K. Sasidharan
Vs. Kerala State Film Development Corpn [1994] INSC 180 (17 March 1994)
Ramaswamy,
K. Ramaswamy, K. Venkatachala N. (J)
CITATION:
1994 AIR 2534 1994 SCC (4) 135 JT 1994 (3) 578 1994 SCALE (2)811
ACT:
HEAD NOTE:
ORDER
1.
Leave granted. Heard both the counsel.
2. The
appellant had on 27-1-1982 entered into a contract with the
respondent to construct a theatre. He completed the work and handed over the
same to the respondent in May 1985. During the execution of the contract a
dispute had arisen on certain items of the work which was sought to be decided
by arbitration. The appellant, therefore, filed OS No. 20 of 1986 in the Court
of Subordinate Judge, Trivandrum under Section 20 of the Arbitration
Act, 1940, for short 'the Act' for reference to an Arbitrator. The respondent
contended that there is no arbitrable agreement under the contract. Overruling
the objection, the Subordinate Judge by his order dated 5-6-1986 held that clause 73 of the Madras Detailed Standard
Specifications for short 'MDSS' would apply to the dispute which contains an arbitrable
clause and, therefore, by order dated 2-7-1986 appointed a retired District Judge
as an Arbitrator. On appeal by the respondent in MFA No. 460 of 1986, by order
dated 15-12- 1986, the Division Bench of the Kerala High Court held that clause
73 of MDSS is inapplicable. There is no arbitrable agreement for reference to
the Arbitrator. Thus, this appeal by special leave.
3. Shri
E.M.S. Anam, learned counsel for the appellant, placing reliance on clause 12
of the "General Condition of the Contract" contended that all items
of work referred to therein would include MDSS in the addenda volume. Clause 73
of the arbitrable agreement therein gets attracted to the dispute. Therefore,
the trial court was right in its conclusion that the dispute is arbitrable
under clause 73.
The
High Court was not right in its contra conclusion.
4.
Having given our anxious consideration, we find that the contention raised by
the appellant is not tenable.
Admittedly,
the contract contains Article 60 which provides .LM15 " arbitration of any
dispute or difference between the parties to the contract either during the
progress or after completion of the works or the interpretation of the contract
or as any matter or thing arising there under except as to the matters left to
the sole discretion of the Corporation Engineer under the clauses of the
contract." While entering into the contract this clause was admittedly
excluded. In Article 2 of the "General Conditions of the Contract"
clause (b) provides that :
137
"the Original Agreement, with its accompanying Schedules forms part of the
Contract Documents and shall be kept by the Corporation but the Contractor
shall be supplied with a copy of the agreement and copies of Tender Notification,
General Conditions of the Contract, Specifications, Drawings and relevant
schedules all duly attested by the Contractor and the Managing Director".
Clause
(f) postulates that "the terms of the Contract cannot be added to, varied
or reduced by any oral agreement previous or subsequent to its signature".
5.
Clause 12 relied upon by Shri Anam, the relevant part reads thus:
"And
item of work shall be carried out as per Madras Detailed Standard
Specifications and its addenda volume and shall be deemed to have been included
here." What clause 12 postulates is that the general conditions regarding
the execution of the work will be as carried on in accordance with the
conditions etc. contained in MDSS and addenda. General Conditions of the Contract
provided the accepted rates, units, tentative quantities etc. which were given
in the Schedule A and the time schedules for the work was given in Schedule B.
The list and details regarding supply of drawings were given in Schedule C. The
short description given in the Schedule A for different items were only the
general specifications. Thereafter, the above 12th clause has been added,
namely, "All items of work shall be carried out as per Madras Detailed
Standard Specifications and its addenda volume and shall be deemed to have been
included here." The arbitration agreement is collateral to the substantial
stipulation of the contract. It is merely procedural and ancillary to the
contract and it is a mode of settling the disputes, though the agreement to do
so is itself subject to the discretion of the court. Arbitration is
distinguishable from other clauses in the contract. The other clauses set out
the obligations which the parties have undertaken towards each other binding
them, but the arbitration clause does not impose on one of the parties an
obligation towards the other. It embodies an agreement of both parties with
consensus ad idem that if any dispute arises with regard to the obligations
undertaken therein which one party has undertaken towards the other, such a
dispute shall be settled by a tribunal of their own constitution. Therefore,
arbitration clause in a contract, stands apart from rest of the contract, it
must be construed according to its language and in the light of the
circumstances in which it was made.
Russel
on Arbitration, 19th Edn., p. 27 states that :
"A
court cannot make a contract between the parties. In general its power would
appear to end with interpretation. It applies equally to the establishment of
an arbitration agreement."
6. The
appellant and the respondent having specifically excluded the arbitration
clause in the contract, by necessary implication they excluded clause 73 in
MDSS, If it were, to be contra it must expressly and specifically 138 be
incorporated in the contract which admittedly was not done. When the parties to
the agreement, in terms of the documents, have not incorporated the arbitration
agreement in clause 73 of MDSS, it cannot, by implication, be imported by
interpretation that the terms of clause 73 including arbitration clause therein
stands attracted. By necessary implication, it conflicts with the expressly
agreed terms of the contract. Thereby, it is manifest that what the terms in
the MDSS, referred to in clause 12 is only of the terms referable to the
execution of the work, etc. and not one concerned with an agreement to refer
any dispute arising between the parties to an arbitration, at a later point of
time, or during the course of the execution of the work or after the completion
thereof of any dispute arising between the parties in relation to the contract.
7.
Therefore, the High Court is right in its conclusion that there is no arbitrable
agreement for reference to the Arbitrator. The civil court in the circumstances
cannot exercise its power under Section 20 of the Act to appoint an arbitrator
and refer the dispute for arbitration.
8. The
appeal is accordingly dismissed. No costs.
Back