G. Ramachandra
Reddy Vs. Chief Engineer [1994] INSC 275 (29 April 1994)
Ramaswamy,
K. Ramaswamy, K. Venkatachala N. (J)
CITATION:
1994 AIR 2381 1994 SCC (5) 142 JT 1994 (4) 181 1994 SCALE (2)1057
ACT:
HEAD NOTE:
ORDER
1.
Leave granted.
2.
This appeal arises from the judgment of the Division Bench of Madras High Court
in OSA No. 281 of 1992 dated 5-1-1993.
3.The
appellant's contract was terminated by the respondent and in consequence
thereof, by notices dated 23-7-1991 and 21-8- 1991, the appellants exercising
the option under clause 17 of General Condition of Contract, called upon the
Engineer-in-Chief to appoint sole Arbitrator, in terms of the contract, to
adjudicate the dispute that had arisen between them. Since no action was taken
by the respondents, the appellant filed a suit on 43-1992 under Section 20 of
the Arbitration Act, 1940 for short 'the Act', requesting the Court to appoint
an arbitrator.
Learned
Single Judge of the High Court by his judgment dated 23-9-1992 appointed Justice M.A. Sattar Syeed, a retired Judge
of the High Court as sole Arbitrator. On appeal, a Division Bench of that High
Court agreed with the Single Judge that despite the issue of notice calling
upon the respondent to appoint the Arbitrator in terms of the contract, no
action was taken by the respondent. Its suggestion that the respondent could
agree for appointment of any one of the five arbitrators named in the list
given by the appellant did not find favour with the respondent.
Yet,
the Division Bench directed the respondent to appoint an arbitrator within 15
days from that date and declared that in case the respondent failed to do so,
the arbitrator appointed by the Single Judge would be deemed to have been
appointed under Section 20. The appellant, feeling aggrieved against the
judgment of the Division Bench, has filed the appeal.
4.Shri
K. Parasaran, learned Senior Counsel for the appellant contended that once the
appellant had issued notice to the respondent calling upon him to appoint an
arbitrator in terms of the contract, the failure to do so had given right to
the appellant to invoke the jurisdiction of the civil court under Section 20(4)
of the Act and that court got jurisdiction to appoint the Arbitrator of its
choice. When the learned Single Judge had exercised its jurisdiction under
Section 20(4) of the Act and appointed the arbitrator, the Division Bench
committed a manifest error of law in interfering with that appointment. Shri
A.S. Nambiar, the learned Senior Counsel for the respondent, sought to support
the Division Bench judgment relying upon the judgment of this Court in Union of
India v. Prafulla Kumar Sanyal1 wherein this Court had observed that before
appointing an arbitrator by the court itself "it is desirable that the
court should consider the feasibility of appointing an arbitrator according to
the terms of the contract" and the issuance of the notice giving 15 days'
time as contemplated under Section 8(a) of the Act did not arise on the facts
in the present case.
Therefore,
his contention was that though the appellant (sic respondent) had not appointed
the arbitrator before the expiry of 15 days' notice before the matter was
decided by the Division Bench the appellant was given an option to accept 1
(1979) 3 SCC 631 145 anyone among the five named persons to be a sole
Arbitrator and having failed to accept anyone, it is not open to the appellant
to impugn the correctness of legality of the appointment of the Arbitrator by
the Division Bench, in terms of the contract, 5.We find no force in the contentions
of Shri Nambiar. This Court interpreting Section 20(4) of the Act, has, in Prafulla
Kumar case' itself, specifically laid down that sub-section (4) requires
"that the court shall make an order of reference to the arbitrator
appointed by the parties under the agreement or otherwise if such arbitrator
had not been appointed when the parties cannot agree to appoint an arbitrator,
the Court may proceed to appoint an arbitrator by itself'. In that case, the
parties agreed before this Court, expressing their desire that the President
should be asked to appoint an arbitrator as contemplated under clause 29 within
two months from the date of the order passed by this Court. In that backdrop
this Court had expressed the desirability or the feasibility to appoint an
arbitrator in terms of the contract. Those observations of this Court cannot be
understood or torn out of context and read in isolation. The court should endeavour
that the contract should always be given effect to, though the contracting
party had failed to act according to contract. It is to be seen, whether the
contract provided for the appointment of a named arbitrator, and if so, the
parties normally would be bound by the terms of contract and the court would
not be justified to appoint any arbitrator unless the arbitrator refused or
neglected to enter upon the reference, etc. In the absence of any named
arbitrator it would be open to the contracting parties to agree for an
appointment of an arbitrator by agreement even after the proceedings were laid
in the Court under Section 20 of the Act.
In the
absence of any such agreement, the Court gets jurisdiction and power to appoint
an arbitrator. In Prafulla Kumar case' no notice was given to the appellant to
appoint an arbitrator in terms of the contract before the suit was filed and no
action was taken pending suit except contending that the matter was under
active consideration. In that context, it was held that in the absence of any
agreement, the court gets jurisdiction. In Nandyal Co-op. Spinning Mills Ltd.
v. K. V. Mohan Rao2 15 days' notice was given to the respondent to act upon the
terms of the contract to appoint an arbitrator, but it was not done, although
it was stated that the matter was under consideration, It was, therefore, held
thus: (SCC pp. 660-6 1, para II) "It would thus be clear that if no
arbitrator had been appointed in terms of the contract within 15 days from the
date of receipt of the notice, the administrative head of the appellant had
abdicated himself of the power to appoint arbitrator under the contract. The
court gets jurisdiction to appoint an arbitrator in place of the contract by
operation of Section 8(1)(a). The contenti on of Shri Rao, therefore, that
since the agreement postulated preference to arbitrator appointed by the
administrative head of the appellant and if he neglects to appoint, the only
remedy open to the contractor was to have recourse to civil suit is 2 (1993) 2
SCC 654 146 without force. It is seen that under the contract the respondent
contracted out from adjudication of.
his
claim by a civil court. Had the contract provided for appointment of a named
arbitrator and the named person was not appointed, certainly the only remedy
left to the contracting party was the right to suit. That is not the case on
hand. The contract did not expressly provide for the appointment of a named
arbitrator. Instead power has been given to the administrative head of the
appellant to appoint sole arbitrator. When he failed to do so within the
stipulated period of 15 days enjoined under Section 8(1)(a), then the
respondent has been given right under clause 65.2 to avail the remedy under
Section 8(1)(a) and request the court to appoint an arbitrator. If the
contention of Shri Rao is given acceptance, it would amount to putting a
premium on inaction depriving the contractor of the remedy of arbitration
frustrating the contract itself." 6.Thus when the notice was given to the
opposite contracting party to appoint an arbitrator in terms of the contract
and if no action had been taken, it must be deemed that he neglected to act
upon the contract. When no agreement was reached, even in the court between the
parties, the court gets jurisdiction and power to appoint an arbitrator. Even
if Section 8(a) per se does not apply, notice was an intimation to the opposite
contracting party to act upon the terms of the contract and his/its non-availment
entails the forfeiture of the power to appoint an arbitrator in terms of the
contract and gives right to the other party to invoke the court's jurisdiction
under Section 20. In the instant case the respondent did not appoint an
arbitrator, after the notice was received. The respondent averred in the
written statement that it was under consideration. Even before the learned
Single Judge he did not even state that he was willing to appoint an
arbitrator. The learned Single Judge rightly exercised the power under Section
20(4) of the Act and appointed the Arbitrator. The Division Bench, therefore,
was not right in holding that the appellant has by giving option to the
respondent to agree for appointment of an arbitrator out of the five named
persons had left it to the respondent to appoint an arbitrator and allowing
respondent to appoint an arbitrator. On the other hand, the appointment of an
arbitrator made by the learned Single Judge must be deemed to have been
approved by us.
7.The
appeal is accordingly allowed. The judgment of the Division Bench is set aside
and that of the learned Single Judge is restored. In the circumstances, parties
are directed to bear their own costs.
Back