State of
Madhya Pradesh & Ors Vs. Orient Paper Mills
Ltd. [1989] INSC 373 (7
December 1989)
Punchhi,
M.M. Punchhi, M.M. Rangnathan, S.
CITATION:
1989 SCR Supl. (2) 436 1990 SCC (1) 176 JT 1989 (4) 495 1989 SCALE (2)1290
ACT:
Administrative
Law: Promissory estoppel--Industrialists generating power through their own new
generating sets--Assurance given by Government--Electricity duty
exemption--Effect of.
Constitution
of India, 1950: Article 136--Interference
with factual findings--Only in exceptional cases.
Madhya
Pradesh Electricity Duty Act, 1949: Section 3-B-Electricity
duty--Exemption--Notification--High Court granting relief without ordering
issuance of notification--Whether amounts to transgression.
HEAD NOTE:
In its
industrial policy, the State Government declared on 1.8.1961 that where power
has to be generated by industrialists themselves, exemption from electricity
duty would be granted for a period of five years from the date of plant goes
into production, and that the concession would be applicable only to new
generating sets installed during the Third Plan period.
The
Respondent indicated to the Government on 3.5.1955 that about 5000 K.W. of
electricity would be required by it to run its paper plant and that it would by
itself make arrangements for obtaining the necessary generating equipment. It
also applied for import licence for the import of a production plant as also a
power plant to run it. The import licence was granted and the Respondent
started negotiation with the foreign supplier. Since the price had gone up it
was rather impossible for the Respondent to import both the production plant
and the power plant, and if the power plant was not purchased along with the
production plant, it would make the project unsound. Hence the Respondent was
in two minds whether to have the power plant or not. Meanwhile, the above said
industrial policy was announced and the Respondent on installation of the power
plant was able to start its production w.e.f. 16.2.1965.
Thereafter
to formalise the matter, the Respondent corresponded 437 with the appellant for
the grant of the requisite exemption, which was rejected, and the Respondent
approached the High Court by way of a petition under Articles 226 and 227 of
the Constitution of India. The High Court held that the Petitioner was entitled
to invoke the doctrine of promissory estoppel in order to claim exemption from
payment of electricity duty for a period of five years from 16.2.1965 in terms
of the assurance of the State Government dated 1.8.1961.
Against
this order of the High Court the State has come in appeal by Special Leave.
On
behalf of the appellant-State it was urged that there was no occasion to invoke
the doctrine of promissory estoppel, since the Respondent had not in any manner
acted on the assurance of the Government to its own prejudice but on its own it
was taking steps to set up a generating plant much before the industrial policy
was announced.
Dismissing
the appeal, this Court,
HELD:
1. Whether the respondent was of one mind right from the beginning to set up a
power plant, with or without the assurance of the State Government dated
1.8.1961, as asserted by the State, is neither borne out nor is the view of the
High Court arrived at from the record. On the contrary, the view taken is that
the respondent's indecision in that regard ended and it became decisive on the
announcement of the assurance dated 1.8.1961. Such view of the High Court was a
possible view to be taken on the material placed before it and the inference
drawn there from could be that the respondent had acted on the basis of the
assurance. [441E-F]
2.
This Court ordinarily does not interfere with factual findings arrived at by
the High Court and this case has not been shown to be an exception. The view
taken by the High Court was unexceptional warranting it to be left uninterferred
with. [441F]
3.
Without commanding the State Government to issue such a Notification, the High
Court has granted relief to the respondent to which there was no bar.
Accordingly no provision of Madhya Pradesh Electricity Duty Act, 1949 or any
other law can be said to have been transgressed. [442A]
CIVIL
APPELLATE JURISDICTION: Civil Appeal No 498 of 1975.
438
From the Judgment and Order dated 31.7.1974 of the Madhya Pradesh High Court in
Misc. Petition No. 3 16 of 1973.
Prithvi
Raj, Satish K. Agnihotri and Ashok Singh for the Appellants.
Shankar
Ghosh, Vivek Gambhir and Parveen Kumar for the Respondent.
The
Judgment of the Court was delivered by PUNCHHI, J. This is an appeal by special
leave against the judgment and order of the High Court of Madhya Pradesh at Jabalpur
whereby the petition under Articles 226 and 227 of the Constitution of India
preferred by Orient Paper Mills Ltd., the sole respondent herein, was allowed
and sequally the order dated 15.3.1973 of the State Government declining to
grant the respondent exemption from payment of electricity duty for the period
from 16.2.1965 to 15.2.1970 and pursuant demand notices dated 20.3.1973 and
3.4.1973 were quashed. The aggrieved State of Madhya Pradesh and its concerned
Officers are the appellants challenging the same The respondent had need to go
to the High Court to have an assurance dated 1.8.1961 regarding exemption from
payment of electricity duty given by the State of Madhya Pradesh in its
declared industrial policy observed, which may well be reproduced here at the
outset:
"Where
power has to be generated by industrialists themselves, exemption from
electricity duty shah be granted for a period of five years from the date of
plant goes into production. The concession shall be applicable only to new
generating sets installed during the Third Plan period." Factually it was
not disputed before the High Court, that the case of the respondent squarely
fall within the scope of the assurance reproduced above since the industrial
plant of the respondent had gone into production w.e.f. 16.2.1965, the
generating set put up was new, and had been installed during the Third Plan
period. To formalise the matter, the respondent had corresponded with the
Government for the grant of the requisite exemption. Since the same was
rejected and demands for payment of electricity duty created, the High Court
was requested to issue suitable writs, directions and orders cancelling the 439
aforesaid orders and demand notices and granting exemption from payment of
electricity duty in respect of electricity self-generated by the respondent
during the said period of five years, and also commanding the State to carry
out the assurance and promises made in the said industrial policy dated
1.8.1961 extracted above and then requiring the State to issue a Notification
under Section 3-B of the Madhya Pradesh Electricity Duty Act, 1949 granting
exemption or exception to the respondent from payment of electricity duty and
other allied consequential reliefs.
Before
the High Court voluminous documentary evidence was given by the parties in
support of their respective pleadings. The High Court, on consideration of the
entire material placed before it, spelled out a promissory estoppel in favour
of the respondent and concluded as follows:
"To
conclude, we are of opinion that the petitioner is entitled to invoke the
doctrine of promissory estoppel in order to claim exemption from payment of
electricity duty for a period of five years from 16.2.1965 to 15.2.1970 in
terms of the assurance of the State Government, dated 1.8.1961. Of course, as
indicated earlier it is not for us to issue any writ directing the State
Government to grant the petitioner exemption in terms of S. 3-A (vii) or
Section 3-B of the M.P. Electricity Duty (Amendment) Act, 1949. But in view of
the unambiguous and unequivocal assurance given by the State Government on
1.8.1961 we can certainly quash the order of the State Government, dated
15.3.1973 as also the demand notices, dated 20.3.1973 (Petitioner's
Annexure-48) and dated 3.4.1973 (Petitioner's Annexure 50) and leave the matter
at that. It would be for the Government to work out its own course of action on
that basis. ' ' Mr. Prithvi Raj, learned counsel for the appellant urged that
on the facts and circumstances of the case there was no occasion to invoke the
doctrine of promissory estoppel. It was asserted that though the industrial
policy was published by the State Government on 1.8.1961 containing the assurance
extracted above, the respondent had not in any manner acted thereon to its own
prejudice, but had rather on its own been taking steps to set up a generating
plant much before the industrial policy was announced and had factually set up
the generating plant as per its earlier resolve. The facts highlighted were
that the 440 respondent Paper Mill, had been set up at Amlai in Vindhya
Pradesh, when a Part-C State under the administration of the Central Government. It had
in its application dated 3.5. 1955 to the Government indicated that about 5000
K.W. electricity would be required by it to run its paper plant and.
it
would by itself make arrangements for obtaining the necessary generating
equipment. It appears that the State Government had at that time its oven
project in view for installing a power plant. On that basis some correspondence
ensued between the respondent and the State Government with regard to its
annual requirement of electricity. That exercise was abandoned for some reasons
which are not relevant here. Thereafter the respondent applied for import licence
for the import of a production plant as also a power plant to run it. The
respondent was granted an import licence on the strength of which it started
negotiation with an American supplier. While negotiations were in process the
American supplier increased the price. It became impossible for the respondent
to import the production plant and the power plant within the funds allotted to
it by the World Bank and in these circumstances, the American suppliers advised
the appellant to drop procurement of the power plant. At the same time the
American supplier warned the respondent that if the power plant was not
purchased along with the production plant, it would make the project unsound and
it would not be able to fulfil its guarantees as desired by the respondent. The
respondent in these circumstances became of two minds, whether to have the
power plant or not. When it was in that state of mind, the industrial policy
was announced by the Government on 1.8.1961. Thereafter, on 21.8.1961, the
respondent applied to the Government of India for sanction of permission to
import 3.5 million dollar worth goods more than the sanctioned amount. Finally,
the respondent with the consent of the Government of India and with the aid of
the World Bank was able to import the production plant and the power plant and
after its installation was able to go on production w.e.f. 16.2.1965.
The
course of the events set out earlier were not disputed as such by the appellants
before the High Court but it was maintained as now before us, that the
respondent would have on its own gone on to install the power plant even
without the announcement of the industrial policy dated 1.8.1961. Additionally,
it was maintained, in the like manner, that the respondent had not acted to its
prejudice on the basis of the aforesaid assurance dated 1.8.1961 and so that
doctrine of promissory estoppel was not invokable.
The defence
of the State thus raised was rejected by the High Court in the following words:
441
"We have already dealt with that aspect earlier and we have already held
that the petitioner's action in setting up a power plant was postponed on
account of certain circumstances and ultimately on the advise of the
manufacturers who refused to continue the guarantee, the petitioner decided to
set up its own power plant. In the meantime, the assurance of the State
Government, dated 1.8.1961 had already been given and the petitioner's action
in making a final decision to set up its own power plant can be directly
connected with the State Government's assurance dated 1.8. 1961.
No
sooner the petitioner took the final decision in that behalf, it applied to the
State Government for grant of an exemption, although that application was
premature, because the petitioner's paper mill had not started functioning. As
such, the petitioner would certainly be entitled to claim exemption in terms of
the assurance of the State Government dated 1.8.1961 with effect from the date
the paper mill started functioning, namely, 16.2.1965 and the exemption would
last for a period of five years upto 15.2. 1970." Whether the respondent
was of one mind right from the beginning to set up a power plant, with or
without the assurance of the State Government dated 1.8.1961, as asserted by
the State, is neither borne out nor is the view of the High Court arrived at
from the record. Rather, on the contrary, the view taken is that the
respondent's indecision in that regard ended and it became decisive on the announcement
of the assurance dated 1.8.1961. Such view of the High Court was a possible
view to be taken on the material placed before it and the inference drawn therefrom
could be that the respondent had acted on the basis of the assurance. The
effort here to re-do the exercise in this regard must inevitably fail, for this
Court ordinarily does not interfere with factual findings arrived at by the
High Court and this case has not been shown to us to be an exception. In this
situation, the view taken by the High Court was unexceptional warranting it to
be left uninterferred with.
Some
attempt was made by learned counsel for the appellant to contend that the
doctrine of promissory estoppel could not be pressed into service to command
the State Government under Section 3-A (vii) (before its amendment) and Section
3-B of the Madhya Pradesh Electricity Duty Act, 1949 (as amended) to issue a
Notification exempting the respondent from payment of electricity duty. The 442
answer to this argument is available in the conclusion arrived at by the High
Court extracted above. Without commanding the State Government to issue such a
Notification, it has granted relief to the respondent to which there was no
bar. Accordingly, no provision of Madhya Pradesh Electricity Duty Act, 1949 or
any other law can be said to have been transgressed. We thus reject this
argument too.
Thus
for the foregoing reasons this appeal fails and is hereby dismissed. No costs.
Back