S. Harcharan
Sinoh Vs. Union of India [1990] INSC 259 (28 August 1990)
Agrawal, S.C. (J) Agrawal, S.C. (J) Misra Rangnath Punchhi, M.M.
CITATION:
1991 AIR 945 1990 SCR Supl. (1) 76 1990 SCC (4) 647 JT 1990 (3) 692 1990 SCALE
(2)413
ACT:
Arbitration
Act, 1940: Sections 14, 17, 30 and 33--Contract for specified work--Claim for
entire additional work at increased rate-Arbitrator awarding increased rate for
part of the additional work-Whether Arbitrator exceeded his
jurisdiction--Award--Whether vitiated.
HEAD NOTE:
The
appellant was awarded a contract for constructing approaches to certain Bridge
structure. As per the agree- ment, he was required to do hard rock cutting to
the extent of 7,54,530 cft. and the rate fixed was Rs.129 per thousand cft. plus
2%. Actually the appellant was required to perform hard rock cutting to the
extent of 18,18,704 cft. For the additional work, the appellant claimed payment
at the rate of Rs.200 per thousand cft. He also claimed certain other sums
under other heads. Dispute in respect of 4 heads was referred to arbitration.
The arbitrator in his award disal- lowed two claims and allowed the other two
claims, one of which was in respect of the additional work of hard rock
cutting, and awarded a sum of Rs.52,800 under this head. The arbitrator filed the
award in the High Court. After consid- ering the objections filed by the
respondent a Single Judge of the High Court ordered that the award be made a
rule of the Court. The respondent filed an appeal against the said order and
the Division Bench set aside, ex-parte, the claim for higher remuneration at
the rate of Rs.200 per thousand cft. Aggrieved, the appellant has preferred an
appeal, by' special leave.
The
other appeal, also by special leave, is against the High Court's rejection of
the prayer for setting aside the ex-parte judgment.
Allowing
the former appeal and disposing of the latter one,
HELD:
1. As regards the award of an arbitrator under the Act, the law is well settled
that the arbitrator's adjudica- tion is generally considered binding between
the parties for he is a tribunal selected by the parties and the power of the
court to set aside the award is restricted to cases set out In section 30 of
the Act. It is, however, not open to the 77 Court to speculate, where no reasons
are given by the arbi- trator, as to what impelled the arbitrator to arrive at
his conclusion. But the jurisdiction of the arbitrator is limit- ed by the
reference and if the arbitrator has assumed juris- diction not possessed by
him, the award to the extent to which it is beyond the arbitrator's
jurisdiction would be invalid and liable to be set aside. An arbitrator or
umpire is under no obligation to give reasons in support of the decision
reached by him unless under the arbitration agree- ment or the deed of
submission he is required to give such reasons. If the arbitrator or umpire
chooses to give reasons in support of his decision it is open to the Court to
set aside the award if it finds that an error of law has been committed by him
on the face of the record. An award can neither be permitted nor set aside
merely on the ground that it does not contain reasons in support of the
conclusion or decisions reached in it except where the arbitration agree- ment
or the deed of submission requires him to give reasons.
[82H;
83A-E] Jivarajbhai Ujamshi Sheth and Others v. Chintamanrao Balaji and Others,
[1964] 5 SCR 480; Raipur Development Authority and Others v. M/s Chokhamal
Contractor and Others, [1989] 2 SCC 721, relied on.
2.1 In
the instant case the arbitration agreement or the deed of submission did not
require the arbitrator to give reasons and, therefore, the award cannot be
questioned on the ground of an error on the face of the award. The Divi- sion
Bench of the High Court set aside the award in respect of the claim relating to
payment for additional work of hard rock cutting on the ground that in making
the award the arbitrator exceeded his jurisdiction by allowing a rate to the
contractor in excess of the agreed rate for the job of hard rock cutting
against the terms and conditions in clause 12 of the agreement. [83F-G]
2.2
Under clause 12 of the agreement, the Engineer-in- charge was empowered to make
any additions to the original specifications that may appear to him to be
necessary or advisable during the progress of the work and the contractor was
bound to carry out the work in accordance with any instructions given to him in
writing signed by the Engineer-in-charge. [85B-C]
2.3 It
has to be inferred from the terms of the contract whether this power to order
extras, although apparently unlimited, is in fact limited to ordering extras upto
a certain value and in such a case, extras ordered in excess of that amount may
be outside the terms of the contract.
78
Parkinson (Sir Lindsay) & Co. Ltd. v. Commissioners of His Majesty's Works
and Public Buildings, [1949] 2 K.B. 632, referred to.
Hudson's Building and Engineering
Contracts, 8th Edn. pp. 294, 296, referred to.
3. In
some awards given by the arbitrators in the Cen- tral Public Works Department
of the Government of India the variation of the tendered quantities under the
variation clause in the contract has been restricted to 10% beyond which the
contractor was entitled to claim as extras and awards have been accepted and
implemented by the Government.
It
appears that the standard form of contract of the Central Public Works
Department has been amended and now it specifi- cally permits for a limit of
variation called "deviation limit" upto a maximum of 20% and upto
such limit the con- tractor has to carry out the work stipulated in the
contract and for the work in excess of that limit at the rates to be determined
in accordance with clause 12-A under which the Engineer-in-Charge can revise
the rates having regard to the prevailing market rates. [88D-F] Gajaria's Law
relating to Building and Engineering Contracts in India, 3rd Edn., pages
410-412, referred to.
4. In
the instant case, the Executive Engineer, the Superintending Engineer and the
Additional Chief Engineer have expressed the view that the additional work
under the terms of the contract may be confined to 20% and the appel- lant may
be paid at the rates prescribed in the contract for 20% of the additional work
and for the extra quantity of additional work he may be paid remuneration at
the increased rate taking into account the increased costs in execution of the
said work on account of the peculiar nature of the work while considering the
claim of the appellant the arbitrator was required to consider the terms of the
contract and to construe the same. It was, therefore, permissible for the
arbitrator to consider whether clause 12 of the contract enables the
Engineer-in-charge to require the appellant to execute additional work without
any limit, or a reasonable limit should be placed on the quantity of the
additional work, which the appellant may be required to execute at the rate
stipulated for the main work under the contract. For that purpose the
arbitrator could take into consideration the practice prevalent in the Central
Public Works Depart- ment in this regard as well as the correspondence between
the appellant and the authorities recommending payment of remuneration at the
increased rate for the additional work in excess of 20% of the quantity
stipulated in the contract.
79 The
appellant was claiming increased rate of Rs.200 per 1000 cft. for the entire
quantity of additional work. The arbi- trator did not accept the said claim of
the appellant in full and has partly allowed the said claim by awarding Rs.52,800
which means that the arbitrator has awarded the increased rate only for a part
of the additional work of hard rock cutting which the appellant was required to
exe- cute. The arbitrator was entitled to do so on the construc- tion placed by
him on clause 12 of the contract and, there- fore, it cannot be said that in
awarding the sum of Rs.52,800 for the additional work the arbitrator has
exceed- ed his jurisdiction and the award is vitiated by an error of
jurisdiction. [88G-H; 89A-E]
5. The
judgment of the Division Bench of the High Court setting aside the award of the
arbitrator with regard to the claim relating to payment for additional work of
hard rock cutting is set aside and the order passed by the Single Judge
upholding the award of the arbitrator in this regard is restored. [89F]
6.
Since the judgment of the Division Bench of the High Court is set aside the
appeal against the order rejecting the prayer for setting aside the ex-parte
judgment, does not survive. [90B]
CIVIL
APPELLATE JURISDICTION: Civil Appeals Nos. 322 & 323 of 1976.
From
the Judgment and Order dated 27.3.1973 and 23.5.75 of the Delhi High Court in
F.A.O. (O.S.) No. 35 of 1969 and C.M. No. 1300 of 1974 in F.A.O. (O.S.) 35 of
1969.
P.P. Juneja
for the Appellant.
B.B. Barua,
Ms. A. Subhashini (N.P.) and Ms. Indira Sawhney ( N.P. ) for the Respondent.
The
Judgment of the Court was delivered by S.C. AGRAWAL, J. Civil Appeal No. 322 of
1976 This appeal by special leave has been filed against the judgment dated
March 27, 1973 of the High Court of Delhi in F.A.O. (O.S.) No. 35 of 1968.
The
appellant, S. Harcharan Singh, was awarded a contract for 80 constructing
approaches to the Bridge Structure B-2 on the North Sikkim Road in 1959-60. Under the agreement the appel- lant was
required to do hard rock cutting to the extent of 7.54,530 cft. The rate fixed
for the said work in the con- tract was Rs.129 per thousand cft. plus 2%. The
appellant was required to perform hard rock cutting to the extent of 18, 18,704
cft. The appellant claimed payment at the rate of Rs.200 per thousand cft. for
the additional work of hard rock cutting. He also claimed certain other sums
under other heads. The dispute in respect of four heads was referred to
arbitration in accordance with the clause 25 of the agree- ment. The arbitrator
gave his award dated February 5, 1965 wherein he disallowed the claim of the
appellant in respect of two items but made an award in favour of the appellant
in respect of two items of claim. In this appeal we are only concerned with the
claim of the appellant in respect of the additional work of hard rock cutting
which the appellant was required to execute. The arbitrator awarded a sum of
Rs.52,800 against the said item. The award was filed in the High Court by the
arbitrator alongwith his letter dated June 6, 1968. Objections were filed by
the respondent under Sections 30 and 33 of the Arbitration Act, 1940
(hereinafter referred to as 'the Act'). The said objections were consid- ered
by the learned single Judge of the Delhi High Court and by order dated April
23, 1969. the said objections of the respondent were rejected and it was
ordered that the award be made a rule of the Court. The respondent filed an
appeal against the said order and decree passed by the learned single Judge.
The appeal was partly allowed by the Division Bench of the High Court by
judgment dated March 27, 1973, whereby the award as regards the claim for
higher remunera- tion at the rate of Rs.200 per thousand cft. for the addi- tional
work of hard rock cutting was set aside. The award in respect of other item of
the claim relating to expenditure incurred by the appellant in reconstructing
the retaining walls after damage, was maintained. Aggrieved by the said
decision of the Division Bench of the High Court the appel- lant has filed this
appeal after obtaining special leave.
As
indicated earlier, this appeal is confined to the claim of the appellant for
payment for the additional work of hard rock cutting which the appellant was
required to execute. The appellant has claimed a higher rate of Rs.200 per
thousand cft. for this additional work. Under the agree- ment the appellant was
required to execute hard rock cutting to the extent of 7,54,530 cft. but
actually he was required to execute such cutting to the extent of 18.15 lacs cft.
The extent of the additional work was about 10.60 lacs cft., i.e. about 140%.
While undertaking the execution of the additional work of hard rock 81 cutting
the appellant in his letter dates August 24, 1960 addressed to the Executive
Engineer, Central Division No. II, Gangtok, had requested for revision of the
rate for hard rock cutting and stated that the minimum working rates for this
item are 52% above the tendered rates. The ExecUtive Engineer by his letter
dated September 2, 1960, requested the appellant to submit
an analysis of rate for hard rock cutting. The appellant submitted his analysis
of rates on September
14, 1960 wherein after
analysing the rates of materials and labour the workable rate worked out to
Rs.200 per thousand cft. The Executive Engineer also got an analy- sis of rates
done on the basis of the data collected on actual observation and he arrived at
a figure of Rs.237 per thousand cft. By his letter dated November 9, 1961 addressed to the Superintending
Engineer, Calcutta
Central Circle No.
III, CPWD, Calcutta, the Executive Engineer recommended
the extra rate of Rs.200 per thousand cft. for work in excess of 20% of the
stipulated quantity. The Superintending Engineer, in his letter dated February 23, 1962 addressed to the Additional Chief
Engineer III, Central P.W.D., New Delhi,
made a similar recommendation and the Additional Chief Engineer made a similar
recommendation in his letter dated July 16, 1962 addressed to the Secretary to the
Government of India, Ministry of Works and Housing. It appears that the
Government did not agree to pay at a rate in excess of the rate of Rs.129 per
thousand cft. plus 2% stipulated under the agreement. The dispute was,
therefore, referred to arbitration.
The
arbitrator in his award has considered this item of claim as under:
Claim
Dispute Award "The contractor claims The arbitrator The claim of the that
for Item No 3 of is to deter- contractor is the agreement he should mine
whether partly justified.
be
paid at the rate of under the He should be paid Rs.200 per 1000 cft. terms and
con- an amount of for the quantities ditions of the Rs.52,800 (Rupees beyond
what is stipu- contract, the fifty two thousand lated in the agreement. claim
is jus- and Eight hundred tified and if only) in addition so, to what ex to the
payment to tent. be made to him at relevant agreement rate for the total
quantity of work executed by him under this item." 82 Before the learned
single Judge it was submitted on behalf of the respondent that the award is a
speaking award and from the award it is apparent that the arbitrator has fixed
rates for additional work done by the contractor which the arbitrator has no
jurisdiction to do by reason of clause 12 of the agreement between the parties
which provides that additions to the contract work shall be carried out by the
contractor on the same conditions in all respects on which he agreed to do the
main work and at the same rates as specified in the tender for the mainwork.
The learned single Judge rejected the said contention and held that the arbi- trator
was determining only the value of the additional work at the rate of Rs.200
which had been agreed by the Engineer-in-charge and the Superintending Engineer
of the Circle as contemplated by clause 12 and the scope of the inquiry before the
arbitrator was only the quantity of work which was additional to the quantities
specified in the agreement. The learned Judges of the Division Bench of the
High Court have disagreed with the said view and have ob- served that it is
clear from the statement of claim as incorporated in the award, and the
affidavit of the contrac- tor that there was no dispute with regard to the
quantity of work and the only dispute was with regard to the rate and that the
arbitrator had allowed a sum of Rs.52,800 to the contractor in respect of the
total quantity of work executed by him under item No. 3 in addition to the
agreed rate and that there was no escape from the conclusion that the arbi- trator
had awarded the above 'amount by applying a rate higher than the agreed rate.
The learned Judges of the Division Bench were of the view that under clause 12
of the agreement the provision with regard to the fixing of the rate by the
Engineer-incharge and the Superintending Engi- neer of the Circle comes into
play only when the additional item of work does not form part of the main work
and the rates for such work are not specified in the schedule of rates. The
learned Judges of the Division Bench have held that since the additional hard
rock cutting job done by the appellant was part of the main work and the
agreement pro- vided the rate for the said item, there was no occasion for the
Engineer-in-charge or the Suprer intending Engineer to fix the rate for the
extra quantity of hard rock cutting and that the action of the arbitrator in
allowing the rate to the contractor in excess of the agreed rate for the job of
hard rock cutting was against clause 12 of the agreement and thereby the
arbitrator had exceeded his jurisdiction.
As
regards the award of an arbitrator under the Act. the law is well settled that
the arbitrator's adjudication is generally considered binding between the
parties for he is a tribunal selected by the parties and the power of the court
to set aside the award is restricted to cases 83 set out in section 30 of the
Act, viz. (a) if the arbitrator has misconducted himself or the proceedings; or
(b) when the award has been made after the issue of an order by the Court
superseding the arbitration or after arbitration proceedings have become
invalid under Section 35; or (c) when the award has been improperly procured or
is otherwise invalid. Under clause (c) of Section 30 the Court can set aside an
award which suffers from an error on the face of the award. It is.
however.
not open to the Court to speculate, where no rea- sons are given by the
arbitrator. as to what impelled the arbitrator to arrive at his conclusion. But
the jurisdiction of the arbitrator is limited by the reference and if the
arbitrator has assumed jurisdiction not possessed by him, the award to the
extent to which it is beyond the arbitra- tor's jurisdiction would be invalid
and liable to be set aside (See: Jivarajbhai Ujarnshi Sheth and Others v. Chin-
tatnanrao Balaji and Others, [1964] 5 SCR 480). This posi- tion at law has been
reiterated by the Constitution Bench of this Court in its recent decision in Raipur
Development Authority and Others v. M/s Chokharnal Contractors and Others,
[1989] 2 S.C.C. 721. It has been held that an arbi- trator or umpire is under
no obligation to give reasons in support of the decision reached by him unless
under the arbitration agreement or the deed of submission he is re- quired to
give such reasons and if the arbitrator or umpire chooses to give reasons in
support of his decision it is open to the Court to set aside the award if it
finds that an error of law has been committed by the arbitrator or umpire on
the face of the record on going through such reasons and that an award can
neither be remitted nor set aside merely on the ground that it does not contain
reasons in support of the conclusion or decisions reached in it except where
the arbitration agreement or the deed of submission requires him to give
reasons.
In the
instant case the arbitration agreement or the deed of submissions did not
require the arbitrator to give reasons and, therefore, the award cannot be
questioned on the ground of an error on the face of the award. The learned
Judges of the Division Bench of the High Court have set aside the award in
relation to claim No. 1 relating payment for additional work of hard rock
cutting on the ground that in making the award the arbitrator exceeded his
jurisdiction by allowing a rate to the contractor in excess of the agreed rate
for the job of hard rock cutting against the terms and conditions contained in
clause 12 of the agreement.
The
question which needs to be considered here is as to whether in awarding the sum
of Rs.52,800 to the appellant for the additional 84 work of hard rock cutting
executed by him the arbitrator has disregarded clause 12 of the agreement. The
said clause reads as under:
"The
Engineer-in-charge shall have power to make any altera- tions in, commissions
from, additions to or substituting for, the original specifications, drawings,
designs and instructions, that may appear to him to be necessary or advisable
during the progress of the work, and the contrac- tor shall be bound to carry
out the work in accordance with any instructions which may be given to him in
writing signed by the Engineer-in-charge, and such alterations, omissions,
additions or substitutions shall not invalidate the con- tract: and any
altered, additional or substituted work which the contractor may be directed to
do in the manner above specified as part of the work shall be carried out by
the contractor on the same conditions in all respects on which he agreed to do
the main work and at the same rates as are specified in the tender for the main
work. The time for the completion of the work shall be extended in the
proportion that the additional or substituted work bears to the Origi- nal
work, and the certificate of the Engineer-in-charge shall be conclusive as to
such proportion. And if the al- tered, additional or substituted work included
any class of work for which no rate is specified in this contract, then such
class of work shall be carried out at the rates entered in the schedule of
rates of the C.P.W.D. Schedule of Rates 53-54 on which the estimated cost shown
on page 1 of tender is based provided that when the tender for the original
work is a percentage above the schedule rates the altered, addi- tional or
substituted work required as aforesaid shall be chargeable at the said schedule
rate plus the same percent- age deduction addition and if such class of work is
not entered in the said schedule of rates, then the contractor shall within
seven days of the date of the receipt of the order to carry out the work inform
the Engineer-incharge of the rat. e which it is his intention to charge for
such class of work, and if the Engineer-in-charge does not agree to this rate
he shall by notice in writing be' at liberty to cancel his order to carry out
such class of work and arrange to carry it out in such manner as he may
consider advisable provided always that if the contractor "shall commence
work or incur any expenditure in regard thereto before the rates shall have
been determined as lastly hereinbefore 85 mentioned, then and in such case he
shall only be entitled to be paid in respect of the work carried out or
expenditure incurred by him prior to the date of the determination of the rate
as aforesaid according to such rate or rates as shall be fixed by the
Engineer-in-charge. In the event of a dispute the decision of the
Superintending Engineer of the Circle shall be final." Under this clause
the Engineer-in-charge was empowered to make any additions to the original
specifications that may appear to him to be necessary or advisable during the
progress of the work and the contractor was bound to carry out the work in
accordance with any instructions given to him in writing signed by the
Engineer-in-charge. As regards payment for the additional work which the
contractor was directed to do it was provided that:
(i)
The contractor shall be paid at the same rates as are specified in the tender
for the main work;
(ii)
If the additional work included any class of work for which no rate was
specified in the contract then the con- tractor shall be paid at the rates
entered into the schedule of rates of the C.P.W.D. Schedule of Rates 53-54 on
which the estimated cost shown on page 1 of tender is based and if the tender
for the original work is a percentage above the schedule rates the additional
work shall be chargeable at the said schedule rates plus the same percentage
deductions/addition; and
(iii)
If such class of work is not entered in the said Schedule of Rates then the
contractor should inform the Engineer-in-charge within seven days of the
receipt of the order the rate he wants to charge for such class of work and the
Engineer-in-charge, if he does not agree to the said rate, may cancel the order
for such additional work and if the contractor has commenced the work or
incurred expendi- ture in regard thereto before the determination of the rates
the contractor shall be paid in respect of work carried out or expenditure
incurred by him prior to the determination of the rates according to such rates
or rates as shall be fixed by the Engineer-in-charge and in the event of a
dispute the decision of the Superintending Engineer of the Circle would be
final.
The
case of the appellant is that clause 12 envisages alter- ations or 86 additions
within reasonable limits and an addition to the extent of 140% in respect of
one particular item alone is not covered by this clause and that in awarding
Rs.52,800 as extra payment for the additional work the arbitrator has not acted
in disregard of clause 12 and he cannot be said to have exceeded his
jurisdiction.
A
clause making provision for additions and variations is generally found in
building and construction contracts.
In Hudson's Building and Engineering
Contracts 8th Edn. it has been observed:
"It
may be that it can be inferred from the terms of the contract that the power to
order extras, although apparently unlimited, is in fact limited to ordering
extras up to a certain value and, in such a case, extras ordered in excess of
that amount, although work of a kind contemplated by the contract, may yet be
quite outside the terms of the con- tract." (p. 294) "If the extra
work ordered is outside the contract the terms of the contract have no
application." (p. 296) In this context it would be relevant to take note
of the decision of the Court of Appeal in England in Parkinson (Sir Lindsay)
& Co. Ltd. v. Commissioners of His Majesty's Works and Public Buildings,
[1949] 2 K.B. 632. In that case the contractors had agreed with His Majesty's
Commissioners of Works and Public Buildings to erect an ordnance factory
according to the general conditions and specifications and bills of quantities
and drawings annexed for the contract sum of Pound 3,500,000 and under the
general conditions of contract the Commissioners had power, at their absolute
discretion, to modify the extent and character of the work or to order
alterations of or additions to the works and it was the duty of the contractor
to comply with the archi- tect's instructions in this respect. In the contract
it was also provided that it is probable that further work to the value of
approximately, Pound 500,000 would be ordered on a measured basis under the
terms of the contract. The contract was amended by a deed of variation and it
was provided that exceptional methods should be used to hasten the work and
that a system of uneconomic working should be introduced to bring about the
completion of the factory by the date fixed by the contract. The Commissioners
ordered work to be exe- cuted greatly in excess of the amount contemplated
although not different in character from that covered by the varied contract,
so that the works could not be completed until a year beyond the time anticipated
and the actual cost of the 87 contracts was L6,683,056 which amount had been
paid to them - alongwith L300,000 the maximum profit under the deed of -
variation. During the progress of the work the contractors had. complained to
the Commissioners that they were being called on to execute more work than was
contemplated by the varied contract and claimed that they were entitled to
extra remuneration for the work in excess of that contemplated but they
proceeded with the work at the request of the Commis- sioners leaving the issue
to be subsequently decided by arbitration. The arbitrator found that the
estimated cost of the work under the varied contract was L500,000 and awarded -
L90,298 as proportionate or reasonable profit or remunera- - tion to the contractors
for the additional work. The said award was upheld by the Court of Appeal on
the view that a term must be implied in the varied contract that the Commis- sioners
should not be entitled to require work materially in excess of the sum of L5,000,000
and that such excess work - having been done by the contractors, the
Commissioners were liable to pay the contractors reasonable remuneration there-
fore. On behalf of the Commissioners reliance was placed on Condition 33 of the
original contract which gave the Commis- sioners an unlimited power of ordering
extras even to the extent of altering the character of the work. The contrac- tors,
on the other hand, placed reliance on the following observations of Mc Cardie,
J. in Naylor, Benzon & Co. v. Krainische Industrie Gesellschart, [1918] 1
K.B.331:
"It
is essential to remember, however, that words, even though general, must be
limited to circumstances within the contemplation of the parties."
Accepting the contention urged on behalf of the contrac- tors Asquith L. J.
observed:
"If
the original contract plus the deed are read without any implied limitation on
their literal meaning, the result, as indicated above, is that after L300,000
profit has been - earned by the contractor, he can be compelled to labour like
the Danaids without reward or limit, or any further "extras" which
the commissioners may elect to exact from him, 'till the last syllable of
recorded time.' Only the most compel- ling language would induce a court to
construe the combined instruments as placing one party so completely at the
mercy of the other. Where the language of the contract is capable of a literal
and a more restricted meaning, all relevant circumstances can be taken into
account in decid- 88 ing whether the literal or a more limited meaning should
be ascribed to it". (p. 662) Similarly Singleton L.J. has observed:
"1
find myself unable to agree with the submission of Mr. Rewcastle that under the
contract as varied by the deed of variation, the contractors would have been
bound to continue making alterations and additions, if ordered, for years and
years, without any extra payment by way of profit. That would have led to
manifest absurdity and injustice, as Mathew, J. said in Bush v. Whitehaven
Trustees, (1). There must be a limit." (p. 673) Here also the question has
often arisen whether the contractor under the variation clause is liable to
execute the extra or additional quantities of the tendered items at the
tendered rates to an unlimited extent. In some awards given by the arbitrators
in the Central Public Works Depart- ment of the Government of India the
variation of the ten- dered quantities under the variation clause in the
contract has been restricted to 10% beyond which the contractor was entitled to
claim as extras and these awards have been accepted and implemented by the
Government. It appears that the standard form of contract of the Central Public
Works Department has been amended and now it specifically permits for a limit
of variation called "deviation limit" upto a maximum of 20% and upto
such limit the contractor has to carry out the work at the rates stipulated in
the contract and for the work in excess of that limit at the rates to be
determined in accordance with clause 12-A under which the Engineer-in-charge
can revise the rates having regard to the prevailing market rates (See: Gajaria's
Law relating to Building and Engineering Contracts in India, 3rd Edn., pages
410-412).
In the
instant case, it appears that the Executive Engineer, the Superintending Engineer
and the Additional Chief Engineer in their letters dated November 9, 1961,
February 23, 1962 and July 16, 1962 respectively have ex- pressed the view that
the additional work under the terms of the contract may be confined to 20% and
the appellant may be paid at the rates prescribed in the contract for 20% of
the additional work and for the extra quantity of additional work he may be
paid remuneration at the increased rate taking into account the increased costs
in execution of the said work on account of the peculiar nature of the work.
While
considering the claim of the appellant the 89 arbitrator was required to
consider the terms of the con- tract and to construe the same. It was,
therefore, permissi- ble for the arbitrator to consider whether clause 12 of
the contract enables the Engineer-incharge to require the appel- lant to
execute additional work without any limit or a reasonable limit should be
placed on the quantity of the additional work, which the appellant may be
required to execute at the rate stipulated for the main work under the
contract. For that purpose the arbitrator could take into consideration the
practice prevalent in the Central Public Works Department in this regard as
well as the correspond- ence between the appellant and the authorities
including the letters dated November 9, 1961, February 23, 1962 and July 16,
1962 of the Executive Engineer, the Superintending Engineer and the Additional
Chief Engineer recommending payment of remuneration at the increased rate for
the addi- tional work in excess of 20% of the quantity stipulated in the
contract. The appellant was claiming increased rate of Rs.200 per 1000 cft. for
the entire quantity of additional work. The arbitrator did not accept the said
claim of the appellant in full and has partly allowed the said claim by
awarding Rs.52,800 which means that the arbitrator has awarded the increased
rate only for a part of the additional work of hard rock cutting which the
appellant was required to execute. The arbitrator was entitled to do so on the
construction placed by him on clause 12 of the contract and, therefore, it
cannot be said that in awarding the sum of Rs.52,800 for the additional work
the arbitrator has exceed- ed his jurisdiction and the award is vitiated by an
error of jurisdiction. In the circumstances, we are unable to agree with the
judgment of the learned Judges of the Division Bench of the High Court on this
part of the claim.
The
appeal is, therefore, allowed and the judgment of the Division Bench of the
High Court setting aside the award of the arbitrator with regard to item No. 1
of the claim relating to payment for additional work of hard rock cutting is
set aside and the order passed by the learned Single Judge upholding the award
of the arbitrator in this regard is restored. The appellant will be entitled to
his costs.
Civil
Appeal No. 323 of 1976 This appeal is directed against the order dated May 23,
1975 of the High Court of Delhi whereby the High Court rejected C.M. No. 1300
of 1974 filed by the appellant under Order 41, rule 21 read with Section 151
C.P.C., praying that the ex-parte judgment dated March 27, 1973 in F.A.O.
(O.S.) No. 35 of 1969 may be set aside and the appeal be re-admit- ted to its
original number and the appeal be heard 90 and decided on merits. The appellant
has filed C.A. No. 322 of 1976 against the said judgment of the High Court
dated March 27, 1973 in F.A.O. (O.S.) No. 35 of 1968. The said appeal has been
allowed by the judgment given today. Since the judgment of the High Court dated
March 27, 1973 has been set aside by this Court in
C.A. No. 322 of 1976 this appeal does not survive and it is disposed of
accordingly. No costs.
G.N.
Appeal disposed of.
Back