Continental
Construction Co. Ltd. Vs. State of Madhya Pradesh [1988] INSC 63 (7 March 1988)
Mukharji,
Sabyasachi (J) Mukharji, Sabyasachi (J) Rangnathan, S.
CITATION:
1988 AIR 1166 1988 SCR (3) 103 1988 SCC (3) 82 JT 1988 (2) 95 1988 SCALE (1)721
CITATOR
INFO : RF 1988 SC2018 (10)
ACT:
Arbitration
Act, 1940-Whether a contractor can claim extra cost and compensation towards
rise in prices of material and labour on account of delay on the part of other
party to contract in discharge of its obligations and allotment of work under
the contract and invoke arbitration clause in contract and ask for a reference
to arbitrator under section 20-Of.
HEAD NOTE:
% The
petitioner in this application under Article 136 of the Constitution entered
into a contract with the respondent State for construction work. The contract
could not be completed within the stipulated time because of alleged gross
delay on the part of the State in allotment of work and discharge of its
obligations under the contract. The petitioner incurred unforeseen expenditure
and approached the Superintending Engineer for payment. Upon refusal of the
Superintending Engineer to pay and also to refer the matter to arbitration, the
petitioner moved the District Judge under Section 20 of the Arbitration Act,
('the Act') for the filing of the arbitration agreement and for reference of
the dispute to arbitration. The District Judge directed the respondent State to
file the agreement, and made a reference for specific question to the
arbitration. The High Court dismissed the State's appeal against the order of
the District Judge. Thereafter, an arbitrator was appointed, who made an award
partly allowing the petitioner's claim. The award was filed in the Court of the
District judge, who made the award a rule of the court. The respondent appealed
to the High Court. The High Court remanded the matter to the District Judge for
a fresh decision. The District Judge accepted the respondent's objections and
set aside the award. The High Court dismissed the appeal of the petitioner. The
petitioner then moved this Court for relief by this petition for special leave.
Dismissing
the petition, the Court, ^
HELD:
The District Judge rightly found that the question regarding extra-cost was a
general question and not a specific legal question and the decision of the
arbitrator was not final. The arbitrator 104 misconducted himself in allowing
the claim without deciding the objection of the State. In view of the specific
clauses, the petitioner was not legally entitled to claim for extra- cost. The
decision of this Court in Seth Thawardas v. Union of India, [1955] 2 SCR 48 was
of no avail on this point. If no specific question of law is referred, the
decision of the arbitrator on that question is not final however much it may be
within his jurisdiction and indeed essential for him to decide the question
incidentally. The arbitrator is not a conciliator and cannot ignore the law or mis-apply
it in order to do what he thinks is just and reasonable. The arbitrator is a
Tribunal selected by the parties to decide their disputes according to law and
so he is bound to follow and apply the law, and if he does not, he can be set
right by the Court provided his error appears on the face of the award. In this
case, the contractor having contracted, could not go back to the agreement
simply because it did not suit him to abide by it. [111C-F] The petitioner had
argued that since specific issues had been framed and referred by the District
Judge to the arbitrator, the same had been answered by a non-speaking award and
there was no mistake of law apparent on the face of the record, and the
District Judge had erred in setting aside the award by looking into the terms
of the contract which neither formed part of the award nor were appended to it.
The Court did not agree. This being a general question, the District Judge
rightly examined the question and found that the petitioner was not entitled to
claim for extra cost in view of the terms of the contract, and the arbitrator
misdirected himself by not considering this objection of the State before
giving the award. [112B-C] The limits of the jurisdiction of the Court to
challenge the award are well-settled. While considering the objection under
section 30 of the Act, the Court does not act as an appellate Court; it can
only interfere with the award if the arbitrator misconducts himself or the
proceedings or if the award has been made after the issue of an order by the
Court superseding the arbitration or if the arbitration proceedings have become
invalid under section 35(c) of the Act, or the award has been improperly
procured or is otherwise invalid. If, a specific question is submitted to the
arbitrator and he answers it, the fact that the answer involves an erroneous
decision in point of law, does not make the award bad on its face so as to
permit it being set aside. [112E-F; 1l3A] The High Court was right that the
District Judge was entitled to examine the contract in order to find out the
legality of the claim of the petitioner regarding extra cost towards rise in
prices of material and 105 labour. Clauses 2.16 and 2.4 stipulated that the
contractor had to complete the work inspite of rise in prices of materials and
also rise in labour charges at the rates stipulated in the contract. There was
a clear finding of the arbitrator that the contract was not rendered
ineffective in terms of section 56 of the Contract Act due to the abnormal rise
in prices of materials and labour. This being so and the contractor having
completed the work, it was not open to him to claim extra cost towards rise in
prices of material and labour. The arbitrator misdirected himself in not
deciding this specific objection raised by the State regarding the legality of
the extra claims of the petitioner. It has to be born in mind that there were
specific clauses which barred consideration of extra claims in the event of
price escalation. [113D-F; 114B] The award was properly set aside by the
District Judge and the High Court was right in the view it took and there was
no ground to interfere. [113G] Seth Thawardas v. Union of India, [1955] 2 SCR
48; M/s Alopi Parshad v. Union of India, [1960] 2 SCR 793; Kapoor Nilokheri
Co-operative Dairy Farm Society Ltd. v. Union of India, A.I.R. 1973 S.C. 1338; Champsey
Bhara and Co. v. Jivraj Balloo Spinning and Weaving Co. Ltd., A.I.R. 1923 P.C.
66; Re. King and Duveen, [1913] 2 K.B. 32; Government of Kelantan v. Duff
Development Co. Ltd., [1923] AC 395; Bungo Steel Furniture v. Union of India, [1967]
1 SCR 633; Saleh Mohd. v. Nathoo Mal, 54 I.A. 427; Abosalom Ltd. v. Great
Western, [1933] A.C. 592; Allen Berry & Co. v. Union of India, [1971] 3 SCR
282 and Tarapare and Company v. Cochin Shipyard Ltd., Cochin and Anr.,[1984] 2 S.C.C. 680,
referred to.
CIVIL
APPELLATE JURISDICTION: Special Leave Petition (Civil) No. 13180 of 1985.
From
the Judgment and order dated 17.4.1985 of the Madhya Pradesh High Court in
Misc. F.A. No. 252 of 1981.
S.N. Kacker
and R. Ramachandran for the Petitioner.
The
Judgment of the Court was delivered by SABYASACHI MUKHARJI, J. This is an
application under Article 136 of the Constitution for leave to appeal to this
Court from the judgment and order of the High Court of Madhya Pradesh dated 17th April, 1985. In order to appreciate the points
involved, it is neces- 106 sary to state that the petitioner entered into a
contract dated 31st
March, 1970 with
respondent, State of Madhya
Pradesh for the
construction of Rip Rap on right bund of Masonary Dam of Tawa Project. The
contract could not be completed within the stipulated time because of alleged
gross delay on the part of the State, according to the petitioner, in allotment
of work and discharge of its obligations under the contract. The petitioner
incurred unforeseen expenditure, it is claimed, to the tune of Rs.5,29,812 and
approached the Superintending Engineer for payment. Upon refusal of the
Superintending Engineer to pay the claim and his refusal to refer the matter to
arbitration, the petitioner moved the learned District Judge under section 20
of the Arbitration Act, 1940 (hereinafter called 'the Act') for filing of the
arbitration agreement and for reference of the disputes to the arbitration. On 24th April, 1976 the learned District Judge allowed
the petitioner's application and directed the respondent, State of Madhya Pradesh to file the agreement in Court and
made a reference for specific question to the arbitration. The High Court on 22nd September, 1976 dismissed the State's appeal
against the order of the District Judge. Thereafter in March, 1977 Retired
Engineer-in-Chief, P.W.D. Bhopal was appointed arbitrator. There was an award
dated 29th October,
1978 on all the issues
referred, partly allowing the petitioner's claim. The award was filed in the
Court of the District Judge and the respondent filed objections to the award
under sections 30 and 33 of the Act and the petitioner filed replies. The
District Judge made the award a rule of the Court. The respondent appealed to
the High Court. The High Court remanded the matter to the District Judge for
fresh decision. The District Judge accepted the objections and set aside the
award. The High Court by the impugned judgment dismissed the appeal of the
petitioner. It is from this judgment of the High Court that the petitioner
seeks leave to appeal to this Court.
As mentioned
hereinbefore by the impugned judgment and order of the High Court the award has
been set aside. The agreement contained an arbitration clause. The work,
however, could not be completed within the stipulated time, the period of
contract was extended. The contractor attributed delay on the part of the State
Government whereas the State Government blamed the contractor. This was a
disputed question. While the work was in progress, the contractor was required
to meet extra expenditure on labour charges and materials due to revision in
wage scales and escalation of prices. Alterations and substitutions of works
also led to extra expenses. There were certain items for which rates were not
provided but all the same work had to be done. The contractor therefore,
advanced claims 107 for compensation. The Superintending Engineer dismissed the
claims on the ground that the claims were barred under clause 3.3.15. He also
held that some of the claims were not covered by the contract. The contractor
sought to invoke the arbitration clause but the State sought to oppose on the
ground that the dispute attracting the arbitration clause had not arisen. It
was contended that the claim was barred by clause 3.3. 15 and it had not been
made within the time.
It was
contended further that there was only one contract and there being no separate
agreement for extension of period of the contract the rate as provided in the
original contract alone was permissible. As there was no separate contract and
no reference under clause 3.3.29 could be made for the enhanced period beyond
the period of the contract.
Relevant
clauses of the contract were as follow:
"3.3.15
Clause 15. Time limit for unforseen claims: Under no circumstances whatever
shall the contractor be entitled to any compensation from Government on any
account unless the contractor shall have submitted claim in writing. to the
Engineer-in-Charge within one month of the cause of such claim occurring.
3.3.29
Clause 29.
Decision
of Superintending Engineer, to be final except where otherwise specified in the
contract. The decision of the Superintending Engineer of the Circle for the
time being shall be final, conclusive and binding on all parties to the
contract upon all question relating to the meaning of the specification, design
drawings and instructions hereinbefore mentioned and as to the quality of
workmanship or material used on the work or as to any other question, claim,
right matter or thing whatsoever, in any way arising out of or relating to the
contract, designs, drawings, specifications, estimates, instructions, orders,
or those conditions or otherwise concerning the work of execution or failure to
execute the same, whether arising during the progress of the work, or after the
completion or abandonment thereof.
Provided
that if the contractor is dissatisfied with the final decision of the
Superintending Engineer in respect of any matter, he may within 28 days after
receiving notice of such decision give notice in writing to the Superintending
108 Engineer requiring that the matter may be referred to the arbitration and
furnishing detailed particulars of the dispute or difference specifying clearly
the point at issue. If the contractor fails to give such notice within the
period of 28 days as stipulated above the decision of the Superintending
Engineer already given shall be conclusive and binding on the contractor.
In
case an arbitration is to be held it shall be effected by an arbitrator to be
appointed by the State Government whose decision shall be final, conclusive and
binding.
If the
work under the contract has not been completed when a dispute is referred to
arbitration work shall continue during arbitration proceedings if it is
reasonably possible and no payment due to contractor should be with held on
account of arbitration proceedings unless it is required by the arbitrator
3.3.32 Clause 32. Action where no specification:
In
case of any class of work for which there is no such specification as is
mentioned in Rules, such work shall be carried out in accordance with the
specification approved by Superintending Engineer/Chief Engineer, or
application to works in the district and the event of there being no such
specification, then in such case the work shall be carried out in all respect
in accordance with the instructions and requirements of the Engineer-in-Charge.
3.3.33
Clause 33. Definition of work:
The
expression "works" or "work" where used in these conditions
shall, unless there by something either in the subject or context repugnant to
such construction be constructed and taken to mean the works by or by virtue of
the contract contracted to be executed, whether temporary or permanent, and
whether original, altered, substituted or additional.
3.3.34
Clause 34. Claim for quantities entered in the tender or estimate:
109
Quantities shown in the tender are approximate and no claim shall be
entertained or work executed being either more or less than those entered in
the tender estimate." The learned single Judge as mentioned hereinbefore
of the High Court after exhaustive discussion dismissed the appeal and upheld
the order. Being aggrieved the petitioner went up in appeal before the Division
Bench and the Division Bench on consideration of the matter dismissed the
appeal.
The
Division Bench considered the following issues raised before the District
Judge:
1.
Whether the contractor had incurred extra costs towards wetting and washing of
stones used in masonry of Group-II Tawa Masonry Dam?
2. Was
the petitioner entitled to payment of this extra costs of Rs. 1.20,355?
3.
Whether the petitioner contractor had to incur extra cost of material and labour
to the tune of Rs.
14,72,456
within the contract period for executing work assigned to it?
4.
Whether the contractor had incurred extra cost of Rs.8,84,336 for the work
beyond the contract period due to unforeseen circumstances?
5.
Whether the petitioner's claim on both the counts was in whole or in part of it
was barred by time in terms of clause 3.3. 15?
6.
Whether the contract was rendered ineffective in terms of section 56 of the
Contract Act due to unexpected change in the market rate of material and labour
charges?
7. Was
the claim not entertainable in accordance with the terms' of the contract under
clause 3.3.32, 3.3.33 and 3.3.34 during the extended period of contract?
8. Was
the work delayed because of the presence of shale-zone in the foundation which
factor was not made known to the contract?
9.
Whether the contractor was entitled to extra costs of damages 110 for the delay
caused on account of shale-zone? The Division Bench came to the findings as
follows:
1. The
contractor did incur expenditure on wetting and washing of stones in Masonry
Group-II, Tawa Masonry Dam but this was according to agreement.
2. The
petitioner is not entitled to the payment of the extra costs of Rs.1,20,355.
3. The
petitioner/contractor did incur an extra cost of Rs.14,72,456 within the
contract period for executing the assigned work.
4. The
petitioner/contractor did incur an extra cost of Rs.6,81,796 for the work done
beyond the contract period due to unforseen circumstances.
5. The
petitioner is entitled to the claim to the extent of Rs.2,65,000 against Issue
No. 3 and Rs.6,81,796 against Issue No. 4 above and the same is not barred by
time in terms of clause 3.3.15.
6. The
contract was not rendered ineffective in terms of section 56 of the Contract
Act due to abnormal rise in the market rates of materials and labour.
7. The
claim under reference cannot be ruled out merely be cause of the provisions of
clause 3.3.32, 3.3.33 and 3.3.34.
8.
Yes, the work was delaved due to the presence of shale-zone in the foundations,
a factor which was unforeseen and was not made known to the contractor.
9. The
contractor is entitled to claim extra cost due to the delay caused on account
of the shale-zone in foundations.
The
Division Bench felt that the four factual issues decided by the District Judge
were more or less by the agreement and therefore, the Division Bench did not
deal with these. So far as three legal issues which were referred to him,
namely, whether the claim was barred under clause 3.3. 15, the contract was
rendered ineffective in terms of 111 section 56 of the Contract Act due to
abnormal rise in the market rate of material and labour and the claim not entertainable
under clause 3.3.32, 3.3.33 and 3.3.34. The High Court considered whether the
appellant was entitled to extra cost towards rise in prices of materials and labour
within and beyond the contract period. The Division Bench noted that the
learned District Judge held that since three legal issues were specifically
referred to the arbitrator and therefore his decision had become final and
binding on the parties and cannot be re-agitated before the Court.
Regarding
the remaining issues, the State had taken objection while opposing the
application under section 20 that the appellant was not entitled to extra cost
for material and labour in terms of the contract but the Court directed that
this matter had to be agitated before the arbitrator and the application under
section 20 could not be dismissed on the ground that the claim would not
ultimately succeed. The District Judge found and in our opinion rightly that
the question regarding extra-cost was a general question and not a specific
legal question and the decision of the arbitrator was not final one. The
arbitrator misconducted himself in allowing the claim without deciding the
objection of the State. In view of the specific clauses, the appellant was not
legally entitled to claim for extra cost. The decision of this Court in Seth Thawardas
v. Union of India, [1955] 2 SCR -18 is of no avail on this point. If no
specific question of law is referred, the decision of the arbitrator on that
question is not final however much it may be within his jurisdiction and indeed
essential for him to decide the question incidentally. The arbitrator is not a
conciliator and cannot ignore the law or misapply it in order to do what he
thinks is just and reasonable. The arbitrator is a tribunal selected by the
parties to decide their disputes according to law and so is bound to follow and
apply the law, and if he does not he can be set right by the Court provided his
error appears on the face of the award. In this case, the contractor having
contracted, he cannot go back to the agreement simply because he does not suit
him to abide by it. The decision of this Court in M/s. Alopi Parshad v. Union
of India, [1960] 2 SCR 793 may be examined. There it was observed that a
contract is not frustrated merely because the circumstances in which the
contract was made, altered. The Contract Act does not enable a party to a
contract to ignore the express covenants thereof, and to claim payment of
consideration for performance of the contract at rates different from the
stipulated rates, on some vague plea of equity. The parties to an executory
contract are often faced, in the course of carrying it out, with a turn of
event which they did not at all anticipate, a wholly abnormal rise or fall in
prices, a sudden depreciation of currency, an unexpected obstacle to execution,
or the like. There is no general 112 liberty reserved to the courts to absolve
a party from liability to perform his part of the contract merely because on
account of an uncontemplated turn of events, the performance of the contract
may become onerous.
It was
argued on behalf of the appellant that since specific issues 13 were framed and
referred by the District Judge to the arbitrator, the same had been answered by
a non-speaking award, there is no mistake of law apparent on the face of record
and the District Judge erred in setting aside the award by looking into the
terms of the contract which it was submitted, neither formed part of the award
nor appended to it. We are unable to agree. This being a general question, in
our opinion, the District Judge rightly examined the question and found that
the appellant was not entitled to claim for extra cost in view of the terms of
the contract and the arbitrator misdirected himself by not considering this
objection of the State before giving the award.
In Kapoor
Nilokheri Co-operative Dairy Farm Society Ltd. v. Union of India, A.I.R. 1973
S.C. 1338, it was held that where an arbitrator is called upon to decide the
effect of the agreement, he has really to decide a question of law, i.e. Of
interpreting the agreement, and hence, his decision is not open to challenge.
This was also a decision against a reasoned award but since the reference was
to a specific question of law, the decision of the arbitrator, it was held, was
not open to challenge. The limits of the jurisdiction of the Court to challenge
the award are well- settled. While considering objection under section 30 of
the Act, the Court does not act as an appellate court, it can only interfere
with the award if the arbitrator misconducts himself or the proceedings or if
the award has been made after the issue of an order by the Court superseding
the arbitration or if the arbitration proceedings have become invalid under
section 35(c) of the Act or the award has been improperly procured or is
otherwise invalid. The Judicial Committee in Champsey Bhara & Co. v. Jivraj
Balloo Spinning & Weaving Co. Ltd., A.I.R. 1923 P.C. 66 has laid down the
extent of the jurisdiction of the Court to set aside an award on the ground of
an error in making the award. It has been reiterated that the award of the
arbitrator may be set aside on the ground of an error on the face thereof only
when in the award or in any document incorporated with it as for instance, a
note appended by the arbitrator, stating the reason for his decision, there is
found some legal proposition which is the basis of the award and which is
erroneous. See also in this connection Re. King & Duveen, [1913] 2 K.B. 32
and Government of Kelantan v. Duff Development Co. Ltd., [1923] A.C. 395, if
how 113 ever, a specific question is submitted to the arbitrator and he answers
it, the fact that the answer involves an erroneous decision in point of law,
does not make the award bad on its face so as to permit of it being set aside.
See also the observations of this Court in Bungo Steel Furniture v.Union of India, [1967] 1 SCR 633. It is well
settled that the contract remained part of the award.
The
Judicial Committee in Saleh Mohd. v. Nathoo Mal, 54 I.A. 427 considered an
award in which the arbitrator recited a contract made between the parties and
the dispute arising under it. It was contended that the contract was
incorporated in the award by its reference and so the award disclosed an error
of law in construing the terms of the contract. But that contention was negatived.
It was held that the reference to the contract in the award was to earmark the
disputes between the parties and was not incorporated into the award. In Abosalom
Ltd. v. Creat Western, [1933] A.C., 592, it was held that if an award referred
to the terms of a clause in the contract, the clause though not set out in full
must be taken to be incorporated in it. This Court has reiterated in Allen
Berry & Co. v. Union of India, 119711 3 SCR 282 that mere reference to the
contract in the award is not to be held as incorporating it.
In the
aforesaid light, we are of the opinion, the High Court was right that the
District Judge was entitled to examine the contract in order to find out the
legality of the claim of the appellant regarding extra cost towards rise in
prices of material and labour. As was pointed out by the learned District Judge
clauses 2.16 and 2.4 stipulated that the contractor had to complete the work inspite
of rise in prices of materials and also rise in labour charges at the rates
stipulated in the contract. There was a clear finding of the arbitrator that
the contract was not rendered ineffective in terms of section 56 of the Act due
to abnormal rise in prices of material and labour. This being so and the
contractor having completed the work, it was not open to him to claim extra
cost towards rise in prices of material and labour. The arbitrator misconducted
himself in not deciding this specific objection raised by the State regarding
the legality of extra claim of the appellant.
In
that view of the matter, the award, in our opinion, was properly set aside by
the learned District Judge and the High Court was right in not interfering with
it.
The
question about specific reference on a question of law was examined by this
Court recently in the case of Tarapore and Comapny v. Cochin Shipyard Ltd.,
Cochin and another, [1984] 2 S.C.C. 680. There it was observed that if the
agreed fact situation, on the basis of 114 which agreement was entered into,
ceases to exist, the agreement to that extent would become otiose. If rate
initially quoted by the contractor became irrelevant due to subsequent price
escalation, it was held in that case that contractor's claim for compensation
for the . excess expenditure incurred due to the price rise could not be turned
down on ground of absence of price escalation clause in that regard in the
contract. Agreement as a whole has to be read. Reliance was placed very heavily
on this decision on behalf of the appellant before us.. It has to be borne in
mind that in the instant case there are specific clauses referred to
hereinbefore which barred consideration of extra claims in the event of price
escalation. That was not so in Tarapore and Company's case. That made all the
difference.
The basis
of bargain between the parties in both these two cases were entirely different.
In the
aforesaid view of the matter we are of the opinion that the High Court was
right in the view it took and there is no ground to interfere. The petition for
special leave fails and is accordingly dismissed.
S.L.
Petition dismissed.