Aluminium Company Limited & Anr Vs. Karnattaka Electricity Board & Ors
[1992] INSC 153 (13 May
1992)
Ray,
G.N. (J) Ray, G.N. (J) Kasliwal,
N.M. (J)
CITATION:
1992 AIR 2169 1992 SCR (3) 213 1992 SCC (3) 580 JT 1992 (3) 535 1992 SCALE
(1)1157
ACT:
Electricity
(Supply) Act, 1948 : Section 49 : (As amended by Karnataka Act 33 of
1981)-Constitutional validity of.
Company-Establishment
of Aluminium Smelter Plant- Tripartite agreement between Company, Electricity
Board and State-Provision for supply of electricity at concessional
rates-Amendment of Electricity (Supply) Act-Effect of- Imposition of enhanced
revised tariff in supersession of the terms of the Agreement-Inclusion of Aluminium
Smelter Plant in power intensive industries i.e. category HT-IA and imposition
of uniform tariff rate on all industries catgorised as HT-IA-Validity of.
Held
Amending Act was not invalid for want of legislative competence-Nor was it violtive
of Article 14 or 19(1) (g)-Revised levy held valid-Direction to consider the levy
of tariff sympathetically.
Administrative
Law-Promissory estoppel-Company- Electricity Board-State-Agreement for supply
of electricity- Concessional rate-Agreement based on negotiations-No unilateral
promise or assurance by State or Electricity Board-Amendment of Act-Imposition
of enhanced tariff on uniform basis on industries classified under one
category- Doctrine of promissory estoppel held inapplicable.
Doctrine
of legitimate expectation:
Constitution
of India, 1950 : Article 14 :
Equality-Classification-Principles
for exclusion or inclusion-Question of hostile discrimination-Examination of-
Not mere phraseology but the real effect of the provisions should be looked
into.
Constitution-Interpretation
of-Ascertainment of legislative competence-Provisions should not be construed
with narrow or pedantic approach-Should be interpreted broadly and liberally.
214
HEAD NOTE:
The
appellant-Company established its Aluminium Smelter Plant at Belgaum in the State of Karnataka. On March 26, 1966 a tripartite agreement was entered into between the
Company, the Electricity Board and the State of Karnataka.
A
second tripartite agreement, in supersession of the earlier one, was entered on
August 7, 1976 between the parties providing for
uninterrupted supply of power to the company at concessional rates. According
to the appellant- Company, the agreement of 1976 was made in view of the
industrial policy of the Government of India and the guidelines stated by the
Government in the matter of electricity tariff to be applied to aluminum
plants. In July 1980, the Electricity Board increased the power rate far beyond
the prescribed rate in the agreement.
Subsequently,
the State of Karnataka enacted the Electricity (Supply)
(Karnataka Amendment) Act, 1981 amending Section 49 of the Electricity (Supply)
Act 1948. The amended Section 49 empowered the Electricity Board to increase
its tariff rates notwithstanding any agreement with the consumers. On February 2, 1981 the Board further increased the
tariff rate. Aggrieved by increase of tariff rates and the consequential
demands for payment of bills on the basis of increased tariff, the company
filed a writ petition challenging the vires of the Amending Act on the score of
legislative competence and also on the ground of arbitrary action of revising
the tariff without justification and the unjust classification of the Aluminium
Smelter Plant in the category of other power tariff industries included in the
category of HT IA Industries ignoring the special features of aluminium smelter
plant. It was also contended that since the State Government invited the
company to establish the plant by assuring uninterrupted supply of power at concessional
rates, the principle of promissory estoppel was applicable and consequently the
demand of tariff contrary to agreement was illegal and arbitrary.
The
High Court upheld the validity of the impugned legislation by holding that :
(1)
under the amended provisions of Section 49 of the Electricity (Supply) Act
uniformity was the basis of tariff and since all the power tariff industries
were treated alike, the treatment meted out to the company was not
discriminatory under Article 14;
(2) the
enhancement of tariff was not violative of Article 19(1) (g);
(3) no
special promise was held out by the State or Electricity Board to the Company
that a particular formula will be applied in the case of consumption of
electricity by the company; that the doctrine of promissory estoppel was not
attracted in the sphere of statutory power and since the impugned action was a
consequence 215 of the amended provision of Section 49 the question of
promissory estoppel did not arise;
(4) the
State Legislature was not denuded of its legislative competence merely because
the Parliament declared aluminium industry as a controlled industry under the
Industries (Development and Regulation) Act, 1951; and
(5) the
notification issued by the Central Government fixing the aluminium policy and
also indicating the tariff affecting the aluminium industry was not repugnant
to the impugned provisions under the Amending Act of State Legislature.
Against
the decision of the High Court, the company filed an Appleal in this Court
challenging the vires of the Amending Act as well as the levy of enhanced
electricity tariff contending that ;
(1) since
the agreement was tripartite it could not have been annulled by taking recourse
to the amended provisions of Section 49 and that the Electricity Board unjustly
repudiated the agreement by revising the tariff exhorbitantly and making it applicable
uniformly to all the power intensive industries;
(2) even
if the Amending Act was intra-vires empowering the Board to charge uniform
tariff from consumers categorised in a particular industry there was no
justification to include the company's plant in other power intensive
industries;
(3)
the smelter aluminium plant has some special and peculiar features and its
inclusion in the category of other power intensive industries included in the
HT IA category was an unjust classification violating Article 14 of the
Constitution;
(4) the
High Court failed to note that a clear case of promissory estoppel was made out
by the appellant- company and that it was still applicable without violating
Section 49 of the Electricity (Supply) Act.
Dismissing
the appeal, this Court,
HELD :
1. The amending Act does not suffer from any infirmity affecting its vires
either on the score of legislative competence or for offending Articles
19(1)(g) or Article 14 of the Constitution. [236 - D]
2. In
deciding the question of legislative competence one must bear in mind that the
Constitution is not to be construed with a narrow or pedantic approach and it
is not to be construed as a mere law but as a machinery by which laws are made.
Such interpretation should be made broadly and liberally. The entries in the
Constitution only demarcate the legislative fields of the respective
legislature and do not confer legislative power as such.
[236 D
- F] 216
3. In
examining the allegations of hostile discriminatory treatment, what is looked
into is not its phraseology but the real effect of its provisions. The
legislature has been permitted to exercise an extremely wide discretion in
classifying items for collection of revenue so long as it refrains from clear
and hostile discrimination against particular persons or classes. It however
should be borne in mind that with all these latitudes certain irreducible
consideration of equality shall govern the differential treatment even in
fiscal legislation. The test could only be of palpable arbitrariness in the
context of left needs of the time and social exigencies informed by experience.
There cannot be any precise or set formulae or doctrinaire test or precise
scientific principles of exclusion or inclusion. [236 G H, 237 - A]
4. It
is true that the smelter plant has distinctive features in its manufacturing
mechanism and in the process of electrolytic operation. Also the smelter plant
is not only power intensive industry but the power assumes a very significant
role and constitutes one of the important raw materials in the productive
process. But the categorisation of the smelter plant as a high power intensive
industry is not by itself illegal or perverse, or without any basis and wholly
unjustified. In the broader classification, the smelter plant is certainly a
high power intensive industry and such categorisation was made by the Board not
for the purpose of enforcing the amended Section 49 with an object to annul the
agreement but such categorisation was made even earlier. In the circumstances,
it cannot be said that the broader categorisation of the smelter plant is
arbitrary, capricious and unreasonable resulting in treating the unequal as
equal thereby offending Article 14 of the Constitution. [ 245 B - E]
5. The
agreement of 1966 and 1976 were not the outcome of any unilateral promise or
assurance held out by the State or the Board to the appellant-Company . [244 H]
Such agreement was the result of negotiations between the parties and on such negotiations,
the terms and conditions were agreed upon between the parties.
Accordingly,
the foundation of promissory estoppel is absent and the case of promissory estoppel
as sought to be made out by the company cannot be accepted. [244 H, 245 - A]
Excise Commissioner, U.P. Etc. Etc. f. Ram Kumar Etc.
Etc.,
A.I.R. 1976 S.C. 2237; Union of India and Ors. v. Godfrey Philips India Ltd., A.I.R. 1986 S.C.
806; Council of Civil Service Union and Ors.
v. Minister for the 217 Civil Service, 1985 (3) All. E.R. 935; R v. Secretary
of State of Home Department, 1985 (1) All.E.R. 40; R v.
Secretary
of State for Home Department ex parte Ruddock & Ors., 1987 (2) All.E.R. 518;
M/s Motilal Padampat Sugar Mills Company (Pvt.) Ltd., v. State of Uttar Pradesh, [1979] 2 S.C.R. 641; Delhi Cloth and Genaral Mills Ltd. v. Union of India, [1988]
1 S.C.R. 383; Indian Aluminium Company v. The Orissa Electricity Board and Anr;.
A.I.R. 1975 Orissa 100, referred to.
Halsbury's
Laws of England, Fourth Edition (Reissue) Vol. 1 (1) Page 151, referred to.
6.
Since the agreements stood annulled in view of the amended provisions of
Section 49 of the Act, the Board was empowered to ask for uniform tariff rate
from the industries classified under one category. However, the question of
tariff for the supply of electricity to the smelter plant should be considered
sympathetically. [245 B, F] Tika Ramji v Stae of U.P., A.I.R. 1956 S.C. 676;
Uttar Pradesh & Ors. v. Synthetics and Chemical Ltd. and Ors., A.I.R. 1980
S.C. 614; Hoechest Pharmaceuticals Ltd. and Anr. Etc. v. State of Bihar & Ors., A.I.R. 1983 S.C. 1019;
Ishwari
Khetan Sugar Mills Pvt. Ltd. Etc. v. The State of U.P. and Ors., A.I.R. 1980 S.C. 1955, relied on.
Indian
Aluminium Co. v. Kerala State Electricity Board, A.I.R. 1975 S.C. 1967; Delhi
Cloth and General Mills Co. Ltd. v. The Rajasthan State Electricity Board,
A.I.R. 1986 S.C. 1126, referred to.
CIVIL
APPELLATE JURISDICTION : Civil Appeal No. 1841 of 1988.
From
the Judgment and Order dated 19.4.1988 of the Karnataka High Court in W.P. No.
6257 of 1981.
K.Parasaran,
A.K. Ganguli, K.R.D. Karanath and S. Sukumaran for the Appellants.
P.P. Rao,
R.N. Naransihma Murthy, S.K. Kulkarni, R.P. Wadhwani M.Veerappa and Kh. Nobin
Singh for the Respondents.
The
Judgment of the Court was delivered by 218 G.N. RAY, J. This Civil Appeal
arising out of Special Leave Petition (Civil) No. 5890 of 1988, is directed
against the judgment passed by the Division Bench of Karnataka High Court on April 19, 1988 in Writ Petition No. 6257 of 1981.
The
appellants prayed for a Writ in the nature of certiorari for directing the
respondents to withdraw the letter dated July 3, 1980 (Annexure G to the Writ Petition)
and Notification dated June
30, 1980 and for
appropriate writs and directions commanding the respondents to refund a sum of Rs,
60,28,175.08 collected by the respondent illegally.
There
was also a prayer for appropriate writs and directions on the respondents to
withdraw the supplementary electricity bills for the months of November and
December, 1980 and also the bills of January, 1981 and February, 1981
respectively (being Annexures CC, Y, X and GG) and for a direction to refund a
sum of Rs. 18,40,800.58 collected by the respondents on accounts of the
electricity bills. There was also a prayer for appropriate directions
restraining the respondents from collecting energy charges in any manner other
than on the basis of supply agreement and also restrain ing them for
disconnecting the supply of electricity to the factory of the appellant No. 1,
Indian Aluminium Company Limited at Belgaum. The appellants also prayed for
directing the respondent No. 1, the Karnataka Electricity Board to exercise its
powers under Section 49 (3) of the Electricity (Supply) Act by either framing
regulations in the tariff or by entering into an agreement providing for
appropriate protective claims.
The
essential facts concerning the writ petition involved in the instant Civil
Appeal may be stated as follows:
The
Indian Aluminium Company Limited registered under the Companies Act and one
shareholder, namely, Shri K.
Ghosh,
were the Writ Petitioners and the respondent No. 1 is the Karnataka Electricity
Board, a Body Corporate constituted under the Electricity (Supply) Act, 1948
and respondents Nos. 2, 3 and 4 are respectively the Executive Engineer
(Electrical), O and M Division, Karnataka, the Chief Engineer (General) and the
Accounts Officers, O and M Division, all the Karnataka Electricity Board.
Respondent No. 5 is the State of Karnataka through the Secretary, Department of Public Works Department and the respondent
No. 6 is Union of India through the Secretary, Ministry of Energy, Government
of India. The case of the appellants was inter alia that in 1966 the Government
of Karnataka had undertaken the Sharvathy Valley Hydro Electric Project in the
State of Karnataka. It had planned for constructing a
hydroelectric 219 generating system to generate a large quantity of electric
power. The State was anticipating the generation of large surplus power. The aluminium
industry particularly the smelter plant requires a large quantity of power for
manufacturing operation. The Karnataka State Electricity Board, (hereinafter
referred to as Board) and the State of Karnataka (hereinafter referred to as
State) had invited the Indian Aluminium Company Limited (hereinafter referred
to as the Company) to establish its aluminium smelter plant within the State of
Karnataka by assuring that uninterrupted supply of electricity would be given
to the smelter plant.
Accordingly,
the Company established a factory with its smelter plant at Belgaum.
There
was a tripartite agreement entered into between the Company, the Board and the
State on March 26, 1966.
Later
on, a fresh tripartite agreement was entered into between the parties in
modification of the aforesaid tripartite agreement and the latter agreement was
entered into on August
7, 1976. In the said
tripartite agreement several clauses were incorporated to ensure uninterrupted
supply of power and there were also provisions for supply of power at concessional
rates.
The
State promulgated the Electricity Supply Karnataka (Amendment) Ordinance, 1980
purporting to amend Section 49 of the Electricity (Supply) Act, 1948. Such
Ordinance was replaced by the Karnataka Act 33 of 1981. Before the promulgation
of the Ordinance which was replaced by the said Act, the Board increased the
power rate in July 1980 far beyond the rate prescribed in the agreement. After
promulgation of the Ordinance since replaced by the Act on February 1, 1981,
the Board futher increased the tariff rates.
The Aluminium
Control Order was issued by the Central Government in 1970 to control the price
of aluminium ingots, wire bars, billets etc. On July 15, 1975, the Central
Government notified the aluminium policy. It was indicated in the said policy
that the proposed new rate for aluminium should remain in force for five years
and such rates should be periodically revised and revision, if any, should be
made only after consultation with the Central Government which was controlling
the price of aluminium. In July, 1975 the rate of tariff was 7 paise per unit.
The second tripartite agreement in supersession of the earlier one was entered
into on August 7, 1976 between the Writ Petitioners and the respondent No. 4
and such agreement inter alia provided that whenever the Board wants to
increase its power 220 rates, it must give at least six months' notice to the
Company to approach the Central Government so that corresponding increase in
retention price of aluminium was effected to absorb the increased power rate.
It was however provided that if the Central Government would not increase the
price within the period of six months, the increased tariff rates would become
effective. On January 22, 1980, the Board issued a letter to the Company
calling upon the Company to contact the Executive Engineer for executing a
supplementary agreement relating to certain changes in the tariff rate proposed
in the letter. The Company by its letter dated February 25, 1980 requested the
Government of Karnataka for arranging a meeting for discussion of the situation
arising out of the proposed change in the tariff rate. It is contended that no
positive result came out of the discussion held between the parties. On July
15, 1980 the Government of India issued a notification inter alia refixing the
retention price. On July 8, 1980, the Company received letter dated July 3,
1980 from the Board indicating that additional surcharge of 2 paise per unit
had been enforced. On August 5, 1980 the Company, by way of abundant caution,
had applied to the Central Government for increasing the retention price. The
request made by the Company not to increase the tariff rate for the supply of
power to its smelter plant however, was not acceded to by the Board. The power
rate was increased to 19.59 paise per unit in 1980. The Board had also imposed
surcharge of 10 paise per unit on June 30, 1980, and such surcharge was made
effective from June 1, 1980. The Company contended that the Board had not given
six months' notice for the surcharge and in the Writ Petition such change of
surcharge effective from June 1, 1980 had also been challenged and the legality
and validity of imposition of surcharge for the period between July 1, 1980 to
November 1, 1980 before the promulgation of the said ordinance, were challenged
in the Writ Petition.
On November 21, 1980, the State of Karnataka promulgated Electricity Supply
(Karnataka Amendment) Ordinance for amending Section 49 of the Electricity
(Supply) Act which as afsoresaid was replaced by Act 33 of 1981. The effect of
such amendment of Section 49 of the Electricity (Supply) Act is that it has
empowered the Board to increase tariff rates notwithstanding any agreement with
the consumers. On February 2, 1981, the Board increased the tariff rate to Rs.
25.93 per unit. Being aggrieved by increase of tariff rates and consequential
demands for payment of bills on the basis of increased tariff in complete
disregard of the said agreement of 1976, the Company and one 221 of its share
holders moved the said Writ Petition No. 6257 to 1981 for the reliefs indicated
hereinbefore.
It may
be indicated here that existing rate of electricity was Rs. 22.5 per unit and Rs.
22 per KVA on 27.5.1991. The Board had thereafter increased the rate
periodically from time to time as follows:
20.08.81
Rs. 30.18 01.11.83 Rs. 38.30 10.11.83 Rs. 41.30 01.01.84 Rs. 41.38 27.09.85 Rs.
58.01 01.09.86 Rs. 68.01 The Company contended that the increased tariff was
not enforceable against the company in view of the agreement between the
parties. However, without prejudice to the rights and contentions, cheques were
sent to cover the bill.
The
Writ Petitioners contended inter alia that the agreement dated August 7, 1976
between the Company and the Board and the State Government was binding on the
parties and the tariff for supply of electricity has to be fixed only on the
basis of the terms of the said agreement. Consequently, excess amount paid by
the Company under protest should be refunded. The Writ Petitioners further
contended that in the first agreement dated March 26, 1966, the then Mysore
State Electricity Board had agreed to supply electric power to the smelter
plant of the Company located at Belgaum.
Elaborate
provisions were made to cover several situations which were likely to arise in
the course of supply of power and utilisation of the same by the Company. The
supply of power under the said agreement commenced from October 22,1969. The said agreement was replaced by
the agreement dated August
7, 1976 (Annexure B to
the Writ Petition). Such agreement of 1976 was made in view of the industrial
policy of the Government of India and the guidelines stated by the Government
of India in the matter of electricity tariff to be applied to the aluminium
plants.
The
Writ Petitioners contended that the smelter plant of the Company is fully
dependent on power and for every tonne of aluminium produced, about 1900 units
of electric energy are consumed by the said smelter plant. It is the specific
case of the Writ Petitioners-appellants that 222 production in the smelter plant
depends mainly on the supply of uninterrupted electrical power and unlike in
other industries where electricity is used as a motive power, in the smelter
plant of the Company the electricity is not only a motive power but also an
important raw material.
Uninterrupted
supply of power at a very high degree is essentially necessary for breaking the
chemical bond for aluminium oxygen in the compound of aluminium oxide. The
process of manufacture of primary alumina is done at two stages-first, alumina,
i.e., pure oxide of aluminium is extracted from its ore, bauxite by a chemical
process. Such alumina is further processed in the smelter plant. In this
smelter plant, the alumina is treated with the help of electrolytic cells. In
the smelter plant at Belgaum, there are three lines with 492 installed electrolyic
cells.
Alumina
is charged into the molten cryolite in which it gets dissolved and direct
electric current is passed through it continuously. By the passage of electric
current the alumina gets split into aluminum and oxygen. The cryolite is kept
at a temperature of about 970 degree C. The melting point of aluminium is less
than this temperature. The aluminium formed by the splitting up of the alumina
is molten at this temperature and then it settles down at the bottom of the
cells from which it is periodically siphoned out in the molten form for casting
into different forms like ingots, slabs, etc. It is contended that if the
electric supply is curtailed or interrupted, the temperature of the cryolite
bath will come down and if the interruption period is more than 2 hours, the
bath will cool down and solidify.
Once
the cryolity bath gets solidified, it will not be able to pass electric current
through the cell and even if the power supply is restored, after solidification
of cryolite bath, the cell cannot be restarted. Once the solidification of cryolite
bath takes place, the cells can be restored only by a complicated procedure.
The entire cryolite bath will have to be dug out, powdered and charged back. The
same has then to be melted again using abnormally high amount of electric
power, and such process entails a very high cost.
The
cathode carbon which will cost more than Rs. 1 lakh per cell will also get
severely damaged with the thermal shock of cooling and heating. It is contended
that apart from the time factor and the large amount of energy required to be
consumed, in the process of restarting the cost of restarting each cell is over
Rs. 60,000. Besides, the financial loss, there will be production loss and it
may take about two months before normalcy of operations can be resumed after
the restart operations. It is also contended that any change 223 or
fluctuations such as power cuts or interruptions in supply of power has severe
adverse costs implication for the production of aluminium quite apart from
production loss of aluminum metal itself.
It is
also a specific case of the Writ Petitioners appellants that manufacturing
process in the smelter plant has special characteristics and such manufacturing
process is distinctively different in metallurgical-cum electrolytic process
and the same cannot be compared with most of the other industries including
power intensive industries where curtailments or interruptions of supply of
power only affect the production during the interrupted period and not after
the full power is resumed. Moreover, unlike in other industries, the power is
itself a very important raw material for production of aluminium in the smelter
plant.
Accordingly,
the smelter plant is not only a high power sensitive plant but it is absolutely
dependent on power being its essential and primary raw material. It is
contended that all over the world, aluminium has been given a special status
with regard to the power and 'firm power' concept is the key note in this
industry. Since aluminium industry requires a large amount of power not
comparable with any other industry, cost of power is the most important element
in the cost of production of aluminium. At the relevant time when the Writ
Petition was presented the cost of power formed about 38% of the total cost of
production and it is very strongly contended that in no other industry such
large amount of power is required and consequently power cost element in the
cost of production in other industries is substantially lower. In the aluminium
policy notified by the Government of India in 1975, it was indicated that the
production of aluminium metal had declined considerably since 1971-72 in spite
of the fact that installed capacity had been going up. It was also indicated
that such decline was primarily due to the restrictions on power supply to the aluminium
producers. It was further indicated that the rates at which electricity Board
had contracted in the past for supply of power to the aluminium industry,
proving to be unremunerative for the Boards has also been responsible for this
situation, and the electricity Boards were the largest users of aluminium.
Government
of India., therefore, considered it imperative that power tariffs need to be revised
in a way which would be fair to the Electricity Boards but which would not
result in rising of the price of aluminium.
The
Writ Petitioners have contended that under clause 5 of the agreement of 1976,
the payment for supply is to be made at the rate at 224 which power is being
drawn and no payment is to be made with reference to the units of electrical
energy consumed in any particular period and the method will operate
reasonably.
Provisions
were made for a formula to find out average from the demands for all the half
hours during the months in which the cut or interruption took place. By such
provision the consumer, namely, the company was given the benefit of a reduced
consumption of the demand during the period where there may have been a power cut
or interruption in supply.
Clause
10 of the agreement provides for relieving the Company from the obligation of
taking and paying for supply of power if the Company was prevented from taking
electric power. It has been contended that if reference is made to various
provisions in the agreement of 1976 it will be evident that the State
Government and the Board having fully appreciated the absolute necessity of
uninterrupted supply of power and the impact of the tariff rate for the supply
of power to the smelter plant agreed to various clauses ensuring smooth and
uninterrupted supply of electricity at the rates agreed upon by the parties. In
view of such facts the Board could not revise the tariff according to its
fancies and the Board being squarely bound by the agreement could not repudiate
the same under the cover of the amendment of Section 49 of the Electricity
(Supply) Act. It was contended by the Writ Petitioners before the High Court
that since this smelter plant was installed at Belgaum on the invitation by the
State of Karnataka and Electricity Board by clearly assuring the Company that
uninterrupted supply of electricity would be made at a reasonable rate and on
the basis of the understanding between the parties as embodied in the first and
the second agreement, the principle of promissory estoppel was squarely
attracted in the facts of the case and any demand of tariff for electric supply
to the smelter plant of the Company at Belgaum contrary to the existing
agreement of 1976 is wholly illegal and inoperative. It was also contended that
in the aforesaid circumstances amendment of Section 49 of the Electricity
(Supply) Act, applicable to the Board and its consumers, was not applicable to
the Company and the Company despite such amendment was entitled to enjoy the
privileges emanating from the agreement of 1976. The validity of the amending
Act was challenged by the Writ Petitioners before the High Court.
It was
contended by the Writ Petitioners before the High Court that the amending act
does not affect the existing agreement of 1976 inter alia 225 on the following grounds
:
(a)
The agreement is a tripartite agreement not contemplated by the amending Act
but the agreement envisaged under the amending Act is a bipartite agreement
between the consumer and the Board.
(b)
The tripartite agreement was the result of aluminium policy of the Government
of India and such Governmental policy cannot be negatived by the amending Act.
(c)
The Board is estoppel from claiming any higher tariff not contemplated by the
agreement.
(d)
The amending Act is ultra vires inasmuch as :
(i) It
treats, all consumers at par irrespective of the special features of each class
of consumers and therefore arbitrary offending Article 14 of the Constitution
(ii) The increase of tariff by virtue of the amending Act directly hits at the
price of aluminium fixed under the Aluminium Control Order issued by the
Central Government and hence illegal and ultra vires.
(iii) Aluminium
industry is a scheduled industry under the control of the Government of India
as declared by Industries Development and Regulation Act and hence falls under
Entry 52 of List I of VIIth Schedule of the Constitution. Therefore policy of
Government of India amounts to direction issued to the State Governments which
they are bound to obey. Consequently, the agreement of 1976 is an agreement
protected by a law coming under Entry 52 of List I, terms of which cannot be
varied by a law enacted by a State by virtue of the power conferred by the
concurrent list (List III of VIIth schedule). The amending Act should be
construed in such a way as not to impinge on or detract from the law, statutory
order or constitutional direction of the Central Government, otherwise the said
amending Act will lack legislative competence.
226
The Respondents opposed the contentions of the Writ Petitioners and the
contentions of the Respondents as advanced before the High Court may broadly be
indicated as follows :
(i)
The remedy of writ petition to enforce the contractual rights under the agreement
was not available.
(ii)
State did not invite the petitioner to establish the factory at Belgaum; it only agreed to make available
the necessary facilities.
(iii) Aluminium
factor does not occupy any unique position and does not constitute a class of
its own from the point of view of power requirement and/or supply. Even if it
is a class by itself, that would not confer any legal right on the petitioner
to be accorded any pereferential treatment among industries or consumers of
electricity.
(iv)
It is not correct to contend that the agreement entered into was by exercise of
the statutory powers under Section 49(3) of the Act alone.
(v)
The clauses in the agreement were included after mutual discussion and
consensus of the concerned parties.
(vi)
The clause relating to the giving of prior notice before revision of tariff is
neither a condition precedent, nor constituted a fundamental term of the
agreement. Similarly, such a clause does not amount to a solemn assurance or
representation on the part of the State Government.
However,
such a term in the agreement will not bind the Board to revise the tariff in
exercise of its statutory powers.
(vii)
Surcharge of 2 paise per unit was levied and collected by the Board, as applied
to others.
(viii)
In view of the ordinance with effect from 22.11.1980 the tariff schedule H.T.1A
(Electrical Power Tariff of 1978, with all other charges like surcharges and
additional surcharge etc.) is applicable and the petitioner is governed by that
H.T.1A Tariff Schedule, in supersession of the terms set out in the 227
agreement. The Ordinance nullifies all the rates and the mode of billing
envisaged in the supply agreement.
(ix)
The plea of promissory estoppel put forward by the petitioner is untenable,
since the amending Act is a legislative measure.
(x)
The State legislature has plenary powers to legislate on all matters pertaining
to electricity and the powers of the State legislature in this behalf, cannot
be curtailed by an agreement entered into by the State with the petitioners or
any other person.
To
appreciate the respective contentions of the parties on the question of
legislative competence for the amending Act, the High Court referred the
Entries 52 and 54 of List I of VIIth Schedule of the Constitution, Entries No.
26 and 27 List II Entries 33,34 and 38 of List III of the VIIth Schedule. The
High Court also referred to and relied on the discussion of this Court in the
case of Tika Ramji v. State of U.P. (AIR 1956
S.C. 676) where the concept of `industry' as a topic of legislation was
explained. The legislative competence of the State of U.P. to regulate the
supply and purchase of sugar cane by the impugned State Act of 1953 was raised
by contending that `sugar' being controlled industry under the Industries Development
and Regulation Act, the topic of impugned legislation pertaining to sugarcane
fall within the purview of Central Control under Entry 52 of List I and hence
the subject is taken away from the field of legislation by the State. It was
also contended that Sugar Control Order 1955 promulgated by Central Government
under the Essential Commodities Act 1955 empowered the Central Government to
regulate the movement of sugarcane and to fix its price. The observation of
this Court at page 695 of the report was copiously quoted by the High Court for
holding that there was no question of lack of legislative competence for
enacting the amending act by the Karnataka Legislature.
The
High Court referred to the observation of this Court to the following effect:-
"It is clear therefore, that all the Acts and the notifications issued
there under by the Centre in regard to sugar and sugar cane were enacted in
exercise of the concurrent jurisdiction.
228
The exercise of such concurrent jurisdiction would not deprive the provincial
legislatures of similar powers which they had under the Provincial Legislature
List and there would, therefore, be no question of legislative incompetence qua
the Provincial Legislatures in regard to similar pieces of legislation enacted
by the latter.
The
provincial Legislatures as well as the Central Legislature would be comptetent
to enact such pieces of legislation and no question of legislative competence
would arise. It also follows as a necessary corollary that, even though sugar
industry was a controlled industry, none of these Acts enacted by the Centre
was in exercise of its jurisdiction under Entry 52 of List I.
Industry
in the wide sense of the term would be capable of comprising three different
aspects (1) raw materials which are an integral part of the industrial process
(2) the process of manufacture or production, and (3) the distribution of the
products of the industry. The raw materials would be goods which would be
comprised in Entry 27 of List II. The process of manufacture or production
would be comprised in Entry 24 of List II except where the industry was a
controlled industry when it would fall within Entry 52 of List I and the
products of the industry would also be comprised in Entry 27 of List II except
where they were the products of the controlled industries when they would fall
within Entry 33 of List III.
This
being the position it cannot be said that the legislation which was enacted by
the Centre in regard to sugar and sugarcane could fall within entry 52 of List
I. Before sugar industry became a controlled industry, both sugar and sugarcane
fell within Entry 27 of List II but, after a declaration was made by Parliament
in 1951 by Act 65 of 1951 sugar industry became a controlled industry and the
product of that industry viz. sugar was comprised in Entry 27 of List II. Even
so, the Centre as well as the Provincial Legislatures had concurrent
jurisdiction in regard to the same.
In no
event could the legislation in regard to sugar and sugarcane be thus included within
entry 52 of List I. The pith 229 and substance argument also cannot be imported
here for the simple reason that, when both the Centre as well as the State
Legislatures were operating in the concurrent field, there was no question of
any trespass upon the exclusive jurisdiction vested in the Centre under Entry
52 of List I, the only question which survived being whether, putting both the
pieces of legislation enacted by the Centre and the State Legislature together,
there was any repugnancy, a contention which will be dealt with
hereafter." The High Court also noted that amending Act was placed before
the President and consent was obtained. Hence by virtue of Article 254(2) of
the Constitution, the State Legislation will prevail even if there is any repugnancy.
The
High Court also held that the Writ Petitioners specifically pleaded that in the
smelter plant electricity was a raw material for aluminum or `relatable
article' to the industry. Hence in the absence of any notification under
Section 18G of the Industries Development and Regulation Act there was no
question of any repugnancy on the score of tariff of electricity fixed by the
amending Act. The High Court also relied on the observation of this Court in Tika
Ramji's case at page 701 and 703 of the report to the following effect:-
"Sugar industry being one of the scheduled industries, it was contended
for the petitioners that sugarcane was an article relatable to the sugar
industry and was, therefore, within the scope of S. 18G and the Central Government
was thus authorised by notified order to provide for regulating the supply and
distribution thereof and trade and commerce therein." Even assuming that
sugarcane was an article or class of articles relatable to the sugar industry
within the meaning of S. 18-G of Act of 1951, it is to be noted that no order
was issued by the Central Government in exercise of the powers vested in it
under that section and no question of repugnancy could ever arise because, as
had been noted above, repugnancy must exist in fact and not depend merely on a
possibility. The possibility of an order under S. 18-G being issued by the
Central Government would not be enough. The existence of such an order would be
the essential prerequisite before any repugnancy 230 could ever arise." It
may be noted here that for the purpose of finding that electricity was a raw
material for the smelter plant, the High Court referred to relevant pleadings
of the Writ Petitioners and also referred to the decision of this Court
concerning the petitioner company itself in Indian Aluminium Co. v. Kerala
State Electricity Board, AIR 1975 SC 1967 wherein this Court referring to the
process of manufacture of aluminium from alumina has held that electricity is a
raw material for such manufacturing process. Similar view was also expressed by
this Court in the decision of Delhi Cloth and General Mills Co. Ltd. v. The
Rajasthan State Electricity Board, AIR 1986 SC 1126 while considering electro
chemical and PVC and other allied industrial products in a power oriented
industry.
The
High Court also negatived the contention of the Writ Petitioners that when
Parliament has evinced interest in Aluminium Industry, the entire field of
legislation touching all aspects of the said industries vests in the Parliament
and State Legislature has lost its competence as the field of legislation will
be only under Entry 52 of List I.
The
High Court has held that mere declaration by Parliament that a particular
industry is a controlled industry under the Industries Development and
Regulation Act is by itself not sufficient to exclude the competence of State
legislature to enact a law over a subject which otherwise falls within its
field of legislation. The High Court referred to the decision of this Court in
the case of State of Uttar Pradesh & others v. Synthetics and Chemical
Limited and others, AIR 1980 SC 614. It was contended that the denatured spirit
or industrial alcohol comes within the purview of the control of the Central
Government and hence Central Government alone was empowered to provide for
regulating the distribution, transport, disposal, acquisition etc. Referring to
the order of the Central Government issued as Ethyl Alcohol (Price Control)
Order, 1971, this Court held to the following effect:- "...We are unable
to read the Ethyl Alcohol (Price Control) Orders as explicitly or impliedly
taking away the power of the State to regulate the distribution of intoxicating
liquor by collecting a levy for parting away with its exclusive rights.
If the
powers of Parliament and the State Legislature were confined to Entry 52 in
List 1 and the Entry 24 in List II, Parliament 231 would have had exclusive
power to legislate in respect of industries notified by Parliament. The power
of the State under Entry 24, List II is subject to the provisions of Entry 52
in List I.
But we
have to take into account Entry 26 in List II and Entry 33 in List III for
determining the scope of legislative power of the Parliament and the State.
Entry 26 in List II is as follows:
`Trade
and commerce within the State subject to the provisions of Entry 33 of List
III'." In the said case, this Court relied on the decision in Tika Ramji's
case. The High Court also referred to the decision of this Court in the case of
Hoechst Pharmaceuticals Ltd. and another etc. v. State of Bihar & Ors., AIR
1983 SC 1019. It was contended in the said case that levy of surcharge of sale
tax imposed by the State Legislature was without legislative competence as it
impinged or affected the price of drugs fixed under Drugs (Price Control)
Order, 1979 issued by the Central Government under the Essential Commodities
Act. This Court has held in the said decision:
"In
the case of a seeming conflict between the Entries in the two lists, the
Entries should be read together without giving a narrow and restricted sense to
either of them. Secondly, an attempt should be made to see whether the two
Entries cannot be reconciled so as to avoid a conflict of jurisdiction. It
should be considered whether a fair reconciliation can be achieved by giving to
the language of the Union Legislative List a meaning which, if less wide than
it might in another context bear, is yet one that can properly be given to it
and equally giving to the language of the State Legislative List a meaning
which it can properly bear. The non obstante clause in Article 246 (1) must
operate only if such reconciliation should prove impossible. Thirdly, no
question of conflict between the two lists will arise if the impugned
legislation, by the application of the doctrine of `pith and substance' appears
to fall exclusively under one list, and the encroachment upon another list is
only incidental.
Union
and State Legislatures have concurrent power with respect to subjects
enumerated in List III, subject only to the provision contained in Cl. (2) of
Article 254 i.e., provided the provisions of the State Act do not conflict with
those of any 232 Central Act on the subject. However, in case of repugnancy
between a State Act and a Union Law on a subject enumerated in List III, the
State law must yield to the Central law unless it has been reserved for the
assent of the President and has received his assent under Article 254 (2). The
question of repugnancy arises only when both the Legislatures are competent to
legislate in the same field i.e., when both the Union and the State laws relate to a subject specified in List
III and occupy the same field." The High Court also referred to the
decision of a Constitution Bench of this Court in Ishwari Khetan Sugar Mills
Pvt. Ltd. etc. etc. v. The State of U.P.
and others, AIR 1980 SC 1955. It has been held by this Court in the said
decision that the question arose for decision in the said case about the
validity of law acquiring undertakings involved in manufacturing sugar by the
State Legislature.
The
contention was sugar as a topic of legislation was under Entry 52 of List I by
virtue of it being declared as an industry control of which vested in the Union as declared by Industries Development and Regulation
Act. The majority view of this Court in the said case at page 1961 of the
report was quoted by the High Court to the following effect:
"The
legislation enacted pursuant to the power to legislate acquired by declaration
must be for assuming control over the industry and the declaration has to be
made by law enacted, of which declaration would an integral part, Legislation
for assuming control containing the declaration will spell out the limit of
control so assumed by the declaration. Therefore, the degree and extent of
control that would be acquired by Parliament pursuant to the declaration would
necessarily depend upon the legislation enacted spelling out the degree of
control assumed. A mere declaration unaccompanied by law is incompatible with
entry 52 List I. A declaration for assuming control of specified industries
coupled with law assuming control is a pre-requisite for taking legislative
action under Entry 52, List I. The declaration and the legislation pursuant to
declaration to the extent denude the power of State Legislature to legislate
under Entry 24, List II. Therefore, the erosion of the power of the State
legislature to legislate in respect of declared industry would not occur merely
by declaration but by the enactment consequent 233 on the declaration
prescribing the extent and scope of control." The High Court also referred
to few more decisions of this Court for the purpose of appreciating the
contention whether the supply of electricity and tariff rates were controlled
by Entry 52 of List I, thereby taking away legislative competence of the State
Legislature and whether or not the Notification issued by the Central
Government fixing the aluminium policy and also indicating the tariff affecting
the aluminium industry became repugnant to the impugned provisions under the
amending Act of State Legislature. The High Court by giving a long reasoning
has come to the finding that the impugned legislation was quite valid and did
not suffer either from the want of legislative competence or on the score of
repugnancy between the Central and the State legislation.
The
High Court also negatived the contention of the Writ Petitioners that aluminium
industry is special class of its own and thus cannot be categorised with other
industries. It was indicated by the High Court that if a microscopic analysis
is to be done almost every industry will have its own special features. Such as
analysis is outside the scope of Article 14. Classification is based on broad
principles, to be connected reasonably with the object to be achieved. It has
been held by the High Court that the Scheme of Section 49 of the Electricity
Supply Act indicates that uniformity will be the basis of tariff and since all
power intensive industries have been treated alike in view of the amended
provision of Section 49 in supersession of agreements between the consumers and
the Board, the High Court held that no discriminatory treatment was meted out
to the Writ Petitioners. The High Court has also held that the contention that Kudremukh
Iron and Steel Industries have been treated favorably resulting in a
discriminatory treatment to the petitioner-Company should not be accepted by
indicating the consideration relating to Kudremukh industry and also noting the
submission made by the learned Advocate General that enforceability of the
agreement with Kudremukh Iron and Steel Industry was also under active
consideration in the light of the impugned amendments. It has been held by the
High Court that since the Company was not comparable with the Kudremukh Iron
and Steel Industry the contention of discrimination was not to be accepted.
The
High Court also rejected the contention that price hike for the power supply
imposes an unreasonable restriction on the right of the petitioner-Company to
carry on its industry, 234 thereby infringing Article 19(1) (g) of the
Constitution.
It has
been indicated by the High Court that the price hike will have its impact on
the cost of production but such increase in the cost of production cannot be
avoided. It has been held that the price of aluminium control order itself
provides for restructure of aluminium for which the petitioner-Company has to
approach the Central Government.
Coming
to the question of promissory estoppel raised by the petitioners, the High
Court referred to paragraphs 91 and 92 of the Writ Petition where the pleading
of promissory estoppel was made by the Writ Petitioners. The High Court has
accepted the contention of the respondents as advanced by the learned
Advocate-General appearing for the respondents that the doctrine of promissory estoppel
is not attracted in the sphere of statutory power and since the impugned action
was a consequence of the amended provision of Section 49, the question of
promissory estoppel did not arise. The reference was made to the decision of this
Court in Excise Commissioner, U.P. etc. etc. v. Ram Kumar etc.
etc.,
AIR 1976 SC 2237 wherein it was observed by this Court to other following
effect:- "It is now well settled by a catena of decisions that there can
be no question of estoppel against the Government in the exercise of its
legislative, sovereign or executive powers." Reference was also made to
another decision of this Court in Union of India and others v. Godfrey Philips
India Ltd., AIR 1986 SC 806. The observation of this Court appearing at para 14
was referred to by the High Court to the following effect:- "...It is
equally true that promissory estoppel cannot be used to compel the Government
or a public authority to carry out a representation or promise which is
contrary to law or which was outside the authority or power of the officer of
the Government or of the public authority to make. We may also point out that
the doctrine of promissory estoppel being an equitable doctrine, it must yield
when the equity so requires, if it can be shown by the Government or public
authority that having regard to the facts as they have transpired, it would be
inequitable to hold the government or public authority to the promise or
representation made by it, the Court would not raise an 235 equity in favour of
the person to whom the promise or representation is made and enforce the
promise or representation against the Government or public authority. The
doctrine of promissory estoppel would be displaced in such a case, because on
the facts, equity would not require that the Government or public authority
should be held bound by the promise or representation made by it." The
High Court has held that Section 49(5) of the Act as introduced by the impugned
amendment by the very language of it overrides any other agreement or law. It
has been held that question of categorisation under Section 49(5) is to compel
the consumer to pay for the electricity consumed according to the uniform
tariff applicable to the category to which it belongs. The High Court has held
the petitioner's contention should not be accepted that the Board is bound to
treat the petitioner as a special category for which the tariff applicable was
to be regulated by the agreed formula. The High Court has also held that
factually also it is not possible to conclude on the existing material that a
special promise was held out to the petitioner- Company that a particular
formula will be applied in the case of the consumption of electricity by the
Writ Petitioners. The High Court has come to the finding that it will not be
possible to hold that there was a promise which was held out for the benefit of
the petitioners but the invitation to start the industries in the State, if at
all, was the motive force for the petitioner and other industries to establish
various factories in the State to avail the advantages of the prevailing
conditions in the State. The contentions of the Writ Petitioners that the bills
containing the revised tariff even before the promulgation of ordinance
amending Section 49 was illegal and unjustified, had not been gone into by the
High Court in view of the specific statement by the learned counsel for the
Board before the High Court that the Writ Petitioners should approach the Board
with particulars in support of their contentions and the Board was prepared to
revise the bills if there had been any error or omission on the part of the
Board. Save as aforesaid, all other reliefs claimed by the petitioners in the
Writ Petition were disallowed by the High Court and the Writ Petition was
accordingly dismissed.
Mr. Parasaran,the
learned Senior Counsel appearing for the appellants in his usual fairness had
indicated that detailed arguments had been advanced before the High Court of
Karnataka at the hearing of the Writ 236 proceeding on the question of vires of
the amending Act, on the score of legislative competence and also on the ground
of arbitrary action in revising the tariffs without justification and unjust
classification of the smelter plant in the category of other power intensive
industries included in the category of HT-1A without appreciating the peculiar
features of the productive mechanism in a smelter plant thereby offending
Article 14 of the Constitution. He has submitted that as he intends to advance
the same contentions raised before the High Court on the question of vires for
appropriate consideration by this Court he does not intend to elaborate the
same once more. It is precisely for the aforesaid reason, we have indicated in
detail the reasonings of the High Court in dispelling the contentions of the
Writ Petitioners that the amending Act is ultra vires.
We
have given our anxious consideration to the contentions raised for challenging
the vires of the amending Act but we are unable to accept the contentions that
the Act suffers from any infirmity affecting its vires either on the score of
legislative competence or for offending Articles 19(1) (g) or Article 14 of the
Constitution. It appears that the High Court has given cogent reasons for
upholding the vires of the amending Act and for dispelling the contentions raised
by the Writ petitioners and we endorse the view taken by the High Court. We may
only indicate her that in deciding the question of legislative competence one
must bear in mind that the Constitution is not to be construed with a narrow or
pedanti approach and it is not to be construed as a mere law but as a machinery
by which laws are made. Such interpretation should be made broadly and
liberally. The entries in the Constitution only demarcate the legislative
fields of the respective legislature and do not confer legislative power as
such.
In
examining the allegations of hostile discriminatory treatment, what is looked
into is not is phraseology but the real effect of its provisions. Decisions of
this Court have permitted the legislature to exercise an extremely wide
discretion in classifying items for collection of revenue so long as it
refrains from clear and hostile discrimination against particular persons or
classes. It, however, should be borne in mind that with all these latitudes
certain irreducible consideration of equality shall govern the differential
treatment even in fiscal legislation.
The
test could only be of palpable arbitrariness in the context of felt needs of
the time and social exigencies informed by experience. There 237 cannot be any
precise or set formulae or doctrinaire tests or precise scientific principles
of exclusion.
Mr. Parasaran
in his fairness has submitted that under the Electricity (Supply) Act, the
Board is empowered to revise tariffs but he has contended that such revision
cannot be made arbitrarily and capriciously. He has submitted that since the
Board is the licencee for supply of electrical energy to various consumers in a
particular area, the Board, as a matter of fact enjoys the privilege of
monopoly to some extent. It is therefore necessary to consider whether in the
exercise of revision of tariffs, the Board has acted reasonably and fairly and
the action is well informed by reasons. He has also contended that the smelter
plant has some special and peculiar features in its manufacturing mechanism of aluminium
from alumina. He has drawn our attention to the pleadings in the Writ Petition
where such mechanism and the key role of electricity have been elaborately high-lighted.
Mr. Parasaran has also drawn our attention to the accepted position all over
the world about the very important and key role of electricity in the
electrolytic process in manufacture of aluminium in a smelter plant and its
impact as a basic raw material with a very high implication in the cost of
manufacture. In the aforesaid context, Mr. Parasaran has contended that it is
only unjust and improper to classify the smelter plant in the general group of
power intensive industries. To classify the smelter plant only as a power
intensive industry like various other power intensive industries, will not be
proper classification. The very distinctive and unique features of smelter
plant are well known to the State and the Board. He has drawn the attention of
the Court to various clauses of the agreement of 1976 for the purpose of
showing that the State and the Board were fully aware of the role of
electricity in the manufacturing mechanism in a smelter plant and the extreme
need of uninterrupted supply of energy to the plant of the petitioner-Company
at Belgaum.
Mr. Parasaran
has submitted that as the State and the Board were fully aware of the
implication of tariff of electricity in the smelter plant, special provisions
were made in the agreement for billing and rates to be charged in the event of
interruption of supply. Mr. Parasaran has contended that as the agreement was
tripartite it could not have been annulled by taking recourse to the amended
provision of Section 49 of the Electricity (Supply) Act, the Boards has
unjustly repudiated the agreement by treating the smelter plant as only a power
intensive industry and revising the tariff exorbitantly and making it
applicable to the petitioner-company on the 238 plea that all the power
intensive industries including the plant of the petitioner-Company have been
placed at par and have been subjected to same tariff for the supply of
electricity.
Mr. Parasaran
has contended that even if the amending Act is intra vires thereby empowering
the Board to annual all existing agreements with the consumers and requiring
the Board to charge uniform tariff to the consumers categorised in a particular
group or class, there was no justification to treat the smelter plant in the
same category as in the case of other power intensive industries.
Mr. Parasaran
has referred to specific pleadings in the Writ Petition wherein a case of
promissory estoppel binding the State and Board in the matter of adhering to
the terms of agreement of 1976 have been made out by the petitioner- Company.
He has submitted that the foundation of promissory estoppel lies in the
legitimate expectation a person may have of being treated in a certain way by
administrative authority. In this connection, Mr. Parasaran has referred to
paragraph 81 at page 151 of Volume 1(1) of Halsbury's Laws of England, Fourth
Edition (Reissue) dealing with "Legitimate Expectation". It has been
indicated in the treatise that a person may have a legitimate expectation of
being treated in a certain way by an administrative authority even though he
has not legal right in private law to receive such treatment. The expectation
may arise either from a representation or promise made by the authority
including an implied representation or from consistent past practice. The existence
of a legitimate expectation may have a number of different consequences and one
of such consequences is that the authority ought not to act so as to defeat the
expectation without some overriding reason of public policy to justify its
doing so. It may also mean that if the authority proposes to defeat a person's
legitimate expectation it must afford him an opportunity to make
representations in the matter. In this connection, Mr. Parasaran has referred
to the decision of House of Lords in Council of Civil Service Union and others
v. Minister for the Civil Service, (1985) 3 All England Reporter page 935.
It has
been held in the said decision that an aggrieved person was entitled to invoke
judicial review if he could show that a decision of public authority affected
him of some benefit or advantage which in the past he had been permitted to
enjoy and which he legitimately expected to be permitted to continue to enjoy
either until he was given reasons for withdrawal and the opportunity to comment
on these reasons. Mr. 239 Parasaran has also referred to a decision of Court of
Appeal in R v. Secretary of State for Home Department, (1985) 1 All England
Reporter page 40 wherein the right of being heard by a person having a
reasonable expectation if likely to be affected by a decision to be taken by an
authority has been indicated. Mr. Parasaran also relied on a decision of
Queen's Bench Division in R v. Secretary of State for Home Department ex parte
Ruddock & others (1987) 2 All England Law Reports page 518. It has been
indicated in the said decision that the doctrine of legitimate expectation
imposed in essence a duty to act fairly and was not restricted to cases that
party having expectation was to be consulted or to be given the opportunity to
make representations before a decision was made. Where ex hypothesis there was
no right to be heard, it could be more important to fair dealing that a promise
or undertaking given by a Minister as to how he would proceed should be kept.
Mr. Parasaran has also submitted that the Courts in India including this Court have also
taken note of the case of promissory estoppel and obligation on the part of the
promisor to honour the commitment or the representation on the basis of which
the other party has altered its position financially, Mr. Parasaran has
referred to some of the decision of this Court including the decision in M/s Motilal
Padampat Sugar Mills Company (Private) Limited v. State of Uttar Pradesh,
[1979] 2 SCR 641 and the decision in Delhi Cloth and General Mills Ltd. v.
Union of India, [1988] 1 SCR 383. In the latter decision, it has been indicated
by the Supreme Court that if one of the representations induced a party to
alter his position, a case of promissory estoppel is attracted. He has
contended that before annulling the agreement and making unjust demand of high
tariff, the Board ought to have given reasonable opportunity to the
petitioner-Company to establish that there was no occasion to resile from the
obligation under the agreement. Mr. Parasaran has further submitted that if the
Court comes to the finding that the action of the Board and the State are
unjust and the Board has an obligation to abide by the agreement of 1976 in
view of the promissory estoppel, there will be no difficulty in issuing
appropriate writs for giving the reliefs claimed in the Writ Petition.
Mr. Prasaran
has submitted that even if it is accepted that in view of amendment of Section
49 of the Electricity (Supply) Act, the Board was required to charge tariff at
uniform rate to all the consumers placed in a particular category, such
amendment does not stand in the way of giving special privilege to the
petitioner-Company in the matter of tariff for the supply of electricity in
view of the fact that the smelter plant cannot be 240 equated with other power
intensive industries placed in the category HT IA and Section 49(3) of the
Electricity (Supply) Act still empowers the Board to fulfil its obligation in
terms of the agreement of 1976. Mr. Parasaran, in his fairness, has stated that
promissory estoppel cannot operate in violation of the statutory provisions but
Section 49(3) of the Act empowers the Board to fix tariff in conformity with
the promise held out to the petitioner- Company because the petitioner-Company
was entitled to be treated altogether differently for the reasons indicated
hereinbefore. In view of such enabling provision under Section 49(3), Mr. Parasaran
has submitted, that the obligation to abide by the agreement consistent with
the case of promissory estoppel still survives. He has also submitted that
there has been clear non-application of mind by the Board in not considering
the manufacturing process in the smelter plant in its proper perspective and
because of such non-application of mind an attempt has been made to treat an
unequal with equals, Mr. Parasaran has also contended that before purporting to
annul the agreement by taking recourse to the amended provisions of Section 49,
the Board should have given proper opportunity to the petitioner-Company to
substantiate that there had been a clear case of promissory estoppel and such
promissory estoppel survived even on the face of the amended provisions. He
has, therefore, submitted that the Board should be directed to give a fresh
look to the question of abiding by the agreement of 1976 by taking into
consideration of the relevant aspects of the manufacturing mechanism in the
smelter plant of the petitioner-company in a proper perspective. Mr. Parasaran
has submitted that unfortunately, the High Court concentrated more on the
question of vires and attack of the amending Act or the score of legitimate
competence. The High Court has failed to note that a clear case of promissory estoppel
was made out by the petitioner-Company and such promissory estoppel was still
applicable without offending the statutory provisions, namely, the amended
provisions of Section 49 of the Electricity (Supply) Act.
Mr. Narasimhamurthy,
learned counsel appearing for the respondent-Board has submitted that the
amending Act does not suffer from any vice either on the score of legislative
competence or on the score of arbitrary or capricious action and/or on account
of offending Article 14 and 19(1)(g) of the Constitution. He has also submitted
that the High Court has discussed the contentions raised by the parties at the
hearing of the Writ Petition at length and has not accepted the contentions
that the amending Act was ultra vires on any account. He has submitted that the
241 reasonings of the High Court should be accepted and the contentions on the
question of the vires of the Act sought to be reiterated in this Appeal should
be discarded by this Court.
We
have already indicated that decision of the High Court in upholding the vires
of the amending Act should be accepted and we have endorsed the reasonings
given by the High Court in that regard which we have referred to in some
details.
Mr. Narasimhamurthy
has submitted that there is no conflict with the proposition that if a strong
case of promissory estoppel is made out by a party and such promissory estoppel
does not come in conflict with any statutory provision, the party having
reasonable expectation flowing from a promise or representation may ask for
enforcement of such legitimate expectation founded on representations or
assurances on the part of the administrative body in appropriate cases. But in
the instant case, the very foundation of promissory estoppel is absent and as
such consideration of the question of promissory estoppel does not arise. In
this connection, he has drawn the attention of this Court to the preamble of
the first agreement of 1966. He has submitted that if a reference is made to
the preamble of the agreement and other clauses it is quite apparent and
evident that the same do not indicate that on the invitation by the electricity
Board or the State Government, the smelter plant of the petitioner-Company had
been established at Belgaum. It is quite evident that on coming
to know that the State and the Board were in a position to supply electric
energy without any interruption according to the need of the smelter plant the
petitioner-Company became interested in establishing its smelter plant at Belgaum
and thereafter negotiations were made between the parties and an agreement
under Section 49(3) of the Electricity (Supply) Act was entered into. He has
contended that later on, in view of changed circumstances a new agreement was
entered into between the parties in 1976 for the purpose of getting
uninterrupted supply of electricity on agreed rate and in a particular manner.
Both the said agreement of 1966 and 1976 were the outcome of usual bargaining
between the parties on terms and counter terms and it is not a case that the
terms were offered unilaterally by the State or the Board to induce the Company
to set up its smelter plant in the State of Karnataka and the Company being
induced by a representation by the State or the board that if the Company would
set up a smelter plant in the State of Karnataka then in the smelter plant of
the Company, 242 concessional rates would be offered for supply of electricity
for all times to come and the smelter plant would be treated altogether in a
different manner. He has also submitted that in the first agreement of 1966
there was no provision relating to the revision of rates but in the agreement
of 1976, there is a specific provision for revision of the rates of tariff of
electricity to be supplied to the smelter plant. Mr. Narasimhamurthy has drawn
the attention of the court to the correspondence between the parties starting
from 1964 for the purpose of showing that such correspondence unmistakably
point out a normal case of bargaining between the parties for getting
uninterrupted supply of electricity in the proposed factory of the Company. In
this connection, Mr. Narasimhamurthy has also referred to a decision of the
High Court of Orissa in the case of Indian Aluminium Company v. The Orissa
Electricity Board and Anr., AIR 1975 Orissa page 100 where the Division Bench
of the Orissa High Court has considered when the principle of promisory estoppel
can be invoked. It has been held in the said decision that the State
Electricity Board may revise the tariff fixed under the binding contract by
relying on Section 49 and 59 of the Electricity (Supply) Act. It has been held
by the Division Bench that simply because the State Government had held out the
assurances to the Company to supply hydro power fixed at low rate, a case of
promissory estoppel is not made out. It has been held that if the agreement was
the result of negotiations between the parties indicating that the Company was
as much desirous of being supplied with electric power as the supplier was
anxious and willing to supply the same, there is no case of promissory estoppel.
Mr. Narasimhamurthy has submitted that facts and circumstances in the instant
case clearly reveal that the State government was eager to have industries
established in the State and for the purpose took steps to supply sufficient
electric energy to various industries including the petitioner-Company. The
petitioner-Company was also equally anxious to establish its smelter plant in
the State of Karnataka in view of the facilities made
available in the State, and both the parties thereafter entered into
negotiations and on such negotiations terms and conditions were arrived at. The
agreement was made in accordance with the Section 49(3) of the Electricity
(Supply) Act. It is not the case that there was no occasion to enter into any
negotiation for settling the terms but clearly unilateral assurances were given
by the State and the Board to give uninterrupted supply of electricity on
specific conditions and on agreed rate promised to the Company and only on the
basis of such promises held out 243 to the petitioner-Company, the said smelter
plant was established and the agreement is only embodiment of the terms and
conditions unilaterally held out by the State and the Board. Mr. Narasimhamurthy
has, therefore contended that the very foundation of promissory estoppel is
absent in the case and the High Court was justified in not accepting the case
of promissory estoppel.
Mr. Narasimhamurthy
has submitted that sub-section 1 and 2 Section 49 of the Electricity (Supply)
Act envisage supply of electric energy to different consumers at uniform
tariffs. It, however, empowers the Board to charge a different tariff in
appropriate case under Section 49(3) of the Act. By the amending Act, Section
49 of the Electricity (Supply) Act has been amended in its application in the
State of Karnataka. Sub-Section 5, sub-section 6 and
sub- section 7 to section 49 have been inserted after sub-section 4 of Section
49 of the Electricity (Supply) Act. Sub- section 5 and 6 of Section 49 of the
Electricity (Supply) Act as applicable to Karnataka in view of the aforesaid
amendment are to the following effect:- "(5) The party to an agreement or
any other arrangement entered into prior to the commencement of the Electricity
(Supply) (Karnataka Amendment) Act, 1981 and providing for supply of
electricity by the Board shall, notwithstanding anything contained in the
instrument of agreement or other arrangement or in any law including this Act,
in force at such commencement, pay, in respect of electricity so supplied after
such commencement, price (by whatever name called) calculated in accordance
with the uniform tariff framed or modified from time to time, under sub-section
(1) and applicable to the category to which such party belongs.
(6)
The party to any such agreement or arrangement entered into after the
commencement of the Electricity (Supply) (Karnataka Amendment) Act, 1981,
shall, notwithstanding anything contained inthis Act, or in such agreement or
other arrangement, pay, in respect of electricity supplied by the Board, price
(by whatever name called) calculated in accordance with the uniform tariff framed
or modified from time to time under sub-section (1) and applicable to the
category to which such party belongs."
244
Mr. Narasimhamurthy has contended that the smelter plant of the
petitioner-Company has always been categorised by the Board as industries
included in HT-IA. He has drawn attention of the Court to tariff rates of 1974
and 1978. It appears that for 1978 tariff rates, the plant of the
petitioner-Company was included in HT
IA category. Mr. Narasimhamuarthy has
contended that such categorisation by the electricity Board made as far back as
in 1978 is not under challenge, and no protest had been made by the
petitioner-Company for categorising the plant of the petitioner-Company in
HT-IA. Mr. Narasimhamurthy has also contended that industries may have some
distinctive features but still then a broader classification is possible taking
into consideration, the power intensive nature of various industries. The Board
has taken into consideration such power intensivity in the manufacturing
process and has made a broad based categorisation. The smelter plant has been
included in HT-IA not only for the first purpose of applying the amended
provisions of Section 49 of the Act but such categorisation was made long back.
Even in 1978 such categorisation was made without any protest from the
petitioner-Company.
If
such categorisation has a rational basis and not arbitrary, capricious or
illusory, no exception need be made to such categorisation. Accordingly,
sub-sections 5 and 6 of Section 49 are squarely applicable to the
petitioner-Company and the Board is justified in treating the agreement as
annulled and subjecting the petitioner-Company to the uniform tariff rate
applicable to all the industries categorised as ST-IA. He has submitted that if
in terms of the statutory provision, a uniform rate of tariff is applicable to
the petitioner-Company on the basis of category of the industry to which it
belongs, and the agreement of 1976 stands annulled in view of the amended
provision, there cannot be any question of promissory estoppel against statute
even if it is assumed that in the facts of the case, a case of promissory estoppel
has otherwise been made out. He has, therefore, submitted that there is no
occasion to interfere with the judgment under appeal and the appeal should be
dismissed with costs.
After
giving our anxious consideration to the respective contentions of the learned
counsel for the parties, it appears to us that the agreement of 1966 and 1976
were not the outcome of any unilateral promise or assurance held out by the
State or the Board to the petitioner-Company. Such agreement was the result of
negotiations between the parties and on 245 such negotiations, the terms and
conditions were agreed upon between the parties. Accordingly, the foundation of
promissory estoppel is absent and the case of promissory estoppel as sought to
be made out by the petitioner-Company cannot be accepted. In our view, Mr. Narasimhamurthy
is justified in his contention that since the agreements stood annulled in view
of the amended provisions of Section 49 of the Act, the Board was empowered to
ask for uniform tariff rate from the industries classified under one category.
It is true that the smelter plant has distinctive features in its manufacturing
mechanism and in the process of electrolytic operation. It also appears to us
that the smelter plant is not only power intensive industry but the power
assumes a very significant role and constitutes one of the important raw
materials in the productive process. But it does not appear to us that categorisation
of the smelter plant a high power intensive industry by itself is illegal or
perverse, or without any basis and wholly unjustified.
In the
broader classification, smelter plant is certainly a high power intensive industry
and such categorisation was made by the Board not for the purpose of enforcing
of the amended Section 49 with an object to annul the agreement but such categorisation
was made even in 1978. In the circumstances, we are unable to accept the
contention that the broader categorisation of the smelter plant is arbitrary,
capricious and unreasonable resulting in treating the unequal as equal thereby
offending Article 14 of the Constitution. We, therefore, find no justification
to interfere with the impugned decision of the High Court and the appeal,
therefore, fails but in the facts of the case, there will be no order as to
costs.
Before
we part with this matter, it appears to us that the question of tariff for the
supply of electricity to the matter plant requires a sympathetic consideration.
In 1975, policy of the Central Government regarding the aluminium industry, it
was highlighted that despite the increase in the productive capacity of the aluminium
plants in India, the production as a whole decreased for various factors
particularly in view of irregular supply of electricity to the plants. It was
also noted in the said policy that the costs for generating the power and
transmission of power to the plants had increased over the years and it was not
possible for the Boards to stick to rates agreed earlier for supply of
electricity to the aluminium plants. The Central Government felt the necessity
to strike a balance so that the Boards do not suffer and the plants for aluminium
get proper supply of electricity 246 at reasonable rates. It was noted that
high rate of tariff and consequential increase in the price of aluminium caused
prejudice to the Boards because the Boards were consumers of aluminium to a
considerable extent. It appears to us that it is only desirable that interest
of both the Boards and the aluminium industry are to be reconciled with a
pragmatic approach and the Central Government, the concerned State Governments
and the Boards should try to evolve a more realistic policy by which the interest
of both the Boards and aluminium industry are safeguarded to the extent
practicable. We have no manner of doubt that if a joint venture is made an
effective policy may be evolved which will ensure to the benefit of both the
supplier and the consumers in the field of production of aluminium, in the
national interest as a whole.
T.N.A.
Appeal dismissed.