P.M.
Paul Vs. Union of India [1989] INSC 8 (16 January 1989)
Mukharji,
Sabyasachi (J) Mukharji, Sabyasachi (J) Rangnathan, S.
CITATION:
1989 AIR 1034 1989 SCR (1) 115 1989 SCC Supl. (1) 368 JT 1989 (1) 299 1989
SCALE (1)221
ACT:
Arbitration
Act 1940: Sections 14, 17, 30 and 33--Award-Setting aside of--Whether
arbitrator has miscon- ducted himself or proceedings--Adjudicating upon matter
not subject matter of adjudication-Legal misconduct.
HEAD NOTE:
The
appellant, a contractor entered into a contract with the respondent for the
construction of a building. The contract consisted of two phases. The date of
commencement of both the phases was March 10, 1979, the date of comple- tion of
Phase I was June 9,
1980 and that of Phase
II was November 9, 1980. Dispute arose about the handing
over of the site. The appellant's case was that the site was not handed over as
stipulated and consequently the work could not either be commenced or completed
as stipulated. The respondent asserted that the appellant had abandoned the
work and committed a breach of contract. This was negated by the appellant.
As the
contract provided for settlement of disputes by an arbitrator, the appellant
filed a suit for the appoint- ment of an arbitrator.
The
matter came up in appeal to this Court, and one of its former Judges was
appointed as an arbitrator. The Arbi- trator entered upon the reference,
examined the documents, heard the parties, considered the evidence, and made an
award after inspecting the sites.
The
respondent aggrieved by the award filed a petition and contested the same. It
was contended that the arbitrator had travelled beyond his jurisdiction in
awarding a sum of Rs.2 lakhs as escalation cost and charges in respect of claim
I.
Disposing
of the Civil Miscellaneous Petition the Court,
HELD:
1. It is well-settled that an award can only be set aside under section 30 of
the Arbitration Act, if the Arbitrator has misconducted himself or the
proceeding. [121C-D] 116
2.
Adjudicating upon a matter which is not the subject- matter of adjudication, is
a legal misconduct for the Arbitrator. [121D]
3.
Escalation is a normal incident arising out of gap of time in this inflationary
age in performing any contract.
[121F]
In the instant case, the dispute that was referred to the arbitrator was, as to
who was responsible for the delay, what are the repercussions of the delay in
completion of the building, and how to apportion the consequences of the
responsibility. After discussing the evidence and the sub- mission of the
parties to the contract, the arbitrator, found that it was evident that there
was escalation and, therefore, he came to the conclusion that it was reasonable
to allow 20% of the compensation under claim I, he accord- ingly allowed the
same. This was a matter which was within the jurisdiction of the arbitrator,
and the arbitrator had not misconducted himself in awarding the amount as he
has done. [121D-E, G-H; 122A]
4.
Once It was found that the arbitrator had jurisdic- tion to find that there was
delay In execution of the con- tract due to the conduct of the respondent, the
respondent was liable for the consequences of the delay, namely, in- crease in
prices. [122C-D]
CIVIL
APPELLATE JURISDICTION:: Civil Miscellaneous Petition No. 265 19 of 1988.
IN
Civil Appeal No. 2632 of 1987.
From
the Judgment and Order dated 10.6.1985 of the Kerala High Court in W.P. No. 210
of 1985 in O.P. No. 897 of 1984.
Mrs.
Baby Krishnan for the Appellant.
A.K. Srivastava
and C.V.S. Rao for the Respondent.
The
Judgment of the Court was delivered by SABYASACHI MUKHARJI, J. This is an
application for making the award dated 17th February, 1988 passed by Mr V. Khalid, a former
Judge of this Court, in a dispute referred to him by this Court's order dated 6th October, 1987, final and to give consequential
directions thereupon.
117 On
7th April, 1979 there was a contract for
construction of the building in question. The contract consisted of two phases.
The date of commencement of both the phases was 10th March, 1979: the date of completion of phase-l was 9th June, 1980 and for phase-Il 9th November, 1980. The dispute arose about the
handing over of the site. According to the appel- lant, the site was not handed
over to him as agreed upon and therefore, the work could not either be
commenced or com- pleted as stipulated. He, therefore, accused the respondent
of obstructionist tactics also. According to the respondent, however, the
claims put forward by the appellant were imagi- nary excuses to gain time and
that he put forward various demands for extension of time and for payment of compensa-
tion to which he was not entitled.
Clause
70 of the general conditions of the contract provided for settlement of
disputes by arbitration. The appellant resorted to this clause and addressed a
letter dated 13th September, 1980 to the Chief Engineer, South West Zone,
Cochin, informing him that if the said disputes were not settled to his
satisfaction within 15 days from the date of receipt of the notice, he would be
taking appropriate steps to refer the disputes to arbitration in accordance
with the said clause. This request of the appellant was turned down by the
Chief Engineer, as according to him, work was in progress and the question of
granting reasonable extension of time was under examination. Dissatisfied with
this, the appellant took the matter to the Engineer-in-Chief by his letter
dated 14th October,
1980 calling upon him
to appoint an Engineer Officer as the sole arbitrator to adju- dicate upon the
disputes between the parties. This request was not acceded to. The relationship
between the parties became strained.
The
respondent asserted that the appellant had abandoned the work and committed
breach of contract. Thereafter, the appellant vide a notice dated 4th October, 1982 called upon the Engineer-in-Chief
to appoint an Engineer Officer as the sole arbitrator. After further
correspondence, the Engineer-in-Chief by his letter dated 9.6.1983 appointed
one Mr. K.C.S. Rao, Chief Engineer, Poona Zone, as the arbitra- tor in respect
of the disputes. Mr Rao, it is asserted, entered into reference. The appellant
asserted that Mr Rao was incompetent to function as arbitrator for it was he
who had terminated the contract when he was officiating as the Chief Engineer
of Sought West Zone.
Aggrieved
by this appointment, he filed a suit in the Court of Subordinate Judge, Cochin, seeking leave to revoke the
authority of the appointed arbitrator under section 5 of the Arbitration Act.
118
(hereinafter referred to as 'the Act'), and for appointment of another person
as arbitrator under section 12 of the Act.
It is
not necessary to set out the various stages of litiga- tion thereafter.
Ultimately, the matter came to this Court and by an order passed by this Court
on 25th August, 1987 in Civil Appeal No. 2632/87, it was observed as follows :--
"Having regard to the facts and circumstances of the case, we are of the
opinion that all the disputes mentioned in the Paper Book be arbitrated by a
former retired Judge of this Court. We accordingly appoint Mr. Justice v. Khalid
(Retd.) a former Judge of this Court, as the Arbitrator. The Arbitrator will
decide his remuneration as he thinks fit and the parties will pay the same in
equal shares. The parties will also bear the costs and charges of holding the
proceedings including the remuneration and other assistance of Stenogra- phers
etc. Councel for both the parties have no objection to the aforesaid order. The
learned Arbitrator will enter into reference within a fortnight from the
receipt of the copy of the order and will make the award within four months
thereafter. Costs of the parties in the Arbitration proceedings will abide by
the decision of the Arbitrator".
The
arbitrator entered upon the reference, examined the documents, heard the
parties and considered the evidence. He made his award after inspecting the
sites on 20th December,
1987 and 21st January, 1988. The claims of the appellants
contractor were as follows:
"1.
On account of losses caused due to increase in prices of materials and cost of labour
and transport during the extended period of contract from 9.6.80 work for under
phase I and from 9.11.80 for work under phase-II. 5,47,612.15
2. On
Account of work done under the contract including fully executed and partly
executed items at the origi- nally agreed rates and for the cost of materials
lying at site and taken over by the Department as well as for the value of
machinery, tools and plants lying over the site and taken over by Department. 7,27,095.01
3. On
account of losses caused due to added and infructuous expenditure on overheads,
establishments, and 119 supervision during the extended period of contract upto
3.12.81, the date of termination. 1,28,864.00
4. On
account of losses caused by way of gains prevented due to unlawful repudiation
of the contract by the Depart- ment and the consequent termination of the
contract by the contractor. 1,04,424.58
5. (a)
Release of Bank Guarantee for Rs. 1,25.000 (Bank Guarantee No. G/19/80 dated
28.4.80 issued by the State Bank of India, Willingdon Island, Conchin-3).
(b)
Refund of the retention amounts recovered by the Department from the Running
Account Bills. Amount not indicated 6.Interest on all the amounts due and
payable. @18% PA from 9.12.81 till actual date of payment or realisation".
The
claims on behalf of the respondent, were as under:
"1.
Excess cost which had to be borne by the Department 19,16,198.82 on account of
the defaults of the contractor and subsequent cancellation of the contract
after adjusting other amounts due from the contractor under this contract.
2.
Cost of reference to Arbitration 7,000.00" The arbitrator by his award
asked the respondent to pay the following:
"(a)
On claim No. I, a sum of Rs.2,00,216.18 with interest at 10% from 9.12.1981
till the date of this Award.
(b) On
claim No. 11, a sum of Rs.2,47,269.69 with interest at 10% from 9.12.1981 till
the date of this Award.
(c)
Claim No. III--Disallowed.
(d)
Claim No. IV--Disallowed.
(e) On
claim No. V(a), the respondent is directed to 120 refund the Bank Guarantee sum
of Rs. 1,25,000 to the Cliamant with interest at 10% from the date of the
encashment till the date of this Award.
II.
The remuneration of the Arbitrator is Rs.75,000. Rs.50,000 has already been
deposit- ed. The claimant and the Respondent are di- rected to. remit the
balance equally (Rs. 12,5000 each) to the Arbitrator to his Madras address by
Account payee Draft within two weeks of receipt of the notice under Section 14
of the Arbitration Act, 1940.
11I. The
respondent is directed to pay to the Claimant by way of cost Rs. 17,500 to-
wards Arbitrator's remuneration and Rs. 10,000 towards Advocates' fees and
cost.
IV.
The respondent is directed to suffer their cost.
V. The
counter claims preferred by the Re- spondent against the Claimant are
disallowed." A petition was filed on behalf of the respondent, where- in
it was stated as follows:
"Regarding
petitioner's claim No. 1, in the absence of any escalation clause, it is not
permissible to the Arbitrator to grant any escalation price as sought by the
petitioner.
On the
other hand, if the work is not complet- ed within the specified time, he has
got right to ask for extension of time. Failure to grant extension of time, the
contractor can claim difference of prices. That is not the case here. Extension
of time was granted and the Arbitrator after considering the contentions
put-forth before him has granted 20% of the escalation price which is not in
accordance with the terms of the contract. Though the term of the contract
envisages that the entire site should be handed over in-time for comple- tion
of the work entrusted to him as referred to above in civil works before
starting of the work, the contractor is required to put up some preliminary
work like construction of temporary store sheds, temporary office which requires
sometime and within that time if the other area or the site is not handed over
the contractor has got grievances to complain against the Department. Further,
by not hand- ing over the site how much damage or loss is sustained has not
been 121 apprised off. Therefore, it is submitted that Claim No. 1 of the
Contractor should have been considered as outside the scope of the con- tract
and hence the arbitrator has exceeded his jurisdiction." Mr Ashok Srivastava,
counsel appearing for the Union of India, submitted before us that this is a
reasoned award and the learned arbitrator had granted a sum of Rs.2 lakhs as
escalation charges and costs. Mr Srivastava tried to urge that the right to get
escalation charges and costs in the absence of escalation clause was not a
matter referred to the arbitrator. In other words, it was urged that the arbi- trator
had travelled beyond his jurisdiction in awarding the escalation cost and
charges. It is difficult to accept this objection for reason more than one.
It is well-settled
that an award can only be set aside under section 30 of the Act, which enjoins
that an award of an arbitrator/umpire can be set aside, inter alia, if he has misconducted
himself or the proceeding. Adjudicating upon a matter which is not the subject-matter
of adjudication, is a legal misconduct for the arbitrator. The dispute that was
referred to the arbitrator was, as to who is responsible for the delay, what
are the repercussions of the delay in com- pletion of the building and how to
apportion the conse- quences of the responsibility. In the objections filed on
behalf of the respondent, it has been stated that if the work was not completed
within the stipulated time the party has got a right for extention of time. On
failure to grant extension of time, it has been asserted, the contractor can
claim difference in prices.
In the
instant case, it is asserted that the extension of time was granted and the
arbitrator has granted 20% of the escalation cost. Escalation is a normal
incident arising out of gap of time in this inflationary age in performing any
contract. The arbitrator has held that there was delay, and he has further
referred to this aspect in his award. The arbitrator has noted that Claim I
related to the losses caused due to increase in prices of materials and cost of
labour and transport during the extended period of contract from 9.5. 1980 for
the work under phase I, and from 9.11.80 for the work under phase II. The total
amount shown was Rs.5,47,618.50. After discussing the evidence and the sub-
missions the arbitrator found that it was evident that there was escalation
and, therefore, he came to the conclusion that it was reasonable to allow 20%
of the compensation under Claim I, he has accordingly allowed the same. This
was a matter which was within the jurisdiction of the arbitrator and, hence,
the arbitrator had not mis- 122 conducted himself in awarding the amount as he
has done.
It was
submitted that if the contract work was not completed within the stipulated
time which it appears, was not done then the contractor has got a right to ask
for extension of time, and he could claim difference in price.
This
is precisely what he has done and has obtained a por- tion of the claim in the
award. It was submitted on behalf of the Union of India that failure to
complete the contract was not the case. Hence, there was no substance in the
objections raised. Furthermore, in the objections raised, it must be within the
time provided for the application under section 30 i.e., 30 days during which
the objection was not specifically taken, we are of the opinion that there is
no substance in this objection sought to be raised in opposi- tion to the
award. Once it was found that the arbitrator had jurisdiction to find that
there was delay in execution of the contract due to the conduct of the
respondent, the respondent was liable for the consequences of the delay,
namely, increase in prices. Therefore, the arbitrator had jurisdiction to go
into this question. He has gone into that question and has awarded as he did.
Claim
I is not outside the purview of the contract. It arises as an incident of the
contract and the arbitrator had jurisdiction. In that view of the matter the
objections raised against the award, cannot be sustained. No other objection
was urged before us. The award, therefore, must be made the rule of the Court
and there will be a decree in terms of the award, and the respondent is
directed to pay Rs. 17,500 as the arbitrator's remuneration and Rs. 10,000 as
advocates' fees and costs.
The
Civil Miscellaneous Petition is disposed of accordingly.
N.V.K.
Petition disposed of.
Back