Union of India & Anr Vs. L.K. Ahuja
& Co [1988] INSC 90 (5
April 1988)
Mukharji,
Sabyasachi (J) Mukharji, Sabyasachi (J) Rangnathan, S.
CITATION:
1988 AIR 1172 1988 SCR (3) 402 1988 SCC (3) 76 JT 1988 (2) 82 1988 SCALE (1)710
ACT:
Arbitration
Act, 1940-Whether application for appointment of Arbitrator under Section
20-Of-Is barred by limitation-Whether the trial Court is right in dismissing
that application as such.
HEAD NOTE:
% Four
agreements were entered into between the respondent and the appellant Union of
India through the Executive Engineer, Northern Railway, followed by a
supplementary agreement. All the four contracts were executed and completed by
the respondent on diverse dates.
The
respondent accepted four final bills and gave no-claim declaration in respect
of the four contracts. Thereafter, the respondent wrote to the Additional Chief
Engineer, R.E.N.R., that Rs.1,91,137 were due on account of work executed and
asked for a reference of the dispute to the Arbitrator. A reply was sent to the
respondent that there was no dispute between the parties and no question of
appointment of any Arbitrator arose. The respondent then filed an application
in the Court of Civil Judge for the appointment of an Arbitrator under Section
20 of the Arbitration Act, 1940 (`the Act'). The application was dismissed as
being barred by limitation. An appeal from the decision of Civil Judge was
allowed by the High Court. The appellants then moved this Court for relief by
this appeal.
Dismissing
the appeal, the Court, ^
HELD:
The sole question involved in this appeal was whether the Civil Judge was right
in dismissing the application and whether the application under section 20 was
within time. [404H] It is well-settled in view of the decision of this Court in
Kerala State Electricity Board, Trivendrum v. T.P.K.K. Amsom and Besom, Kerala,
[1977] 1 SCR 996 that Article 137 would apply to any petition or application
filed under any Act in a Civil Court. The words "any other
application", this Court held under Article 137, cannot be read on the
principle of ejusdem generis to be applications under the Civil Procedure Code
other than those mentioned in Part I of the third division. [405A-B] 403 There
are two aspects of the matter. One is whether the claim made in the arbitration
is barred by limitation under the relevant provisions of the limitation Act,
and secondly, whether the claim made for application under section 20 is
barred. To be a valid claim for reference under section 20 of the Arbitration
Act, 1940, it is necessary that there should be an arbitration agreement and
secondly, differences must arise to which the agreement in question applied,
and thirdly, that must be within time as stipulated in section 20 of the Act.
In this case, there was an arbitration agreement as found by the High Court,
covering the disputes.
It was
also obvious that differences had existed. There was assertion of claim and
denial of it. As such, the dispute was liable to be referred to arbitration in
terms of the agreements between the parties. The question was whether there was
a valid claim under section 20 of the Act to be referred in accordance with
law. [407C-E, G-H] In view of the well-settled principles, it would be entirely
wrong to mix up the two aspects, namely, whether there was any valid claim for
reference under Section 20 of the Act and, secondly, whether the claim to be
adjudicated by the arbitrator was barred by lapse of time. The second is a
matter which the arbitrator would decide unless on admitted facts a claim is
found at the time of making an order under Section 20 of the Act, to be barred
by time. To be entitled to ask for a reference under section 20 of the Act,
there must be entitlement to money and a difference or a dispute in respect of
the same. It is true that on completion of work the right to get payment would
normally arise and it is also true that on settlement of the final bill, the
right to get further payment gets weakened but the claim subsists, and whether
it does subsist is a matter which is arbitrable. In this case, the claim for
reference was made within three years commencing from April 16, 1976, and the application was filed on December 18, 1976. [408A-D] The High Court was right
in this case. See in this connection the observations of this Court in Major (Retd.)
Inder Singh Rekhi v. D.D.A., [1988] 3 SCR 351. The appeal failed. [408D] Kerala
State Electricity Board, Trivandrum v. T.P.K.K. Amsom and Besom, Kerala,
[1977] 1 SCR 996; Wazirchand Mahajan & Anr. v. Union of India, [1967]
1 SCR 303; Mohd.
Usman
Military Contractor, Jhansi v. Union of India, Ministry of Defence, [1969] 2 SCR
233; Jiwnani Engineering Works P. Ltd. v. Union
of India, [1978] AIR Cal. 228 and Major (Retd.) Inder Singh Rekhi v. D.D.A.,
[1988] 3 SCR 351 referred to.
404
CIVIL
APPELLATE JURISDICTION: Civil Appeal No 757 of 1988.
From
the Judgment and Order dated 14.8.1986 of the Allahabad High Court in F.A. No.
448 of 1978.
G. Ramaswamy,
Additional Solicitor General, Pramod Swarup and P. Parmeshwaran for the
Appellants.
R.P.
Gupta for the Respondent.
The
Judgment of the Court was delivered by SABYASACHI MUKHARJI, J. Special leave
granted. The appeal is disposed of by the judgment hereunder.
It
appears that on or about 18th
September, 1969, four
agreements were entered into between M/s. L.K. Ahuja & Co. and Union of
India, represented by the Executive Engineer, Northern Railway, Allahabad, for the construction of certain
quarters. It was followed by supplementary agreement entered into sometime in
1972. It is stated that all the four contracts were executed and completed by
the first respondent on diverse dates. The last one was on 30th May, 1971. Between 29th May, 1972 to 19th June, 1972, the respondent accepted the four final bills and gave no
claim declaration in respect of the four contracts. The respondent wrote a
letter to the Additional Chief Engineer, R.E.N.R.
Allahabad, stating that Rs.1,91,137 were due
on account of the work executed and requested him to refer the dispute to the
Arbitrator. On 4th
June, 1976 a reply was
sent to the above letter stating that there was no dispute between the parties
and, hence, no question of appointment of any Arbitrator arose. On 13th December, 1976, an application was filed by the
respondent in the Court of Civil Judge, Allahabad, for appointment of an Arbitrator under Section 20 of the Arbitration
Act, 1940 (hereinafter called `the Act').
That
application was dismissed on 10th February, 1978 as being barred by limitation. There was an appeal from the said
decision to the High Court of Allahabad and the High Court by its impugned
Judgment and Order dated 14th
August, 1986 allowed
the appeal. Hence, this appeal.
The
sole question, involved in this appeal, is whether the High Court was right in
dismissing the application. In matters of this nature, the main question is
whether the application under Section 20 was within time. Though there was some
doubt before but now it is well- 405 settled in view of the decision of this
Court in Kerala State Electricity Board, Trivandrum v. T.P.K.K. Amson & Beson,
Kerala, [1977] 1 SCR 996 that Article 137 would apply to any petition or
application filed under any Act to a Civil Court. The Words "any other
application" this Court held under Article 137, cannot be read on the
principle of ejusdem generis to be applications under the Civil Procedure Code
other than those mentioned in part I of the third division.
The
aforesaid view has to be harmonised with the view of this Court in Wazirchand Mahajan
& Anr. v. Union of India, [1967] 1 SCR 303. There this Court found that the second
appellant had purchased from the Himachal Pradesh Government the right to
extract and collect certain medicinal herbs from the forests of Chamba
District. The period of agreement was one year from September 1, 1960.
Under
an arbitration clause in the agreement all disputes between the parties were to
be referred to the Deputy Commissioner, Mandi District Himachal Pradesh. The
second appellant transferred all his rights under the agreement to the first
appellant with the consent of the State of Himachal Pradesh. Disputes arose between the parties in October, 1950. On May 30, 1952 the appellants addressed a letter
to the Chief Conservator of Forests, Himachal Pradesh requiring that officer to
submit the matters in difference to the arbitration of the Deputy Commissioner,
Mandi Distt.
By a
letter dated June 23,
1952, the Chief
Conservator declined to agree to a reference contending that the matters
desired to be referred were outside the arbitration clause.
On June 22, 1955 the appellants applied to the
District Court of Chamba for an order that the agreement be filed in Court and
the disputes between them and the State be referred to the sole arbitration of
the Deputy Commissioner of Mandi Distt. The State of Himachal Pradesh contended,
inter alia that the application for filing the arbitration agreement was barred
by law of limitation as the right to apply if any arose in 1950 and not in
June, 1952 as alleged.
The
Court of First Instance held in favour of the appellants. In appeal the
Judicial Commissioner reversed the order of the Trial Court. In the view of the
Judicial Commissioner an application for filing an arbitration agreement under
Section 20 of the Act was governed by Article 181 of the Limitation Act, 1908
and since the period of three years prescribed thereby commenced to run from
the date on which the differences arose between the parties from the month of
September, 1950 and in any case on September 1, 1951, the application of the
appellants was held to be barred. The Judicial Commissioner was in error,
hence, according to this Court in rejecting the application of the appellants
for filing the arbitration agreement as barred under Article 181 of the
Limitation 406 Act. It was reiterated that the terms of Article 181, though
general and apparently not restricted to applications under the Code of Civil
Procedure have always been interpreted as so restricted. In the aforesaid
background this Court directed the arbitration agreement to be filed.
This
question was again considered by this Court in Mohd. Usman Military Contractor,
Jhansi v. Union of India, Ministry of Defence, [1969] 2 SCR
233. There the appellant had entered into a contract with the Government of
India.
The
contract contained an arbitration clause. For certain supplies made under the
contract the appellant made representations to the Government for payment and
for arbitration of disputes. On or about July 10, 1958 Government refused to refer the
matter for arbitration. On July 11, 1961
the appellant filed an application in the Court of District Judge under
Sections 8 & 20 of the Act, for filing the arbitration agreement and for an
order of reference of the disputes to an arbitrator appointed by the Court. The
respondent contended that the application was barred by Limitation. The learned
District Judge allowed the application, holding that there was no limitation
for making an application under Sections 8 & 20 of the Act. The defendant's
appeal was dismissed by the High Court as incompetent insofar as it challenged
the order under Section 8 but was allowed insofar as it challenged the order
under Section 20 of the Act. The High Court held that an application under
Section 20 was governed by Article 181 of the Indian Limitation Act, 1908. In
coming to this conclusion the High Court took into account the settled judicial
view that the operation of Article 181 was limited to applications under the
Code of Civil Procedure and reasoned that Article 181 should be construed as if
the words `under the Code' were added in it. The Arbitration Act, 1940 repealed
para 17 of the second schedule to the Code and re-enacted it in Section 70 with
minor modifications. That being so Section 8(1) of the General Clauses Act,
1897 applied and the implied reference in Article 181 to para 17 of the second
schedule to the Code should be construed as a reference to Section 20 of the
Act.
In the
appeal by certificate this Court held that by the Arbitration Act, 1940 the
Legislature amended Articles 158 and 178 of the Limitation Act and made them
applicable to the relevant proceedings under the Arbitration Act but no similar
change was made in Article 181. It was manifest that save as provided in
Articles 158 & 178 there would not be any limitation for other application.
In the circumstances the Court found it impossible to construe the implied
reference in Article 181 as a reference to the Arbitration Act, or to hold that
Article 181 applied to applications under that Act. In the premises the Court
held that an application under Sections 8 & 20 of 407 the Arbitration Act,
1940 was not governed by Article 181 of the Limitation Act. In that view of the
matter the application was held to be barred by limitation. The question is now
concluded as mentioned hereinbefore vide this Court's decision in Kerala State
Electricity Board, Trivandrum v. T.P.K.K. Amsom & Besom,
(supra).
It
appears that these questions were discussed in the decision of the Calcutta
High Court in Jiwnani Engineering Works P. Ltd. v. Union of India, [1978] AIR
Cal. 228 where (one of us-Sabyasachi Mukharji) was a party and which held after
discussing all these authorities the question whether the claim sought to be
raised was barred by limitation or not, was not relevant for an Order under
Section 20 of the Act. Therefore, there are two aspects. One is whether the
claim made in the arbitration is barred by limitation under the relevant
provisions of the Limitation Act and secondly, whether the claim made for
application under Section 20 is barred. In order to be a valid claim for reference
under Section 20 of the Arbitration Act, 1940, it is necessary that there
should be an arbitration agreement and secondly differences must arise to which
the agreement in question applied and, thirdly, that must be within time as
stipulated in Section 20 of the Act.
In the
instant case it appears that there was an arbitration agreement as found by the
High Court covering the disputes. It is also obvious that differences existed.
There
was an assertion of claim and denial of the same. It is stated in the judgment
of the High Court that under the agreement the appellants had claimed a sum of Rs.
1,91,636 and, as such, the dispute was liable to be referred to arbitration in
terms of the agreements entered into between the parties. Further, for the purpose
of getting an arbitrator appointed, a letter dated June 4, 1976 was sent by the
appellant to the Additional Chief Engineer, Allahabad. The respondent did not
take any step in time. The appellant filed an application on 4.6.1976 under
Section 20 of the Act. It was contended before the learned Trial Judge that the
work under all the four contracts had been fully executed by the appellant on
different dates and the respondents claimed that the appellant had accepted
full and final payment of the agreements which had been executed by it and no
claim declaration in respect of the same had been given by the appellant. It
was, therefore, submitted that since there was no dispute, the application
filed under Section 20 of the Act, was misconceived. The Trial Court held that
the Court had no jurisdiction under Section 20 of the Act. The respondent came
up in appeal before the High Court. The question, therefore, was whether there
was a valid claim under section 20 of the Act to be referred in accordance with
law.
408 In
view of the well-settled principles we are of the view that it will be entirely
a wrong to mix-up the two aspects, namely, whether there was any valid claim
for reference under Section 20 of the Act and, secondly, whether the claim to
be adjudicated by the arbitrator, was barred by lapse of time. The second is a
matter which the arbitrator would decide unless, however, if on admitted facts
a claim is found at the time of making an Order under Section 20 of the
Arbitration Act, to be barred by limitation. In order to be entitled to ask for
a reference under Section 20 of the Act, there must be an entitlement to money
and a difference or dispute in respect of the same. It is true that on
completion of the work, right to get payment would normally arise and it is
also true that on settlement of the final bill, the right to get further
payment gets weakened but the claim subsists and whether it does subsist, is a
matter which is arbitrable. In this case the claim for reference was made
within three years commencing from April 16, 1976 and the application was filed
on December 18, 1976. We are, therefore, of the view that the High Court was
right in this case. See in this connection the observations of this Court in
Major (Retd.) Inder Singh Rekhi v. D.D.A., [1988] 3 SCR 351.
In the
aforesaid view of the matter this appeal must fail and is accordingly
dismissed. The costs of this appeal would be the costs in the arbitration
proceedings.
S.L.
Appeal dismissed.
Back