M/S Ashok
Paper Mills Kamgar Union Vs. Union of India & Ors [1997] INSC 488 (1 May
1997)
K.
RAMASWAMY, S. SAGHIR AHMAD, G.B. PATTANAIK
ACT:
HEADNOTE:
Present:
Hon'ble
Mr. Justice K.Ramaswamy Hon'ble Mr.Justice S.Saghir Ahmad Hon'ble Mr.Justice G.B.Pattanaik
R. Venkataramani and S.M. Garg, Advs. for the Petitioner V.R. Reddy, Additional
Solicitor General, A.S. Nambiar, Harish Salve, Sr, Advs., Ms. Binu Tamta, D.S. Mehra,
A.K. Ghose, M. Mishra, Ms. Sangeeta Mandal, Chandra Bhushan Prasad, Ranjit
Kumar, B.B. Singh, E.C. Agarwala, Advs. with them for the Respondents.
O R D
E R The following Order of the Court was delivered:
The
Scheme for rehabilitation of the Ashok Paper Mills situated in Darbhanga in the
state of Bihar came to be finalised after a
prolonged negotiation and after extension of time given by this court from time
to time and it came to be approved by this court on July 8, 1996. It is rather very unfortunate that when the implementation
part has come up, some spokes have been put in attempting to re-start the
functioning of the factory. Attempts are to undo the scheme which conduct is
highly reprehensible and cannot be approved of. Nonetheless, we are not
pointing out the intention of any individual. The technicalities have been put
up in the usual bureaucratic manner to see that the scheme is not put into
operation. Some objections came to be raised by the IDBI for the grant of the
loans for rehabilitation. We directed the Cabinet secretary to look into the
matter after hearing all the parties and sort out the problems. When Shri R. Venkataramani,
learned senior counsel appearing for the petitioner, requested that it may be
given permission to participate in the deliberations before the cabinet
Secretary and an opportunity of hearing may be given to them, we gave the
directions accordingly. Now, a report has been filed by cabinet secretary
stating that IDBI is backing out and is not prepared to give the finances. This
would indicate the typical beaurocratic sickler to the letter of law
sacrificing the spirit behind the direction so that the executive itself,
without further necessity of judicial intervention, may solve the problem, for
the proper and true implementation of the Scheme.
We
have heard Mr. Harish salve, learned senior counsel appearing for the IDBI, Shri
V.R. Reddy, learned Additional solicitor General appearing for the union of India and Mr. R. Venkataramani, learned
counsel appearing for the petitioner. Shri Harish Salve points out that certain
technicalities are standing in their way due to the instructions issued by the
RBI. They have not agreed in the meeting held on June 20, 1996 that the IDBI should agree to release of the loans on the
collateral security being given by the promoters to the extent of Rs. 10 crores.
Now affidavit has been filed by Mohd. Zakir who participated in the meeting on
behalf of IDBI; obviously, he is now trying to back out from the acceptance to
the proposal he agreed in the meeting. In fact, the Industry Secretary in his
letter has categorically pointed out consensus in that behalf reached on June 20, 1996. We have little doubt to accept the
correctness of the statement made by the Industry secretary. Due to the change
in the circumstances, viz., Mr. R.P. Chhabra having taken over the charge as
chief General Manager, the IDBI seems to have raised the objections to the
implementation of the Scheme. Mr. Chhabra is present in Court, we have heard
Mr. Chhabra in person. We are not satisfied with his explanation. We think that
the attitude of the IDBI is reprehensible and cannot be condoned. The Financial
Institution when it is called upon to build up India as industrial country among word nations, it is under duty
to ensure industrial growth of the country.
When
Scheme framed was approved by this Court, it is but its duty to see that the
same is implemented. It is unfortunate that such an attempt has not been made
by the IDBI, instead of doing it, it has been a self help to the persons
managing etc. Therefore, we direct that all the persons and institutions
concerned should participate in the implementation concerned should participate
in the implementation of the scheme and Finance Secretary, Ministry of Finance,
Government of India is directed to ensure that the legal conditions are
fulfilled and the mill is rehabilitated and both, Phase-I and Phase II of the
Scheme are given effect to. The arrears to workmen would be taken care by the
Committee during the process of implementation.
The
application is accordingly ordered.
It is
hereby directed that the authorities should ensure the implementation of the
scheme framed by Government of India and approved by this Court. If anyone
stands in the way by surreptitious technicalities in the implementation of the
Scheme, it is hereby made clear that such technicalities would not stand in the
way of the implementation of the scheme and the same will be seriously dealt
with.
Back