Haryana
State Industrial Development Corporation Ltd. Vs. Inderj [1996] INSC 97 (18 January 1996)
Kirpal
B.N. (J) Kirpal B.N. (J) Verma, Jagdish Saran (J) Kirpal.J.
CITATION:
1996 SCC (7) 339 JT 1996 (1) 573 1996 SCALE (1)469
ACT:
HEAD NOTE:
Leave
granted
In
this appeal, by special leave, there is challenge to two judgments of the
Punjab & Haryana High Court. the first being judgment dated 14.11.1994
whereby the respondent's writ petition was allowed and the appellant was
directed to allot a plot of land measuring half acre and the second judgment is
dated 9.8.1995 whereby the Review Application filed by the appellant herein,
was dismissed.
The
relevant facts are that the appellant is a Government company which is, inter alia,
engaged in carrying out activities towards the advancement of industrial
development in the State of Haryana. In
the course of its activities, in 1983 it invited applications for allotment of
certain plots of land to set up industrial units in Gurgaon.
The
respondent applied for an industrial plot in Phase-IV, Udyog Vihar, Gurgaon for
setting up a unit to manufacture reinforced concrete cement pipe and assessories.
Allotment of plot of one acre in favour of the respondent was approved and he
was requested to deposit 15% of the cost of land vide letter dated 27.10.1983.
On the said 15% having been deposited by the respondent, he was offered an
industrial plot No. 359 measuring one acre in Udyog Vihar, Phase-IV, Gurgaon at
the tentative rate of Rs. 120/- per sq. meter. A provisional letter of
allotment dated 27.12.1984 was issued and it was made clear therein that the
respondent was required to fulfil certain pre-requisites connected with the
implementation of the proposed project before the final allotment could be made
in his favour. These pre-requisites were to be completed within 120 days of the
date of allotment. This letter further stipulated that the provisional letter
of allotment will not give any legal right of allotment unless the final
allotment letter is issued.
It is
the case of the appellant that the respondent neither complied with the
formalities, as contemplated by the aforesaid letter dated 27.12.1984, within
the time schedule nor deposited any further amount with the appellant.
According to the appellant, for administrative reasons the industrial plot No.
359 which had been allotted to the respondent was changed to two plots
measuring half acres each and renumbered as plot Nos. 374-375. Another
provisional letter of allotment dated 5.11.1986 was written to the respondent stating
therein that it had been decided to offer him industrial plot Nos. 374-375
measuring one acre at the tentative rate of Rs. 120-60 per Sq. yard. But,
before the allotment was issued in his favour, he was required to comply with
certain pre-requisites enumerated in the said letter of allotment which were
connected with the implementation of the respondent's proposed project. These
pre-requisites included the unit being registered with the appropriate
authority, drawing of the unit approved, building and machinery being
sanctioned and list of plant and machinery to be installed at the unit. These
pre- requisite formalities were required to be completed within 120 days of the
said letter dated 5.11.1986 and it was stipulated that if this was nor done within
the specified time, then the provisional letter of allotment shall be treated
as having been withdrawn, unless its validity was extended in writing by the
Corporation. It was again mentioned in the letter dated 5.11.1986 that the said
letter shall not give the respondent any legal right for allotment unless the
final allotment is issued.
Soon
after the despatch of the letter dated 5.11.1986, the appellant learnt that the
aforesaid plot Nos. 374-375 were not available and had been wrongly offered to
the respondent. The respondent was, accordingly, informed vide letter dated
10.11.1986 that the plot Nos. 374-375 had been wrongly mentioned in the
provisional letter of allotment dated 5.11.1986 and that the respondent's case
for allotment of alternative plot of one acre had been considered and approved
but the plot number would be intimated shortly.
Thereafter,
it seems that discussion took place between the appellant and the respondent
regarding the allotment of one acre plot. The case of the appellant is that a
mutual agreement was arrived at as a result of which letter dated 5.1.1989 was
written by the appellant to the respondent whereby the respondent was offered a
half acre plot in Udyog Vihar, Phase-IV at the old rate of Rs. 120/- per sq.
meter.
It was
further stated in this letter that with this offer of half acre of plot at Rs.
120/- per sq. meter "the present case will be treated as closed
thereafter" and request for additional space would be considered on
submission of a fresh application, but the rate of land will be at the rate
prevailing at that time. The respondent was requested to confirm the acceptance
of an area of 2000 sq. meters for the proposed project and this acceptance was
required to be given within 15 days of the issue of the said letter. Vide
letter dated 14.1.1989 the respondent conveyed his acceptance of half acre plot
and observed as follows:
"However,
I accept 1/2 acre plot as desired by you in the letter dated 5.1.1989 mentioned
above at the original rates, but reserve the right to claim further 1/2 acre
plot it may be mentioned that I have deposited the required money for 1 acre
plot." On the receipt of the aforesaid reply, a formal provisional letter
of allotment dated 24.2.1989 was issued to the respondent whereby two industrial
plot Nos. 1 & 2 measuring 1000 sq. meters each at Udyog Vihar, Phase-IV at
the tentative rate of Rs. 120 per sq. meter was proposed to be allotted to the
respondent. By this letter, the respondent was again required to complete the
pre-requisites connected with the implementation of the respondent's project
and he was also asked to convey his acceptance to the conditions within 30
days. In this letter, it was further stated as under:
"Reverting
to your letter of 14th January, 1989 we would like to clarify here that this
offer for 1/2 acre size plot has been made in your favour as per the concept
you given to our Managing Director during the course of discussion on 3rd
December and it will not be possible to give you any more plot against this
application. However, you are at liberty to apply for plot against our further
advertisement on new rates and on terms and conditions prevalent at that time
and in that event your case will be considered alongwith others on merits.
You
may please note that since the plot has been offered to you at the old rate of Rs.
120/- per sq. meter, the corporation shall not be in a position to accede to
any of your request for transfer of plot and that your are required to
implement your project within one year from the date of issue of allotment
letter. In the end, we remind you to complete the conditions mentioned at (i)
to (iii) and furnish us proof thereof within the stipulated period to enable us
to issue the allotment letter." (emphasis added) In response to the
aforesaid provisional letter of allotment dated 24.2.1989, the respondent wrote
a letter dated 4.3.1989 in which it was stated as follows:
"Offer
of half acre plot Nos. 1 & 2 measuring 1000 sq. meters each (total 2000 sq.
meters) is acceptable. I am in touch with the District Industries Center, Divisional Town Planner and Haryana Financial Corporation.
I hope to complete all the formalities very soon." On the receipt of the
aforesaid letter, a final letter of allotment dated 6.7.1990 was issued to the
respondent.
This
was followed by the signing of an agreement between the parties after which the
possession of the said plots was handed over to the respondent on 4.9.1990.
The
respondent then filed a Writ Petition No. 5123 of 1994 in the Punjab and Haryana High Court. Basing his
claim on the earlier provisional allotment letter dated 27.12.1984, the
respondent, inter alia, prayed that the appellant herein should and ought to
deliver the remaining half acre of plot. The appellant herein contended that
the letter dated 27.12.1984 had been superseded and a fresh agreement had been
entered into between the parties after the respondent herein had accepted 2000
sq. meters of land which had been allotted to him. It was also stated that one
of the conditions of allotment vide letter dated 6.7.1990 was that the unit was
to be set up within two years from the date of allotment put the respondent had
even failed to utilize the plots of land which had been handed over to him.
The
High Court by its judgment dated 14.11.1994 came to the conclusion that there
was no reason shown by any correspondence on record as to why the area of the
plot which was to be allotted to the respondent vide allotment letter dated
24.12.1984 had been reduced. It did not accept the contention of the appellant
herein that while accepting plot Nos. 1 & 2 measuring 1000 sq. meters each,
the respondent had given up his right for the remaining half acre of land. The
High Court, accordingly, directed the appellant to allot the remaining half
acre of plot within a specified period.
Thereafter,
Review Application No. 41 1995 was filed by the appellant herein but the same
was dismissed by judgment dated 9.8.1995.
From
the facts as narrated above, it appears that the High Court erred in directing
that a further plot of half acre should be allotted to the respondent. The High
Court did not appreciate that the correspondence on record of the case clearly
shows that the respondent was stopped from making the claim for a further area
of half acre after head accepted the allotment of plot Nos. 1 & 2 measuring
2000 sq.meters in total. In the present case even though in the letter dated
27.12.1984 the respondent had been offered a plot of land measuring one acre
yet by subsequent letter dated 5.1.1989, a revised offer was made whereby he
was offered a plot measuring half acre at the old rate of Rs.120/- per sq.
meter as a special case. In this letter, it was stated that while making this
offer the case would be considered as closed and the respondent was requested
to confirm the acceptance of the area of 2000 sq. meters. Vide letter dated
14.1.1989, a conditional acceptance was conveyed by the respondent whereby he
had stated that he accepted the half acre of plot but he reserve the right to
claim further half acre of plot of this, the appellant wrote letter dated
24.2.1989 again stating that half acre of land was offered to him and that he
was clarified that this offer was made in his favour as per the consent given
by him to the appellant's Managing Director during the course of discussion on
3.12.1990. It is in response to this letter seeking the aforesaid clarification
that the respondent wrote the letter dated 4.3.1989 wherein he unconditionally
accepted the plot Nos. 1 and 2. It is only thereafter that the formal allotment
letter dated 6.7.1990 was issued to him which was followed by a formal
agreement and handing over possession of the said plot Nos. 1 and 2 to the
respondent.
There
can be no manner of doubt that the appellant had categorically stated that it
was unable to offer the respondent an area larger than half an acre and
acceptance of this was insisted upon and the same was given by the respondent
vide letter dated 4.3.1989. Had this unconditional acceptance not been given,
it would appear.
The
appellant would not have made the allotment in favour of respondent.
It is
further to be borne in mind that the letter dated 27.12.1984, on which reliance
is placed by the respondent and on the basis of which the High Court had given
relief, it was stated that the said letter was only a provisional letter of
allotment and it was specifically mentioned therein that the same shall not
give you any legal right for allotment unless a final allotment letter is
issued". There was, therefore, no final commitment to allot one acre of
land to the respondent and the High Court clearly misconstrued the said
provisional letter of allotment to mean as if the respondent had acquired a
vested right to obtain an allotment of one acre of land.
The
respondent was not only stopped from claiming an additional half acre of land
but even the letter dated 27.12.1984 did not give the respondent any legal
right to insist upon the allotment of one acre of land because the only letter
of final allotment which was issued in favour of the respondent, was the one
dated 6.7.1990 whereby only half acre of land was allotted and the said
allotment was accepted by the respondent without demure, till he chose to file
the Writ Petition four years thereafter.
In
view of the above, the appellant was not liable to allot an additional half
acre of land to the respondent to whom plot Nos. 1 & 2 at Udyog Vihar,
Phase-IV, Gurgaon measuring 2000 sq. meters had already been validly allotted.
For
the aforesaid reasons, this appeal is allowed and the judgments of the High
Court dated 14.11.1994 in C.W.P.No. 5123/1994 and dated 18.8.1995 in Review
Petition No. 41 of 1995 are set aside, the result of which would be that the
Writ Petition filed by the respondent before the High Court would stand
dismissed Parties to bear their own costs.
Back
Pages: 1 2