Burn
Standard Company Limited Vs. McDermott International Inc. & Anr [1991] INSC
88 (3 April 1991)
Ahmadi,
A.M. (J) Ahmadi, A.M. (J) Ramaswami, V. (J) II Fathima Beevi, M. (J)
CITATION:
1991 AIR 1191 1991 SCR (2) 67 1991 SCC (2) 669 JT 1991 (2) 95 1991 SCALE (1)587
ACT:
Foreign
Exchange Regulation Act 1973 / Foreign Exchange Manual 1978-Section 28(1)
Paragraphs 24A.11(1) and 25A.2- Indian Company-Technical Collaboration
agreement with foreign corporation-General or special permission of RBI- Colloboration
approved by Secretariat for Industrial Approvals-Agreement taken on record by
Government-Whether separtate permission of RBI necessary-Decision taken by RBI,
but approval not communicated-Whether failure to discharge ministerial duty
obliterates conscious decision taken-Non- filing of FNC5 form for grant of
permission-Whether erases decision already taken.
Arbitration
Act, 1940; Sections 14,17,30 and 33-Foreign collaboration agreement-RBI's
approval-Whether arbitration clause rendered void by virtue of agreement itself
being void ab initio for want of RBI permission under Section 28(1) of Foreign
Exchange Regulation Act,1973.
Administrative
Law: Administrative action-Whether decision becomes binding.
HEAD NOTE:
The
appellant, a Government company, entered into a Technical collaboration
agreement with the respondent, a foreign corporation, under which the
respondent was to provide technical know-how to the appellant, and the
appellant was to pay the respondent fee in foreign currency in three installments.
The appellant was required to apply for registration and/or Governmental
approval and furnish satisfactory evidence of receipt of such approval. The
effective date of the agreement was the date on which the notification was
received by the respondent that all governmental approvals in that regard had
been secured. The agreement was entered into with the approval of the
Secretariat for Industrial Approvals. The agreement as well as the
supplementary agreement, incorporating certain changes suggested by the
Government, were filed with the Government, which took the same on record, by
its letter of approval, A copy of the letter of approval and also the 68
collaboration agreement was sent to the RBI.
After
obtaining the necessary order under Section 195(2) of the Income Tax Act from
the Income Tax Officer and the permit from the RBI, the appellant remitted the
first installment of fee to the respondent. Thereafter, the respondent,
alleging non-payment of subsequent installments, and consequent breach of terms
of contract, sought to invoke clause 8.2 of the agreement for terminating the
agreement.
The
appellant questioned respondent's right to invoke clause 8.2. Thereafter the
respondent invoked the arbitration clause, clause 12.1 of the agreement, for
referring disputes and difference to the arbitration of International Chamber
of Commerce and claimed certain amount for the services actually rendered and
also informed the ICC accordingly.
The
appellant challenged the legality and validity of the agreement as void ab initio,
and also clause 12.1 as non-est and legally unforceable, and filed an
application under Section 33 of the Arbitration Act, contending that the
agreement being a contingent one, commencing from the effective date, and
necessary approval having not been secured, the agreement had not commenced
and, consequently the arbitration clause, being part of the very same
agreement, the respondent was not entitled to invoke the said clause, and that
in the absence of a valid permission from the RBI under Section 28(1) (b) of
the Foreign Exchange Regulation Act, 1973, the agreement was clearly void by
the thrust of Section 28(2) of the Act.
The
respondent contended that the necessary Government approvals were obtained and
hence the `effective date' was reached and that under the Exchange Control
Manual only the Indian Company could apply to SIA for approval and once such
approval was accorded, the foreign collaborator to the contract was not
expected to secure the RBI permission under Section 28(1) (b), since under the
manual, SIA approval was to be deemed to be RBI's permission also; and
therefore, the agreement was legal and valid and the respondent was entitled to
seek its enforcement.
The
High Court held that on a true interpretation of the contract, it must be held
to be voidable at the discretion of either party, that even if the contract was
terminated or rendered void, the arbitration clause therein did not perish ipso
facto, that the application to the Income Tax Officer for making payment of first
installment could not have been made unless the necessary approvals were
obtained, that the RBI had granted permission to remit the installment money
(fee), after the Income Tax Officer had made the order under Section 195(2) of
the 69 Income Tax Act, and it was only on account of this payment, that the
respondent furnished the technology and provided technical services, and that,
on account of appellant's failure to pay subsequent installments, a dispute had
clearly arisen which had to be resolved through arbitration.
In the
appeal before this Court it was contended on behalf of the appellant company
that paragraph 25A.2 of the Exchange Control Manual, 1978, provided that
applications for permission under Section 28(1)(b) should be made in FNC5 and
since no such application in FNC5 was made, a clear inference could be raised
that the RBI had not granted permission under Section 28(1), and accordingly
the agreement and the arbitration clause forming part of it were void ab initio
by the thrust of Section 28(2), and that the prescribed form for SIA approval
under paragraph 24A.11 was not the same as FNC5 prescribed under paragraph
25A.2 and administrative direction in paragraph 24A.11 that no separate
permission under Section 28(1) was necessary could not override the statutory
requirement of the Section.
It was
contended on behalf of the respondent that requirements of Section 28(1) were
fully complied with and the RBI's sanction, being essentially administrative,
it was enough to show that the RBI had granted permission, no matter whether it
had followed the procedure of paragraph 24A.11(i) or 25A.2 of the Exchange
Control Manual.
Dismissing
the appeal, this Court,
HELD:
1.1 Section 28(1) of the Foreign Exchange Regulation Act, 1973 places
restrictions on appointment of certain individuals and companies as technical
or management advisers in India unless the RBI approves the same by a general
or special permission. The section is silent on the mode and manner of securing
such permission. However, sub- section (4) of Section 73 provides that where
any provision of the Act requires the RBI's permission for doing anything under
such provision, the RBI may specify the form in which an application for such
permission shall be made. On a plain reading of paragraph 24A.11 Exchange
Control Manual, 1978., it becomes clear that the intention is to introduce the
single counter or window procedure to avoid duplication and hardship to the
foreign collaborators, and once the collaboration is approved by SIA, and the agreement
is `taken on record' there is no need to obtain a separate permission from the
RBI. Paragraph 9 of the Guidelines for Industries stipulates that after the
agreement is taken on record, a copy thereof has to be sent to the RBI to
enable it to 70 authorise remittances to the foreign collaborator. [82E,84C,85A]
1.2 In
the instant case, the appellant had sought the SIA approval, which was granted
subject to the terms and conditions set out in the letter of approval. It was
only thereafter that the agreement was executed. The appellant then sent a copy
of the agreement to the Government of India which was duly examined in the
light of the terms and conditions on which the approval was granted by the SIA
and certain discrepancies were communicated to the appellant which necessitated
the execution of supplementary agreement.
It was
only thereafter that the appellant was informed that the collaboration
agreement and the supplementary agreement `have been taken on record. This was
then forwarded to the RBI. The matter was processed by the RBI and the
remittance of the first instalment of the fees took place after the income-tax
was duly recovered at source. [85A-D]
1.3
The affidavits filed on behalf of the RBI leave no doubt that the remittance
was permitted only after the RBI was satisfied that all the terms and
conditions were duly satisfied, though the RBI's approval `remained to be
communicated' to the appellant company. Failure to discharge the ministerial
duty cannot obliterate the conscious decision taken by the RBI after
application of mind. [85E,G]
1.4
The RBI had applied its mind to the question of grant of permission and had
only thereafter permitted remittance of the first instalment of the fees
payable to the foreign collaborator. Merely because application for such
permission was not made in FNC5 form cannot cloud the fact that the decision to
grant the permission was actually taken, but the ministerial function of
communicating the same remained to be done by oversight. This lapse cannot
erase the decision already taken. [86H,87A]
2.1
The prescription of the form is merely to aid the RBI to process the
application for permission. Emphasis must be laid on substance and not on mere
form. If there has been substantial compliance mere lapse on the part of the
RBI in failing to communicate its decision should make no difference. Paragraph
25A.2 is not in derogation of paragraph 24.A.11(i) nor does it dilute the
requirement of Section 28(1). Factum of permission, and not the procedure
followed, is relevant. [86G]
2.2
The RBI had granted the permission contemplated by Section 28(1) and hence the
agreement cannot be voided by virtue of Section 28(2) of FERA. Once the
decision to grant the permission is taken, 71 whether through the course
charted by paragraph 24A.11(i) or 25A.2, that decision stands unless rescinded
and the authorities are bound to act in aid thereof.[87B-C]
3. In
the circumstances it is unnecessary to examine the question whether clause 12.1
of the agreement would stand or perish if the agreement is rendered void under
Section 28(2) for failure to secure permission under Section 28(1).[87D] M/s. Dhanrajmal
Gobindram v. M/s. Shamji Kalidas & Co., [1961] 3 SCR 1020; LIC of India v.
Escorts Ltd. & Ors., [1986] 1 SCC 264 at 318 and Shri Sitaram Sugar Co.
Ltd. & Anr. v. U.P. State Sugar Corporation Ltd. & Anr., [1990]3 SCC
222 at page 246-247, referred to,
CIVIL
APPELLATE JURISDICTION : Civil Appeal No.1423 of 1991.
From
the Judgement and Order dated 6.12.1989 of Calcutta High Court in Case No.5696
of 1988.
Soli
J. Sorabjee, Deepanker Ghosh, R.M. Chatterjee, A.K. Ghose, S. Mandal and Ms. Madhukhatri
for the Appellant.
Dipankar
Gupta, O.P. Khaitan, A.K. Bhatnagar, Ms. Kiran Choudhary and Ms. B. Gupta for
the Respondents.
H.N.
Salve and H.S. Parihar for the Reserve Bank of India.
The Judgement
of the Court was delivered by AHMADI,J. Special leave granted.
The
principal question which this Court is called upon to answer in this appeal by
special leave is whether the arbitration clause contained in Article XII
(Paragraph 12.1) of the Technical Collaboration Agreement entered into at
Dubai, United Arab Emirates, on September 25, 1984, between the appellant Burn
Standard Company Ltd., a Government of India Undertaking, and the respondent Mcdermott
International, Inc., a foreign company, is rendered void by virtue of the
agreement itself being ab-initio void for want of general or special permission
of the Reserve Bank of India (RBI) under 72 Section 28 of The Foreign Exchange
Regulation Act. 1973 (FERA). The relevant part of the said provision reads as under
:
"28(1)-Without
prejudice to the provisions of Section 47 and notwithstanding any contained in
any other provisions of this Act or the Companies Act, 1956, a person resident
outside India (whether a citizen of India or not) or a person who is not a
citizen of India but is resident in India, or a company (other than a banking
company) which is not incorporated under any law in force in India or in which
the non-resident interest is more than forty percent or any branch of such
company, shall not, except with the general or special permission of the
Reserve Bank,- (a) act, or accept appointment, as agent in India or any person
or company, in the trading or commercial transactions of such person or
company;
or (b)
act, or accept appointment, as technical or management adviser in India or any
person or company; or (c) permit any trade mark, which he or it is entitled to
use, to be used by any person or company for any direct or indirect consideration.
(2)
Where any such person or company (including its branch) as it referred to in
sub-section (1) acts or accepts appointment as such agent, or technical
management adviser, or permits the use of any such trade mark, without the
permission of the Reserve Bank, such acting, appointment or permission, as the
case may be, shall be void.
The
petitioner is a Government Company incorporated under the Companies Act, 1956,
having its registered office at 10C, Hungerford Street, Calcutta, whereas the
respondent is a Corporation organized and existing under the laws of the
Republic of Panama with its executive office at P.O. Box 61961, 1010 Common
Street, Near Orleans, Louisiana 701610, U.S.A., with a branch office at P.O.
Box 3098, Dubai, UAE.
On
25th September,1984 the said parties entered into an agreement, styled
"Technical Collaboration Agreement", for the fabrication of off-shore
platform structure, including but not limited to Jackets, Piles, Decks,
Modules, Platform & pipeline components, including their sub-components,
for the oil and gas industry which 73 required the high degree of expertise and
experience as well as the technical know-how possessed by the respondent. The
duration of the agreement was fixed under Article VIII to be five years from
the effective date or five years after commencement of commercial production,
whichever is greater, or until otherwise terminated earlier under the
Agreement.
The
expression `effective date' as defined in Article 1 means the date of which
notification is received by the repondent that all Governmental approvals
relating to the agreement have been secured; provided that if such approvals
are not secured within 180 days from the signing of the agreement, the
agreement, upon notice pursuant to Article XVII of the agreement by either
party may be made ineffective whereupon the agreement shall be treated as null
and void. Obviously the purpose of the agreement was to establish the basis
where under the respondent was to provide and the appellant was to receive
technology and special technical services related to the establishment and
operation of Fabrication Yard for fabricating off-shore platform structures and
additional special technical services for any contracts related to marine
construction activities that are awarded to the appellant. Article X of the
agreement enjoins upon the appellant to apply for necessary registration and/or
governmental approval of the agreement in India within 60 days after the agreement is signed by both parties and is
delivered to the appellant. A duty is cast on the appellant to furnish
satisfactory evidence to receipt of the required governmental approval.
The
next important clause in the contract which needs to be noticed at this stage
is Article XII which reads as under:
"Article
XII-Arbitration
12.1
Any claim, dispute or controversy arising out of or relating to this Agreement,
or the breach thereof, shall be finally settled by arbitration, pursuant to and
in accordance with the Rules of Conciliation and Arbitration of the International
Chamber of Commerce by three(3) arbitrators appointed in accordance with said
Rules. Judgement upon the award rendered by the Arbitrators may be entered in
any court having jurisdiction thereof.
The situs
of Arbitration shall be New Delhi, India or an alternate location if the
parties shall mutually agree and the arbitration proceedings shall be conducted
in the English language." Under Article XII the validity, construction and
performance of the agreement was to be governed by the Indian laws.
74 The
aforesaid agreement was entered into after it was approved by the Secretariat
for Industrial Approvals (SIA) by their letter dated 18th June, 1984. After the
execution of the agreement it was filed with the Government of India on 5th
October, 1984. By the letter dated 15th December, 1984 of the Ministry of
Industry, Department of Heavy Industry, New Delhi, addressed to the appellant
it was pointed out that clauses 3.2. and 4.2 of the agreement were not
consistent with the terms and conditions of collaboration approved by
Secretariat letter dated 18th June, 1984. in that, clause 3.2 should contain a
clause that any additional payment made for specific Technical Services would
be subject to prior approval of Government of India and in clause 4.2 the payment
expressed in U.S. Dollars 298,200 should be 298,500 and the figure of the 3rd instalment
should be 99,450 instead of 99,400 U.S. dollars.
To
carry out these changes, the parties entered into a supplementary agreement on
29th December, 1984 and filed it with the Government of India on 9th January,
1985.
Under
Article IV of the agreement, in consideration of the respondent having agreed
to transfer technology to the appellant, the latter undertook to pay a lump sum
of $298,200 in three installments, the first payment of U.S. $ 99,400 within
thirty (30) days of the signing of the agreement or receipt of approval from
the Government of India, whichever is later; the second payment of U.S. $
99,400 upon completion of items 1 to 10 of clause 3.4 of Article III and the
third payment of U.S. $ 99,400 upon the commencement of commercial production
of the Fabrication Yard or four years after the effective date, whichever is
earlier. As stated earlier the figure `298,200' was replaced by the figure
`298,250' and the amount of the third instalment was raised from U.S.$99,400 to
U.S.$99,450 under the supplementary agreement dated 9th January, 1985. After
this suuplementary agreement was filed with the Govt., of India, the latter
took the collaboration agreement on record under the communication dated 15th
January,1985. A copy of the Govt. of India's letter along with a copy of the
collaboration agreement was received by the RBI on 21st January, 1985. In para
7 of its affidavit dated 18th September, 1990, the RBI has clarified as under:
"However,
the Bank's letter of authorization indicating the terms and conditions to be
fulfilled for remittances falling due under collaboration agreement remained to
be issued to the petitioner company. Hence the Bank's approval under Section
28(1) (b) of the Act for rendering technical etc. services under the
collaboration agreement also re- 75 mained to be communicated to the petitioner
company. Later, when the petitioner company applied for remittance of the first
instalment under the collaboration agreement, the Bank being satisfied that the
remittance was strictly in accordance with the terms and conditions approved by
the Government, allowed the same." On 5th February, 1985, the appellant
made an application to the income tax authorities for determination of income
tax deduction for the payment of the first instalment of fees.
The
order passed under Section 195(2) of the Income-Tax Act determining the tax at
40% of the consideration proceeds on the premise that the agreement was approved
by the Government of India. Soon thereafter the appellant applied on 14th
February,1985 to the United Bank of India for remitting the first instalment of
fees minus 40% chargeable as income tax. The United Bank of India intimated the
rate of exchange on the very next date. The Income-tax Officer issued the
`No-objection certificate' on 19th February, 1985 whereupon the RBI issued the
permit dated 6th March, 1985 for remittance of U.S. $ 59,640 ($
99,640-40%=$59,640).
By the
appellant's letter dated 18h March, 1985 the appellant enclosed a draft for the
said amount to the respondent.
After
the payment in respect of the first instalment was thus made, the respondent
wrote a letter dated 16th September, 1986 invoking clause 8.2 of the agreement.
That clause reads thus :
"
In the event of any breach of this Agreement not cured within sixty (60) days
after notification thereof, in addition to all other rights and remedies which
either party may have in law or equity, the party not in default may at its option
terminate this Agreement by written notice. Such termination shall become
effective on the date set forth in such notice of termination, but in no event
shall it be earlier than sixty (60) days from the mailing thereof. Any waiver
of the right of termination for default shall not constitute a waiver of the
right to claim damages for such default or the right to terminate for any
subsequent breach." By the said letter the respondent laments lack of
payment of installments due from the appellant and consequential breach of the
terms of the contract. The respondent then puts the appellant to notice as per
clause 8.2 reproduced above of its right to terminate the agreement if 76 the
appellant fails to cure the breach within 60 days of the receipt of the communication.
The appellant by its reply dated 12th December, 1986 questioned the
respondent's right to invoke clause 8.2 of the agreement since in its view
there was no breach of agreement and called upon the respondent to discharge
its obligations under clause 3.4 of the agreement and receipt payment of the
second instalment thereafter. On receipt of this reply, the respondent by their
Advocate's letter date 27th
September, 1988
invoked the arbitration clause extracted earlier for referring the disputes and
differences to the arbitration of International Chamber of Commerce. At the
same time the respondent claimed that it was entitled to recover U.S. $ 621,777,09
with 15% per annum interest from the appellant for services actually rendered.
On the same day the respondent wrote to the International Chamber of Commerce
informing it of its decision to invoke the arbitration agreement. The appellant
responded by its letter dated 11th October, 1988 stating that the collaboration
agreement dated 25th September, 1984 was void ab-initio and not binding on the
parties thereto and therefore, clause 12.1 of Article XII of the agreement was
non-est and legally unenforceable. On the other hand the appellant blamed the
respondent for breach of contract, in that, there was failure to comply with
clause 3.4 of the agreement, and stated that no disputes or differences of the
type which could be referred to arbitration had arisen between the parties.
Thus
by challenging the legality and validity of the agreement and branding it void ab-initio
the appellant also challenged the arbitration clause as similarly void. This
was followed by the appellant filing an application under Section 33 of the
Arbitration Act inter alia contending (i) that the agreement in question being
a contingent one which was to commence from the `effective date' and since the
necessary approvals had not been secured, the agreement had not commenced and
as the arbitration clause was a part of the very same agreement it too had not
commenced and hence the respondent was not entitled to invoke the said clause
and (ii) since under the agreement the respondent was appointed as Technical or
Management Adviser in India within the meaning of Section 28(1) (b) of FERA, in
the absence of a valid permission from the RBI, the agreement was clear void by
the thrust of Section 28(2) of the said enactment. The respondent countered
these contentions (i) by pointing out that the necessary Government approvals
were obtained and hence the `effective date' was reached and (ii) under the
Exchange Control Manual (1978 Edition) only the Indian company could apply to
SIA for approval and once such approval was accorded as in the present case,
the foreign collaborator to the contract was not expected to secure the RBI
permission under Section 28(1) (b) since under the 77 manual SIA approval was
to be deemed to the RBI's permission also. It was, therefore, contended that
the agreement was legal and valid and the respondent was entitled to seek its
enforcement. The arbitration clause being a part of the agreement, it was
imperative on the part of the respondent to follow that course in the event of
a dispute or difference arising between the parties concerning any matter
covered by the agreement.
The
High Court on a proper construction of clause 8.1 of the agreement held that
the principal duties and obligations incorporated in clauses 1.3 and 1.4
commence after governmental approvals are obtained. The obligation to secure
necessary registration and governmental approvals is cast by virtue of clause
10.1 on the appellant. Obviously the said clause comes into operation
immediately on the execution of the agreement since clause 1.2 clearly
contemplates that if governmental approvals are not obtained within 180 days,
the parties will be entitled to put an end to the agreement. It is thus
manifest from the terms of the agreement that some of its provisions come into
effect on the execution of the agreement and remain in force for 180 days till
the contract is terminated by either party. But if the parties choose to
continue the contract even beyond the period of 180 days notwithstanding the
right to terminate the same, there is nothing in the agreement prohibiting the
same and, therefore, on a true interpretation of the contract it must be held to
be voidable at the discretion of either party. The High Court further held on a
reading of Sections 39 and 56 of the Contract Act that even if the contract is
terminated or rendered void the arbitration clause therein does not perish ipso
facto for even in contingent contracts there exists a distinction between
principle obligation and subsidiary obligations. After referring to the case
law in detail, the High Court observed:
In my
opinion the arbitration clause in the instant case is wide enough to include
"any claim, dispute or controversy arising out of or relating to this
agreement" so as to mean any dispute as to the interpretation itself
including the validity thereof. Therefore, if there is any dispute relating to
the interpretation of Article 8.1 of the agreement the same can also be decided
by the arbitrator." Pointing out that an agreement of arbitration, though
a contract, is different in its nature from the main contract of which it may
form a part, the High Court held that the breach of the obligation and
liabilities arising under the main contract may bring about termination 78 of
the main contract but not of the arbitration agreement.
Indeed,
the arbitration agreement would be invoked only when disputes arise under the
main contract including a repudiation of the main contract by any of the
parties and in that sense the arbitration agreement is remedial while the main
contract is substantive. The High Court, therefore, held that in law the
jurisdiction of the arbitrator under the arbitration clause would cover the
decision as to voidability of the main contract also. The High Court then
concluded as under:
"It
is apparent from the sequence of events appearing from the list of dates
already noted hereinbefore that the petitioner really made an application to
the secretariat for Industrial Approvals, Department of Industrial Development
and a letter of approval was issued. Thereafter the agreement dated September
25, 1984 was executed. The Government pointed out certain deficiencies as a
result of which the supplementary agreement dated September 28, 1984 was
executed. The said documents were all filed with the Govt. and thereafter the
Government took the agreement on record and nothing was really required to be
done by the repondent. In fact the paragraph 11 at Chapter III of Guidelines
for industries of the Government of India provide for such a procedure for
taking the agreement on record after the approval is given for Foreign
Collaboration." After quoting paragraph 11 of the said guidelines the High
Court referred to the appellant's application to the Income- tax Officer for
payment of the first instalment under clause
4.1 of
the agreement and concluded that such an application could not have been made
unless the necessary approvals were obtained. After the Income-tax Officer made
the order, the RBI granted permission to remit the instalment money (fee) on
6th March, 1985. It was only on account of this payment that the repondent
furnished the technology and provided the technical services to the appellant
in pursuance of Article III of the contract. The High Court dismissed the
application holding that on the appellant's failure to pay the subsequent
installments, a dispute had clearly arisen between the parties which had to be
resolved through arbitration.
Mr. Soli
Sorabjee, learned counsel for the appellant, placed the appellant's case thus:
Under Section 73(4) of FERA, where permission of RBI is required under any
provision of the said statute for doing anything thereunder, the RBI has to specify
the form in which 79 the application for such permission must be made.
Paragraph 25A.2 of the Exchange Control Manual, 1978 (Manual) refers to
permission to be obtained under Section 28(1) (b) and provides that
applications for such permission should be made in form FNC5. Indisputably the
respondent had made no such application in the prescribed form seeking RBI
permission and, therefore , the question of grant of such permission by the RBI
did not arise. The respondent having failed to secure the RBI permission as
required by Section 28(1) rendered the agreement void by the thrust of Section
28(2).
Besides
breach of Section 28(1) is made punishable under Section 50 of FERA. That being
so, the agreement is ab-initio void and as the arbitration clause is a part of
the said agreement, it too must fall along with the agreement. The SIA approval
is not synonymous with grant of permission under Section 28(1) is since the two
operate in different fields and it is, therefore erroneous to think that such
approval satisfies the requirement of Section 28(1) . Paragraph 24A.11 of the
Manual is not referable to permission under Section 28(1) and must be read
harmoniously with the statutory provisions, for if it runs counter to the said
provisions, it would have to be ignored for the obvious reason that it cannot
override the requirement of law being merely in the nature of administrative
instructions. Nor can the letter of 15th January, 1985 be read to convey the
grant of permission under Section 28(1). So also the permit issued by the RBI
dated 6th March, 1985 for remittance of the first instalment payable under
Clause 4.1 of the agreement is referable to the exemption contemplated by
Section 9 and has no relevance whatsoever to the permission envisaged by
Section 28(1) of FERA. Thus the permission contemplated under Section 28(1) is
an express permission and it would be an entire wasteful exercise to find out
from the correspondence and documents placed on record if a permission can be
culled out or be deemed to have been granted. In the absence of a permission,
Section 28(2) declares the agreement or contract to be void and, therefore, the
said agreement or any part thereof cannot be enforced in a court of law. The
High Court was, therefore, clearly wrong in the view it took in upholding the
respondent's effort to invoke the arbitration clause.
Mr.
D.P. Gupta, learned counsel for the respondent countered: The RBI has published
the Manual to detail the procedure for entering into such Technical
Collaboration Agreements; paragraph 24A.11 lays down the procedure for securing
the RBI permission contemplated by Section 28(1) and where the situation does
not stand covered thereunder the application has to be made under paragraph
25A.2 of the said manual which lays down a different procedure and prescribes
the 80 FNC5 form.
In
other words, if the case is governed under paragraph 24A.11 when it is
unnecessary to resort to paragraph 25A.2 which prescribes the FNC5 form. The
Government policy for dealing with such foreign collaboration agreements is
generally set out in the industrial policy document entitled `Guidelines for
Industries', Chapter IV whereof sets out a procedure identical to the one
contained in the manual. The appellant had made an application under paragraph 24A.11
to SIA for approval of the technical collaboration arrangement with the
respondent which was granted on 18th June, 1984 subject to certain terms and conditions. Certain
discrepancies were pointed out by the Government of India and on the appellant
having drawn the respondent's attention thereto by the letter of 21st September, 1984 a supplementary agreement was
immediately executed and filed with the Government of India on 9th January, 1985. It was thereafter the that
Government of India informed the appellant that the agreement was `taken on
record', an expression which has special significance as explained in paragraph
9 of Part I of Guidelines for Industries. Copies of the letter of 15th January, 1985 were forwarded to RBI authorities
as well. It was only thereafter that the appellant applied for determination of
the Income-tax amount under Section 195(2) of Income-Tax Act which
determination was made by an order dated 11th February, 1985. The appellant then applied for
permission to remit the first instalment of fees and on receipt thereof
enclosed a draft for U.S. $ 59,640 ( after deducting 40% income tax) under
letter dated 18th
March, 1985 addressed
to the respondent. It was only when the subsequent payment was not forthcoming
that the respondent gave notice under clause 8.2 of the agreement and
thereafter sought to resort to arbitration. Thus the requirements of Section
28(1) were fully complied with.
Mr.Salve,
the learned counsel for the RBI, placed on record an additional affidavit dated
24th January, 1991 sworn by Shivaji D. Kadam, Deputy
Controller, Exchange Control Department of the RBI explaining what steps the
bank had taken after it received the Government of India's letter of approval
together with a copy of the collaboration agreement dated 21st January, 1985. Since the said letter was only a
covering letter taken on record the said agreement, the bank had by its letter
dated 7th February, 1985 sought copies of the earlier letters from the
Government as they were of vital importance because without those letters it
was not possible for the RBI to proceed under paragraph 24A.11 of the manual.
Thereafter on 14th
February, 1985 the
appellant reminded the RBI to forward its approval to enable payment of the
fees to the respondent.
Again
on 81 20th February, 1985 1985 the appellant approached the RBI for sanction to
remit the fees and enclosed therewith the Government of india letters dated
18th June, 1984 and 4th August, 1984 along with an application in A-2 form. The
Government of india also forwarded copies of the said
two letters by a covering letter dated 1st March, 1985 which was delivered to the RBI on 4th March, 1985. On the same day a note was put up
to the Staff Officer, Grade A, who observed:
``In
view of the Government letter having now been received, we may allow the
remittance of U.S.$ 59.640 being the 1st instalment of technical know- how
fees.'' The Exchange Control Officer then said :
``We
may allow the remittance of U.S.$ 59.640 being 1st instalment of know-how
fees''.
This final
note of the Exchange Control Officer was countersigned by the Assistant
Controller on 6th March, 1985 The deponent fairly clarifies that ``as per the
RBI practice, the permission under para 24A.11, that is, grant of sanction
under Section 28(1)(b) as well as permission under section 9 for allowing
remittances are generally authorised by the Assistant Collector.'' It becomes
clear from this statement that the permission under Section 28(1) and the
exemption under Section 9 are generally granted by one and the same officer.
In the
backdrop of the said facts we may now proceed to consider the main submission
placed before us by counsel for the appellant, namely, the agreement is
rendered void ab- initio for want of permission under Section 28(1) of FERA.
It is
only if we accept the contention that in fact the RBI had not granted any
permission under Section 28(1) that the question of the agreement having been
rendered void by the thrust of Section 28(2) would arise. And the question of
survival of the arbitration clause contained in the Agreement notwithstanding
the agreement having been rendered void by Section 28(2), would arise
thereafter.
On a
plain reading of Section 28(1) it is clear that it opens with the words
``without prejudice to the provisions of Section 47'', which in turn says that
``no person shall enter into any contract or agreement which would directly or
indirectly evade or avoid in any way the operation of any provisions of the Act
or of any rule, direction or order made there under.'' Contravention of any
provision of the Act (other 82 than Section 13, 18(1)(a) and 19(1)(a) or of any
rules directions or order made there under, is made penal by Section 50.
Secondly, the said Section 28(1) places an embargo on a resident outside India
or a person who is resident in india but is not a citizen of India or a company
(other than a banking company) which is not incorporated under any law in force
in India or in which the non-resident interest is more than 40% or any branch
of such company to (a) act or accept appointment, as agent in india or any
person or company, in the trading or commercial transactions of such person or
company; or (b) act or accept appointment, as a technical or management adviser
in India of any person or company except with the general or special permission
of the Reserve Bank. Admittedly there existed no general permission and,
therefore, special permission must be shown to prove satisfaction of the
requirement of the said provision. Under Sub-section (2) where any person
mentioned in sub-section (1) acts or accepts appointment as such agent or
technical/management adviser without the permission of the RBI, such acting or
appointment shall be void.
Therefore,
let us first focus our attention on the question whether or not the RBI's
permission was obtained in regard to the collaboration agreement in question ?
Section 28(1) places restrictions on the appointment of certain individuals and
companies as technical or management adviser in India unless the RBI approves
the same by a general or special permission. The section is silent on the mode
and manner of securing such permission. However, sub- section (4) of Section 73
provides that where any provision of the Act requires the RBI's permission for
doing anything under such provision, the RBI may specify the form in which an
application for such permission shall be made. In this connection it is
essential that we notice paragraphs 24A.11 and 25A.2 at this stage. These two
paragraphs read as under :
``24A.11.
Persons, firms and companies wishing to establish new industrial units or
expand/diversify existing units with foreign technical collaboration should
apply on prescribed form to the Secretariat for Industrial Approvals (SIA),
Department of Industrial Development, Government of India, New Delhi, for
approval. In case where proposal for collaboration is approved by Government,
Government will issue its letter of approval to the applicant indicating the
terms. The applicant may thereafter execute the collaboration agreement with
the collaborators strictly in accordance with the approved terms and furnish
requisite 83 number of copies of the agreement to Government.
Government
will take the agreement on record if it is in conformity with the approved
terms and advise the applicant accordingly under intimation to Reserve Bank.
Reserve Bank will thereafter issue its formal authorization under Foreign
Exchange Regulation Act, 1973, to the applicant. Although the rendering of
technical advisory services by foreign collaborators under foreign
collaboration agreements approved by government attracts Section 28(1)(b) of
Foreign Exchange Regulation Act, 1973, it will not be necessary for the foreign
collaborators to seek Reserve Bank permission under the Section separately.
Accordingly, while granting approval for foreign collaboration, Reserve Bank
will confirm that the approval will also be deemed to be the Bank's permission
to the foreign collaborators under this section for rendering technical
services to the Indian company concerned under the collaboration agreement.
Permission given under this Section is, however, without prejudice to the
decision that the Bank may take on the foreign company's application, if any
under section 28(1)(c) of the Act for use by the Indian company of foreign
trade mark(s) involving direct or indirect consideration.'' ``25A.2. Under
Section 28(1)(b) of Foreign Exchange Regulation Act, 1973, it is obligatory for
foreign companies to obtain permission of Reserve Bank for acting or accepting
appointment, as technical or management adviser in India of any person or
company. Reserve Bank's permission is also necessary under Section 28(3) of the
Act in case where appointments as technical/management advisers were held by
such foreign companies since prior to the coming into force of the Act i.e. 1st
January, 1974 and are continuing thereafter.
Applications
for permission in either case should be submitted to Reserve Bank in form FNC5.
These provisions are also applicable to foreign collaborators rendering technical
advice to Indian firms and companies under collaboration agreements approved by
Government of India. While, however, communication approval for new
collaboration agreements between Indian companies and overseas collaborators,
Reserve Bank will specifically indicate that the approval also permits the
foreign collaborator to render technical advice to the 84 Indian company and
separate approval need not be sought by the former from Reserve Bank under
Section 28(1)(b) of the Act.'' The appellant's contention that the application
for permission under Section 28(1) ought to have been made in the prescribed
form FNC5 and since admittedly no such application was made by either party
there was no valid permission approving the contract and hence by virtue of Section
28(2) the contract was rendered void ab-initio. On a plain reading of paragraph
24A.11 it becomes clear that the intention is to introduce the single counter
or window procedure to avoid duplication and hardship to the foreign
collaborators. Once the collaboration is approved by SIA, as in the present
case, and the agreement is `taken on record' there is no need to obtain a
separate permission from the RBI. Paragraph 9 of the Guidelines for Industries
explains what is meant by the expression `Taking of Agreements on Record' and
its import thus:
`The
approvals given for foreign collaboration are valid for a period of six months
from the date of issue. In case the terms of collaboration approved by
Government are acceptable to the Indian party, an intimation in this regard has
to be sent by him to the concerned administrative Ministry. The Indian party
can then execute the collaboration agreement with the collaborator which should
be strictly in accordance with the terms approved by the Government. Ten copies
of the collaboration agreement so executed all of which should be signed by
both the collaborating parties are to be furnished to the administrative
Ministry. The collaboration agreement is scrutinised by the administrative
Ministry and is found to be in accordance with the terms specifically approved
by Government is taken on record and an intimation is sent to the party. A copy
of the agreement is then transmitted to the Reserve Bank of India through the
Ministry of Finance (Department of Economic Affairs) on the basis of which
remittances to the foreign collaborator are authorised by the Reserve Bank of
India. Representations against the terms and conditions of collaboration
approved by the Government are sent by the SIA to the administrative Ministry/Department
concerned with the item of manufacture who will continue to deal with such
representations and take appropriate action.'' 85 It will be seen from the
above that after the agreement is taken on record a copy thereof has to be sent
to the RBI to enable it to authorise remittances to the foreign collaborator.
In the present case the appellant had sought the SIA approval which was granted
on 18th June, 1984 subject to the terms and conditions
set out in the letter of approval. It was only thereafter that the agreement
was executed on 25th
September, 1984. The
appellant then sent a copy of the agreement to the Government of India by the
letter of 5th October, 1984 which was duly examined in the light of the terms
and conditions on which the approval was granted under the letter of 18th June,
1984 and certain discrepancies were communicated to the appellant by he
Ministry of Industry, Department of Heavy Industry, which necessitated the
execution of the supplementary agreement of 29th December, 1984. It was only
thereafter that the said department by the letter of 15 January 1985 informed the appellant that the
collaboration agreement and the supplementary agreement `have been taken on
record'. This was then forwarded to the RBI which the bank received on 21st January, 1985. We have already indicated earlier
how the matter was processed by the RBI before the remittance of the first instalment
of the fees of U.S. $ 59,640 could take place after the income-tax was duly
recovered at source.
Paragraph
7 of the RBI's affidavit dated 18th September, 1990 extracted earlier and the
details of the action taken by the RBI as disclosed in the further affidavit of
24th January, 1991 leave no doubt that the remittance was permitted only after
the RBI was satisfied that all the terms and conditions were duly satisfied. To
place the matter beyond the pale of doubt, the further affidavit field on
behalf of the RBI carries the following statement.
``As
per the practice of the RBI, the permission under para 24A.11, that is, grant
of sanction under Section 28(1)(b) as well as permission under Section 9 for
allowing remittances are generally authorised by the Assistant Controller.''
This statement places the question regarding the grant of permission under
Section 28(1) beyond doubt. The affidavits file on behalf of the RBI show that
the RBI's approval `remained to be communicated' to the appellant company.
Failure
to discharge the ministerial duty cannot obliterate the conscious decision
taken by the RBI after application of mind.
But
counsel for the appellant stressed that the facts placed on record clearly
reveal that no application for permission under Section 28(1) was made in the
prescribed FNC5 as contemplated by paragraph 86 25A.2 of the manual. It is
indeed true that the record does not disclose making of an application in the
said prescribed form by either party to the agreement. Counsel, therefore,
submitted that once it is found that no application for permission was ever
made in the prescribed form, the provisions of sub-section (2) and (3) of
Section 47 of FERA cannot save the agreement declared void by the statute
itself. He further submitted that the case was governed by paragraph 25A.2 and
not 24A.11 and hence making of an application in the prescribed FNC5 form was
imperative and failure to do so raised a clear inference that the RBI had not
granted permission under Section 28(1) since it had never been approached for
such permission. he emphasised that the prescribed form for SIA `approval'
under paragraph 24A.11 is not the same as FNC5 and hence the administrative
direction in the said paragraph that `it will not be necessary for the foreign
collaborators to seek Reserve Bank permission under this section separately'
cannot override the statutory requirement of Section 28(1). The statutory duty
cast on the RBI by Section 28(1) cannot be abdicated by the RBI by the deeming
clause contained in paragraph 24A.11(i) extracted earlier. To buttress the
submission counsel invited our attention to two cases, viz., (i)M/s. Dhanrajmal
Gobindram v. M/s. Shamji Kalidas & Co., (1961) 3 SCR 1020 and (ii) LIC of
India v. Escorts Ltd. & Ors. [1986] 1 SCC 264 at 318 (Para 69) wherein this Court held that paragraph 24A. I
was merely an explanatory statement of guideline for the benefit of the authorised
dealers and was neither a statutory direction nor a mandatory instruction.
On the
other hand counsel for the respondent argued that the RBI's action in regard to
grant of permission under Section 28(1) being essentially administrative=see Shri
Sitaram Sugar Co. Ltd. & Anr. v. U.P.State Sugar Corporation Ltd. & anr.
[1990] 3 SCC 223 at page 246-247 it is enough to show that the RBI had granted
the permission no matter whether it had followed the procedure of paragraph
24A.11(i) or 25A.2 of the manual. We think there is considerable force in this
contention for the simple reason that we are concerned with the factum of
permission and not the procedure followed by the RBI for granting the same. The
prescription of the form is merely to aid the RBI to process the application
for permission. Emphasis must be laid on substances and not on mere form. If
there has been substantial compliance, as in this case, the mere lapse on the
part of the RBI in failing to communicate its decision should make no
difference.
Paragraph
25A.2 is not in derogation of paragraph 24A.11(i) nor does it dilute th
requirement of Section 28(1). In any case the facts of the present case clearly
reveal that the RBI had applied its mind to the question of grant of permission
and had only thereafter permitted remittance of the first instalment of the
fees payable 87 to the foreign collaborator. Merely because application for
such permission was not made in FNC5 form cannot cloud the fact that the
decision to grant the permission was actually taken but the ministerial
function of communicating the same remained to be done by oversight. This lapse
cannot erase the decision already taken. We are, therefore, of the opinion that
the RBI had granted the permission contemplated by Section 28(1) and hence the
agreement cannot be voided by virtue of Section 28(2) of FERA. It is not the
case of RBi that it at any time had second thoughts about its action. It never
contemplated withdrawal of the permission at any point for time thereafter.
Once the decision to grant the permission is taken, whether through the course
charted by paragraph 24A.11(i) or 25A.2, that decision stands unless rescinded
and the authorities are bound to act in aid thereof.
In the
view that we take it is unnecessary to examine the question whether clause 12.1
of the agreement would stand or perish if the agreement is rendered void under
Section 28(2) for failure to secure permission under Section 28(1). Since we
have come to the conclusion that the RBI permission was in fact secured under
Section 28(1), the second question recedes in the background. We, therefore,
need not examine the same.
Before
we part we are constrained to observe that we were pained at the attitude of
the appellant company attempting to thwart a valid agreement, part performed by
the payment of the first instalment, on hypertechnical grounds, an attitude
which would scare away collaborators and tarnish the image and credibility of
our entrepreneurs abroad. We do hope the appellant company will honour its
obligations under the agreement and settle its differences with the respondent
across the table in a business-like manner rather than litigate.
For
the aforesaid reasons we dismiss this appeal with cost. Cost quantified at
Rs.5000.
Back