M.Dayanand
Reddy Vs. A.P. Industrial Infrastructure Corporation Ltd. & Ors [1993] INSC
152 (24 March 1993)
Ray,
G.N. (J) Ray, G.N. (J) Venkatachalliah, M.N.(Cj)
CITATION:
1993 AIR 2268 1993 SCR (2) 629 1993 SCC (3) 137 JT 1993 (3) 566 1993 SCALE
(2)270
ACT:
Indian
Arbitration Act 1940. Sections 3, 5, 11 and 12 read with Sections 8 and 9-Scope
of-Removal and Appointment of Arbitrator by Civil Court-Power thereto--Original
agreement vis-a- vis copy of agreement-Preferability.
Whether
the existence of an arbitration agreement to refer the dispute to arbitrator
can be ascertained in the facts and circumstances of the case. And whether in
the absence of an arbitration clause, it was necessary to find out the terms
agreed between the parties-Whether unwritten arbitration agreement can be recognised
under the Act.
Arbitration
Agreement and other agreement-Distinct feature- Mode Of enforcement Whether the
Courts have discretionary power of dispensation of a valid arbitration
agreement vis-a-vis other agreements-Obligations of the Parties.
HEAD NOTE:
The
appellant, entered into an agreement with the first respondent on December 11, 1986 for construction of sewer line. On June 27, 1988 he requested the Chairman to refer
the dispute to arbitration as per the preliminary specification of the A.P.
Standard specifications. As the first respondent refused to settle the claims,
the appellant sent a claim petition dated October 3, 1988 to the named arbitrator. He sent a
reminder but the named arbitrator did not enter the reference. The appellant
gave further notice dated January 5, 1989
calling upon the first respondent to concur for the appointment of an
arbitrator to adjudicate the disputes and differences arising between the
parties.
On January 18, 1989 the first respondent informed the
appellant that there was no arbitration clause in the agreement between the
parties, so the question of entertaining the request to appoint an arbitrator
did not arise. The appellant then riled an application in the Civil Court praying 629 630 for removal of the
named arbitrator in the agreement and appointment of the sole arbitrator in his
place.
The
respondent contested the application contending that the appellant completed
only a part of the work within the stipulated time though the site was handed
over to him. But the accounts were settled before the completion of work and
the final bill of the appellant was paid, while the balance of work was got
completed through other agencies. The respondent also contended that the
original agreement signed between the parties did not provide for any
arbitration clause and such fact was known to the appellant.
The Civil Court found that the agreement did not
contain any arbitration clause. However, it held that the agreement was silent
about the mode of settlement of the disputes, if any, while every agreement of
civil contract contains an arbitration clause. However, since there was clause
3 in the copy of the agreement supplied to the appellant sub- sequently under a
covering letter with the seal and signature of the second respondent, which
provided for reference to arbitration in accordance with standard specification
and since the copy of agreement was not fabricated by the appellant, the
respondents were bound by the arbitration clause.
The
respondents had neglected to refer the matter to arbitration despite the
agreement, so the civil court appointed the sole arbitrator.
The
respondents assailed the order of the civil court in Civil Revision before the
High Court. The High Court also found that the original agreement did not
contain any arbitration agreement at all. Since there was no arbitration clause
in the original agreement, it was not necessary to consider other material or
circumstances. The High Court rejected the contention that the existence of
such a clause should be assumed because the government contractors were
governed by the standard specification.
Therefore
the High Court set aside the order appointing the arbitrator.
This
Court granted special leave to appeal to the appellant and on consideration of
respective contentions of the parties, this Court dismissing the appeal.
HELD:Only
an arbitration agreement in writing is- recognised under 631 the Arbitration
Act, 1940. [635-G] Law is well settled that arbitration clause may be
incorporated by reference to a specific document which is in existence and
whose terms are easily ascertainable.
However,
the question whether or not the arbitration clause contained in another
document has been incorporated in the contract, is always a question of
construction.[636 C-D] The arbitration clause is quite distinct from the other
clauses of the contract. While other clauses of agreement impose obligation
which the parties undertake towards each other, arbitration clause does not
impose on any of the parties any obligation in favour of the other party. Such
arbitration agreement embodies an agreement between the parties that in case of
dispute, such dispute shall be settled by arbitrator or umpire of their own
constitution or by an arbitrator to be appointed by the court in appropriate
cases. [636-E] There is a material difference in an arbitration agreement
inasmuch as in an ordinary contract the obligations of the parties to each
other cannot be specifically enforced and breach of such terms of contract
results only in damages, but the arbitration clause can be specifically
enforced by the machinery of the Arbitration. Act. While the courts have
discretionary power of dispensation of a valid arbitration agreement, there is
no such power of dispensation of other terms of contract. An arbitration
agreement in no way classifies the right of the parties under the contract but
it relates wholly to the mode of determining the rights. [636 F-H, 637 A] In
the instant case, it is the specific finding of the High Court and civil court
that there is no arbitration clause In the original agreement signed by both
the parties.
Therefore
it Is not necessary to make any effort for the purpose of finding out as to
what were the terms agreed between the parties. In the absence of clear
intention of both the parties, agreement for arbitration cannot and should not
be inferred, more so when the specific case of the respondent is that by
mistake the clause relating to arbitration crept in the copy of agreement. [637
C-D, 638 D] The High Court was justified in holding on facts that only the
original agreement and not the copy, was binding between the parties and no
reference to arbitration could thus be made. In the aforesaid circumstances, no
interference in called for. [638 H, 639 A] 632
CIVIL
APPELLATE JURISDICTION : Civil Appeal No. 1427 of 1993.
From
the Judgment and Order dated 13.2.1992 of the Andhra Pradesh High Court in
Civil Revision Petition No .2269 of 1.991.
S.K.
Mehta for the Appellant.
K. Ram
Kumar for the Respondents.
The
Judgment of the Court was delivered by G.N. RAY, J. Leave granted.
Pursuant
to the notice issued on the Special Leave Petition No.7575 of 1992, the
respondents have appeared and have filed counter affidavits and the appellant has
also filed affidavit of rejoinder. The special leave petition out of which this
appeal arises is directed against Order dated February 13, 1992 passed by the Andhra Pradesh High Court in Civil Revision
No.2269 of 1991. The said Civil Revision was filed by the respondents against
Order dated May 10, 1991 by which the learned Vth Additional Judge, City Civil
Court of Hyderabad allowed the application filed under Sections 3, 5, 11 and 12
read with Sections 8 and 9 of the Indian Arbitration Act for removal of the
named Arbitrator in the agreement dated December 11, 1986 and to appoint the
sole arbitrator in his place.
The
learned Judge, City Civil Court, inter alia came to the finding that it was a
fit case where the sole arbitrator should be appointed for adjudicating the
disputes and differences between the parties arising out of the agreement in
question and the learned judge appointed a retired District Judge as the sole
arbitrator for adjudicating the disputes and differences arising out of the
arbitration agreement for entering upon the reference and sign and pass the
award according to law.
The
case of the appellant in short is that the appellant is a Class I Contractor.
He entered into an agreement with the respondent No.1, A.P. Industrial
Infrastructure Corporation Ltd., for the construction of main sewer line from
Point (H) near C.C. Building IDA Nacharam to the disposal units of Nallacheru (near Uppal)
on December 11, 1986. Pursuant to such agreement, the
appellant completed the work in question. Since 633 certain disputes and
differences had arisen between the appellant and the said Corporation during
the execution and completion of the contract, the appellant by notice dated June 27, 1988 requested the. Chairman of the
Corporation to refer the dispute for arbitration as per Clause 73 of the
preliminary specifications of A.P. Standard specifications, hereinafter
referred to as the standard specifications. As the first respondent refused to
settle the claims, the appellant sent a claim petition dated October 3, 1988 to the named arbitrator which was
received by the said named arbitrator on October 5, 1988. As the appellant did not receive
any communication from the named arbitrator, he sent a reminder under
registered post on November
28, 1988 to the named
arbitrator. The named arbitrator, however, did not enter upon the reference
within a period of one month and also did not pass any award within a period of
four months as contemplated in the Indian Arbitration Act. The appellant also
contended in the said application for appointment of arbitrator in place of the
named arbitrator that the Chairman of the Corporation, namely, the first
respondent had sent an undated letter signed on November 8, 1988 informing the
appellant that para 3 of the article of the agreement since referred to by the
appellant was erroneous and while making copies of the arbitration agreement
entered into between the parties, wrong sheets were enclosed but in the
original agreement, since signed between the parties, there was no arbitration
clause for the work in question. The appellant, however, gave a further notice
dated January 5, 1989 through his learned Advocate
calling upon the said respondent to concur for the appointment of any one of
the three persons named in the said notice to act as an arbitrator to
adjudicate the disputes and differences arising between the parties. On
receiving such notice, the first respondent by his letter dated January 18,
1989 informed the learned Advocate of the appellant that as there was no arbitration
clause in the agreement entered into between the parties, the question of
entertaining the request to appoint arbitrator did not arise. In view of such
failure on the part of the respondent to refer the dispute to the arbitration
in terms of the said agreement between the parties, the appellant made a prayer
for removing the named arbitrator in respect of the works in question and to
appoint any one of the three persons named in the application as sole
arbitrator to adjudicate the disputes and differences.
On
such application made by the applicant in the Court of the Vth Additional
Judge, City Civil Court, Hyderabad, the proceeding being O.P. 634 No.132 of 1989 arose.
The
respondent No.1 opposed the said application and filed counter to the said application
inter alia contending therein that the appellant entered into the agreement
dated December 11, 1986 with the A.P. Industrial Infrastructure Corporation for
the said work and the time stipulated for the construction of the work was six
months from the date of handing over of the site. The appellant, however,
completed only a part of the work although the, site was handed over to him.
But before the completion to the entire work, the accounts were settled between
the parties and the final bill was also paid to the appellant and the balance
of work was got completed through other agencies. It was further contended that
the original agreement signed between the parties did not provide for any
arbitration clause and such fact was made known to the appellant. In view of
the aforesaid position,, the question of referring the matter to the
arbitration or to the named arbitrator or to any other arbitrator did not
arise.
The
learned Judge inter alia came to the finding that the original agreement dated
December 11, 1986 executed between the parties in relation to the contract work
did not contain any arbitration clause and the articles of the agreement only
provided for various terms and conditions of the work and such agreement
containing the aforesaid terms was also signed by both the parties. The learned
Judge, however, held that conspicuously the agreement was silent about the mode
of settlement of the disputes, if any, arising between the parties in respect
of the work. Generally, every agreement of civil contract between the
government and the contractors or between the local bodies and the contractors
contains an arbitration clause for settling the disputes between the parties.
In the copy of the agreement which was supplied to the appellant since marked
as Ex. A-3, the clauses appearing in the agreement were similarly entered
without variation. In the copy of agreement since furnished to the applicant,
there was a clause being clause 3 which provided for reference to arbitration
in accordance with the standard specifications. It was further held by the
learned Judge that the copy since supplied to the applicant had the stamp of
the respondent No.2 and the covering letter under which the copy of the
agreement was forwarded to the applicant also bore the seal and signature of
the second respondent. Since the said copy of the agreement had not been
fabricated by the applicant, the respondents were bound by the said 635 Clause
(3) as referred to in the copy of the agreement' As, despite such agreement,
the respondents failed and neglected to refer the matter for arbitration, the
learned Judge was of the view that the application should be allowed. The
learned Judge, therefore, appointed Sri J. VenuGopal Rao, a retired District
Judge, as the sole arbitrator for adjudicating all the disputes and differences
between the parties and for entering upon the reference and thereafter sip and
pass the award in accordance with law.
The
respondents being aggrieved by the aforesaid order of the learned Civil
Additional Judge, moved the Andhra Pradesh High Court for revision. The learned
Judge inter alia came to the finding that the original agreement Ex.B-1 since
signed by the parties did not contain any arbitration clause at all. A copy of
the agreement (Ex.A-3) was, however, for- warded to the applicant eleven days
after the original agreement and the clause relating to arbitration as
contained in Ex.A-3 was absent in the original agreement.
The
learned Judge was of the view that only the terms contained in original agreement
since signed by the parties and not the terms contained in the copy forwarded
to the applicant were binding between the parties. The learned Judge was also
of the view. that as in the original agreement, (Ex.B-1) signed by both the
parties, there was no arbitration clause at all, it was not necessary to look
into the other material or to consider other circumstances for the purpose of
finding that the parties had also agreed for arbitration. The contention on
behalf of the applicant that in the absence of any specific clause for
reference of disputes to arbitration in the original agreement (Ex.B-1) the
existence of such a clause should be assumed because the government contractors
arc governed by the standard specifications, was not accepted by the High
Court. In that view of the matter, the revision application was allowed by the
High Court inter alia holding that the impugned order appointing an arbitrator
was erroneous and not sustainable in law. As aforesaid, such order of the
Andhra Pradesh High Court is impugned in the instant appeal.
Under
the Arbitration Act, 1940, only an arbitration agreement in writing is recognised
by the Act. In has been held by this Court in Jugal Kishore Rameshwardas v.
Mrs. Goolbai Hormusji, [1955] 2 SCR 857 that it is not necessary that the
contract between the parties should be signed by both the parties. But it is
necessary that the terms should be reduced in writing and the agreement between
the parties on such written terms is 636 established. It has also been held by
this Court in Rallia Ram v. Union of India, [1964] 3 SCR 164 that it is not
necessary that all the terms of the agreement should be contained in one
document. Such terms may be ascertained from the correspondence consisting of
number of letters.
In Smt.
Rukmanibai Gupta v. The Collector, Jabalpur & Ors., AIR 1981 SC 479 this
Court has laid down that an arbitration clause is not required to be stated in
any particular form.
If the
intention of the parties to refer the dispute to arbitration can be clearly
ascertained from the terms of the agreement, it is immaterial whether or not
the expression arbitration or 'arbitrator' or 'arbitrators' has been used in
the agreement. It is also not necessary that agreement to arbitration should
appear in the document containing the other terms of agreement between the
parties. Law is well settled that arbitration clause may be incorporated by
reference to a specific document which is in existence and whose terms are
easily ascertainable. It is to be noted, however, that the question whether or
not the arbitration clause contained in another document is incorporated in the
contract, is always a question of construction. It should also be noted that
the arbitration clause is quite distinct from the other clauses of the contract.
Other clauses of agreement impose obligation which the parties undertake
towards each other. But arbitration clause does not impose on any of the
parties any obligation in favour of the other party. Such arbitration agreement
embodies an agreement between the parties that in case of a dispute, such
dispute shall be settled by arbitrator, or umpire of their own constitution or
by an arbitrator to be appointed by the Court in an appropriate case. It is
pertinent to mention that there is a material difference in an arbitration
agreement inasmuch as in an ordinary contract the obligation of the parties to
each other cannot, in general, be specifically enforced and breach of such
terms of contract results only in damages. The arbitration clause however can
be specifically enforced by the machinery of the Arbitration Act. The
appropriate remedy for breach of an agreement to arbitrate is enforcement of
the agreement to arbitrate and not to damage arising out of such breach.
Moreover, there is a further significant difference between an ordinary
agreement and an arbitration agreement. In An arbitration agreement, the Courts
have discretionary power of dispen- sation of a valid arbitration agreement but
the Courts have no such power of dispensation of other terms of contract
entered between the parties. This very distinctive feature of an agreement for
arbitration has been highlighted 637 in the decision in Heyman v. Damins Ltd.,
1942 AC 356. It has been held in North Westen Rubber Company, 1908 2 KB 907
(over-ruled in (1961 (1) AC 1314) on other points), that an arbitration
agreement in no way classifies the right of the parties under the Contract but
it relates wholly to the mode of determining the rights. In the backdrop of
such position in law relating to an agreement for arbitration, it is to be
decided whether the existence of an agreement to refer the dispute to
arbitration can be clearly ascertained in the facts and circumstances of the
case. This, in turn, depends on the interaction of the parties to be gathered
from the relevant documents and surrounding circumstances. In the instant case,
it is the specific finding of the learned Judge of the City Civil Court, Hyderabad and also the Andhra Pradesh High Court that in the original
agreement signed by the parties, there is no clause for referring the disputes
to arbitration. The agreement between the parties in this case has been reduced
in writing and has been signed by both the parties. It is therefore not
necessary to make any effort for the purpose of finding out as to what were the
terms agreed between the parties.
The
learned Judge, City Civil Court, allowed the application for appointment of
arbitrator simply on the ground that a copy of the agreement was forwarded to
the appellant with the seal and signature of a competent officer of the
Corporation, namely, the respondent No.2 and in such copy, which was not
fabricated by the applicant there was a reference for arbitration as contained
in the standard specifications. The learned Judge, City Civil Court, also proceeded on the footing that
usually in the agreements relating to the nature of the contract, a provision
for arbitration is made. As in the original agreement signed between the
parties there was no such provision and the agreement was silent on the
question as to what would happen if the disputes would arise between the
parties, it should be presumed that the parties had really intended to refer
the dispute to arbitration in accordance with the standard specifications and
in the copy of the agreement which was forwarded to the applicant the provision
for arbitration was included. The High Court however, was not inclined to
accept this view of the learned Judge of the City Civil Court. The High Court was of the view that it was the signed
agreement between the parties which was binding on the parties and only such
written terms in the original agreement signed by the parties should be taken
into consideration and not the terms contained in the copy of the agreement
which was forwarded to the applicant after some time.
638 It
has been indicated herein before that the case of the respondent is that
through mistake the clause containing the arbitration agreement was not scored
out in the copy of the agreement since forwarded to the applicant. The attention
of the appellant was drawn to such mistake by the respondents before initiation
of the proceedings before the City Civil Court.
It also appears that on April
9, 1984, which is long
before the agreement dated December 11, 1986,
the respondent No.1, Corporation, came to the decision that arbitration was not
really necessary as the aggrieved party to the agreement could always seek
redress in a court of law. It was, therefore, decided that the arbitration
clause in the standard specifications should be deleted altogether and the
agreement was to be finalised in respect of engineering work without any
provision for arbitration. It was also indicated that the instruction for
deleting the arbitration clause should be followed with immediate effect.
If inspite
of such policy decision, the original agreement entered between the parties had
contained the arbitration clause there is no manner of doubt that the parties
to the agreement would have been bound by such arbitration agreement.
Admittedly, in the instant case, in the original agreement signed between the
parties, there is no clause for arbitration and the reason for absence of
arbitration clause can be well explained by the aforesaid policy decision of
the Corporation. An arbitration clause may be incorporated by reference to a
specific document but the intention to refer to arbitration by such
incorporation must be clear and specific. In the instant case, the original
agreement signed between the parties does not contain any clause for
arbitration. It is not the case of the applicant that the applicant had no
occasion to know the terms of the agreement since singed by the parties and
there was any clear representation that the copy of agreement was to be
followed by the parties and terms contained in the copy were to be treated as
the terms of agreement between the parties.
Hence,
it cannot be held that after the signed agreement the parties had clearly
intended to include arbitration clause in the standard specifications. In the
absence of clear intention of both the parties, agreement for arbitration
cannot and should not be inferred more so when the specific case of the
respondents is that by mistake the clause relating to arbitration crept. in the
copy of agreement. In our view, the High Court was justified in holding that in
the facts of the case, only the original agreement, and not the copy, was
binding between the parties. Hence, no reference to arbitration could be made.
In 639 the aforesaid circumstances, no interference is called for in the instant
appeal and the appeal therefore, fails and is dismissed without, however, my
order as to costs.
S.P.S.
Appeal dismissed.
Back