Star Wire (India) Ltd. Vs. The State of Haryana & Ors [1996] INSC 1204 (25 September 1996)
K. Ramaswamy,
S.B. Majmudar
ACT:
HEAD NOTE:
O R D
E R
Delay
condoned.
This
special leave petition arises from the judgment of the Punjab & Haryana
High Court made on April
25, 1996 in LPA No.
437/96. Notification under Section 4(1) of the Land Acquisition Act, 1894 [for
short, the 'Act'] was published on June 1, 1976. Declaration under Section 6 of the
Act was published on February
16, 1977. The award
was passed on July 3,
1981. Thereafter, the reference
also become final. The petitioner has challenged the notification, the
declaration and the award as illegal, it contends that the award does not come
in the way of the petitioner in filing the writ petition on January 21, 1994. The High Court has dismissed the
writ petition on the grounds of laches.
Shri
P.P. Rao, learned senior counsel for the petitioner, contends that the
petitioner had no knowledge of the acquisition proceedings; as soon as it came
to know of the acquisition, it had challenged the validity of the acquisition
proceedings and, therefore, it furnishes cause of action to the petitioner. He
further contends that the writ petition could not be dismissed on the ground of
laches but was required to be considered on merits. We find no force in the
contention. Any encumbrance created by the erstwhile owner of the land after
publication of the notification under Section 4(1) does not bind the State if
the possession of land is already taken over after the award came to be passed.
The land stood vested in the State free from all encumbrances under Section 16.
In Gurmukh Singh & Ors. vs. The State of Haryana [J] 1995 (8) SC 208], this
Court had held that a subsequent purchaser is not entitled to challenge the
legality of the acquisition proceedings on the ground of lack of publication of
the notification. In Y.N. Garg vs State of Rajasthan [1996 (1) SCC 284] and Sneh
Prabha vs. State of U.P. [1996 (7) 325], this Court had held the alienation
made by the erstwhile owner of the land after publication of the notification
under Section 4(1), do not bind either the State Government or the beneficiary
for whose benefit the land was acquired. The purchaser does not acquire any
valid title. Even the colour of title claimed by the purchaser was void. The
beneficiary is entitled to have absolute possession free from encumbrances. In
U.P. Jal Nigam, Lucknow through its Chairman & Anr. vs.
M/s Kalra Properties (P) Ltd., Lucknow & Ors. {(1996) 1 SCC 124], this
Court had further held that the purchaser of the property, after the
notification under Section 4(1) was published, is devoid of right to challenge
the validity of the notification or irregularity in taking possession of the
land before publication of the declaration under Section 6.
As
regards laches in approaching the Court, this Court has been consistently
taking the view starting from State of Madhya Pradesh & Anr. vs. Bhailal Bhai
& Ors. [AIR 1964 SC 1006] wherein a Constitution Bench had held that it is
not either desirable or expedient to lay down a rule of universal application
but the unreasonable delay denies to the petitioner, the discretionary
extraordinary remedy of mandamus, certiorari or any other relief. The same was
view reiterated in catena of decisions, viz., Rabindranath Bose & Ors. vs.
The Union of India & Ors. [(1970 (1) SCC
84]; State of Mysore & Ors. vs. Narsimha Ram Naik [AIR 1975 SC 2190];
Aflatoon
& Anr. vs. Lt. Governor of Delhi [ (1975)
4 SCC 285]; M/s. Tilokchand Motichand & Ors. vs. H.B. Munshi, Commissioner
of Sales Tax, Bombay & Anr. [AIR 1970 SC 898]; State
of Tamil Nadu & Ors. etc. V. L. Krishnan & Ors. etc. [JT 1995 (8) SC
1]; Improvement Trust, Faridkot & Ors. vs. Jagjit Singh & Ors. [1987
Supp. SCC 608]; State of Punjab & Ors. vs. Hari Om Co-operative House
Building Society Ltd., Amritsar [1987 Supp. SCC 687]; Market
Committee, Hodal vs. Krishan Murari & Ors. [JT 1995 (8) SC 494] and State
of Haryana vs. Dewan Singh [(1996 (7) SCC 394]
wherein this Court had held that the High Court was not justified in
interfering with the acquisition proceedings. This Court in the latest judgement
in Municipal Corporation of Great Bombay vs. The Industrial Development &
Investment Co. Pvt. Ltd. & Ors. [JT 1996 (8) SC 16], reviewed the entire
case law and held that the person who approaches the Court belatedly will be
told that laches close the gates of the Court for him to question the legality
of the notification under Section 4(1), declaration under Section 6 and the
award of the Collector under Section 11.
In
this case, admittedly, the petitioner has purchased the property covered by the
notification under Section 4(1) after it was published and, therefore, it's
title is a void title. It has no right to challenge the acquisition proceedings
much less the award. The Division Bench of the High Court has exhaustively
reviewed the case law to negate the claim of the petitioner. We do not find any
illegality in the judgment of the High Court warranting interference.
The
special leave petition is accordingly dismissed.