Union of India Vs. Jain Associates [1994] INSC 246 (19 April 1994)
Ramaswamy,
K. Ramaswamy, K. Venkatachala N. (J)
CITATION:
1994 SCC (4) 665 JT 1994 (3) 303 1994 SCALE (2)604
ACT:
HEAD NOTE:
The
Judgment of the Court was delivered by K. RAMASWAMY, J.- Special leave granted.
2. The
respondent had entered into a contract on 7-1-1983 to construct 13 units of Type-V
Quarters at the estimated cost of Rs 27,34,000. He was to complete the
construction and hand over possession on 13-8-1984. Despite extension of the time on 7
occasions, finally up to 30-6-1988, the construction was not completed
resulting in termination of the contract.
As up
to 34th bill the appellant paid to the respondent a sum of Rs 24,34,100.91 ps.
towards the executed work. The contractor laid proceedings under Section 20 of
the Arbitration Act, 1940 (for short 'the Act') for reference to arbitrate the
disputes. The joint arbitrators appointed thereon entered upon reference on 10-4-1989 and nominated Mr A. Biswas, the second respondent as
an umpire. Since the joint arbitrators could not make and publish the award
within the time, the umpire was called upon to enter upon the reference.
Accordingly on 25-4-1990 the umpire had entered upon the
reference and made an interim award on 26-7-1990 for a sum of Rs 6,02,000. The
contractor laid his claim for a sum of Rs 37,37,885. The appellant laid
counter-claim for Rs 9,49,701.50 ps. On 3-9-1990 the appellant requested the umpire
to consider the counter- claim. On 4-9-1990, the umpire refused to consider the
counter-claim on the ground of belated counter-claim. On request the time to
make and publish the award was extended up to 31-1-1991. The umpire held finally sitting on 19-12- 1990 (it is
disputed across the bar by the contractor) and he made the award on 24-12-1990 for a sum of Rs 24,18,320 in favour of the
contractor. The umpire also awarded interest at 18% up to 10-4-1989 and post-award interest. He did not grant any pendente
lite interest. The appellant challenged the award on diverse grounds under
Sections 30 and 33 of the Act. Ultimately the Division Bench of the Calcutta
High Court in Appeal No. 453 of 1991 dated 16-9-1992 668 confirmed the award
for a sum of Rs 20,07,320 and awarded pendente lite interest. On a review, it
was held by an order dated 4-2-1993 that the Bench committed mistake in
thinking that the umpire granted pendente lite interest and is a mistake of
fact and law but had confirmed the pendente lite interest on its power. Thus
these two appeals, with a delay of 137 days in filing the appeal against
original judgment. The delay is condoned.
3. The
learned Solicitor General contended that the Division Bench having held that
the umpire committed illegality in awarding damages twice over on claims 11 and
12, though the contractor was entitled to damages only in respect of one claim,
committed manifest error of law in upholding the entire award. The fact that
the umpire had committed illegality in awarding damages twice over would
indicate his non-application of judicious mind to the claims in an objective
manner. In a non-speaking award it is difficult to decide how he adjudged the
claims. Thereby he committed misconduct which entails the setting aside of the
award as a whole and the doctrine of severability becomes inapplicable to the
facts of this case. His next contention was that under clause 62 of the general
conditions, certain matters were to be finally determined by the Railways and
the arbitrator lacked jurisdiction to decide these claims and thereby the award
gets vitiated by manifest illegality on its face. There was sufficient time for
the arbitrator, even after the extended time to make the award in respect of
the counter-claim. But was not done, which would also prove the non-application
of judicious mind in an objective and dispassionate manner and thereby the
award gets vitiated by misconduct committed by the umpire. The 3rd contention
is that the court lacked power to award pendente lite interest by operation of
Section 29 of the Act. Shri Soli Sorabjee, the learned Senior Counsel for the
respondent-contractor contended inter alia that though the award is a
non-speaking award since the umpire granted each claim separately, the claims
on items 11 and 12 are severable from the rest of the award. The High Court
upheld the highest of the two claims granted by the umpire. The claim for loss
of profits on item 11 and for damages on item 12 are distinct and separate
concepts. The umpire, therefore, was justified to grant separate amounts on
each of the claims which would show active consideration and application of the
mind. Hence it is Dot a misconduct. Even otherwise they are severable from the
rest of the award, which could be sustained. The grant of pendente lite
interest by arbitrator was not a settled principle till the Constitution Bench
decision of this Court in Secretary, Irrigation Department v. G. C. Roy' was
rendered. Earlier Division Bench of this Court in Executive Engineer
(Irrigation) v. Abhaduta Jena2 where it was held that arbitrator had no power
to award interest pendente lite, was overruled. In this twilight zone of law,
the arbitrator did not award interest pendente lite. In view of the
Constitution Bench judgment in G. C. Roy case, the grant of pendente lite
interest by the court is legal. Even otherwise if this 1 (1992) 1 SCC 508 2
(1988) 1 SCC 418:(1988) 1 SCR 253 669 Court finds that the High Court committed
illegality in granting interest pendente lite the matter requires remittance to
the umpire, for fresh decision in this behalf.
Similarly
on the counter-claim, it was contended, that no counter-claim in fact was laid,
although belatedly a counter-statement was made, as found by the umpire. This
point was not argued before the Single Judge nor seriously disputed before the
Division Bench. Even otherwise, this dispute also could be remitted to the
umpire for reconsideration.
4. The
first question that arises for consideration is whether the court could award
interest pendente lite.
Section
29 of the Act says that insofar as award is, for the payment of money, the
court may in the decree, order interest from the date of the decree at such
rate as it deems reasonable, to be paid on the principal sum adjudged by the
award and confirmed by the decree. In Srikantia & Co. v. Union of India3 it
was held that Section 29 carries with it the negative import that it shall not
be permissible to the court to award interest on the principal sum adjudged in
the award for a period prior to the date of the passing of the decree. The same
principle was reiterated in Ram Singh v. Ram Singh4. Section 29 of the Act
empowers the court, that where the award is for payment of money, to grant
reasonable rate of interest on the principal amount adjudged and confirmed in
the decree, only from the date of the decree. Section 34 CPC empowers the
court, where there is a decree for payment of money to grant interest pendente lite
and future, till the date of realisation. Since Section 29 of the Act enables
the court to grant interest on the principal amount adjudged in the award and
confirmed in the decree only from the date of the decree, it carries a negative
import with it that the court has no power to grant interest pendente lite. The
High Court, therefore, was not right in granting interest pendente lite, which
the arbitrator himself had not granted.
5. The
second question relates to rejection of the counter- claim. It is seen that the
point was taken before the Single Judge that counter-claims were laid before
the arbitrator.
The
record also discloses that the appellant laid counter- claim. On 4-9-1990 the umpire refused to consider the counter-claim. It
is further seen that the parties mutually agreed to extend time to enable the
arbitrator to make and publish the award by 31-1-1991. Whether or not the final sitting was held on 19-12-1990, the fact remains that there was ample time for the
umpire to consider the counter-claim of the appellant and pass appropriate
award in that behalf.
But he
failed to do so. This would bear upon the finding on second question raised by
the parties and shows that the rejection of counter-claim was unwarranted.
6. The
crucial question is whether the umpire committed misconduct by non-application
of mind to the claims and counter-claims and of its consequences. Claim 11 is
founded upon the allegations of delay, ]aches, negligence and default on the
part of the appellant, said to have resulted in loss of profits to the
contractor in a sum of Rs 4,93,696 and the umpire 3 AIR 1967 Bom 347 4 AIR 1985
Raj 148 : 1984 WLN 572 670 awarded Rs 4,11,400. Claim 12 again founded upon the
self same alleged laches and negligence of the appellant for the damages
suffered by the contractor in a sum of Rs 12,00,000 and the umpire awarded Rs
6,00,000. The High Court found in its judgment that "there is much
substance in the submission of the learned counsel for the petitioner that the
umpire has given damages twice over against the same claim though shown as two
claims, namely, claims 11 and 12 and the claimant is not entitled to both the
claims due to damages".
"There
is an error of law as well as fact" but "in the interest of justice
and fair play the lesser amount of Rs 4,11,400 against claim 11 is omitted and Rs
6,00,000 towards claim 12 is retained". Section 73 of the Contract Act
provides that when a contract has been broken, the party which suffers by such
breach is entitled to receive from the party which has broken the contract,
compensation for any loss or damages caused to him thereby which naturally
arose in the usual course of things from such breach. A perusal of both the
claims would show that claim 11 is founded on loss of profits and claim 12 is
founded for damages, based upon delay, laches and negligence alleged against
the appellant, resulting in breach of the contract. In other words the
contractor claimed compensation for breach of contract arising under Section 73
of the Contract Act. The respondent, it is held by the Division Bench, is given
same type of damages twice over and that holding is not challenged by
respondent. Yet the question is whether the umpire had applied his mind in a
judicious manner so as to bind the parties by his award made on various claims.
In Law of Arbitration, by Justice Bachawat, a former Judge of this Court at p.
316, it is stated that:
"An
arbitrator is not a conciliator. His duty is to decide the question submitted
to him according to the legal rights of the parties and not according to what
he may consider fair and reasonable." Russell on Arbitration, 20th Edn. at
p. 318 also lays the same principle.
7. In
K.P. Poulose v. State of Kerala5 this Court held that misconduct
under Section 30(a) does not connote a moral lapse. It comprises legal
misconduct which is complete if the arbitrator, on the face of the award,
arrives at an inconsistent conclusion even on his own finding, by ignoring
material documents which would throw abundant light on the controversy and help
in arriving at a just and fair decision. It is in this sense that the
arbitrator has misconducted the proceedings in the case. In that case the
omission to consider the material documents to resolve the controversy was held
to suffer from manifest error apparent ex facie. The award was accordingly
quashed. In Dandasi Sahu v. State of Orissa6 this Court held that the arbitrator need not give any reasons. The
award could be impeached only in limited circumstances as provided under
Sections 16 and 30 of the Act. If the award is disproportionately high having
regard to the original claim made and the totality of the circumstances it
would certainly be a case of non- application of mind amounting to legal
misconduct and it is not 5 (1975) 2 SCC 236 : 1975 Supp SCR 214 6 (1990) 1 SCC
214 671 possible to set aside only invalid part while retaining the valid part.
In other words the doctrine of severability was held inapplicable in such a
situation. It is, therefore, clear that the word 'misconduct' in Section 30(a)
does not necessarily comprehend or include misconduct of fraudulent or improper
conduct or moral lapse but does comprehend and include actions on the part of the
arbitrator, which on the face of the award, are opposed to all rational and
reasonable principles resulting in excessive award or unjust result or the like
circumstances which tend to show non- application of the mind to the material
facts placed before the arbitrator or umpire. In truth it points to fact that
the arbitrator or umpire had not applied his mind and not adjudicated upon the
matter, although the award professes to determine them. Such situation would
amount to misconduct.
In
other words, if the arbitrator or umpire is found to have not applied his mind
to the matters in controversy and yet, has adjudicated upon those matters in
law, there can be no adjudication made on them. The arbitrator/umpire may not
be guilty of any act which can possibly be construed as indicative of
partiality or unfairness. Misconduct is often used, in a technical sense
denoting irregularity and not guilt of any moral turpitude, that is, in the
sense of non- application of the mind to the relevant aspects of the dispute in
its adjudication. In K. V. George v. Secretary to Government, Water & Power
Department, Trivandrum7 this Court held that the arbitrator had committed
misconduct in the proceedings by making an award without adjudicating the
counter-claim made by the respondent. In Indian Oil Corpn. Ltd. v. Amritsar Gas
Service8 the counter-claim was rejected on the ground of delay and
non-consideration of the claim, it was held, constituted an error on the face
of the award.
8. The
question therefore is whether the umpire had committed misconduct in making the
award. It is seen that claims 11 and 12 for damages and loss of profit are
founded on the breach of contract and Section 73 encompasses both the claims as
damages. The umpire, it is held by the High Court, awarded mechanically,
different amounts on each claim. He also totally failed to consider the
counter-claim on the specious plea that it is belated counter-statement.
These
facts would show, not only the state of mind of the umpire but also
non-application of the mind, as is demonstrable from the above facts. It would
also show that he did not act in a judicious manner objectively and
dispassionately which would go to the root of the competence of the arbitrator
to decide the disputes.
9. It
is true that if the bad portion of the award is severable from the good part
the court may set aside the bad part and uphold the rest of the award. But when
it hinges upon the state of mind of the arbitrator or the umpire, the award
being a non-speaking award, it is not reasonably certain as to what part of the
award is good and vice versa.
And if
such a part cannot be separated then the whole award must be declared as
invalid and it would be set aside on the ground of misconduct under Section
30(a) of the Act.
7
(1989) 4 SCC 595 8 (1991) 1 SCC 533, 544 672
10. In
Russell on Arbitration at p. 485, it is stated thus:
"The
bad portion however must be clearly separable in its nature in order that the
award may be good or the residue. Where it is divisible is the faulty direction
will alone be set aside or treated as null." At p. 486 it is stated that:
"If
the objectionable portion in the award is inseparable from the rest, on not so
clearly separable that it can be seen that the part of the award attempted to
be supported is not at all affected by faulty portion, the award will be
altogether avoided." In Basant Lal Banarsi Lal v. Bansi Lal Dagdulal9 this
Court finding that the contract in question was illegal and prohibited by law
and consequently the award made under the arbitration clause this Court held
that the award was one and inseparable from the rest of the disputes covered by
it and the disputes might not have legally and validly been referred, the whole
award was rightly set aside. In Jivarajbhai Ujamshi Sheth v. Chintamanrao Bala
ill' this Court found that it was impossible to sever the award since the
arbitrator had committed not a mere error of fact or law in reaching its
conclusion, the entire award was set aside.
In Mattapalli
Chelamayya v. M. Venkataratnam11 this Court held that where a severable part of
an award cannot be given effect to for a lawful reason, there is no bar to
enforce the part to which effect could be justly given. The same principle was
reiterated in Upper Ganges Valley Electricity Supply Co. Ltd. v. U.P.
Electricity Board1 2 holding (SCR at p. 1 15 : SCC pp. 260-6 1) that the mere
error which occurred in the award of the umpire relating to matter which is
distinct and separate from the rest of the award, the part which is invalid
being severable from that which is valid, there was no justification for
setting aside the entire award.
11.It
is clear from the above facts and legal position that the arbitrator committed
misconduct in non-application of his mind in deciding claims 11 and 12. It
being a non- speaking award, it is difficult to find whether he had applied his
judicious mind in deciding which of the two claims the respondent would be
entitled to, in particular, on the finding of the High Court in this behalf.
Therefore, the award in respect of claims 11 and 12 is set aside. The order of
the High Court to award Rs 6,00,000 stands set aside, Since the counter-claim
was not considered the matter requires determination. Accordingly the rejection
of the counter-claim would be treated as a nil award of the counter-claim and
for the above reasons it stands set aside and the matter is remitted to be
adjusted afresh. The decree of the High Court granting interest pendente is
also set aside.
12.The
appeals are accordingly allowed to the above extent and the judgment of the
Division Bench of the High Court stands modified and tile 9 (1961) 2 SCR 780:
AIR 1961 SC 823 10 (1964) 5 SCR 480: AIR 1965 SC 214 11 (1972) 3 SCC 799 : AIR
1972 SC It 21, 1125 (para 12) 12 (1973) 1 SCC 254 :(1973) 3 SCR 107 673 award
of the severable part stands confirmed accordingly.
In the
circumstances parties are directed to bear their own costs.
Back