Ansal
Properties & Industries (P) Ltd. & Anr Vs. Delhi Development Authority & Ors
[1992] INSC 168 (28 May
1992)
Kasliwal, N.M. (J) Kasliwal, N.M. (J) Sahai, R.M. (J)
CITATION:
1992 SCR (3) 465 1993 SCC Supl. (1) 61 JT 1992 (4) 264 1992 SCALE (2)2
ACT:
Delhi
Development Act, 1947-Sections 9(2), 41- Legislative object-Master
plan-Restriction on high rise construction by Central Government-Legality of.
Delhi
Development Act, 1947-Sections 41 read with Bye- Laws 6.7.4, 6.1 of the
Building Bye-Laws, 1983 of the Delhi Development Authority-Requirement
under-Deemed sanction-When arises-Compounding fee-Charging of interest-Whether
arises.
HEAD NOTE:
The
auction of leasehold rights on the plot in question was in favour of the
appellant for Rs. 8.13 crores on 19.1.1981. The appellant paid 25% of the
auction amount on the fail of the hammer. According to the terms and conditions
of the auction balance 75% was required to be paid within 90 days of the formal
acceptance of the bid which was made on 18.2.1982.
The
appellants did not pay the balance amount and took a stand that there was some
confusion as to whether it was D.D.A. or the Union of India, which was the
owner of the plot in question. The appellant also sought for time for payment
on the ground that money market in relation to the land property had gone down
tremendously.
On
14.12.1984 revised terms were communicated by the D.D.A. to the appellants. The
essential terms of the revised agreement were that 25% of the bid amount was to
be paid within 90 days of the issuance of the letter of revised terms. 50% of
the remaining bid amount along with interest for delayed payments was to be
paid in five equal half yearly instalments which included the interest
calculated at 18% per annum.
The
appellants submitted a bank guarantee dated 15th July, 1985 in favour of the D.D.A. The fresh schedule of instalments
was specifically mentioned in the bank guarantee. Thereafter on 23.7.1985, a
formal deed 466 of agreement was executed between the parties and possession
over the plot was given on 25.7.1985. The building plans were submitted by the
appellant on 12.8.1985.
The
D.D.A. forwarded building plans to the Delhi Urban Arts Commission (DUAC). The
DUAC by its letter dated 18.9.1985 sought certain clarifications from the
appellant within ten days and again sent a reminder on 24.9.1985, but the
appellant did not send any reply.
The
appellant sent a notice for commencement of construction on 15.10.1985 claiming
that they having not received any order of rejection of the plans within sixty
days as contemplated under bye-law No. 6.7.4. had become entitled to deemed
sanction; that the first instalment, according to the re-schedule of instalments
was payable on 15.11.1985 but even before that they had paid Rs.47 lakhs on
8.10.1985 itself.
Thereafter
the Government of India by an office memorandum dated 17.10.1985 decided to
stop construction of multi-storeyed building in New Delhi including areas under D.D.A. and Municipal Corporation,
with immediate effect till the Master plan for 2001 was finalised.
The
DUAC then returned the proposals of the buildings plans of the appellant to the
D.D.A. on 20.11.1985. The D.D.A. by its letter dated 9.12.1985 informed the
appellants regarding the decision of the Government of India and returned the
building plans and it was directed not to process the sanction further till
further directions were received from the Government of India.
A
notice to stop the construction immediately till the plans were sanctioned
finally by the D.D.A. was given to the appellants on 17.1.1986.
On
25.3.86 the D.D.A. informed the appellants that their plans had been rejected
as the same had no been approved by the DUAC.
The
appellants filed writ petition challenging the notice issued by the D.D.A. of
stopping the construction work and also the ban introduced by the Government of
India.
The
High Court on 17.9.1986 passed an interim order permitting the appellants to
continue the construction work at their own risk.
On
15.10.1987 the bank guarantee was invoked by the D.D.A. for a sum of Rs.8 crores
approximately.
467
The appellants filed a second writ petition challenging the encashment of the
bank gurantee by D.D.A. and obtained an interim order on 28.10.1987 restraining
the D.D.A. from encashing the bank guarantee.
The
ban imposed by the Central Government was lifted on 8.2.1988. The appellants
completed the construction of the building in 1988 under the cover of the stay
order given by the High Court. The two writ petitions were dismissed by the
High Court.
These
appeals were filed by the contractors against the judgment of the High Court,
by special leave, contending that the D.D.A. was not entitled to charge any
compound interest; that the D.D.A. was not entitiled to claim any interest for
the period 7.10.1985 to 8.2.1988 during which the ban in respect of
construction of multi-storeyed buildings remained in force; that the ban itself
was also illegal; that the D.D.A. was not entitled to claim any compounding
fee; and that the D.D.A. was not entitled to claim any interest on the
compounding fee.
Partly
allowing the appeals of the contractors, this court,
HELD:
1.1.
The object of Delhi Development Act is to provide for the development of Delhi according to the plan.
While
under Section 9(2) of the Delhi Development Act every master plan has to be
submitted to the Central Government for approval and the Government may either
approve the plan without modifications or with such modifications as it may
consider necessary or reject the plan with directions to the Authority to
prepare a fresh plan according to such directions. The Development Authority
had sent the new master plan for approval of the Central Government and as such
the Government for the planned development of Delhi was entitled to issue directions in consonance with law.
[475H- 476B]
1.2.
There was no violation of law in issuing a restriction on high rise
constructions during the formulation stages of the new master plan pending for
approval before the Central Government. Thus it cannot be said that the ban
imposed by the Central Government was in any manner unauthorised or illegal.
[476 D]
2.1.
The question of deemed sanction only arises if within sixty days of the receipt
of notice under 6.1. of the bye-laws the authority fails to intimate in writing
to the person who has given a notice of its refusal or 468 sanction or any
intimation. [478 B]
2.2.
In the instant case the D.D.A. had informed the appellant that the plans had
been sent to DUAC for approval and the DUAC was also seeking some clarifications
from the appellant by their letters dated 18.9.1985 and 24.9.1985. [478 B]
2.3.
The requirement as contemplated under bye-law 6.7.4. is that the fact of deemed
sanction has to be immediately brought to the notice of the authority in
writing by the person who has given notice and thereafter if no intimation is
received from the authority within 15 days of giving such written notice the
provision of deemed sanction comes into operation. [478 C]
2.4.
The appellant only sent a notice for commencement of construction on 15.10.1985
and the same does not fulfil the requirement of the notice which is
contemplated under bye-law 6.7.4. in as much as intimation had already been
given by DUAC seeking information. Apart from this the ban on the construction
of multi-storeyed buildings came into operation from 17.10.1985 itself and in
view of this circumstance also there was no question of the applicability of
deemed sanction in the facts of this case. [478D-E]
2.5.
The amount which was required to be paid in five instalments of Rs. 166.20 lakhs
each from 15.11.1985 to 15.11.1987, included simple interest charged at the
rate of 18% per annum but it was based on a fresh agreement and the appellants
cannot claim any right to re-open the transaction on the basis of terms of
auction made originally in 1982.
The
indulgence of re-scheduling of delayed payment of bid amount in July, 1985 was
made on the request of the appellant and for its own benefit. Thus the D.D.A.
is perfectly right and justified in claiming future interest at the rate of 18%
per annum on the instalments fixed in the agreement dated 23rd July, 1985. The D.D.A. is not charging any
compound interest but are claiming simple interest at the rate of 18% per annum
on the amount of instalments fixed in the fresh agreement dated 23rd July, 1985
till payment, After novation of the agreement the instalments fixed shall be
considered as principal amount and thus it is not a case of charging compound
interest. [474H-475C]
2.6.
For charging of interest during the ban period is concerned, the D.D.A. cannot
be held responsible as the ban was imposed by the Central Government. This
action was taken for the whole of Delhi and the D.D.A.
469 was
to carry out such directions as provided under Section 41 of the Delhi Development
Act, 1957. [475D-E] 2.7. It is not in dispute that the building has been
constructed without any sanction or permit from the D.D.A. as required under
the building bye-laws and the building has been constructed at the risk of the
appellant under the stay order of the High Court. [478 F]
2.8.
No building permit has been given to the appellants and as such they are bound
to pay the compounding fee according to the rates prescribed in this regard.
[479 C]
2.9.
In the facts and circumstances of the case the D.D.A. is not entitled to charge
any interest on the compounding fee. [479 D]
CIVIL
APPELLANTS JURISDICTION : Civil Appeal Nos. 2457 and 58 of 1992.
From
the Judgment and Order dated 31.10.1991 of the Delhi High Court in C.W.P. Nos.
1499/86 and 3068 of 1987.
Harish
Salve, Ms. J.S. Wad, Ms. Tamali Wad and Manoj Wad for the Appellants.
V.R.
Reddy, Addl. Solicitor General, Arun Jaitley, Ms. Indu Malhotra, C. Ramesh,
V.K. Verma and C.V.S. Rao for the Respondents.
D.D.
Sharma, C.L. Chopra and Ms. Rachna Issar for the Intervener.
The
Judgment of the Court was delivered by KASLIWAL, J. Sepcial leave granted.
It is one
more avoidable litigation between Ansals, a big building contractor and the
Delhi Development Authority in which allegations and counter allegations for
breach of terms of contract have been levelled against each other. We would
have asked the appellant to stand in queue for hearing of the matter, but the
real sufferers would be those persons who have invested their hard earned life
time savings in forlorn hope of an allotment of a flat in a commercial building
on plot No. 38 situated in Nehru Palce near Kalkaji a prime place of importance
in Delhi. It is the repetition of the usual bureaucratic rigmarole from the
side of the Delhi 470 Development Authority and the usual payment of some instalments
of the lease money and thereafter withholding the payment of the balance amount
on one pretext or the other form the side of the builders.
Facts
in brief, shorn of details and necessary for the disposal of this case are that
the auction of leasehold rights on plot No. 38, Nehru Place was knocked down in
favour of M/s Ansal Properties & Industries (P) Ltd., hereinafter referred
to as "the appellant" for Rs. 8.13 crores on 19.1.1981. 25% of the auction
amount was paid on the fall of the hammer. According to the terms and
conditions of the auction the balance 75% was required to be paid within 90
days of the formal acceptance of the bid which was made on 18.2.1982. The
appellant admittedly did not pay the balance amount and took a stand that there
was some confusion as to whether it was D.D.A. or the Union of India, which was
the owner of the plot in question. The appellant also sought the indulgence of
granting more time for payment on the ground that money market in relation to
the land property had gone down tremendously. On 14.12.1984 revised terms were
communicated by the D.D.A. to the appellant. The essential terms of the revised
agreement were that 25% of the bid amount was to be paid within 90 days of the
issuance of the letter of revised terms. 50% of the remaining bid amount along
with interest for delayed payments was to be paid in five equal half yearly instalments
which included the interest calculated at 18% per annum. These instalments were
fixed in the following manner :
(i) Ist
instalment payable on 15.11.1985 Rs. 166.20 lacs.
(ii)
2nd instalment payable on 15.5.1986 Rs. 166.20 lacs.
(iii)
3rd instalment payable on 15.11.1986 Rs. 166.20 lacs.
(iv)
4th instalment payable on 15.5.1987 Rs. 166.20 lacs.
(v)
5th instamlent payment on 15.11.1987 Rs. 166.20 lacs.
The
appellant is this regard submitted a bank guarantee dated 15th July, 1985 of the Canara Bank and New Bank of India in favour of the D.D.A. The
aforesaid fresh schedule of instalments was specifically mentioned in the bank gurantee.
Thereafter a formal deed of agreement was executed between the parties on
23.7.1985 and possession over the plot was given on 25.7.1985. The building
plans were submitted by the appellant on 12.8.1985. The D.D.A.
vide
letter dated 13.9.1985 forwarded building plans 471 to the Delhi Urban Arts
Commission (DUAC). The DUAC by its letter dated 18.9.1985 sought certain
clarifications from the appellant within ten days and again sent reminder on
24.9.1985, but the appellant did not send any reply. The appellant then sent a
notice for commencement of construction on 15.10.1985. The appellant claimed
that they having not received any order of rejection of the plans within sixty
days as contemplated under bye law No. 6.7.4. had become entitled to deemed
sanction. The appellant claimed that the first instalment, according to the re-
schedule of instalments was payable on 15.11.1985 but even before that they had
paid Rs. 47 lakhs on 8.10.1985 itself.
Thereafter
the Government of India by an office memorandum dated 17.10.1985 decided to
stop construction of multi-storeyed buildings in New Delhi including areas
under D.D.A. and Municipal Corporation of Delhi falling in South Delhi, with
immediate effect till the Master plan for 2001 was finalised. It was clarified
that a `multi-storeyed building' may be taken as a building going beyond 45
feet or above four storeys, which has to be serviced by lifts. The DUAC then
returned the proposals of the building plans of the appellant to the D.D.A. on
20th November, 1985. The D.D.A. by its letter dated 9.12.1985 informed the
appellant regarding the decision of the Government of India and returned the
building `' plans and requested them to depute their architect to discuss about
the height of the building.
It was
mentioned in the letter that the sanction shall not be processed further till
further directions are received from the Ministry of Urban Development,
Government of India.
A
notice to stop the construction immediately till the plans were sanctioned
finally by the D.D.A. was given to the appellant on 17.1.1986. By another
letter dated 25.3.1986 the D.D.A. informed the appellant that their plans had
been rejected as the same had not been approved by the DUAC. The appellants
then filed writ petition No. 1499/86 on 17th July, 1986 challenging the notice
issued by the D.D.A. of stopping the construction work and also the ban
introduced by the Government of India. The High Court on 17.9.1986 passed an
interim order permitting the appellants to continue the construction work at
their own risk. On 15.10.1987 the bank guarantee was invoked by the D.D.A. for
a sum of Rs. 8 crores approximately. The appellants filed a second writ
petition No. 3068 of 1987 challenging the encashment of the bank gurantee by
D.D.A. and obtained an interim order on 28.10.1987 restraining the D.D.A. from encashing
the bank guarantee. The ban imposed by the Central Government was lifted on
8.2.1988. The appellants completed the construction of the building in 1988 472
under the cover of they stay order given by the High Court.
The
aforesaid two writ petitions have been disposed of by the High Court by order
dated October 31, 1991. The High Court after examining the matter in detail
arrived to the conclusion as under:- "After considering the pleadings of
the parties, documents on record and submissions made before this court, it is
absolutely evident that the petitioner has been consistently making defaults in
payment of the amount due to the D.D.A. on one pretext or the other. According
to the terms of the auction, the petitioner's bid was accepted on February 19,
1982 and the petitioner was supposed to deposit the balance 75% of the bid
amount within 90 days. The amount which ought to have been deposited with the
D.D.A. way back in 1982 has not been deposited till this date. Further more at
the request of the petitioner, the D.D.A. entered into an agreement with the
petitioner. This agreement was entered into because the petitioner pleaded
grave financial difficulty and according to the agreement, the first instalment
had to be deposited by the petitioner on or before November 15, 1985 and all
subsequent instalments on or before 15th November, 1987. Astonishingly, till
this date not even one full instalment has been deposited by the petitioner.
Looking to the entire past conduct of the petitioner, no indulgence can be
granted in any manner because any indulgence would be at the cost of public
money".
The
High Court then observed that after careful consideration of the facts and the
issues involved in the case it would be proper to dispose of the writ petitions
with the following directions:
(i)
The petitioner is directed to pay the balance outstanding amount due to the
Delhi Development Authority, including interest at the rate of 18% per annum
within a period of two months from today.
(ii) the
respondent-D.D.A. would be entitled to encash the bank guarantee furnished by
the petitioner. The amount recovered by encashment of bank guarantee from the
petitioner would stand adjusted from the total outstanding amount.
(iii)
On the petitioner's making the entire payment, the respondent 473 shall
sanction the building plans forthwith and in no case later than one month of
receiving the entire outstanding amount from the petitioner.
(iv)
Thereafter the petitioner shall apply for the grant of occupancy certificate as
per rules, if not already applied.
The
respondent D.D.A. shall grant necessary certificate as per rules without any
delay but in any event not later than two weeks from the date of the
petitioner's submitting application pertaining to occupancy certificate.
Subject
to these directions, both these writ petitions are dismissed. Counsel's fee is
addressed at Rs. 5,000. It is made clear that if the petitioner fails to comply
with the above directions, the respondent shall be at liberty to take necessary
action as permissible according to law.
Aggrieved
against the aforesaid Judgment of the High Court the appellants by grant of
special leave have come in appeal before this Court. We have heard learned
counsel for the parties at length and have thoroughly perused the record. The
contentions now raised before us on behalf of the appellants can be summarised
under the following points:
(i)
The D.D.A. is not entitled to charge any compound interest.
(ii)
The D.D.A. is not entitled to claim any interest for the period 7.10.1985 to
8.2.1988 during which the ban in respect of construction of multi-storeyed
building remained in force. The ban itself was also illegal.
(iii)
The D.D.A. is not entitled to claim any compounding fee which amounts to Rs. 93
lakhs.
(iv)
The D.D.A. is not entitled to claim any interest on the compounding fee.
We
shall consider the above submissions in seriatim.
Point
No. 1: It has been submitted by the Learned counsel for the appellants that the
authority to levy interest in the instant case flows from the statutory
directive issued by the Government and incorporated in the letter dated
14.12.1984. This letter states that ".........The delayed payment of
premium will carry interest 18 per cent p.a. from the due date, viz.
474
17.5.1982, to the actual dated of payment.......". The revised agreement
dated 23rd July, 1985 accordingly provides in clause 2 "......The balance
amount and the interest for delayed payment of the bid amount shall be payable
by the auction purchaser in five equated half yearly instalments including
interest calculated at 18 per cent per annum on the following
dates.......".
It has
been contended that the bank guarantee dated 15.7.1985 is really a part of the
same transaction. In fact the licence agreement of 23.7.1985 was issued only
upon furnishing of the bank guarantee dated 15.7.1985. It is submitted that the
total amount demanded by the D.D.A. includes an element of Rs. 6.69 crores as
further interest.
This
interest amounting to Rs. 6.69 crores comprises of the following ......... (a) Rs.
3.27 crores is the interest on the balance unpaid premium of Rs. 3.60 crores
(as on 15.11.1985) (b) Rs. 3.42 crores is the interest on interest component
already included in the instalments referred to in the bank guarantee.
It has
been contended that the further claim of interest on the five instalments of Rs.
1.66 crores each amounts to charging compound interest as the instalments
already include interest. According to the appellants even if the interest is
charged then it should be a simple interest re-calculated as though the instalments
instead of being paid in the period 1985-87 are being paid in 1991-92 on the
same principle which was adopted when the instalments were initially fixed in
1985. We find no force in the above contention. As already mentioned above the
auction was knoked down for Rs. 8.13 crores on 19.1.1982 and the appellant had
paid only 25% of the auction amount on the fall of the hammer. According to the
conditions of the auction the balance 75% was required to be paid within 90
days of the formal acceptance of the bid which was made on 18.2.1982. The
balance amount was thus payable by 18.5.1982. Admittedly the appellant did not
pay the balance amount until 18.5.1982 and thereafter sought to raise certain
objections regarding the ownership of the plot in question, but ultimately made
a request that due to money market in relation to the land property having gone
down tremendously some more time may be given for making the balance payment.
Thereafter a fresh agreement was executed by the appellant on 23.7.1985
re-scheduling the payment in instalments and according to which the amount was
required to be paid in five instalments of Rs. 166.20 lakhs each from
15.11.1985 to 15.11.1987. This amount no doubt included simple interest charged
at the rate of 18% per 475 annum but it was based on a fresh agreement and the
appellants cannot claim any right to re-open the transaction on the basis of
terms of auction made originally in 1982.
The
indulgence of re-scheduling of delayed payment of bid amount in July, 1985 was
made on the request of the appellant and for its own benefit. Thus the D.D.A.
is perfectly right and justified in claiming future interest at the rate of 18%
per annmum on the instalments fixed in the agreement dated 23rd July, 1985. The
D.D.A. is not charging any compound interest but are claiming simple interest
at the rate of 18% per annum on the amount of instalments fixed in the fresh
agreement dated 23rd July, 1985 till payment.
After novation
of the agreement the instalments fixed shall be considered as principal amount
and thus it is not a case of charging compound interest as contended on behalf
of the appellants.
Point
No. (ii) :- So far as charging of interest during the ban period is concerned,
the D.D.A. cannot be held responsible as the ban was imposed by the Central
Government. The Central Government by an office memorandum dated 17.10.1985 decided
to stop construction of multi- storeyed buildings in New Delhi including areas under D.D.A. and
Municipal Corporation of Delhi falling in South Delhi with immediate effect till master
plan for 2001 was finalised. This action was taken for the whole of Delhi and
the D.D.A. was to carry out such directions as provided under Section 41 of the
Delhi Development Act, 1957. There is no allegation that such action was taken malafidely
and it cannot be considered as a valid ground for not paying the interest for
the period during which the ban on multi- storeyed constructions remained in
force. It may also be noted that so far as the appellant is concerned it was
not affected by such ban as the construction contained under the umbrella of
stay order obtained from the High Court.
According
to the admitted case of the appellant the construction of the building had
completed in 1988 itself and as such the appellant was not put to any loss on
account of the ban imposed by the Central Government.
The
master plan for Delhi was formulated originally in 1962 with projections up to
1981. There was no provision in any law, master plan, zonal development plans
or building bye-laws wherein the appellant was entitled to construct sixteen storeys.
Thus the directive of the Central Government dated 17.10.1985 imposing a ban on
high rise structures was not contrary to any law. The object of Delhi
Development Act is to provide 476 for the development of Delhi according to the
plan. While under Section 9(2) of the Delhi Development Act every master plan
has to be submitted to the Central Government for approval and the Government
may either approve the plan without modifications or with such modifications as
it may consider necessary or reject the plan with directions to the Authority
to prepare a fresh plan according to such directions. The Development Authority
had sent the new master plan for approval of the Central Government and as such
the Government for the planned development of Delhi was entitled to issue
directions in consonance with law.
Learned
counsel for the appellants has placed strong reliance on Bangalore Medical
Trust v. B.S. Muddappa and others, (1991) 3 JT 172. This case is clearly
distinguishable since in that case the zonal plan statutorily provided for the
user of a plot of land as a park. The Chief Minister contrary to the said plan,
sanctioned the plot for a nursing home. Thus there was a positive violation of
law in that case. In the case in hand before us there was no violation of law
in issuing a restriction on high rise constructions during the formulation
stages of the new master plan pending for approval before the Central
Government. Thus it cannot be said that the ban imposed by the Central
Government was in any manner unauthorised or illegal.
Point
No. (iii) :- It has been contended on behalf of the appellants that no
compounding fee can be levied since the D.D.A. had wrongfully withheld grant of
sanction to the building plans submitted by the appellant. It has been further
contended that in view of the commitment made in the licence deed as well as
the agreement read together with the letter of 14.12.1984, the D.D.A. was bound
to sanction the plans. It has been contended that when the plans were submitted
to the D.D.A. for sanction on 12.8.1985, there was no sum outstanding as due
and payable as all the sums which were payable under the agreement up to that
date had been duly paid. According to the fresh agreement the first instalment
was payable on 15.11.1985 and so far as other payments are concerned the same
had already been paid by the appellants. Even according to the bye-laws, the
D.D.A. had to sanction plans within sixty days and the D.D.A. had no
justification of withholding the sanction as nothing was required to be done on
behalf of the appellants. It has been further contended that according to the
stand taken by the D.D.A. itself the sanction was not withheld on account of
non-payment of any dues but on account of the ban put by the Central
Government. It has been further argued that in any event, the building has been
constructed pursuant to the interim orders of the High 477 Court which
expressly permitted the construction of the building albeit at the risk and
cost of the appellant. The High Court has itself recorded a finding that the 16
storeyed building stands constructed according to the bye- laws and even if a
formal sanction is given now it should relate back to the date on which such
sanction ought to have been granted and the building constructed by the
appellant in the present case cannot be considered as unauthorised in law.
The
admitted facts of the case are that the building plans were submitted to the
D.D.A. on 12.8.1985 and the D.D.A. had forwarded the plans for approval of
Delhi Urban Arts Commission (DUAC) on 13.9.1985. Section 12 of the Delhi Urban
Art Commission Act, 1973 clearly provides that notwithstanding anything
contained in any other law for the time being in force, every local body shall,
before according approval in respect of any building operation refer the same
to the DUAC for scrutiny and the decision of the Commission in respect thereof
shall be binding on such local body. The DUAC by its letter dated 18.9.1985
sought certain clarifications from the appellant within ten days and again sent
a reminder on 24.9.1985 but the appellant did not send any reply. In the other
hand the appellant sent notice of commencement of construction on 15.10.1985
and on that basis is claiming that having not received any order of rejection
of the plans within sixty days as contemplated under bye-law No.6.7.4. the
appellant had become entitled to deemed sanction. We find no force in this
submission. As already mentioned above, it was necessary to obtain the approval
of the DUAC and the DUAC by letter dated 18.9.1985 and 24.9.1985 were seeking
certain clarifications from the appellant. Bye-law No.6.7.4 of the building
bye-law, 1983 of the Delhi Development Authority reads as under:- "If
within 60 days of the receipt of notice under
6.1 of
the Bye-Laws, the authority fails to intimate in writing to the person, who has
given the notice, of its refusal or sanction or any intimation, the notice with
its plan and statements shall be deemed to have been sanctioned provided the
fact is immediately brought to the notice of the Authority in writing by the
person who has given notice and having not received any intimation from the
Authority within fifteen days of giving such written notice. Subject to the
conditions mentioned in this bay-laws, nothing shall be construed to authorise
any person to 478 do anything in contravention or against the terms of lease or
titles of the land or against any other regulations, bye-laws or ordinance
operating on the site of the work".
According
to the above provision the question of deemed sanction only arises if within
sixty days of the receipt of notice under 6.1 of the bye-laws the authority
fails to intimate in writing to the person who has given a notice of its
refusal or sanction or any intimation. In the present case the D.D.A. had
informed the appellant that the plans had been sent to DUAC for approval and
the DUAC was also seeking some clarifications from the appellant by their
letters dated 18.9.1985 and 24.9.1985. The further requirement as contemplated
under bye-law 6.7.4. is that the fact of deemed sanction has to be immediately
brought to the notice of the authority in writing by the person who has given
notice and thereafter if no intimation is received from the authority within 15
days of giving such written notice the provision of deemed sanction comes into
operation. In the present case the appellant only sent a notice for
commencement of construction on 15.10.1985 and the same in our view does not fulfil
the requirement of the notice which is contemplated under by-law 6.7.4. in as
much as intimation had already been given by DUAC seeking information. Apart
from this the ban on the construction of multi-storeyed buildings came into
operation from 17.10.1985 itself and in view of this circumstance also there
was no question of the applicability of deemed sanction in the facts of this
case. It is not dispute that the building has been constructed without any
sanction or permit from the D.D.A. as required under the building bye-laws and
the building has been constructed at the risk of the appellant under the stay
order of the High Court. Clause (B) of the Appendix "q" of the
building bye-laws, 1983 provides for compoundable items as under:- COMPOUNDABLE
ITEMS Deviations in terms of covered area - If a building or part thereof has
been constructed unauthorisedly i.e. without obtaining the requisite building
permit from the authority as required under clause 6.1 & 6.7.1 of the
building bye-laws, the same shall be compounded at the following rates provided
the building or part thereof so constructed otherwise conforms to the
provisions contained in the Building Bye-Laws and 479 Master/Zonal Plan
regulations. For this party shall have to submit the request for building
permit in the prescribed procedure".
Thus
under the above provision any building or part thereof constructed without
obtaining the requisite building permit from the authority as required under
clause 6.1 and 6.7.1 of the building bye-laws will be considered as a
construction made unauthorisedly and the same can be compounded at the rates
mentioned in clause (B). It is an admitted position in the present case that no
building permit has been given to the appellants till now and as such they are
bound to pay the compounding fee according to the rates prescribed in this
regard. Thus we find no force in the contention of the appellant that they are
not liable to pay any compounding fee.
(iv)
So far as charging of interest on the compounding fee is concerned, we are
definitely of the view that in the facts and circumstances of the case the
D.D.A. is not entitled to charge any interest on the compounding fee.
In the
result we find no force in these appeals and we uphold the order of the High
Court except with the modification that the D.D.A. is not entitled to charge
any interest on the amount of compounding fee. It is further ordered that the
directions given by the High Court shall now be carried out from the date of
the Judgment of this Court instead of the date of the Judgment of the High
Court.
Thus
except the abovementioned modifications, we uphold the order of the High Court
as well as the directions given by it. There will be no order as to costs in
this Court.
V.P.R.
Appeals Partly allowed.
Back