Dandasi
Sahu Vs. State of Orissa [1989] INSC 366 (30 November 1989)
Ramaswami,
V. (J) Ii Ramaswami, V. (J) II Mukharji, Sabyasachi (J)
CITATION:
1990 AIR 1128 1989 SCR Supl. (2) 348 1990 SCC (1) 214 JT 1989 (4) 466 1989
SCALE (2)1234
ACT:
A rbitration
Act, 1940: Sections 30 and 16---A ward not disclosing documentary evidence
considered--Original and supplemental claims not making total claim--Inclusion
of interest amount Award amount disproportonately excessive--Validity
of--Whether amounts to legal misconduct--Non-application of mind.
HEAD NOTE:
The
appellant-contractor claimed a sum of Rs.3,87,796 before the sole arbitrator on
April 5, 1977 for the value of 15 items of works
not paid. To this he added interest to the tune of Rs.2, 95,894 at 18 per cent
from the date which according to him each of the claims should have been
settled, making a total of Rs.6,83,690. He also prayed for further interest at
18 per cent from April
6, 1977 till date of
award and thereafter until payment. The respondent State filed its written
statement and the arbitration proceedings continued for some time. But before
the arbitrator could make an award, an application under ss. 8(2) and 12 of the
Arbitration Act was filed before Subordinate Judge who by his order removed the
arbitrator and appointed another person as the sole arbitrator. The new
arbitrator entered on the reference, got all the records from the previous
arbitrator and continued the hearing. The appellant made a supplemental claim
for a sum of Rs.8,27,857 and also prayed for interest on that amount at 18 per
cent from October 14,
1973 till date of
payment. The respondent State objected to the entertainment of additional
claim. The arbitrator, however, proceeded with the hearing. On November 8, 1981, the day the hearing was closed,
the appellant-contractor filed one consolidated 'abstract' of his two claim
statements showing a total claim of Rs.31.44.437 and also prayed for interest
at 18 per cent per annum from November 9, 1981
till the date of payment.
The
arbitrator made an award on December 7, 1981
allowing a lump-sum of Rs.25,00,156 together with interest at 9 per cent after
the expiry of 30 days from the date of making the award, till the date of
payment or decree whichever was earlier. The award was made a decree of the
court. The court, however, disallowed interest from the date of decree till realisation.
349 On
appeal by the respondent-State the High Court came to the conclusion that the
award was vitiated by non-application of mind amounting to legal misconduct. In
that view, it set aside the award and remitted the matter back to the
Arbitration Tribunal constituted under s. 41A of the Arbitration Act, as
amended by Orissa Act 3 of 1983.
Dismissing
the appeal, the Court,
HELD:
1.1 Though the arbitrator is not bound to disclose as to what interpretation he
has made and what inference he has derived from the documentary evidence, he is
bound to refer in the award that he had considered all the documents placed
before him, no matter whether he relies on them or discards them from
consideration. [353A]
1.2 In
the instant case, the arbitrator in his award ex-facie did not mention that he
had referred to or considered the documents placed before him in respect of the
original claim. The order-sheet mentions about the nearing on different dates
relating to tile supplemental claim statement which was filed before him. It
was this argument in respect of the supplemental claim that has been mentioned
in the award. [353B]
2.1
The arbitrator in case of a reference to him in pursuance of an arbitration
agreement between the parties, being a person chosen by parties is constituted
as the sole and final judge of all the questions and the parties bind
themselves as a rule to accept the award as final and conclusive. Even in a
case where the arbitrator does not give any reason or he commits a mistake
either in law or in fact in determining the matter referred to him and such a
mistake does not appear on the face of the award, the same cannot be assailed.
It could be interfered with only in limited circumstances as provided under ss.
16 and 30 of the Act. The court has, therefore, to test the award with
circumspection.
1354F,
E, G] 2..2 All the same, if the amount awarded is disproportionately high
having regard to the original claim made and the totality of the circumstances,
it would certainly be a case where the arbitrator could be said to have not
applied his mind amounting to legal misconduct. [354G-H] State of Orissa v. Dandasi Sahu, [1988] 4 SCC 12,
referred to.
In the
instant case, in the original claim made before the arbitrator the value of the
work not paid was stated as Rs.3,87,796. The supplemental claim made before the
arbitrator amounted to 350 Rs.8,27,857. Thus, the total value of work not paid,
according to the appellant, was Rs.12,15,653. As against this claim, the
arbitrator had awarded a lump sum of Rs.25,00,156. No doubt, the appellant had
asked for payment of interest and including interest his claim was Rs.31,44,437.
[354H; 355A]
2.3
Where a reference to arbitration was made prior to the commencement of the
Interest Act, 1978 which came into force on August 19, 1981 the arbitrator is
not empowered to grant interest for the period upto the date of submission of
the claim or the period during which the dispute was pending before the
arbitrator, and where the award granted a lump sum amount it shall deem to have
included the interest also if interest had been claimed before the arbitrator
and the inclusion of such interest would render that part of award invalid.
[355B-C] In the instant case, if the interest portion is excluded, then it
becomes evident that award of Rs.25.00,156 suffers from the vice of giving
disproportionately high amount. [355C-D]
2.4
Since the award suffers not merely on the ground that it included interest but
also on the ground of nonapplication of the mind the question of setting aside
only the invalid part relating to the grant of interest does not arise.
[355F-G] State of Orissa v. Niranjan Swain, [1989] 4 SCC
269, distinguished.
CIVIL
APPELLATE JURISDICTION: Civil Appeal No. 4800 of 1989.
From
the Judgment and Order dated 20.3.1987 of the Orissa High Court in Misc. Appeal
No. 453 of 1982.
Anil
B. Divan and Vinoo Bhagat for the Appellant.
G.L. Sanghi
and A.K. Panda for the Respondent.
The
Judgment of the Court was delivered by V. RAMASWAMI, J. Special leave granted.
In
respect of a dispute relating to the work Lankagada Minor Irrigation Project
(Balance Work) in Jagannathaprasad Block which 351 was entrusted to him, the
appellant-contractor, invoking clause 23 of the agreement and section 8 of the
Arbitration Act requested the Chief Engineer, Rural Engineering Organisation, Bhubaneswar, Orissa, to nominate an arbitrator.
It may be mentioned that before making this request for nomination of an
arbitrator the appellant made a claim on 16.6. 1975 before the Executive
Engineer, M.I. Division, Berhampur, Ganjam, claiming to be paid a sum of Rs.2,81,745.
He had also claimed interest on this at the rate of 18 per cent from the date
of receiving of the claim book till payment.
The
work entrusted to the appellant was to commence on 6.12. 1971 and to be
completed within 18 months i.e. on or before 5.6.1973 and the total cost of the
work was Rs.9.98,970. One Shri D.C. Panda, Superintending Engineer, Central Range, was nominated as the sole arbitrator to decide the dispute
and give the award. This arbitrator having accepted the appointment entered on
the reference and issued notices to both the parties directing them to file
their claims. The appellant filed a claim statement on 5.4. 1977 before the
arbitrator.
In
this claim statement he had made a detailed description of each of the items of
the claim and the total of the 15 items claimed came to Rs. 3,87,796. To this
he added interest at 18 per cent from the date which according to him each of
the claims should have been settled making a total claim of interest to the
tune of Rs.2,95,894. He thus prayed for an award of Rs.6,83,690 and also prayed
for further interest on Rs.3,87,796 from 6.4. 1977 till date of award and
thereafter until payment at 18 per cent. It may be mentioned that in this
statement of claim made before the arbitrator some of the claims made before
the Executive Engineer were omitted, some were reduced whereas some new claims
were introduced and some other items of claim were enhanced. The State of Orissa filed a written statement and the
arbitration proceedings continued for some time but before the arbitrator could
make the award an application before the Subordinate Judge, Bhubaneswar was filed under sections 8(2) and
12 of the Arbitration Act. By an order dated 17.12.1979 the learned Subordinate
Judge removed the arbitrator and appointed one Shri J. Pati, Chief Construction
Engineer, Paradip Port as the sole arbitrator to decide the dispute between the
parties. However, since Shri J. Pati expressed his inability to arbitrate, by
another order dated 16.4.1980 the court appointed Shri Banabasi Patnaik,
Superintending Engineer, Sambalpur as the sole arbitrator in place of Shri J. Pati.
This arbitrator entered on the reference, got all the relevant records from the
previous arbitrator continued the hearing on the 9th June and 9th July, 1980.
On the ground that the appellant has not included some of his claims
"relating to this work" in the claim statement submitted to the
previous arbitrator, he made a supplemental claim for a sum of 352 Rs.8,27,857
and prayed that in addition to the claim stated in the original claim statement
a sum of Rs.8,27,857 be awarded in his favour with interest at 18 per cent per
annum on Rs.8.27,857 from 14.10. 1973 till date of payment. The State of Orissa
not only disputed the claim made but also objected to the entertainment of an
additional claim in their written statement dated August 13, 1981. The arbitrator,
however, decided to entertain the supplemental claim and proceeded with the
hearing of the dispute. The supplement claim consisted of 11 items. As seen
from the note papers, the arguments on supplemental claims 1 to 6 were heard on
two different dates and the hearing was adjourned to 8.11. 1981. On that day
arguments in respect of rest of the supplemental claim items were heard and the
hearing was closed. On the same day the appellant-contractor filed what he
termed as one consolidated 'abstract' of his two claim statements and the
abstract showed a total claim of Rs.31,44,437 and he had further prayed in this
that the total amount of Rs.31,44,437 may be allowed along with an interest at
18 per cent per annum on the said amount from 9.11. 198 1 till date of payment.
The arbitrator made an award on 7.12. 1981 allowing a lump sum of Rs.25,00,156
together with interest at 9 per cent after the expiry of 30 days from the date
of making the award, till the date of payment or decree whichever is earlier.
The award was filed in court for making a decree and the Government filed an
application to set aside the award on various grounds. The trial court
overruled the objections of the State and the award was made a decree of the
court. However, learned Judge disallowed the interest from the date of decree
till realisation. On appeal by the State Government, the High Court came to the
conclusion that award suffers from non-application of the mind amounting to
legal misconduct. In that view the award was set aside and the matter was
remitted back to the Arbitration Tribunal constituted under section 41-A of the
Arbitration Act as amended by Orissa Act 3 of 1983. The contractor-claimant has
filed this appeal against this judgment of the High Court.
As is
seen from the award though it refers to getting all the relevant record from
the ex-arbitrator there is no reference to the heating of the parties or
consideration of the documents relating to the original claim made on 6.4.
1977. In the order-sheet it has been mentioned that both parties had agreed
that they had nothing more to add except what had been already given in their
respective claim and counter statement and what had been recorded in the
depositions already made before the previous arbitrator. The reference to
depositions already made is incorrect as it is admitted by both the parties
that no deposition was at all recorded before the previous arbitrator nor 353
there is any record of the previous arbitrator showing such oral evidence was
recorded by him. Neither of the parties adduced any oral evidence before the
new arbitrator. Though the arbitrator is not bound to disclose as to what
interpretation he has made and what inference he has derived from the
documentary evidence, he is bound to refer in the award that he had considered
all the documents placed before him no matter whether he relies on them or
discards them from consideration. The arbitrator in his award ex facie does not
mention that he has referred to or considered the documents placed before him
in respect of the original claim. The order-sheet mentions about the hearing on
different dates relating to the supplemental claim statement which was filed
before him. It is this argument in respect of the supplemental claim that has
been mentioned in the award.
The
other point to be noted. is that the original claim together with the
supplemental claim do not make total claim of Rs.31,44,437. It is seen from the
records that the arbitrator directed the claimant to submit a consolidated
claim abstract which was submitted by him on 8.11. 1981 the date on which the
hearing by the arbitrator was concluded. There is clearly some discrepancy
while consolidating both the claims. In addition to the total of both the
claims some other amounts, may be by way of extra interest or otherwise, have
been included but the arbitrator seem to have not applied his mind. Then again
in the award it is stated that the total amount claimed by the claimantappellant
inclusive of "damages, compensation and interest" is Rs.31,44,437.
Even
the 'abstract' filed before the arbitrator does not show any claim of
"damages" or "compensation". As may be seen from the facts
set out above, before the appellant demanded the appointment of an arbitrator
he had made a claim before the Executive Engineer for a sum of Rs.2.81,745.
This is an iternised claim. This claim was made in the claim book kept by the
Executive Engineer. It may be that this claim did not cover the entire amount
due. We may point out that in the letter demanding the appointment of an
arbitrator he had stated that during the execution of the work he had executed
many extra items of work as per directions of the Department and also incurred
heavy expenditure which were not covered in the agreement and that he had
submitted "most of my claims in the claim book on 16.6.1965 but these have
not yet been decided". It may also be mentioned that in this letter itself
he has stated that he has completed the work in all respects on 14.9.1973 and
that though the final bill which should have been prepared within one month of
the completion of the work has not yet been paid to him. The claim made before
the arbitrator originally as already stated was Rs.6,83,690 of which a sum 354
of Rs.3,87,796 represented the value of the work not paid and the remaining
represented interest claimed. The total agreed value of the work entrusted to
the appellant was Rs.9,98,970. In the counter affidavit filed by the State of Orissa in the special leave petition it is
stated that a total of Rs.23,11,887 had been paid to the appellant contractor
by 20.11. 1976 which was with reference to the original work entrusted and the
extra work done by the appellant.
Arejoinder
was filed by the appellant to this counter affidavit but the fact of payment of
Rs.23, 11,887 is admitted.
The
supplemental claim itself was filed on 10.7.1980 and that amounted to Rs.8,27,857
over and above Rs.6,83,690 which he had claimed originally before the
arbitrator. Then again the 'abstract' filed by him on 8.11.1981 showed a figure
of Rs.31,44,437 as the claim. We have already pointed out that the total of the
claim made on 5.4. 1976 and the supplemental claim made on 10.7. 1980 itself
will not make anyway that figure of Rs.31,44,437 and, therefore, some more
claims have been included. The foregoing facts do show that the award suffers
from non-application of the mind by the arbitrator.
This
Court in State of Orissa v. Dandasi Sahu, [1988] 4 SCC 12 to which one of us (Sabyasachi
Mukharji, J.) was a party while noting that the amount award is quite high or
that a large amount has been awarded does not by itself vitiate the award as
such, observed that one has to judge whether the amount of the award was so
disproportionately high to make it per se bad on the facts and circumstances of
a particular case. In this connection we have to keep in mind that we are
concerned with a situation where the arbitrator need not give any reason and
that even if he commits a mistake either in law or in fact in determining the
matter referred to him, where such mistake does not appear on the face of the
award, the same could not be assailed. The arbitrator, in the case of a
reference to him in pursuance of an arbitration agreement between the parties,
being a person chosen by parties is constituted as the sole and final judge of
all the questions and the parties bind themselves as a rule to accept the award
as final and conclusive. The award could be interfered with only in limited
circumstances as provided under sections 16 and 30 of the Arbitration Act. In this
situation we have to test the award with circumspection. Even with all this
limitations on the power of Court and probably because of these limitations, we
have to hold that if the amount awarded was disproportionately high having
regard to the original claim made and the totality of the circumstances it
would certainly be a case where the arbitrator could be said to have not
applied his mind amounting to legal misconduct. It may be seen that in this
case in the 355 original claim made before the arbitrator the value of the work
not paid was stated as Rs.3,87,796, The supplemental claim made before the
arbitrator amounted to Rs.8,27,857.
Thus
the total value of the work not paid, according to the appellant, was Rs. 12,
15,653. As against this claim the arbitrator has awarded a lump sum of Rs.25,00,156.
It is true that the appellant has asked for payment of interest and including
interest his claim was Rs.31,44,437. In a recent judgment of this Court in
State of Orissa v. Niranjan Swain, [1989] 4 SCC 269 it has been held that where
a reference to arbitration was made prior to the commencement of the Interest
Act, 1978 (which Act came into force on August 19, 198l) the arbitrator is not
empowered to grant interest for the period upto the date of submission of the
claim or the period during which the dispute was pending before the arbitrator.
It was further held that where the award granted a lump sum amount it shall
deem to have included the interest also if interest had been claimed before the
arbitrator and the inclusion of such interest rendered that part of award
invalid. If we exclude the interest portion then there could be no doubt that
award of Rs.25,00,156 suffers from the vice of giving disproportionately high
amount.
The
learned counsel for the appellant, however, contended that the invalid part
relating to the grant of interest may be set aside and the award may be
accepted so far as the claim for the value of the work done applying the
formula adopted in State of Orissa v. Niranjan
Swain, (supra). The learned Judges who decided the case after holding that
inclusion of the interest rendered the award invalid, proceeded to separate the
invalid part from the rest stating that the total amount awarded is principal
plus interest, the rate of interest and the period for which the interest was
claimed before known, the principal could be determined easily, and on that
basis the principal amount and the interest out of the total amount awarded was
divided and the award was sustained relating to the principal. We are unable to
apply this principle in this case as the State had disputed major part of the
claim in their counter statements before the arbitrator and we have held that
the award suffers not merely on the ground that it included interest but also on
the ground of non-application of the mind.
We are
also of the view that there was nothing wrong in the approach of the High Court
and that this is not a fit case for interference under Article 136 of the
Constitution.
We
accordingly dismiss the appeal with costs.
P.S.S
Appeal dismissed.
Back