India
Cement Ltd. Vs. Union of India & Ors [1990] INSC 245
(21 August 1990)
Verma,
Jagdish Saran (J) Verma, Jagdish Saran (J) Punchhi, M.M. Reddy, K. Jayachandra
(J)
CITATION:
1991 AIR 724 1990 SCR (3) 850 1990 SCC (4) 356 JT 1990 (3) 572 1990 SCALE (2)291
ACT:
Cement
Control Order 1967 Clause 12--Fixation of uniform retention price--Legality of.
HEAD NOTE:
The
appellants filed writ petitions in the Madras High Court challenging the
fixation in 1969 of a uniform reten- tion price of Rs. 100 per tonne of cement
instead of the existing three different retention prices for different
categories of producers fixed earlier on the basis of the recommendations made
by the Second Tariff Commission in 1961. The grievance of the appellants was
that the fixation of a uniform retention price to be paid to all producers for
the cement produced by them and acquired by the State Trad- ing Corporation
amounted to discrimination contravening Article 14 of the Constitution. The
challenge was rejected by a Single Judge and, thereafter, a Division Bench of
the High Court.
Cement
has been a controlled commodity for a long time and its production,
distribution and price were regulated by Cement Control Orders issued by the
Central Government from time to time in exercise of the powers conferred under
sections 18G and 25 of the Industrial (Development & Regula- tion) Act,
1951.
On
behalf of the appellants it was contended that the impugned Order made in 1969
fixing a uniform retention price for all three categories of cement producers
treated un- equals as equals; that the increase of Rs.7 per tonne was to be
made to the existing three-tier retention prices, but an irrational basis was
adopted in fixing the uniform price of Rs. 100 per tonne which resulted in an
unequal increase to the three different retention prices then existing; that
clause 12 of the Cement Control Order, 1967 did not permit one uniform
retention price; and that atleast in the case of Chettinad Cement Corporation
Ltd. discrimination was proved on the basis of the distinction made by the High
Court in the case of M/s Travancore Cement Ltd. The appellants howev- er did
not dispute before this court that no grievance would survive if the uniform
retention price was fixed at Rs. 104 per tonne instead of Rs. 100.
851 On
behalf of the respondents it was asserted that the industry itself had sought a
revision of the prices and had accepted in principle that there should be one
uniform retention price.
Dismissing
the appeals, this Court,
HELD:
{1) The fixation of Rs. 100 per tonne as the uniform retention price for the
entire industry with the solitary exception of M/S Travancore Cement Ltd. for
which justification had been shown, was on a rational basis taking into account
all relevant data and factors including the cement industry's acceptance of the
principle of a uniform retention price for the entire industry, the only
difference being in the price actually fixed at Rs. 100 per tonne instead of Rs.
104 per tonne claimed by the cement industry.
It is
obvious, therefore, that the principle of a uniform retention price for the
entire industry had not been fault- ed. [857H; 858A-B]
(2)
The principle of fixation of a uniform price for the industry was an accepted
principle and this had to be done by fixing the uniform price on the basis of
the cost of a reasonably efficient and economic representative cross- section
of manufacturing units and not with reference to the cost in relation to each
unit. [859A-B] M/s. Shri Sitaram Sugar Company Limited & Anr. v. Union of India & Ors. and U.P. State Sugar Corporation
Ltd. & Anr. v. Union of India & Ors., J.T. 1990 (1)
SC 462, referred to.
(3)
Fixation of a uniform retention price being clearly permissible and the same
having been determined at Rs. 100 per tonne on the basis of expert opinion,
rounded on rele- vant factors, there was no scope for interference within the
limits of permissible judicial review in the present case. [859E] Anakapalle
Co-operative Agricultural & Industrial Socie- ty Ltd. v. Union of India,
[1973] 2 SCR 982 and The Panipat Cooperative Sugar Mills v. Union of India,
[1973] 2 SCR 860, referred to.
(4)
The Central Government's power under Clause 12 of the Cement Control Order,
1967 to refix the price can be exercised 'having regard to any change in any of
the factors relevant for determination of price of cement'. The meaning of the
expression 'having regard to' is well-settled. It indicates that in exercising
the power, regard must be had also to the factors enumerated together with all
factors relevant for 852 exercise of that power. One such factor specified in
Clause 12 is "such
(5) No
material has been produced by the appellant to show that M/s Chettinad Cement
Corporation is a similar substandard unit without any capacity for expansion,
so that it too must continue to be an uneconomic unit like M/s Travancore
Cement Ltd. deserving a similar treatment. [860F-G]
CIVIL
APPELLATE JURISDICTION: Civil Appeal Nos. 2 192/93 of 1972.
From
the Judgment and Decree dated 23.4.1971 of the Madras High Court in Writ Appeal
Nos. 155 and 157 of 1970.
G.L. Sanghi,
K. Parasaran, S. Krishnamurthy Iyer, K.K. Venugopal, D.N. Mishra and Ms. Lira Goswami
for the Appel- lants. V.C. Mahajan, Gobind Das, N.L. Kakar, C.V. Subba Rao,
B.R. Aggarwala, T.C. Sharma, Mrs. Sushma Suri and Ms. Sushma Manchanda for the
Respondents.
The
Judgment of the Court was delivered by VERMA, J. Both these appeals are against
the common judgment of the Madras High Court (hereinafter referred to as 'the
High Court') by a certificate under Article 133(1) of the Constitution prior to
its amendment. The appellants' writ petitions were dismissed by a common
judgment dated 18.12.1969 by a learned Single Judge of the High Court and
thereafter, the writ appeals were dismissed by a Division Bench of the High
Court on 23.4.1971. The grievance of the appellants before us is, as it was in
the High Court, against the fixation of a uniform retention price in 1969 to be
paid to all producers for the cement produced by them and acquired by the State
Trading Corporation. In short, the appellants' grievance is that the fixation
of a uniform retention price for all producers in 1969 instead of three
different retention prices for different categories of producers, as was done
earlier, amounted to discrimination contravening Article 14 of the
Constitution.
The
background in which the argument of discrimination has to be tested may now be
stated. Cement has been a con- trolled com- 853 modity for a long time and its
production, distribution and price were regulated by Cement Control Orders
issued by the Central Government from time to time in exercise of the powers
conferred under the Industries (Development & Regula- tion) Act, 1951. The
arrangement made in 1856 was that the entire quantity of cement produced by all
producers was acquired by the State Trading Corporation which distributed it
throughout the country at a uniform price on f.o.r. basis. The price payable by
the State Trading Corporation to the producer was, however, the 'retention
price' or 'ex- works' or 'ex-factory price' fixed by the Government. In
accordance with the recommendations of the First Tariff Commission in 1958, the
Central Government fixed f.o.r. and ex-factory prices for a period of three
years from July 1958, under the Cement Control Order, 1958. Even though the
consumer price was one uniform f.o.r. destination price, there were different
retention prices for cement relating to the producers. In case of a new unit
commencing production, the Government fixed suitable retention price for it on
the basis of cost of production.
Pursuant
to representation by the cement industry for revision in the prices, the Second
Tariff Commission was set up by the Government to examine the question. The
Tariff Commission, after a comprehensive study, submitted its report on
26.8.1961. In the report, it was noticed that fixation of ex-works price for
individual cement producers had brought stagnation in the cement industry due
to lack of competition and incentive amongst producers to reduce the cost of
production, improve the operational efficiency and increase the output. It was
observed that instead of reward- ing efficiency, it had promoted a tendency to
inflate costs which facilitated increase in the margin of profit to the
producer. The Tariff Commission ultimately grouped the various units under
three broad categories on the basis of return on the capital employed. These
were: the lowest cost group, the high cost group, and those whose cost of produc-
tion was in between the other two groups. Accordingly, the Tariff Commission
recommended different retention prices for the manufacturers of cement. The
Government generally ac- cepted the recommendations and passed the Cement
Control Order, 1961, fixing three different retention prices for three
different groups of manufacturers. The Central Govern- ment from time to time permitted increase in the retention
prices so fixed.
The
Central Government decided on discontrol of cement w.e.f. 1.1.1966, but the
cement industry imposed a system of self-regulation and set up an unofficial
body known as "Cement Allocation and 854 Coordinating Organisation".
The cement was to be distributed to consumers at uniform f.o.r. destination
price all over India. This price included a freight
component. A cement regulation account was also established to which a manufac-
turer would either contribute or draw from depending on the actual freight
incurred. This system was not found workable and the Central Government decided
to re-impose control. The Cement Control Order, 1967 was passed under Section
18G and Section 25 of the Industries (Development & Regulation) Act, 1951,
to be effective from 1.1.1968. Under this Order, the threetier retention price
system was continued and the retention prices fixed for the three groups were
specified in the Schedule as Rs.90.50, Rs.93.50 and Rs.96. Both the appellants
fell under the category for which the retention price specified in the Schedule
was Rs.96. Under this Cement Control Order, the system of uniform consumer
price was preserved and freight equalisation was maintained by requir- ing the
manufacturer to either contribute or draw from the cement regulation account
set up under clause 9 of the Order. The Cement Controller replaced the Cement
Allocation and Co-ordinating Organisation.
Pursuant
to the representation made by various manufac- turers, the Central Government
enquired into the increase in the cost of production since 1.1.1966. In
consultation with the concerned authorities, it was estimated that the weight- ed
average increase in the cost of production since 1.1.1966 was Rs7 per tonne.
The Central Government then issued the Cement Control (Amendment) Order, 1969
on 14.4.1969 effec- tive from 16.4.1969 by which the Cement Control Order, 1967
was amended and in respect of all cement manufacturers, except M/s. Travancore
Cement Limited, Kottayam, a uniform retention price of Rs. 100 per tonne was
fixed.
The
appellants filed writ petitions in the Madras High Court challenging the
fixation of a uniform retention price of Rs. 100 per tonne in this manner on
the ground that it violated Articles 14 and 19(1)(g) of the Constitution. As
earlier stated, the challenge was rejected by a Single Judge and thereafter, a
Division Bench of the High Court, Hence, these appeals by a certificate granted
by the High Court under the unamended Article 133(1) of the Constitution of
India, The challenge before us in these appeals is based only on Article 14 of
the Constitution. Shri K. Parasaran, learned counsel for the appellant in the
Civil Appeal No. 2193 of 1972 (Chettinad Cement 855 Corporation Ltd. v. Union
of India, contended that the impugned Order made in 1969 fixing a uniform
retention price for all three categories of cement producers treats unequals as
equals. He argued that the fixation of three different retention prices earlier
was based on the Tariff Commis- sion's Report on the postulate that different
.producers were differently situated with different cost of production and
therefore, the fixation of different retention prices for them was reasonable.
He next contended that increase in the cost of production being the real cause
for re-fixation of a higher price, the exercise purports to be under Clause 12
of the Cement Control Order, 1967, which does not permit fixation of the same
price for all producers in spite of the difference in their cost of production,
particularly when the Schedule to the order initially specified different
prices for them. He also contended that on the finding of the High Court that
the Chettinad Cement Corporation Ltd.
(appellant
in Civil Appeal No. 2193 of 1972)--a newly born unit in infancy--has suffered
by this common treatment because there are several features which distinguish
the Chettinad Cement Corporation Ltd. from the other units, fixation of the
same price for this appellant is discrimina- tory, particularly when a
distinction was made in the case of M/s. Travancore Cement Ltd., Kottayam, for
which a higher retention price was fixed. Shri Parasaran, therefore, con-
tended that atleast in the case of this appellant, discrimi- nation is proved
on the basis of the High Court's finding of fact and a direction for
re-fixation of a reasonable price 'for this appellant would be justified. Shri
G.L. Sanghi, learned counsel for the appellant in Civil Appeal No. 2192 of
1972, advanced a slightly modified argument. He too referred to Clause 12 of
the Cement Control Order, 1967 to contend that fixation of one uniform
retention price for all producers is not permissible thereunder. He argued that
the increase of Rs.7 per tonne was to be made to the existing three-tier
retention prices, but an irrational basis was adopted in fixing the uniform
price of Rs. 100 per tonne which results in an unequal increase to the three
different retention prices then existing. Both the learned counsel contended
that the result, therefore, is that whereas pro- ducers for whom the retention
price fixed earlier was Rs.90.50 per tonne have got an increase of more than
Rs.7, the producers for whom the retention price was fixed at Rs.96 per tonne have
been given an increase of less than Rs.7. It was, therefore, contended that
fixation of the uniform retention price of Rs. 100 per tonne in case of all
cement producers except M/s. Travancore Cement Ltd., Kotta- yam, is
discriminatory resulting in contravention of Article 14 of the Constitution.
To
recapitulate, the arrangement in vogue from 1956 was that 856 the cement
produced by all the producers was acquired by the State Trading Corporation
which distributed the commodity throughout the country at a uniform price on f.o.r.
destina- tion basis. The price payable by the S.T.C. to the producers was known
as the 'retention price' or 'ex-works' or 'ex- factory price' at a uniform
rate. On a representation by the industry for revision of prices, the Government
appointed the Second Tariff Commission to go into the question. The Tariff
Commission, after a comprehensive review, submitted its report on 26.8.1961,
and recommended the fixation of different retention prices for different groups
of cement producers. The Government generally accepted the recommenda- tions of
the Tariff Commission and fixed three different retention prices which remained
in vogue till fixation of a uniform retention price by the impugned Order in
1969.
It may
be mentioned that the fixation of three different prices instead of one uniform
retention price in the inter- vening period was challenged before the Rajasthan
High Court on the ground that it was discriminatory, but that challenge was
rejected in Jaipur Udyog Ltd. v. Union of India, AIR 1969 Rajasthan 28 1.
Thereafter,
the cement industry sought a further revi- sion of the prices and the industry
accepted in principle that there should be one uniform retention price or ex-
factory price in place of the three-tier system, though the claim of the
industry was that the uniform price be fixed at Rs.96 instead of Rs.93. The
real controversy, therefore, between the cement industry and the Central
Government was, whether the addition of Rs.7 per tonne for fixation of a
uniform retention price should be made to the sum of Rs.96 or to Rs.93. In
other words, if the uniform retention price were fixed at Rs. 104 per tonne
instead of Rs. 100 per tonne, there was no grievance to anyone in the cement indus-
try against fixation of the uniform retention price. Even at the hearing before
us, in reply to this specific query by us, learned counsel for the appellants
did not dispute that no grievance would survive to the appellants if the
uniform retention price was fixed at Rs. 104 per tonne instead of Rs. 100 per tonne.
In substance, the grievance of both the appellants, therefore, is only to this
extent and the argu- ment of discrimination has been advanced for this purpose.
In the
counter-affidavit filed on behalf of the Central Government, the manner in
which the uniform retention price for the industry was fixed at Rs. 100 per tonne
has been elaborately explained. A portion of the counter-affidavit, relied on
by the High Court also, is as under:
857
"The question of introduction of a uniform price for the entire industry
had been under consideration from time to time since 1961. The opportunity of
the request of the industry for an upward revision of their retention price due
to increase in cost of production as a result of Governmen- tal actions since
1.1.1966, was availed of to consider whether it was not opportune to introduce
finally a uniform price for the entire industry as a Whole. In view of the
observations of the Tariff Commission in 1961 that econo- mies were possible
with better management control and that the industry should make every effort
to reduce its cost of production in future and the time elapsed since 196 1 it
was felt that the additional price granted to the industry in 196 1, need not
any longer be continued. The weighted aver- age increase in the cost of
production as a result of Gov- ernmental actions since 1.1.1966, was determined
in consul- tation with the Chief Cost Accounts Officer as Rs.7 per tonne. The
uniform price thus works out to Rs.90.50 per tome, i.e. Rs.69.50 per tonne
prescribed in '1961 together with subsequent increases amounting in all to
Rs.21. The weighted average retention price on the basis of three different
retention prices amounted to Rs.93 per tonne. The uniform price for the
industry was thus fixed at Rs. 100 i.e. Rs.93 per tonne, the weighted average
of the three retention prices on the basis of actual production plus Rs.7 per tonne,
as a result of the increase in the cost of pro- duction due to Governmental
actions since 1.1.1966. The fixation of a uniform retention price does not
therefore involve any inequality or arbitrariness. It is denied that the Cement
Control (Amendment) Order, 1969, has introduced any unfair and arbitrary
inequality among the various pro- ducers and would cause considerable loss to
the petitioner or would amount to an unjust and arbitrary discrimination violative
of Article 14 or 19(1)(g) of the Constitution of India." The assertion in
the counter-affidavit of the Government is that the industry was itself in favour
of a single uni- form retention price which was taken into account by the
Government in fixing the uniform price. This was not rebut- ted by the
appellants. The High Court has rightly relied on this fact. It is, therefore,
clear that the fixation of Rs. 100 per tonne as the uniform retention price for
the entire industry with the solitary exception of M/s. Travancore Cement Ltd.,
Kotta- 858 yam, for which justification has been shown, was on a ra- tional
basis taking into account all relevant data and factors including the cement
industry's acceptance of the principle of a uniform retention price for the
entire indus- try, the only difference being in the price, actually fixed at Rs.
100 per tonne instead of Rs. 104 per tonne claimed by the cement industry. It
is obvious that the fixation at Rs. 100 per tonne being shows to be made on a
principle which has not been faulted, the actual fixation at Rs. 100 instead of
Rs. 104 to be received by the industry is not within the domain of permissible
judicial review if the principle of a uniform retention price for the entire
industry cannot be faulted, The principles of price fixation permitting the
fixation of a uniform price for the entire industry are no longer debatable
after the recent decision of a Constitution Bench in M/s, Shri Sitaram Sugar
Company Limited & Anr. v. Union of India & Ors., and U.P. Stale Sugar
Corporation Ltd. & Anr. v. Union of India & Ors., JT 1990 (1) SC 462
even if the same were debatable when the controversy arose in the present case.
In this decision, the Constitution Bench while affirming the earlier decisions
of this Court in Anakapalle Co-operative Agricultural & Industrial Society
Ltd. etc.
etc.
v. Union of India & Ors., [1973] 2 SCR 882 and The Panipat Cooperative
Sugar Mills v. Union of India, [1973] 2 SCR 860 reiterated the settled
principles. It was pointed out that what is best for the industry and in what
manner the policy should be formulated and implemented, bearing in mind the
object of supply and equitable distribution of the commodity at a fair price in
the best interest of the gener- al public, is a matter for decision exclusively
within the province of the Central Government and such matters do not
ordinarily attract the power of judicial review. It was also held that even if
some persons are at a disadvantage and have suffered losses on account of the
formulation and implementation of the Government policy, that is not by itself
sufficient ground for interference with the Govern- mental action. Rejection of
the principle of fixation of price unitwise on actual cost basis of each unit
was reiter- ated and it was pointed out that such a policy promotes efficiency
and provides an incentive to cut down the cost introducing an element of
healthy competition among the units. Similarly, the criticism against the
principle of weighted average adopted in fixation of price was rejected as
baseless. It is obvious that even if there be no price control, the uneconomic
units would be at a great disadvan- tage and, therefore, the position should
not be different for the purpose of price fixation. The "cost-plus"
price fixation perpetuates inefficiency in the industry and is against the
long-term interest of the country. It was held "that 859 price, ..... , is
to be arrived at by a process of cost- ing with reference to a reasonably
efficient and economic representative cross-section of manufacturing
units." It is, therefore, clear that the principle of fixation of a
uniform price for the industry is an accepted principle and this has to be done
by fixing a uniform price on the basis of the cost of a reasonably efficient
and economic representative cross-section of manufacturing units and not with
reference to the cost in relation to each unit. Obviously, such a practice is
in larger public interest and also promotes efficiency in the industry
providing an incentive to the uneconomic units to achieve efficiency and to
reduce their cost. In the same decision, the permitted scope of judicial review
was summarised as under:
"The
true position, therefore, is that any act of the repos- itory of power, whether
legislative or administrative or quasi-judicial, is open to challenge if it is
in conflict with the Constitution or the governing Act or the general
principles of the law of the land or it is so arbitrary or unreasonable that no
fair minded authority could ever have made it." In the present case, we
find that the fixation of the uniform retention price at Rs. 100 per tonne is
based on the weighted average increase of Rs.7 in the cost of production and
the weighted average retention price on the basis of three different retention
prices determined at Rs.93 per tonne on the basis of expert opinion. Fixation
of a uniform retention price being clearly permissible and the same having been
determined at Rs. 100 per tonne on the basis of expert opinion, rounded on
relevant factors, there is no scope for interference within the limits of
permissible judicial review in the present case.
A
brief reference to Clause 12 of the Cement Control Order, 1967 may also be
made. Clause 12 reads as under:
"12.
POWER TO VARY THE PRICES AND TO ALTER THE SCHEDULE . The Central Government
may, having regard to any change in any of the factors relevant for the price
of cement, such as an increase or decrease in the cost of production or
distribution, by notification in the Official Gazette, vary the price fixed in
this Order or alter the Schedule to this Order as appear to it to be
necessary." 860 We are unable to appreciate how Clause 12 in any manner
restricts the Central Government's power to fix a uniform retention price for
all the units specified in the Schedule to the Order, even though different
prices were specified in the Schedule as initially enacted. The Central
Government's power to refix the price can be exercised 'having regard to any
change in any of the factors relevant for determination of price of cement'.
The meaning of the expression 'having regard to' is wellsettled. It indicates
that in exercising the power, regard must be had also to the factors enumerated
together with all factors relevant for exercise of that power. Once such factor
specified in Clause 12 is "such as an increase or decrease in the cost of
production or distri- bution". Admittedly, the fixation of the uniform
retention price at Rs. I00 per tonne was made on the industry's demand for
revision of the price as a result of increase in the cost of production, the
only dispute between the industry and the Central Government being with regard
to the extent of increase and not to the effect of increase or the mode of
increase by fixation of a uniform price. It is, therefore, difficult to
appreciate the support that the learned counsel for the appellants seek from
Clause 12.
The
only surviving question for consideration is the argument in Civil Appeal No. 2
193 of 1972 for a differen- tial treatment to the appellant, M/s. Chettinad
Cement Corporation Limited, on the analogy of M/s. Travancore Cement Limited, Kottayam.
In the counter-affidavit of Shri G. Ramanathan, Under Secretary to the
Government of India, the reason for treating Travancore Cement Limited
different- ly has been clearly stated. It has been stated that it is a
sub-standard unit with a capacity of 50000 tonnes per annum only without any
scope for expansion while the standard capacity for a unit is two lakh tonnes
per annum; so that this unit is not capable of expanding the capacity and it is
on the whole an uneconomic unit deserving a special consid- eration. No
material has been produced by the appellant, M/s. Chettinad Cement Corporation
Limited, to show that it is a similar sub-standard unit without any capacity
for expansion, so that it too must continue to be an uneconomic unit like M/s. Travancore
Cement Limited, Kottayam deserving a similar treatment. The counter-affidavit,
therefore, shows a rational basis for classifying M/s. Travancore Cement
Limited, Kottayam, differently as a sub-standard and an uneconomic unit without
any scope for improvement in com- parison to other units. This argument also is
untenable.
As a
result of the aforesaid discussion, we do not find merit in 861 any of the
contentions advanced in support of these appeals to support the challenge on
the basis of Article 14 of the Constitution to the fixation of a uniform
retention price of Rs. 100 per tonne in 1969 by the impugned Order or to the
practice of a uniform retention price being followed upto 1979.
These
appeals are accordingly dismissed. In the circum- stances of the case, the
parties shall bear their own costs.
R.S.S.
Appeals dismissed.
Back