the learned Judge was not inclined to interfere
under Articles 226 and 227. As seen earlier, that he was considering the
aforesaid Writ Petition moved under Articles 226 as well as 227 of the
Constitution of India. Under these circumstances, it is not possible to agree
with the contention of learned counsel for the appellant that the learned
Single Judge had refused to interfere only under Article 227 of the
Constitution of India when he dismissed the Writ Petition of the respondent.
In
this connection, it is profitable to have a look at the decision of this Court
in the case of Umaji Keshao Meshram and Others vs. Radhikabai, widow of
Anandrao Banapurkar and Anr., [(1986) Supp SCC 401]. In that case O.Chinnappa
Reddy and D.P.Madon, JJ., considered the very same question in the light of
clause 15 of the Letters Patent Appeal of the Bombay High Court. Madon J.,
speaking for the Court in para 107 of the Report at page 473, made the
following pertinent observations :
"Petitions
are at times filed both under Articles 226 and 227 of the Constitution. The case
of Hari Vishnu Kamath v. Syed Ahmad Ishaque before this Court was of such a
type. Rule 18 provides that where such petitions are filed against orders of
the tribunals or authorities specified in Rule 18 of Chapter XVII of the
Appellate Side Rules or against decrees or orders of courts specified in that
rule, they shall be heard and finally disposed of by a Single Judge.
The
question is whether an appeal would lie from the decision of the Single Judge
in such a case. In our opinion, where the facts justify a party in filing an
application either under Article 226 or 227 of the Constitution, and the party
chooses to file his application under both these articles, in fairness and
justice to such party and in order not to deprive him of the valuable right of
appeal the court ought to treat the application as being made under Article
226, and if in deciding the matter, in the final order the court gives
ancillary directions which may pertain to Article 227, this ought not to be
held to deprive a party of the right of appeal under Clause 15 of the Letters
Patent where the substantial part of the order sought to be appealed against is
under Article 226. Such was the view taken by the Allahabad High court in Aidal
Singh v. Karan Singh and by the Punjab High Court in Raj Kishan Jain v. Tulsi
Dass and Barham Dutt v. Peoples' Co-operative Transport Society Ltd., New Delhi and we are in agreement with
it." The aforesaid decision squarely gets attracted on the facts of the
present case. It was open to the respondent to invoke jurisdiction of the High
Court both under Articles 226 and 227 of the Constitution of India. Once such
jurisdiction was invoked and when his Writ Petition was dismissed on merits, it
cannot be said that the learned Single Judge had exercised his jurisdiction
only under Article 226 of the Constitution of India. This conclusion directly
flows from the relevant averments made in the Writ Petition and the nature of
jurisdiction invoked by the respondent as noted by the learned Single Judge in
his Judgment, as seen earlier. Consequently, it could not be said that Clause
15 of the Letters Patent was not attracted for preferring appeal against the
judgment of learned Single Judge. It is also necessary to note that the
appellant being respondent in Letters Patent Appeal joined issues on merits and
did not take up the contention that Letters Patent Appeal was not maintainable.
For all these reasons, therefore, the primary objection to the maintainability
of the Letters Patent Appeal as canvassed by learned counsel for the appellant,
has to be repelled. Point no.1 is, therefore, answered in affirmative against
the appellant and in favour of the respondent. It takes us to the consideration
of points arising for our decision on merits.
Point
No.2: The question of violation of Section 33(1) of the I.D. Act requires to be
considered in the light of the relevant statutory provisions. Section 33 as
found in Chapter VII of the I.D. Act, sub-section (1) thereof, which is
relevant for our present discussion, reads as under : "33. Conditions of
service, etc., to remain unchanged under certain circumstances during pendency
of proceedings.- (1) During the pendency of any conciliation proceeding before
[an arbitrator or] a conciliation officer or a Board or of any proceeding before
a Labour Court or Tribunal or National Tribunal in respect of an industrial
dispute, no employer shall,- (a) in regard to any matter connected with the
dispute, alter, to the prejudice of the workmen concerned in such dispute, the
conditions of service applicable to them immediately before the commencement of
such proceeding; or (b) for any misconduct connected with the dispute,
discharge or punish, whether by dismissal or otherwise, any workman concerned
in such dispute;
save
with the express permission in writing of the authority before which the
proceeding is pending." Now it must be stated that the impugned
termination order was passed against the respondent-workman on 22nd June, 1982. Within three days thereof, the
respondent raised an industrial dispute by filing a complaint under Section 28
of the Maharashtra Act alleging that the impugned termination order amounted to
`unfair labour practice'.
Before
the impugned termination order was passed by the management, it had already
served a notice under Section 9-A of the I.D. Act to the respondents union to
the effect that it proposed to introduce a change in the conditions of service
of the respondent and other members of the union on the ground that it was
proposing to rationalise the printing work at the appellant's concern at Nagpur
by setting up photo-type machine for carrying out the work of composing,
resulting in substantial reduction in the work of composing by hand. It may be
stated that the respondent was employed as a foreman in the hand-composing
department of the appellant at the relevant time. The respondent's union
objected to the said notice of change and approached the Conciliation Officer
under Section 12(1) of the I.D. Act which reads as under :- "12. Duties of
Conciliation Officers.- (1) Where an industrial dispute exists or is
apprehended, the conciliation officer may, or where the dispute relates to a
public utility service and a notice under Section 22 has been given shall, hold
conciliation proceedings in the prescribed manner." The Conciliation
Officer took the dispute in conciliation within his discretion even though as
appellant's concern was not a public utility service it was not mandatory for
the Conciliation Officer to start conciliation proceedings. As the report of
the Conciliation Officer submitted to the State Government shows, he invited
the management and the respondent's union for preliminary discussions on
14.4.1982 in his office and thereafter the matter was adjourned during
conciliation from time to time.
It
can, therefore, be said that by 14th April, 1982 the matter was taken up for investigation and thus the
conciliation proceedings had commenced. It is also well established on the
record of the case that the parties could not come to any settlement with the
result that on 22nd
June, 1982 the
investigation was closed by the Conciliation Officer at 4.35 p.m. at Nagpur.
Immediately thereafter the appellant passed the impugned order of termination
against the respondent and others on the very same day i.e. on 22.6.1982 at 5.00 p.m. The said order was placed on the notice board of the
appellant's office at Nagpur on the evening of that day. It is
not in dispute between the parties that thereafter the Conciliation Officer
submitted his report to the Government which reached the State Government on
13.8.1982.
On the
aforesaid facts, the question arises whether the impugned termination order
dated 22.6.1982 was passed during the pendency of the conciliation proceedings.
It is not in dispute between the parties that before passing such an order no
express permission in writing was obtained by the appellant from the
Conciliation Officer. The Labour Court, the Industrial Court and the learned
Single Judge of the High Court have taken the view that because investigation
was closed by the conciliator by 4.35 p.m. on 22.6.1982, immediately thereafter
the conciliation proceedings could be said to have ended and were not pending
before him. Consequently at 5.00 p.m. on
that very day when the appellant issued the impugned order, it did not violate
Section 33 of the I.D. Act. While, on the other hand, the Division Bench of the
High Court in the impugned judgment has taken the view that merely because the
conciliator closed the investigation in the evening of 22.6.1982 till he
prepared his report as per Section 12(4) of the I.D. Act and till that report
reached the Government, conciliation proceedings were deemed to have continued
and had not got terminated till 13th August, 1982 and as in the meantime on
22.6.1982, the impugned termination order was passed without following the
procedure of Section 33(1) of the I.D. Act it got vitiated in law.
Under
these circumstances, a moot question arises whether the impugned retrenchment
order was passed on 22.6.1982 during the pendency of conciliation proceedings.
It
cannot be disputed that the impugned order was directly connected with the
matter in dispute before the Conciliation Officer wherein the question of
legality of notice under Section 9-A of the I.D. Act was under consideration
for the purpose of arriving at any settlement between the parties in this
connection. The impugned order had definitely altered to the prejudice of the
respondent his conditions of service. It was not a case of retrenchment
simpliciter but was a consequential retrenchment on the introduction of the
scheme of rationalisation as contemplated by Section 9-A read with Schedule IV
item no.1 of the I.D. Act.
We
shall refer to these provisions in greater detail later on while considering
the question of legality of notice under Section 9-A of the I.D. Act. For the
time being, it is sufficient to note that the question of violation of Section
33(1) of the I.D. Act has a direct nexus with the further question whether on
22.6.1982 when the impugned termination order was passed, conciliation
proceedings were pending before the authority or not.
In
order to answer these questions, it is necessary to note sub- section (4) of
Section 12 of the I.D. Act which reads as under : "(4) If no such
settlement is arrived at, the conciliation officer shall, as soon as
practicable after the close of the investigation, send to the appropriate
Government a full report setting forth the steps taken by him for ascertaining
the facts and circumstances relating to the dispute and for bringing about a settlement
thereof, together with a full statement of such facts and circumstances, and
the reasons on account of which, in his opinion, a settlement could not be
arrived at." A mere look at this provision shows that if the Conciliation
Officer finds during conciliation proceedings that no settlement is arrived at
between the disputing parties, then after closing the investigation he has, as
soon as practicable, to send to the appropriate Government a full report
setting forth the steps taken by him for ascertaining the facts and
circumstances relating to the dispute and has also to mention all other details
as required to be mentioned in the report under Section 12(4) of the I.D.Act.
The
aforesaid statutory requirements leave no room for doubt that after closing the
investigation and after having arrived at the conclusion that no settlement is
possible between the parties, the Conciliation Officer has to spend some more
time before submitting his detailed written report about failure of
consideration for information and necessary action by the State Government. In
the very nature of things, therefore, such requirement will take at least a
couple of days, if not more, for the conciliator after closing the
investigation to enable him to send an appropriate report to the State
Government. It is, therefore, obvious that on 22.6.1982 when by 4.35 p.m.
the
Conciliation Officer declared that settlement was not possible between the
parties and he closed the investigation, neither his statutory function did not
come to an end nor did he become functus officio. His jurisdiction had to
continue till he submitted his report as per Section 12(4) to the appropriate
Government. Even such preparation of the report and sending of the same from
his end to the appropriate Government would obviously have taken at least a few
days after 22.6.1982. It must, therefore, be held that the conciliator remained
in charge of the conciliation proceedings at least for a couple of days after
22.6.1982. It is, therefore, difficult to appreciate how within half an hour
after the closing of investigation by the conciliator and before his getting
even a breathing time to prepare his detailed written report about failure of
conciliation to be sent to the Government as per Section 12(4), the appellant could
persuade itself to presume that conciliation proceedings had ended and,
therefore, it was not required to follow the procedure of Section 33(1) and
straightaway could pass the impugned order of retrenchment within 25 minutes of
the closing of the investigation by the conciliator on the very same day. It is
difficult to appreciate the reasoning of the Labour Court that after the closer of investigation the conciliator
became functus officio and the management could not have approached him for
express written permission to pass the impugned order. It is easy to visualise
that even on the same day i.e. on 22.6.1982 or even on the next day, before the
conciliator had time even to start writing his report, such an express
permission could have been asked for by the appellant as the conciliator by
then could not be said to have washed his hand off the conciliation
proceedings. He remained very much seized of these proceedings till at least
the time the report left his end apart from the further question whether
conciliation proceedings could be said to have continued till the report
reached the State Government. Thus, on the express language of Section 12(4)
the conclusion is inevitable that closer of investigation by 4.35 p.m. on 22.6.1982 did not amount to termination of
conciliation proceedings by that very time. The argument of learned counsel for
the appellant was that closer of investigation automatically amounted to
termination of conciliation proceedings. This argument proceeds on a wrong
premise that closer of investigation by the conciliator is the same as closer
of conciliation proceedings. The legislature while enacting Section 12(4) has
deliberately not used the words `closer of conciliation' but, on the contrary,
provided that after closer of investigation something more was required to be
done by the conciliator as laid down under Section 12(4) before he can be said
to have done away with conciliation proceedings earlier initiated by him. On
this conclusion alone the decision rendered by the Division Bench of the High
Court that the impugned order of termination dated 22.6.1982 was issued by the
appellant without following the procedure of Section 33(1) of the I.D. Act has
to be sustained.
But
even that apart, sub-sections (1) and (2) of Section 20 of the I.D. Act also
become relevant in this connection. They read as under :- "Commencement
and conclusion of proceedings- (1) A conciliation proceeding shall be deemed to
have commenced on the date on which a notice of strike or lock-out under Section
22 is received by the conciliation officer or on the date of the order
referring the dispute to a Board, as the case may be.
(2) A
conciliation proceeding shall be deemed to have concluded- (a) where a
settlement is arrived at, when a memorandum of the settlement is signed by the
parties to the dispute; (b) where no settlement is arrived at, when the report
of the conciliation officer is received by the appropriate Government or when
the report of the Board is published under Section 17, as the case may be ; or
(c) when a reference is made to a Court, [Labour Court, Tribunal or National
Tribunal] under Section 10 during the pendency of conciliation proceedings.
(Emphasis
supplied) A mere look at the aforesaid provisions shows that in cases of public
utility services referred to in Section 22 (2) of the I.D. Act, the
conciliation proceedings shall be deemed to have commenced on the date on which
a notice of strike or lockout under Section 22 is received by the Conciliation
Officer. That deals with commencement of mandatory conciliation proceedings as
laid down by Section 12(1) read with Section 20(1). But when we come to Section
20(2), it becomes obvious that the legislature has introduced by way of legal
fiction an irrebutable presumption as per sub-clause (b) of Section 20(2) that
when during conciliation proceedings no settlement is arrived at between the
parties, the conciliation proceedings shall be deemed to have concluded when
the failure report of the Conciliation Officer is received by the appropriate
Government. Consequently, the legislative intention becomes clear that
conciliation proceedings initiated under Section 12(1) whether of a
discretionary nature or of a mandatory nature shall be treated to have
continued and only to have concluded when the failure report reaches the
appropriate Government. As noted earlier, it is not in dispute between the
parties that after the closer of investigation on 22.6.1982 when the
conciliator sent the failure report, it reached the State Government only on
13.8.1982. Therefore, it has to be held that the conciliation proceedings in
the present case had not got terminated and got concluded only on 13.8.1982 as
per the aforesaid statutory presumption created by the legal fiction provided
in Section 20(2)(b).
Therefore,
as a necessary corollary, it must be held that these conciliation proceedings
were pending till 13.8.1982.
It is
axiomatic that conciliation proceedings which are deemed not to have concluded
must be deemed to have continued or remained pending. That which is not
concluded is pending, equally that which is pending cannot be said to be
concluded.
Learned
counsel for the appellant tried to salvage the situation by submitting that the
deeming fiction created by Section 20(2) of the I.D. Act referred to only deemed
conclusion of the proceedings, but had nothing to do with the pendency of the
proceedings. To highlight this submission, he invited our attention to Section
22(1)(d) and Section 22(2)(d) as well as Section 23(b) of the I.D. Act.
We
fail to appreciate how these provisions can be of any avail to him. Section
22(1)(d) reads as under:
"during
the pendency of any conciliation proceedings before a conciliation officer and
seven days after the conclusion of such proceedings." Similar is the
wording of Section 22(2)(d). Section 23(b) contains similar phrase in
connection with pending proceedings before the Labour Court or the Tribunal. All these provisions show that even after
the pending proceedings are concluded for further period of time no strikes or
lock- outs can be permitted to take place between the parties. But the said
provisions do not indicate that pendency of proceedings is a concept which is
different from the conclusion of such proceedings. On the contrary, the
conclusion of proceedings puts an end to the pendency of such proceedings.
Learned counsel for the appellant in support of his contention seeking a
dichotomy between the concept of pendency and concept of deemed conclusion of
proceedings placed strong reliance on a decision of this Court in Chemicals
& Fibres of India Ltd. vs. D.G. Bhoir & Ors. [(1975) (4) SCC 332]. In
that case this Court was concerned with entirely a different situation under
Section 2A of the I.D. Act after it was brought on the Statute Book. As per
this provision, an individual dispute raised by workman who had suffered
dismissal from service was to be considered as an `industrial dispute' within
the meaning of the relevant provisions of the Act so that such a dispute could
be conciliated upon, arbitrated or could be referred for adjudication before
competent authorities under the Act.
For
that limited purpose, an individual workman could be said to have raised an
industrial dispute. The question before this Court was whether raising of such
a dispute by an individual workman which was not sponsored by a large body of
workmen could attract Section 33 of the I.D. Act even qua other workmen who had
nothing to do with this individual dispute. Answering the question in negative,
it was held by this Court that the fiction created by Section 2A had a limited
effect and could not be pressed in service for applicability of Section 33(1)
in connection with lock-out qua other workmen who were not the parties to the
said industrial dispute. In that case during the pendency of such individual
dispute the appellant company before this Court discharged about 312 of its
employees and filed 12 applications before the Industrial Tribunal for approval
of such a discharge on the ground that a reference was pending before it. The
question was whether these applications were maintainable for approval under
Section 33(1) when the dispute which was pending before the Industrial Tribunal
was one under Section 2A of the I.D. Act. In this connection, it was held by
this Court that the legal fiction created by Section 2A had a limited effect
and those workmen who were not parties to such a dispute, if had gone on
strike, it could not be said that their strike was necessarily illegal.
In
para-5 of the report, it was observed that:
"..While
there is justification for preventing a strike when a dispute between the
employer and the general body of workmen is pending adjudication or resolution,
it would be too much to expect that the Legislature intended that a lid should
be put on all strikes just because the case of a single workman was
pending.." We fail to appreciate how this decision can be pressed in
service by learned counsel for the appellant while construing Section 20(2) of
the I.D. Act. That Section, as noted earlier, has created an irrebutable presumption
by way of legal fiction and that presumption covers the very question as to
when conciliation proceedings once commenced can be said to have concluded. In
other words, when they can be said to have not remained in pending. As seen
earlier, the legal fiction which is created for that purpose by Section 20(2)
has to be given its full effect. As it is well- settled while giving effect to
the legal fiction for the purpose for which it is created by Legislature it has
to be given full play for fructifying the said legislative intention. We cannot
allow our imagination to boggle on that score. It is, of course, true as laid
down by the Constitutional Bench of this Court in the case of Bengal Immunity
Co. Ltd., vs. State of Bihar and Others (AIR 1955 SC 661 at 680). Das, Actg.
C.J.
speaking
for the Court in Para 31 of the report, made the following pertinent
observations : ".Legal fictions are created only for some definite
purpose. Xxxxxx xxxxx xxxxxx a legal fiction is to be limited to the purpose
for which it was created and should not be extended beyond that legitimate
field.." However, as noted earlier, legal fiction created by Section 20(2)
is for the purpose of laying down as to till what stage conciliation
proceedings can be said to be pending and when they can be said to have
concluded. On that basis if it is held that conciliation proceedings once
validly started under Section 12(1) of the I.D. Act can by way of an
irrevocable presumption be treated to have continued till the failure report
reached the appropriate Government, during the interregnum of necessity such
conciliation proceedings have to be treated as pending before the conciliation
officer. In fact, on these aspects of the matter, we have a decision of this
Court in Andheri Marol Kurla Bus Service & Anr. vs. The State of Bombay
[AIR 1959 SC 841]. In that case a Bench of two judges of this Court had to
consider the question as to when conciliation proceedings can be said to have
concluded under the relevant provisions of this very Act. In that case during
the admitted pendency of conciliation proceedings the management had dismissed
the workman bus conductor.
However,
the submission on the part of the management was that such dismissal was after
the expiry of statutory period of 14 days within which the conciliation
proceedings once started had to be concluded and as 14 days were already over
the dismissal did not attract Section 33(1) and consequently the management
could not be penalised under Section 31(1) of the I.D. Act which lays down as
under: "Any employer who contravenes the provisions of Section 33 shall be
punishable with imprisonment for a term which may extend to six months or with
fine which may extend to one thousand rupees, or with both." In the
aforesaid factual matrix of the case, this Court in Andheri Marol Kurla Bus
Service & Anr vs. The State of Bombay, (supra) had to consider the scope of
Section 33(1) read with Section 20(2)(b). On a conjoint reading of these
relevant provisions at page 841, paragraphs 4 & 5 of the report, J.L. Kapur
J., speaking for the Court, made the following pertinent observations :
"..The provisions of sub-s. 20(2) apply to all conciliation proceedings
whether in regard to utility services or otherwise. All conciliation
proceedings under this sub-section shall be deemed to have concluded in the
case where no settlement is reached, when the report of the Conciliation
Officer is received by the appropriate Government. The conciliation proceedings
therefore do not end when the report under S.12(6) is made by the Conciliation
Officer but when that report is received by the appropriate Government. It was
contended that the conciliation proceedings should be held to terminate when
the Conciliation Officer is required under S.12(6) of the Act to submit his
report but the provisions of the Act above quoted do not support this
contention as the termination of the conciliation proceedings is deemed to take
place when the report is received by the appropriate Government. That is how
S.20(2)(b) was interpreted in Workers of the Industry Colliery Dhanbad v.
Management of the Industry Colliery, 1953 SCR 428: (AIR 1953 SC 88).
It was
next contended that on this interpretation the conciliation proceedings could
be prolonged much beyond what was contemplated by the Act and the termination
would depend upon how soon a report is received by the appropriate Government.
It is true that S.12(6) of the Act contemplates the submission of the report by
the Conciliation Officer within 14 days but that does not affect the pendency
of the conciliation proceedings and if for some reason the Conciliation Officer
delays the submission of his report his action may be reprehensible but that
will not affect the interpretation to be put on S.20(2)(b) of the Act. Section
12 lays down the duties of the Conciliation Officer. He is required to bring
about settlement between the parties and must begin his investigation without
delay and if no settlement is arrived at he is to submit his report to the
appropriate Government. No doubt S.12 contemplates that the report should be
made and the proceedings closed within a fortnight and if proceedings are not
closed but are carried on, as they were in the present case, or if the
Conciliation Officer does not make his report within 14 days he may be guilty
of a breach of duty but in law the proceedings do not automatically come to an
end after 14 days but only terminate as provided in S.20(2)(b) of the Act.
(Colliery Mazdoor Congress Asansol v. New Beerbhoom Coal Co., Ltd., 1952 Lab AC
219 (222)" The aforesaid decision, therefore, has settled the controversy
on this aspect by holding that conciliation proceedings would terminate only as
provided by Section 20(2)(b) of the Act. Meaning thereby, till the failure
report reaches the appropriate State Government, conciliation proceedings
cannot be said to have terminated.
Hence,
breach of Section 33(1) during the pendency of such proceedings could attract
penal liability of the employer under Section 31(1) of the Act. Learned counsel
for the appellant tried to submit that the aforesaid decision had not
considered the legal effect of the fiction created by Section 20(2)(b) and its
limited scope regarding deemed conclusion of the conciliation proceedings which
was different from actual pendency of the proceedings as required by Section
33(1). It is difficult to appreciate this contention for the simple reason that
the relevant provisions of the Act to which our attention was drawn by learned
counsel for the appellant for submitting that there was a difference between
pendency and conclusion of proceedings do not advance the case of the
appellant, as we have seen earlier, nor can it be said that any relevant
provisions of the Act were not noticed by the Division Bench of this Court
which decided the case referred in Andheri Marol Kurla Bus Service & Anr.
vs. The State of Bombay (supra). On the contrary, we find that the aforesaid
decision has taken a correct view on the question posed for our consideration
in the present case. In view of the aforesaid discussion, therefore, there was
no escape from the conclusion to which the Division Bench in the impugned
judgment reached that on 22.6.1982 when the order of retrenchment was passed
against the respondent, the appellant-management had committed breach of
Section 33(1) of the Act by not passing the said order after obtaining express
previous permission in writing of the Conciliation Officer before whom the
conciliation proceedings must be held to be pending in the evening of
22.6.1982. The impugned retrenchment order must be held to be illegal being
contrary to the aforesaid provision of the I.D. Act. Point No.2 is, therefore,
answered in affirmative against the appellant and in favour of the respondent.
Point No.3: So far as this point is concerned, we have to turn to Section 9- A
of the I.D. Act. The relevant provision thereof reads as under : "Notice
of change.-No employer, who proposes to effect any change in the conditions of
service applicable to any workman in respect of any matter specified in the
Fourth Schedule, shall effect such change,- (a) without giving to the workman
likely to be affected by such change a notice in the prescribed manner of the
nature of the change proposed to be effected ; or (b) within twenty-one days of
giving such notice'' A mere look at the aforesaid provision shows that if an
employer proposes to effect any change in the conditions of service applicable
to any workman in respect of any matter specified in the Fourth Schedule, such
change has to be preceded by the procedure laid down in the said section.
When
we turn to the Fourth Schedule of the I.D. Act, we find mentioned therein
various conditions of service of workmen. The said schedule with all of its
items reads as follows :
"CONDITIONS
OF SERVICE FOR CHANGE OF WHICH NOTICE IS TO BE GIVEN 1. Wages, including the
period and mode of payment;
2.
Contribution paid, or payable, by the employer to any provident fund or pension
fund or for the benefit of the workmen under any law for the time being in
force;
3. Compensatory
and other allowances;
4. Hours
of work and rest intervals;
5.
Leave with wages and holidays;
6. Starting,
alteration or discontinuance of shift working otherwise than in accordance with
standing orders;
7. Classification
by grades;
8.
Withdrawal of any customary concession or privilege or change in usage;
9. Introduction
of new rules of discipline, or alteration of existing rules except insofar as
they are provided in standing orders; 10. Rationalisation, standardisation or
improvement of plant or technique which is likely to lead to retrenchment of
workmen; 11. Any increases or reduction (other than casual) in the number of
persons employed or to be employed in any occupation or process or department
or shift [not occasioned by circumstances over which the employer has no control]"
So far as item nos.1-9 and 11 are concerned, it becomes obvious that before any
such change in conditions of service of the workmen is to be effected, as a
pre-condition for such proposed change, notice under Section 9-A has to be
issued; without complying with such a pre-condition of notice, proposed change
would not legally come into operation. We are directly concerned with item no.
10 of this Schedule. It, therefore, becomes obvious that before any
rationalisation, standardisation or improvement of plant or technique is to be
resorted to by any management if by such an exercise retrenchment of workmen is
likely to result, then before introducing such rationalisation, standardisation
or improvement of plant or technique, as the case may be, a prior notice under
Section 9-A is to be issued to the workmen who can get an opportunity to show
that they may not be retrenched because of the new scheme of rationalisation
etc. which is in the offing and can suggest ways and means available to the
management to avoid such proposed retrenchment of the workmen despite such
introduction of a new scheme. Consequently, it must be held on the very
wordings of Section 9-A read with item no.10 of Fourth Schedule "that any
management which seeks to introduce a new working pattern for its existing work
force by any future scheme of rationalisation, standardisation or improvement
of plant or technique which has a tendency to lead to future retrenchment of
workmen" has to give prior notice of proposed change. Therefore, it must
be held that notice under Section 9-A must precede the introduction of
rationalisation concerned, it cannot follow the introduction of such a
rationalisation. In the present case, it is not in dispute between the parties
that in the composing department of the appellant where the respondent was
working, composing work was earlier being done by hand i.e. manually. That was
the existing condition of service of the respondent. By substitution of that
type of work by mechanical work having resort to photo type composition through
machine, the then existing service condition of the respondent was bound to be
affected adversely.
Consequently,
before introducing such a change in the condition of service of the respondent
by installing photo type composing machine, introduction of which was directly
likely to lead to retrenchment of the respondent, a notice under Section 9-A
was a must before commissioning such a photo type machine at the work place of
the appellant. It is not in dispute between the parties that such a photo type
machine was already installed by the appellant in January 1981. Learned counsel
for the appellant seeks to contend that it was installed on an experimental
basis. Even granting that, the evidence on record clearly established that by November,
1981 because of the successful working of the photo type composing machine it
was felt by the appellant that respondent and other compositors working in the
hand composing department were rendered surplus. Of course, the appellant on
humanitarian ground tried to shift them to its another concern at Jalgaon, but
those transfer orders were held to amount to `unfair labour practice' on the
part of the appellant when the Industrial Court on the complaints of these
transferee workmen held that such transfer orders would amount to `unfair
labour practice' being illegal at law. Thus the attempt on the part of the
appellant to transfer these excess workmen from November, 1981 on the admitted
position that they had become surplus in the composition department at Nagpur
because of the successful installation and working of the photo type composing
machine at the premises, became abortive. Consequently, from November, 1981 the
installation of the photo type machine ceased to remain an experimental measure
but became a stark reality and this machine had necessarily a tendency to
displace the workmen who were earlier working in the hand composing department.
Thus,
at least from November, 1981 scheme of rationalisation had come to stay in
composing department of the appellant.
Under
these circumstances, even accepting the contention of learned counsel for the
appellant that the likelihood of the respondent and other workmen being
retrenched because of the aforesaid machine was not a realised possibility from
January, 1981 at last became a certainty from November, 1981. In fact the
Labour Court has also come to this very conclusion in paragraph 13 of its
judgment wherein the Labour Court on the admitted position on record has held
as under :
".The
management had transferred about 11 hand compositors including the complainant
to Jalgaon by order dated 4.11.81. It appears that at that time only the
management was ready to get the work of composing done exclusively by that
photo type setting machine and hence the services of hand compositors were no
longer required at Nagpur. In fact at least that time the notice of change
ought to have been given by the respondent because the services of hand
compositors were not useful and were transferred only in November 1981
obviously because the work of composing was done on the photo type setting
machines." The aforesaid finding of fact which was confirmed by the
Revisional Court as well as the learned Single Judge of the High Court leaves
no room for doubt that by 4.11.1981 the scheme of rationalisation had already
come into force and that scheme had a direct nexus and a realised possibility
of making the respondent and other workmen surplus liable to retrenchment as
surplus staff. Once that happened, it becomes obvious that there remained no
occasion thereafter for the appellant-management to resort to Section 9-A of
the Act belatedly by giving notice of change only in February, 1982. The
appellant in this connection had missed the bus. It was a futile attempt to
lock the stables after horses had bolted.
As
noted earlier, on the scheme of Section 9-A read with item 10 of the Fourth
Schedule, before introducing such a new scheme of rationalisation which had a
likelihood and a tendency to affect the existing service conditions of the workmen,
a notice under Section 9-A was required to be issued prior to the installation
of the photo composing machine. Such a notice could have been sent before
January, 1981 when such a machine was brought in the premises as an
experimental measure or at least before 4.11.1981 when the same was continued
to be installed as a confirmed necessary component of machinery for printing at
the appellant's premises at Nagpur. If such a notice was given to the
respondent - workman and other workmen similarly situated they could have
persuaded the appellant to resort to any other type of rationalisation or to
absorb them on suitable jobs in the same premises in any other department of
the appellant at Nagpur. That opportunity was never made available to the
respondent. Therefore, notice under Section 9-A issued after installation of
the machine and after bringing into force the rationalisation scheme was ex
facie a stillborn and incompetent notice and was clearly violative of the
provisions of Section 9-A of the Act which amounted to putting the cart before
the horse. Such an incompetent and illegal notice under Section 9-A could not
legally enable the appellant to terminate the services of the respondent. We
may mention at this stage that the impugned termination order dated 22.6.1982
clearly recites as follows :
"In
the notice given on 25th March, 1982, under Section 9-A of the Industrial
Disputes Act, 1947, the Management had noted that it may require to reduce 25
workmen from service for the purpose of introducing new technology in the
composing section.
The
Conciliation Officer has noted in his order dated 22.6.82 that the proceedings
started on the basis of this notice have proved unsuccessful and, therefore,
the Management has now decided to terminate with immediate effect the following
25 workmen. Name of Workmen Post 1. Shri Maniram Choudhary Foreman 2. Shri
Shankarprasad Pathak Foreman 3. to 25 Xxxxxxxxxxxxxx"
---------------------------------------------------------------------------------
That is how the listed workmen, including the respondent herein, were sought to
be discharged from service. Thus the foundation of the impugned order of
discharge is the notice under Section 9-A dated 25th March, 1982. Once that
foundation is knocked off as incompetent, illegal and uncalled for the entire
edifice of retrenchment order against the respondent falls to the ground.
It may
also be noted at this stage that by two decisions rendered by Bench of three
learned Judges of this Court in connection with the time for issuance of notice
under Section 9-A read with item 10 Schedule IV with which we are concerned in
the present case it has been clearly ruled that such notice must precede the
introduction of rationalisation scheme. We may usefully refer to them at this
stage. In the case of M/s. North Brook Jute Co. Ltd. & Anr. vs. Their
Workmen (1960 (3) S.C.R. 364), a three Judge Bench of this Court had to
consider the question whether in a reference regarding proposed introduction of
rationalisation scheme which was preceded by notice under Section 9-A of the
I.D. Act, such a scheme could be actually introduced pending reference
proceedings and whether such an act on the part of the management could be
treated to be illegal entitling the workmen affected by such an introduction to
go on strike and still earn wages for the strike period. Answering this
question in affirmative it was held by this Court that after notice under
Section 9-A of the I.D. Act when a scheme of rationalisation was said to be
introduced but was not actually introduced it could not be introduced till the
dispute regarding such proposed introduction was resolved by the competent
Court. Dealing with the scheme of proposed rationalisation as envisaged by item
no.10 of Schedule IV of the I.D. Act it was observed that :
"Rationalisation
which was introduced had therefore two effects- first that some workers would
become surplus and would face discharge; and secondly, the other workmen would
have to carry more workload. The introduction of the rationalisation scheme was
therefore clearly an alteration of conditions of service to the prejudice of
the workmen.
The
alteration was made on the 16th December, when reference as regards the scheme
had already been made and was pending before the Industrial Tribunal. The
Tribunal has therefore rightly held that this introduction was a contravention
of s. 33." The aforesaid decision, therefore, has clearly ruled that
introduction of rationalised scheme by itself would amount to alteration of
conditions of service of the workmen to their prejudice. It, therefore, follows
that before effecting such a change, meaning thereby, before introducing such a
rationalisation scheme which has a tendency to change the conditions of service
of workmen, notice under Section 9-A as a condition precedent becomes a must.
If learned counsel for the appellant is right, that machine can be introduced
on experimental basis first or even after it has already worked for some time
and is required to be continued as a full-fledged machine, as and when the employer
decides to terminate the services of the workmen as a direct consequence of
such introduction of machine, he can give notice under Section 9-A of the Act
at any such time, then the very scheme of Section 9-A read with Schedule IV
item no.10 of the I.D. Act would be rendered ineffective and inoperative. The
purpose of issuing such a notice prior to the introduction of the scheme of
rationalisation would get frustrated and then there would remain no effective
opportunity for the conciliator to try to arrive at an amicable settlement
regarding the dispute centering round the proposed introduction of the scheme
of rationalisation which is likely to result in the retrenchment of workmen.
Equally
there would remain no opportunity for the State Government on receipt of
failure report from the conciliator to make a reference of such live industrial
dispute for adjudication by the competent Court on merits. It is obvious that
when such dispute regarding the proposed introduction of the rationalisation
scheme is referred for adjudication of the competent Court, the said Court
after hearing the parties and considering the evidence can come to the
conclusion whether the proposed scheme is justified on facts or not and whether
any violation of the provisions of Section 9-A had resulted into illegality of
the consequential orders of retrenchment. Such competent Court can also
accordingly pass appropriate consequential orders directing the management to
withdraw such a scheme of rationalisation or in any case, can order
reinstatement of workmen with proper back-wages if such retrenchment is found
to be illegal on account of failure to comply with the provisions of Section
9-A of the Act. The question regarding the stage at which notice under Section
9-A can be issued in connection with proposed scheme of rationalisation which
has likelihood of rendering existing workmen surplus and liable to retrenchment
as mentioned in item no.10 of Schedule IV of the I.D. Act was once again
examined by a three judge bench of this Court in Hindustan Lever Ltd. vs.
Ram
Mohan Ray & Ors. (1973 (4) SCC 141). In that case, this Court was concerned
with a scheme of rationalisation and re-organisation which were proposed to be
introduced by Hindustan Lever Ltd., appellant before this court, and for which
a prior notice under Section 9-A before introducing such re- organisation
scheme was issued to the workmen but which had no tendency or likelihood of
displacing or retrenching them. It was the contention of the workmen that even
for such a scheme a notice under Section 9-A was a must. Examining the scheme
of reorganisation in question, it was held that once the scheme was not likely
to result in retrenchment of any workman Section 9-A read with item no.10 of
Schedule IV did not get attracted on the facts of the case. In this connection
the following pertinent observations on the scheme of Section 9-A read with
item no.10 of Schedule IV were made by Alagiriswami J., while dealing with the
contention of learned counsel for the workmen :
"He
also urged that rationalisation and standardisation per se would fall under
item 10 even if they were not likely to lead to retrenchment of workmen and
only improvement of plant or technique would require that they should lead to
retrenchment of workmen in order to fall under item 10. A further submission of
his was that standardisation merely meant standardisation of wages. We are not
able to accept this argument. It appears to us that the arrangement of words
and phrases in that item shows that only rationalisation or standardisation or
improvement of plant or technique, which is likely to lead to retrenchment of
workmen would fall under that item. In other words, rationalisation or
standardisation by itself would not fall under item 10 unless it is likely to
lead to retrenchment of workmen. The reference to rationalisation at page 257
of the report of the Labour Commission and the reference to standardisation of
wages in it are not very helpful in this connection. Standardisation can be of
anything, not necessarily of wages. It may be standardisation of workload,
standardisation of product, standardisation of working hours or standardisation
of leave privileges.
Indeed
in one decision in Alembic Chemical Works Co. Ltd. v. The Workmen, there is
reference to standardisation of conditions of service, standardisation of hours
of work, wage structure. That case itself was concerned with standardisation of
leave. The whole question whether this reorganisation falls under item 10
depends upon whether it was likely to lead to retrenchment of workmen." In
view of the aforesaid decision, it becomes obvious that if the proposed scheme
of rationalisation has a likelihood of rendering existing workmen surplus and
liable to retrenchment, then item no.10 of Schedule IV would squarely get
attracted and would require as a condition precedent to introduction of such a
scheme a notice to be issued under Section 9-A by the management proposing such
an introduction of the scheme of rationalisation, but if the proposed scheme is
not likely to displace any existing workmen then mere rationalisation which has
no nexus with the possibility of future retrenchment of workmen would not
attract item no.10 of Schedule IV and would remain a benign scheme of
rationalisation having no pernicious effect on the existing working staff. In
view of the aforesaid settled legal position, there is no escape from the
conclusion that the impugned notice dated 25th March, 1982 under Section 9-A
which was issued long after the actual installation of the photo composing
machine had fallen foul on the touchstone of Section 9-A read with Schedule IV
item no.10. Such a notice in order to become valid and legal must have preceded
introduction of such a machine and could not have followed the actual
installation and effective commission of such a machine. The decision rendered
by the Division Bench in this connection is found to be perfectly justified
both on facts and in law. It must, therefore, be held that the impugned
termination or discharge of the respondent was violative of the provisions of
Section 9-A of the I.D. Act and he was discharged from service without the
appellant's following the mandatory requirements of Section 9-A of the I.D.
Act. Effect of non-compliance of Section 9-A of the I.D. Act renders the change
in conditions of service void ab initio. This legal position is well settled in
the case of Workmen of the Food Corporation of India vs. Food Corporation of
India [(1985) (2) SCC 136], a three Judge Bench of this Court, speaking through
Desai J., in para 19 of the report, laid down as under :- "It is at this
stage necessary to examine the implication of Section 9-A of the I.D. Act,
1947. As hereinbefore pointed out, Section 9-A makes it obligatory upon an
employer who proposes to effect any change in the conditions of service
applicable to any workman in respect of any matter specified in the Fourth
Schedule to give a notice of desired or intended change. It cannot do so
without giving to the workman likely to be affected by the change, a notice in
the prescribed manner of the nature of the change proposed to be effected and
within 21 days of giving such notice. There is a proviso to Section 9-A which
has no relevance here.
Xxxxxx
xxxxx xxxxx Xxxxxxx xxxxx xxxxx Therefore, obviously a notice of change was a
must before introducing the change, otherwise it would be an illegal change.
Any such illegal change invites a penalty under Section 31(2) of the I.D. Act,
1947. Such a change which is punishable as a criminal offence would obviously
be an illegal change. It must be held that without anything more such an
illegal change would be wholly ineffective." Point No.3, therefore, is
answered in affirmative against the appellant and in favour of the respondent.
Point
No.4: It has to be kept in view that the present proceedings arise out of a
complaint filed by the respondent-workman alleging `unfair labour practice' on
the part of the appellant-management when it passed the impugned order of
retrenchment against him.
The
said complaint was moved under Section 28 of the Maharashtra Act. The topic of
`unfair labour practice' is dealt with in Chapter VI of the said Act. Section
26 is the first section in the said chapter which provides as follows :
"`unfair labour practices:- In this Act, unless the context requires otherwise,
`unfair labour practices' mean any of the practices listed in Schedules II, III
and IV." Section 27 lays down as follows : "Prohibition on engaging
in unfair labour practices:- No employer or union and no employee shall engage
in any unfair labour practice." Section 28 lays down the procedure for
dealing with complaints relating to `unfair labour practices'.
Sub-section
(1) thereof provides as follows :- "(1) Where any person has engaged in or
is engaging in any unfair labour practice, then any union or any employee or
any employer or any Investigating Officer may, within ninety days of the
occurrence of such `unfair labour practice', file a complaint before the Court
competent to deal with such complaint either under section 5, or as the case
may be, under section 7, of this Act:
Provided
that, the Court may entertain a complaint after the period of ninety days from
the date of the alleged occurrence, if good and sufficient reasons are shown by
the complainant for the late filing of the complaint." It is not in
dispute in this case that the respondent invoked the jurisdiction of the Labour
Court which was competent to deal with his complaint regarding `unfair labour
practice', under items 1 (a), (b), (d) and (f) of Schedule IV of the
Maharashtra Act. Section 7 of the Act lays down the duties of Labour Court and states as under :- "It
shall be the duty of the Labour
Court to decide
complaints relating to unfair labour practices described in item 1 of Schedule
IV and to try offences punishable under this Act." When we turn to
Schedule IV item no.1, we find therein listed number of heads of `unfair labour
practice's which can support any complaint thereunder. The relevant clauses of
item no.1 of Schedule IV which were invoked by the respondent for supporting
his complaint against the impugned retrenchment order were clauses (a), (b),
(d) and (f). Item no.1 with all its sub-clauses reads as under :- "To
discharge or dismiss employees - (a) by way of victimisation; (b) not in good
faith, but in the colourable exercise of the employer's rights; (c) by falsely
implicating an employee in a criminal case on false evidence or on concocted
evidence; (d) for patently false reasons; (e) on untrue or trumped up
allegations of absence without leave; (f) in utter disregard of the principles
of natural justice in the conduct of domestic enquiry or with undue haste; (g)
for misconduct of a minor or technical character, without having any regard to
the nature of the particular misconduct or the past record of service of the
employee, so as to amount to a shockingly disproportionate punishment." We
have, therefore, to see as to whether in the light of our findings on point
nos.2 and 3 the respondent could rely upon any of these clauses of item no.1 of
Schedule IV in support of his complaint. Now a mere look at the aforesaid
provision shows that an employee who makes a grievance against order of
discharge or dismissal passed against him can invoke any of the listed clauses
(a) to (g) of item no.1 of Schedule IV. Learned counsel for the appellant was,
therefore, right when he contended that first it should be alleged by the
complainant-employee that he was discharged or dismissed from service by the
employer and then he has to further show whether such an order attracted any of
the clauses (a) to (g) of item no.1 of Schedule IV.
Learned
counsel for the appellant, in this connection, vehemently contended that item
no. 1 of Schedule IV of the Maharashtra Act deals with only punitive discharges
or dismissals and not any simpliciter discharge order or termination order
which is not passed by way of punishment.
In
order to support this contention, learned counsel for the appellant relied upon
principles of interpretation, namely, the principle of noscitur a sociis as
well as the principle of ejusdem generis. So far as the first principle of
interpretation is concerned, he referred to "Maxwell on The Interpretation
of Statutes", 12th Edition at page 289 dealing with the question regarding
understanding associated words in common sense. The learned author in
connection with this principle has made the aforesaid pertinent observations :
"Where two or more words which are susceptible of analogous meaning are
coupled together, noscuntur a sociis. They are understood to be used in their cognate
sense. They take, as it were, their colour from each other, the meaning of the
more general being restricted to a sense analogous to that of the less general.
(One application of this general principle is the ejusdem generis rule, which
is discussed in the next section of this chapter.)" It becomes, therefore,
obvious that before this principle of interpretation can be pressed in service,
it must be shown that both the words `discharge and dismissal' are employed by
the Legislature in Schedule IV item no.1 in the same sense or that they are
susceptible of analogous meaning. This rule of construction in other words lays
down as follows : "The meaning of a word is to be judged by the company it
keeps." As held by this Court in the case of M.K. Ranganathan & Anr
vs. Govt. of Madras & Ors. (AIR 1955 SC 604 at 609) relying upon Privy
Council decision in `Angus Robertson v.
George
Day', [(1879) 5 AC 63 at p 69 (E)]: "It is a legitimate rule of
construction to construe words in an Act of Parliament with reference to words
found in immediate connection with them".
Keeping
in view this well settled principle of construction of statutes, let us see
whether in the settings of item no.1 clauses (a) to (g) the word `discharge' as
employed by the Legislature has meaning analogous to that of the word
`dismiss'. When we have a close look at clauses (a) to (g) of item no.1 of
Schedule IV, we find that the word `discharge' is not intended by the
Legislature to have the same or analogous meaning as the word `dismiss'. The
reason is obvious. The word `dismiss' necessarily connotes an action of the
employer who seeks to impose punishment on his mis- conducting employee. Such a
punishment cannot be imposed without following the principles of natural
justice and the relevant applicable rules of domestic inquiry. But the word
`discharge' is not necessarily confined to orders of termination by way of
penalty only. The word `discharge' has wider connotations. A mis-conducting
employee facing charges in a domestic inquiry may be punished by way of
imposing on him an order of dismissal which may make him ineligible for any
other employment but if it is found that the charges which are proved are not
that serious but the employee would not deserve to be continued in service then
an order of discharge by way of lesser penalty can be imposed on him. Such an
order would remain a punitive discharge. Thereby the employer wants to punish
the employee for his misconduct but does not want him to become ineligible for
employment elsewhere considering less serious nature of proved charges of
misconduct against him in domestic inquiry. But that is not the end of the
matter.
In
service jurisprudence the term `discharge' has assumed a wider connotation and
may include in its fold not only punitive discharge orders but also simpliciter
discharge orders where the employer seeks to snap the relationship of employer
and employee but without any intention to penalise the employee. He does so
because of exigencies of service and employment conditions which may require
him to say goodbye to the employee but without any intention to punish him.
Such simpliciter discharge orders can be illustrated as under :
An
employee, on probation, may not be found to be suitable and may not earn
sufficient merit so as to be confirmed in service. Consequently, his probation
may be terminated and an order of discharge simpliciter can be passed against
him. There may also be other cases of single discharge under the contract of
employment for a fixed period where an employee on efflux of time may be
terminated. There may also be cases where an employee may become surplus and
would no longer be required by the employer. An order of retrenchment,
therefore, may be passed against him subject, of course, to following the
statutory requirements of Section 25-F and 25-G of the I.D.
Act if
they are applicable. These illustrations are not exhaustive but they indicate
such orders of discharge are passed by an employer who does not want to punish
the employees but still is not in a position to continue them in service. Such
simpliciter discharge orders are also a category of discharge orders.
Therefore, the word `discharge' as employed by the Legislature in item no.1 of
Schedule IV cannot necessarily be confined only to punitive discharges as tried
to be submitted by learned counsel for the appellant. Once we consider the
words `discharge' or `dismissal' as employed in the opening part of item no.1
by the Legislature in the light of various clauses representing different
situations under which such discharge or dismissal orders are said to amount to
`unfair labour practice' on the part of the employers, it becomes at once clear
that the Legislature was not contemplating only punitive discharge orders but
was contemplating both types of discharge orders, namely, punitive as well as
non-punitive discharge orders.
The
very first item (`a') deals with the discharge or dismissal order passed by way
of victimisation of the employee. It is easy to visualise that an employer may
like to dispense with the services of an employee who, according to him, is a
trouble maker. He may not have been involved in any misconduct as such still by
way of putting an end to his service on extraneous reasons, if an order of
discharge is passed it may remain simpliciter order of discharge but if it is
found based on extraneous reasons it would be by way of victimisation. Such a
discharge order may not necessarily be a punitive discharge order. The employer
would not like to punish the employee for any of his misconduct but would not
like him to continue in service as according to the employer he may be an
undesirable person not suitable to the management is for example a militant
trade union leader who, according to the employer, is any how to be required to
be sent out of service. When such type of discharge orders are passed by way of
victimisation they would be simpliciter discharge orders when not backed up by
relevant reasons. It cannot be said that such simpliciter discharge orders are
not covered by item `1' clause (`a') of Schedule IV. Similarly clause (`b') may
contemplate a discharge order which is not passed in good faith but in the
colourable exercise of employer's rights.
Thus,
the employer may have merely a pretext to put an end to the service of the
employee who may not have misconducted himself at all. Therefore, there will be
no occasion to have any departmental inquiry against him as no charge could be
framed regarding any misconduct on his part. Still if such an undesirable
employee is to be removed from service then even though the simpliciter
discharge order is passed if it is shown that it is not in good faith but as a
result of malafide intention of the employer, then such a discharge order can
also attract the category of `unfair labour practice' as enacted by the
Legislature in item nos. (`a') and (`b'). Similar Legislature scheme is
discernible from clause (c) of item no. 1 which deals with an order of
discharge or dismissal by falsely implicating an employee in a criminal case on
false evidence or on concreted evidence.
In
such a situation discharge or dismissal order may operate as a penal order.
Similarly, clause (d) may cover cases which are orders of discharge or
dismissal by way of penalty as well as simpliciter discharge orders based on a
patently false reasons. Clause (e) referring to discharge or dismissal may
cover both the cases of dismissal by way of penalty on such grounds or
discharge by way of penalty on such grounds and equally a discharge order
simplicitor on account of false allegations of absence without leave. So far as
Clause (f) is concerned, the first part squarely covers a case of dismissal or
discharge by way of penalty as it deals with such orders passed after
conducting domestic inquiry about the alleged misconduct of the employee but in
utter disregard of the principles of natural justice but so far as the second
part of clause (f) of item no.1 is concerned, if an employee is dismissed with
undue haste it may be by way of penalty as in domestic inquiry apart from
following the principles of natural justice, sufficient and reasonable
opportunity to defend may be denied to the employee and with undue haste the
dismissal order may be passed. That would obviously be a penal order but so far
as discharge order is concerned, it may also be passed by way of penalty with
undue haste but the said part of clause (f) may equally cover those discharge
orders which are simpliciter discharge orders not by way of penalty but still
being passed with undue haste on the part of the employer who may not be
wishing to punish the employee but wishing to say goodbye to the employee on
the ground that he is otherwise an unwanted person. Such discharge orders
passed with undue haste may not necessarily be penal and still may amount to
`unfair labour practice' if they are passed with undue haste. Clause (g) of
item no.1 obviously refers to only discharge or dismissal orders which are
penal in nature as they have a direct linkage with misconduct of the employee.
The
aforesaid resume of various clauses of item no.1 of Schedule IV leaves no room
for doubt that when the Legislature used the words `discharge' or `dismissal'
of the employees under circumstances enumerated in clauses (a) to (g) in item
no.1 of Schedule IV it contemplated dismissal orders which obviously are penal
in nature but it also contemplated discharge orders which may either be penal
or non- penal in nature and still if any of the relevant clauses of item no. 1
got attracted in connection with such discharge orders they would make the
employer, author of such discharge orders answerable for the alleged `unfair
labour practice' permeating the passing of such simpliciter discharge orders.
To recapitulate, in the present case, respondent's complaint is not that his
discharge was by way of penalty but his complaint is that the discharge order
in his case was a result of victimisation and was not passed in good faith but
was passed on patently false reasons and was a result of undue haste on the
part of the appellant-employer. Whether the said complaint was justified on
merits or not is a different matter but it can not be said that such a
complaint regarding non-penal discharge order was dehors the scope and ambit of
item no.1 of Schedule IV of the Maharashtra Act. Before parting with the
discussion on this aspect we may mention that learned counsel for the appellant
also relied upon the other rule of interpretation, namely, rule of ejusdem
generis. The said rule of interpretation provides as follows :
"When
particular words pertaining to a class, category or genus are followed by
general words, the general words are construed as limited to things of the same
kind as those specified. This rule which is known as the rule of ejusdem
generis reflects an attempt "to reconcile incompatibility between the specific
and general words in view of the other rules of interpretation that all words
in a statute are given effect if possible, that a statute is to be construed as
a whole and that no words in a statute are presumed to be superfluous".
It is
difficult to appreciate how this principle of interpretation can be invoked by
learned counsel for the appellant in connection with item no.1 of Schedule IV.
The word `discharge' is a general word. It is followed by the word `dismissal'
which contemplates only one category of cases or situations where penalty is
imposed by the employer on the workmen concerned. The rule of ejusdem generis
would have applied if the word `discharge' represented a particular species
belonging to the genus reflected by the general word `dismiss'. This is a
converse case where a general word `discharge' is followed by the word
`dismiss' which is of a particular nature or pertains to a limited class or
category of penal situations. Obviously, therefore, neither of them is a genus
and nor of them is a species of the very same genus. The word `discharge'
connotes an entirely different category of orders comprising of both
simpliciter discharge orders not by way of penalty as well as discharge orders
by way of penalty but not involving extremely pernicious results flowing from
such orders while the word `dismiss' is purely an order of penalty and that too
of an extreme type. Consequently, the aforesaid rule of interpretation cannot
be of any avail to learned senior counsel for the appellant. On the contrary,
as seen by us earlier, the words `discharge' and `dismissal' as employed by the
Legislature in item no.1 of Schedule IV covered different types of situations
and circumstances under which they are passed. It is, therefore, not possible
to agree with the submission of learned senior counsel for the appellant that
unless the respondent shows that he was discharged by way of penalty, he cannot
invoke any of the clauses of item no.1 of Schedule IV.
Before
leaving the discussion on this aspect, we may refer to a decision of this Court
on which strong reliance was placed by learned counsel for the appellant. In
the decision of the Constitutional Bench of this Court in State of Rajasthan
& ANR. vs. Sripal Jain, (1964 (1) SCR 742), this Court was concerned with
the interpretation of Rule 244(2) of the Rajasthan Service Rules read with rule
31(vii) (a) of the Rules. In the light of the said statutory scheme of these
Rules, the Court made the following pertinent observations :
"Held,
that compulsory retirement provided in r. 31(vii)(a) is a compulsory retirement
as a penalty and not compulsory retirement of the other two kinds namely (1)
Compulsory retirement on attaining the age of superannuation and (2) compulsory
retirement under r.244(2), neither of which is a punishment." It is
difficult to appreciate how the said decision rendered on the special scheme
considered by this Court in that case can be of any assistance to learned
counsel in the present case. The scheme with which we are concerned contraindicates
any such conclusion as tried to be pressed in service by learned counsel in
support of his contention that the word `discharge' is used synonymously or
analogously by the Legislature along with the word `dismissal'. It is also well
settled that the word `discharge' may not only be by way of penalty. Discharge
of a probationer on unsuitability, as noted earlier, would not be by way of
penalty. Similarly, even in case of compulsory retirement as laid down by a
catena of decisions of this Court in the context of the relevant statutory
rules, this action may not be penal. In this connection, we may refer to a
decision of this Court in K. Kandaswamy vs. Union of India & Anr., (JT 1995
(7) S.C. 80), wherein it has been observed that "..Compulsory retirement
does not amount to dismissal or removal from service within the meaning of
Article 311 of the Constitution. It is neither punishment nor visits with loss
of retiral benefits ; nor does it cast stigma." Consequently, it cannot be
held that wherever the word `discharge' is used in any statutory instrument it
must necessarily connote a penal discharge as tried to be submitted by learned
counsel for the appellant. In the case of High Court of Judicature at Patna vs.
Pandey Madan Mohan Prasad Sinha & Ors. [(1997) 10 SCC 409], it has been
held by the Bench of this Court that if a probationer is discharged on the
ground of unsuitability, the said order can be challenged only on the ground
that it is arbitrary or punitive. If it is not punitive then such an order
cannot be challenged at all. It is further observed that principles of natural
justice have no application in case of termination of services of a probationer
during the period of probation since he has no right to hold that post. In such
case, it is obvious that discharge of such a probationer on the ground of
unsuitability cannot be treated to be a punitive discharge.
Once
this ground is cleared, the arena of contest between the parties becomes well
defined. It has to be pleaded and proved by the respondent-complainant that
though the order of termination or retrenchment was not passed by way of
penalty by the appellant, it attracted all or any of the clauses (a),(b),(d)
& (f) of item no.1 of Schedule IV as his complaint was based on these
clauses only. In the light of the evidence which is on record and on which
there is no dispute between the parties, it becomes clear that the appellant
wanted to switch over to the process of composing by utilising photo
type-setting machine and in the process the hand composing department engaging
respondent and other workmen had to be wound up. That naturally resulted in the
employees in the erstwhile hand composing department becoming excess and
surplus. That is the reason why impugned notice under Section 9-A of the I.D.
Act was issued to the respondent and other workmen and ultimately resulted in
the impugned retrenchment order. It is difficult to appreciate how such an
action on the part of the appellant can be treated to have been the result of
victimisation. The respondent was not being victimised for any extraneous
reason. On the contrary, it was based on a genuine factual reason. Hence clause
(a) of item no.1 of Schedule IV is out of picture. Parameters of the term
`victimisation' have been considered by a three Judge Bench of this Court in
the case of Colour-chem Limited vs. A.L.
Alaspurkar
& Ors. [1998 (1) Scale 432], where one of us, S.B.Majmudar J., speaking for
the Bench in para 13 of the report observed that the term `victimisation' is a
term of comprehensive import. Thus, if a person is made to suffer by treatment,
it would amount to victimisation. On the facts of the present case, therefore,
it is not possible to hold that the impugned discharge of the respondent was
based on non-germane or extraneous reasons or it was passed with a view to make
the respondent suffer for no real reason.
It is,
therefore, not possible to agree with the reason of the Division Bench of the
High Court in the impugned judgment that the action of the appellant was by way
of victimisation of the respondent. Item no.1 clause (a) of Schedule IV,
therefore, does not apply to the facts of the present case.
On a
parity of reasoning it has to be held that the discharge of the respondent from
service cannot be said to be not in good faith but in the colourable exercise
of employer's rights. It cannot be gainsaid that the appellant had good reason
to discharge the respondent who was rendered surplus in hand composing
department because of the introduction of the machine in question. It is
difficult to impute any bad faith to the appellant as the appellant tried its
best to provide alternative job to the respondent at Jalgaon but the said offer
was not accepted by the respondent and, on the contrary, the transfer order was
got declared illegal and an act of `unfair labour practice' in proceedings
culminating before the Tribunal. Clause (b) of item no.1 of Schedule IV,
therefore, is also not attracted on the facts of the present case. The third
prank of respondent's complaint pertains to the applicability of clause (d) of
item no.1 of Schedule IV. The said clause can be attracted only if it is shown
that the impugned termination was for patently false reasons. It is difficult
to appreciate how the Division Bench persuaded itself to hold that the said
clause was attracted on the facts of the present case. The appellant had a
genuine reason for terminating the services of the respondent as hand
composition department had become redundant on account of the introduction of
the machine in question. It is true, as submitted by learned counsel for the
respondent, that the impugned retrenchment order dated 22.6.1982 showed that
the management, as per notice under Section 9-A, had noted that it may require
to reduce 25 workmen from service for the purpose of introducing new
technology. It is also true that the new technology was already introduced by
the management months prior to the day of the termination order dated 22nd
June, 1982, to be precise from January, 1981 on an experimental basis as
submitted by learned counsel for the appellant and on regular basis at least
from November, 1981.
Still
it cannot be held that the proposed termination was not based on real reason or
was effected on patently false reasons. If no such machine was ever introduced
and still such a ground was made out for passing the impugned order, then it
could have been said that the impugned termination was passed on patently false
reasons. The patently false reason would be one which has no existence at all
in fact and is a mere pretext or an excuse. Such is not the situation in the
present case. It may be that the reason given may not be strictly accurate in
the sense machine was already introduced and was not likely to be introduced by
the time notice under Section 9-A was given followed by the impugned
termination order. That may have effect of non-compliance of the provisions of
Section 9-A. The said notice, as we have seen earlier, on that score may become
inoperative or illegal. Still the reason for termination cannot be said to be
patently false. We, therefore, disagree with the conclusion of the Division
Bench of the High Court in view of our aforesaid findings regarding
non-applicability of clauses (a), (b) & (d) of item 1 of Schedule IV. On
this conclusion, we would have been required to dismiss the respondent's
complaint but for the fact that the fourth leg of the respondent's complaint
invoking clause (f) second part of item no.1 cannot be said to be non-existent
or unjustified or uncalled for. As we have already discussed, order of discharge
whether punitive or non-punitive if found to be the result of undue haste on
the part of the employer, the inevitable result will be that the employer would
be guilty of `unfair labour practice' as laid down by Schedule IV item no.1
clause (f) second part.
In the
facts of the present case, the decision rendered by the Division Bench of the
High Court on this score cannot be found fault with. It has to be recalled that
the proceedings in connection with notice under Section 9-A were pending in
conciliation. Efforts were made by the Conciliation Officer for seeing that the
parties come to an amicable settlement. Of course, those efforts failed and on
22nd June, 1982 by 4.35 p.m. the Conciliation Officer orally declared that the
conciliation had failed and investigation was at an end. However, as seen
earlier, that was not the end of the matter. The Conciliation Officer did not
become functus officio on that day. As per Section 12 sub-section (4) of the
I.D. Act thereafter he had to give a full report setting forth the steps taken
by him for ascertaining the facts and circumstances relating to the dispute and
for bringing about a settlement thereof, together with a full statement of such
facts and circumstances, and the reasons on account of which, in his opinion, a
settlement could not be arrived at. That obviously would have taken a few days,
if not more, before such report could have been prepared by the Conciliation
Officer. It is, therefore, difficult to appreciate how the appellant in hot
hurry and within almost half an hour from the close of investigation on the
very same day by 5'O clock in the evening could pass the impugned termination
order against the respondent. It has to be appreciated that in the report which
was to follow, the Conciliation Officer was required to highlight the nature of
the dispute between the parties in the light of the notice under Section 9-A
given by the appellant to the respondent union. It is easy to visualise that
even in such a failure report the conciliator could have given his prima-facie
opinion regarding the nature of the dispute and the reasonableness thereof. It
is also to be kept in mind that once such report reaches the State Government,
in the light of the report if the State Government finds that the dispute is a
genuine dispute which requires adjudication, it may make an order of reference
or if, on the other hand, the State Government finds from the report that the
dispute is frivolous it may not make a reference but that stage could reach
only after the report is received and scrutinised by the State Government.
Under these circumstances, for passing the impugned retrenchment order within
half an hour of the close of investigation by the Conciliation Officer, the
appellant could not have presumed that the report would necessarily indicate
total frivolousness of the dispute and that would not persuade the State to
make a reference of the dispute for adjudication by a competent Court. Without
waiting to see as to what will be the nature of the report and the contents,
the appellant tried to help itself and in undue hurry passed the impugned
order. The result was that by one stroke the appellant pre-empted the report of
the conciliator on the one hand and on the other hand even the future objective
action of the State Government on such a report. It is also important to note
that on the report of the conciliator, the State Government could have thought
it fit to refer the dispute for adjudication and in the present case on the
basis of the said report, reference was in fact made by the State Government
regarding the legality of the scheme of rationalisation resulting in the
likelihood of retrenchment of the workmen concerned. The said reference became
infructuous only because the appellant, in the meantime, invoked jurisdiction
of the Labour Court under Section 28 of the Maharashtra Act. That resulted in
the applicability of Section 59 of the Maharashtra Act which lays down as under
: "If any proceeding in respect of any matter falling within the purview
of this Act is instituted under this Act, then no proceeding shall at any time
be entertained by any authority in respect of that matter under the Central Act
or, as the case may be, the Bombay Act; and if any proceeding in respect of any
matter within the purview of this Act is instituted under the Central Act, or,
as the case may be, the Bombay Act, then no proceeding shall at any time be
entertained by the Industrial or Labour Court under this Act." It is
because of the aforesaid provision of Section 59 of the Maharashtra Act that
the referred dispute under Section 10 of the I.D. Act got disposed of. However,
the fact remains that on the failure report submitted by the Conciliation
Officer the appropriate Government had thought it fit to prima facie hold that
the dispute was a real one which required adjudication by the competent Court
under the I.D. Act. It is also necessary to note that in such references
received by the competent Court under the I.D.
Act in
appropriate cases, the Court to which such references are made has ample
jurisdiction to pass interim orders and if the Court had found that the
impugned retrenchment order was required to be stayed even though it had been
passed after conciliation proceedings were over and when there was no
prohibitory order from any authority such retrenchment order could have been
stayed. Further implementation of the impugned change could have been stayed
vide The Management Hotel Imperial, New Delhi and others vs. Hotel Workers'
Union (AIR 1959 SC 1342) and The Hind Cycles Ltd. and another vs. The Workmen
(AIR 1974 SC 588).
It is
also to be noted that in the facts of the present case, as already held by us
on point no.1, the conciliation proceedings had not terminated when the
impugned order was passed. The result was that Section 33(1) got violated and
the appellant became liable to be punished as per Section 31(1) of the I.D. Act
incurring a penalty for being convicted of an offence punishable with
imprisonment for a term which may extend to 6 months or with fine or with both.
Thus the impugned order cannot, but be held to have been passed with undue
haste. The intention behind passing such a hurried order was obviously to cut
across and pre-empt the submission of failure report by the conciliator on the
one hand and its consideration by the State on the other and even for avoiding
the future possibility of a reference under the I.D. Act and also the future
possibility of the Court's intervention by way of interim relief against such
order. But to crown it all by such undue hurry the appellant made itself liable
to be punished and incurred a criminal liability for the same.
All
these consequences unequivocally project only one picture that the impugned
order was passed in a great hurry and with undue haste. This conclusion is inevitable
on the aforesaid facts which have remained well established on the record of
the present case. Consequently, agreeing with the view of the Division Bench in
the impugned judgment it must be held that the respondent's complaint was well
sustained at least under clause (f) second part of item 1 of Schedule IV and as
the impugned order was passed with undue haste the inevitable result is that by
the said act the appellant is liable to be treated as guilty of `unfair labour
practice'.
We may
also mention in this connection one another facet of this question. As the
Conciliation Officer, after hearing the parties, had declared that
investigation was over and settlement had not taken place, at least a few days
were available after 22nd June, 1982 to the appellant for moving the
Conciliation Officer to give the appellant permission to retrench the
respondent. It is not possible to agree with the finding of the Labour Court
that the Conciliation Officer could not have entertained such a request. He had
not even drafted his report, much less submitted the same to the State
Government at least within a few days after 22nd June, 1982. The very fact that
the report reached the State Government on 13th August, 1982 shows that the
conciliator would have despatched the same at least a couple of days after 22nd
June, 1982, having complied with all the statutory requirements under Section
12(6) for preparation of such a report. Even on the next day of 22nd June, 1982
such a request could have been made by the appellant and the conciliator would
not have felt any inhibition in recalling both the parties and hearing them on
such a request on the part of the appellant to give permission to it to pass
the impugned termination order as the conciliation had failed. Even by passing
such a legally permissible and factually feasible course, and without waiting
even for more than half an hour the impugned order was passed. It is easy to
visualise that it was possible that if such a request was made by the appellant
it could have been granted or it could have been rejected. If such a request
was rejected by the conciliator then, of course, the impugned order could not
have seen the light of the day and if thereafter the State Government had made
the reference after reading the failure report, then the existing position
regarding service condition of the respondent could have been continued by the
reference Court pending the adjudication of such a dispute. The appellant with
a view to avoid all these uncomfortable situations indulged in self help and
passed the impugned order on the very evening of 22nd June, 1982. This is an
additional facet of the deliberate undue haste resorted to by the appellant for
short circuiting all possible inconvenient situations and to present the
respondent with a fait accompli and also to placate the Conciliation Officer on
the one hand and the State Government on the other and ultimately the reference
Court also. Consequently it must be held that the impugned order was clearly a
result of undue haste and, obviously amounted to `unfair labour practice' on
the part of the appellant as per Schedule IV item 1 clause (f) second part.
Consequently,
this point for determination is held against the appellant and in favour of the
respondent only to the extent of applicability of the aforesaid provision.
Point
No.5: So far as this point is concerned, we have already noted that the Labour
Court itself has found that notice under Section 9-A was a belated one and
should have been given at least by November, 1981 when the machine in question
became fully operative resulting in displacement of workers in hand composing
department. Still by curious reasoning, it has been held that there was nothing
wrong with the notice though given belatedly and that the termination order was
also not offending Section 33(1) of the Act. These findings show patent errors
of law and could not be sustained. The Industrial Court, on the other hand,
came to an equally erroneous finding on the applicability of item 10 of
Schedule IV of the I.D. Act when it held that the said item would apply not at
the time when the rationalisation scheme was introduced, but at the time when
the employer desired or decided to terminate the services of the employees.
This reasoning of the Industrial Court is contrary to the very scheme of item
10 of Schedule IV of I.D. Act and totally ignores the term `likely to lead to
retrenchment' as found in the said item. The reasoning of the Industrial Court
almost amounts to rewriting the said phrase as "decide to retrench the
workmen". These patent errors of law committed by the Labour Court and the
Industrial Court were totally bypassed by the learned Single Judge while he
dismissed the Writ Petition. These patent errors of law, therefore, were
rightly set aside by the Division Bench of the High Court in the Letters Patent
Appeal. It could not, therefore, be said that the impugned judgment had tried
to interfere with the pure findings of the fact reached by the authorities
below on evidence against the respondent. It was perfectly open to the
Appellate Court in the hierarchy of proceedings to interfere with such patent
errors of law and to correct them, otherwise it could have been said that it
had failed to discharge its duty and that would have also amounted to failure
to exercise jurisdiction on its part. The aforesaid point is, therefore,
answered in affirmative against the appellant and in favour of the respondent
by holding that the Appellate Court had corrected patent errors of law and had
not interfered with the pure findings of the facts not connected with the
relevant questions of law with which they were intertwined.
Point
No.6: Now is the time for us to take stock of the situation in view of our
aforesaid findings on the relevant points for determination. The final order
passed by the High Court in the impugned judgment has to be sustained. However,
one aspect of the matter cannot be lost sight of while closing the present
chapter. The respondent's services were terminated on 22nd June, 1982 and that
the termination is found to be amounting to `unfair labour practice' as per the
provisions of Section 30 of the Maharashtra Act. On this conclusion, the
appellant has to be asked to withdraw such `unfair labour practice', meaning
thereby, the impugned order has to be set aside and, thereafter, affirmative
action including reinstatement of the employee with or without back-wages could
be ordered by the Labour Court in these proceedings. However, as the High Court
has noted that reinstatement is out of question as respondent has reached the
age of superannuation, in the meantime, with effect from 3.5.1995, therefore,
at the highest the respondent is entitled to back-wages for 13 years with
gratuity and other retirement benefits. That is precisely what is ordered by
the High Court in the impugned judgement. However, learned counsel for the
appellant is right when he contends that even before the conciliator the
respondent's union on behalf of its members including the present respondent
who were all facing retrenchment suggested that they were prepared to accept
compensation @ 4 months wages per every completed year of service with a view
to settle the dispute. This suggestion on behalf of the workmen by their union
is noted by the conciliation officer in his report which reached the State
Government on 13th August, 1982. It may be seen that by that time the impugned
retrenchment order was only two months old as it was passed on 22nd June, 1982.
It is also noted by the conciliation officer that this proposal did not find
favour with the management. If it had been accepted by the management at that
time the respondent-workman would have been satisfied by way of compensation
amounting to only one third of the back- wages for each year of service. It is,
of course, true that years rolled by thereafter and the compromise did not go
through. It is also true that the value of money in 1982 was much higher than
what it is today. It is also true that the respondent has been denied not only
back-wages but also interest on the said amount which would have been available
to him years back. However, one aspect of the matter cannot be lost sight of.
There is nothing on record to show that the respondent was gainfully employed
or was not employed in any alternative avocation during all these years. It is,
of course, true that it was for the appellant to point out as to how grant of
back-wages should be reduced on account of the gainful employment of the
respondent, in the meantime. Such an effort was not made by the appellant.
However,
still one fact which stares in the face of the respondent is well established
that the appellant has tried his best to accommodate the respondent in
alternative employment at Jalgaon where hand composing department was working.
If the respondent accepted the said offer he would have earned his full wages
all throughout till retirement.
Thus
in a way the respondent also was responsible for the unfortunate situation in
which he found himself during all these years. It is also to be noted that the
complaint filed as early as on 25th June, 1982 remained dismissed in the
hierarchy of proceedings from the Labour Court onwards up to the learned Single
Judge's decision in the High Court and it is only in the Letters Patent Appeal
that he ultimately succeeded. Considering all these aspects, in our view,
interest of the justice will be served if, while confirming the final order of
the High Court impugned in this appeal, a modification is made regarding
back-wages payable to the respondent. This is required also in view of the further
fact that we disagree with the conclusion of the Division Bench of the High
Court that the appellant was guilty of `unfair labour practice' under item
Nos.1(a), (b) and (d) of Schedule IV of the Maharashtra Act and the decision of
the High Court is being confirmed regarding `unfair labour practice' of the
appellant only under item 1(f) second part of Schedule IV of the said Act.
While considering the grant of appropriate back-wages, we deem it fit to adopt
the same yardstick which was suggested by the respondent-workman's union for
all its members including the respondent that one third of back wages for each
completed year of service would be acceptable to them. We, accordingly, deem it
fit to modify the final order of the High Court to the following extent : The
appeal of the respondent before the High Court will be treated to be allowed by
holding that the appellant management had indulged in `unfair labour practice'
only under item 1(f) second part of Schedule IV of the Maharashtra Act with the
consequential direction that the appellant was not to indulge into and shall
desist from indulging into such unfair labour practice.
The
second modification in the impugned judgment of the High Court will be to the
extent that the appellant shall pay to the respondent-workman 1/3rd (i.e. 33%
approx.) of back-wages with all other consequential benefits from 22nd June,
1982 till the date of his superannuation i.e. 3rd May, 1995. The said amount
shall be paid by the appellant to the respondent within a period of 3 months
from the date of this judgment and in case of failure to pay the said amount
within that time the appellant shall be liable to pay the said amount with
running interest of 12% on the expiry of 3 months from today till the date of
actual payment. Subject to the aforesaid modifications in the judgment and
final order of the High Court impugned in this appeal, the appeal stands
dismissed.
In the
facts and circumstances of the case, there will be no order as to costs.
Back