M.P.E.B.
& Ors Vs. Smt. Basantibai [1987] INSC 321 (10 November 1987)
RAY,
B.C. (J) RAY, B.C. (J) SHETTY, K.J. (J)
CITATION:
1988 AIR 71 1988 SCR (1) 890 1988 SCC (1) 23 JT 1987 (4) 294 1987 SCALE (2)985
ACT:
Indian
Electricity Act, 1910: Section 26(6)-Scope of- Disputes regarding electricity
meter-Jurisdiction of Electrical Inspector to decide-Electricity Board-Whether
competent to issue supplementary bill for energy consumed during pendency of
dispute regarding inherent defect/fault in the meter.
HEADNOTE:
%
An electricity meter with three phases installed by appellant No. 1 for running
an oil mill owned by the respondent was burnt. This was brought to the notice
of appellant No. 4. The respondent was directed to deposit a certain amount
towards price of the meter and the meter connection charges, which the
respondent complied, but the meter was not installed, nor electric supply
connection restored. The respondent requested appellant No. 1 to restore electric
supply by installation of another meter.
However,
appellant No. 1 sent a letter dated 4.3.1983 calling upon respondent to pay a
sum of Rs.12,346.10 as per the attached supplementary bill dated 2.3.1983,
prepared on the basis that the meter was not recording actual energy supplied
and consumed, as it was running on two phases, since one of the three phases
was not working, and threatening disconnection of supply without notice, for
non- payment.
The
respondent filed a writ petition in the High Court challenging the legality of
the aforesaid letter and the supplementary bill.
On
behalf of the appellants, it was contended that when the power connection was
checked by an Assistant Engineer of the Board, it was found that out of three
phases, one phase was not working, and body seal of the meter was intact and,
therefore, respondent was informed that the bill should be revised due to
non-working of one phase. It was alleged that respondent got the meter burnt,
since it did not burn ordinarily, and the body seal of the meter was broken,
and the meter tampered with subsequently in order to avoid any liability.
The
High Court held that since the dispute, was as to whether the meter was or was
not correct it had to be decided by the Electrical 891 Inspector, under
sub-section (6) of s. 26 of the Indian Electricity Act, 1910 and so long as it
was not decided, appellant No. 1 was not competent to prepare the supplementary
bill or revised bill, and quashed the letter dated 4.3.83 and supplementary
bill of 2.3.83, as illegal.
In
the appeal by special leave it was urged on behalf of the appellants that the
respondent committed fraud in breaking the body seal of the meter and running
the same, and as such, the dispute did not attract the provisions of s. 26(6)
of the Act and the dispute could not be decided by the Electrical Inspector.
Dismising
the appeal, ^
HELD:
Under sub-section (6) of s. 26 of the Indian Electricity Act, 1910, it is only
the dispute as to whether any meter referred to in sub-section (1) is/is not correct
or it is inherently defective or faulty, not recording correctly the
electricity consumed, which can be decided by the Electrical Inspector.
[896A-B] It is also evident from the said provision that till the decision is
made, no supplementary bill can be prepared by the Board, estimating the energy
supplied to the consumer, as the Board is not empowered by the Act to do so.
[896C-D]
A dispute regarding the commission of fraud in tampering with the meter and
breaking the body seal is one outside the ambit of section 26(6) of the Act. An
Electrical Inspector has no jurisdiction to decide such cases of fraud.
[895H;
896A] In the instant case, it appears from the report of the Assistant Engineer
of the State Electricity Board that one phase of the meter was not working at
all; so, there is undoubtedly a dispute as to whether the meter in question is
a correct one or a faulty one. This dispute, therefore, squarely falls within
the provisions of the Act, and it has been rightly held by the High Court that it
is the Electrical Inspector, who alone is empowered to decide the dispute. If
the Electrical Inspector comes to the finding that the, meter is faulty and due
to some defect it has not registered the actual consumption of electrical
energy, then the Inspector will estimate the amount of energy consumed and will
fix the amount to he paid in respect of such energy consumed within a period
not exceeding six months. The appellant No. 1 is not competent, pending the
determination of this dispute by the Electrical Inspector, to issue the
impugned notice threatening disconnection of supply of electricity 892 for
non-payment of supplementary bill prepared and sent by it. The A Board is also
not competent to prepare and send a supplementary bill in respect of energy
consumed by the respondent from the one phase which stopped functioning and did
not record any consumption of energy. [896B-C; 897F-H; 898A-B] It appears from
the report of the Executive Engineer dated 17th February, 1983 that the body
seal of the meter was intact at the time of inspection. He only found that the
meter which was installed was closed on one phase.
Therefore,
there is no question of fraud in breaking the body seal of the meter. The story
of so-called fraud was an after thought, and was not raised at any stage prior
to the filing of the return in the High Court. [894E-F] Gadag Betgiri,
Municipal Borough, Gadag v. The Electrical Inspector, Government Electrical
Inspectorate, Government of Mysore, AIR 1962 Mysore 209 and M. P.
Electricity
Board Jabalpur and another v. Chhanganlal, AIR 1981 M.P. 170 approved.
Abdul
Razak v. M.P. Electricity Board, [1982] M.P.L.J. 22 overruled.
CIVIL
APPELLATE JURISDICTION: Civil Appeal No. 716 of 1985.
From
the Judgment and order dated 20.9.1984 of the Madhya Pradesh High Court in
Misc. Petition No. 307 of 1983.
K.K.
Venugopal, S.K. Gambhir and Sanjay Sareen for the Appellants.
C.P.
Mittal and C.K. Ratnaparkhi for the Respondent.
The
Judgment of the Court was delivered by RAY, J. This appeal on special leave is
directed against the judgment and order passed by the High Court of Madhya
Pradesh on 20.9.1984 in Civil Misc. Petition No. 307 of 1983 allowing the writ
petition and directing the respondents to reconnect and restore the electric
supply by installing another meter.
The
petitioner is a proprietor of Santosh Industries DII BC, Sector, Sanwar Road,
Indore and she obtained service connection 893 No. 192352 of 30 H.P. Ioad for
running the oil mill. The Madhya Pradesh Electricity Board, the appellant No. 1,
who is the licensee installed a meter with three phases for ascertaining the
amount of energy supplied and consumed by the petitioner under the aforesaid
service connection. On February 18, 1983 the meter was burnt and this was
brought to the notice of respondent No. 4, an Assistant Engineer of the Zone
wherein the petitioner's industry is situated. On March 1, 1983 the petitioner
was directed to deposit a sum of Rs.433 as price of the meter and Rs.44 for
meter connection charges.
The
sum was deposited on the same day but no meter was installed and the electric
supply connection was not restored. A letter was sent by the petitioner to the
respondent No. 1 requesting to restore the electric supply by installation of
another meter. The State Electricity Board sent a letter dated 4.3.1983 calling
upon the petitioner to pay a sum of Rs.12346.10 as per the supplementary bill
dated 2.3.1983 sent along with said letter failing which the supply will be
disconnected without notice. The basis of the supplementary bill was that the
meter was not recording actual energy supplied and consumed as it was found
that one phase out of the three phases was not working and the meter was
running two phases only.
The
petitioners filed a writ petition No. 307 of 1983 challenging the said letter
dated 4.3.1983 as well as the supplementary bill dated 2.3.1983 on the ground
that the demand made on the basis of the supplementary bill was illegal.
A
return was filed by the respondent to the effect that on 17.2.1983 the power
connection was checked by an Assistant Engineer of the respondent Board and it
was found that out of three phases one phase was not working. The body seal of
the meter was found to be intact. It has also been stated therein that the
petitioner was informed that the bill should be revised due to non working of
one phase as found at the time of checking. It has also been submitted that the
petitioner got the meter burnt as the meter according to respondent did not
burn ordinarily. It was further alleged that body seal of the meter was broken.
This tampering of the meter was alleged to have been done between 17 to 19 of
February, 1983 in order to avoid any liability.
The
respondent further alleged that the petitioner's husband refused to sign the
panchnama which was prepared on the spot.
The
High Court of Madhyra Pradesh after hearing the parties held that since the
dispute relates to whether the meter is or is not 894 correct has to be decided
by the Electrical Inspector and so long the A said dispute is not decided, the
respondent No.
1,
Madhya Pradesh Electricity Board was not competent to prepare the supplementary
bill or revised bill as the said power is entrusted to the Electrical Inspector
under sub- section 6 of section 26 of the Indian Electricity Act, 1910 (Act 9
of 19 10). It has been further held that the alleged notice calling upon the
petitioner to deposit the amount of supplementary bill before seeking
reconnection or restoration of electricity supply was also not in accordance
with the provisions of the Act. The letter dated 4.3.1983 issued by the
respondent no. 1 as well as the supplementary bill of 2.3.1983 were quashed
holding the same to be illegal. The question of fraud was not even intimated to
the respondent consumer. It was raised for the first time in the return to the
writ petition. It is an after thought. The respondents were directed to
reconnect and restore the electricity supply by installing another meter.
Against
this judgment and order the instant appeal on special leave has been filed. It
has been urged by Mr. Venugopal, learned counsel appearing on behalf of the
appellant that the respondent committed fraud in breaking the body seal of the
meter and in burning the same and as such the dispute does not attract the
provisions of the section 26(6) of the said Act. This dispute cannot be decided
by the Electrical Inspector. In support of the submission our attention was
drawn to the said provisions of the Act. It appears from the report of the
Executive Engineer dated 17th February, 1983 that the body seal of the meter
was intact at the time of inspection. He only found that the meter which was
installed was closed on one phase.
So
the contention that there was fraud in breaking the body seal of the meter
cannot be sustained. Moreover, it has been found that the question of fraud was
raised at no stage prior to the filing of the return in the High Court. The
said story of so called fraud was an after thought. Mr. Venugopal after seeing
the report of the Assistant Engineer frankly submitted that he would not press
the ground of fraud.
In
order to decide the question whether the impugned notice dated 4.3.1983 can be
issued by appellant calling upon her to pay the amount of supplementary bill as
well as whether supplementary bill can be prepared by the Board when there is a
dispute relating to question whether the meter is a correct meter or not, it is
necessary to consider the relevant provisions of sub sections (1) and (6) of section
26 of the said Act. The said provisions are set out hereunder:
"26(1):
In the absence of an agreement to the contrary, 895 the amount of energy
supplied to a consumer or the electrical quantity contained in the supply shall
be ascertained by means of a correct meter, and the licensee shall, if required
by the consumer, cause the consumer to be supplied with such a meter:
Provided
that the licensee may require the consumer to give him security for the price
of a meter and enter into an agreement for the hire thereof, unless the
consumer elects to purchase a meter." "26(6): Where any difference or
dispute arises as to whether any meter referred to in sub-section (1) is or is
not correct, the matter shall be decided upon the application of the either
party, by an Electrical Inspector; and where the meter has, in the opinion of
such Inspector ceased to be correct, such Inspector shall estimate the amount
of energy supplied to the consumer or the electrical quantity contained in the
supply, during such time, not exceeding six months, as the meter shall not, in
the opinion of such Inspector has been correct; but save as aforesaid, the
register of the meter shall, in the absence of fraud, be conclusive proof of
such amount or quantity;
Provided
that before either a licensee or a consumer applies to the Electrical Inspector
under this sub-section, he shall give to the other party not less than seven
days' notice of his intention so to do." It is evident from the provisions
of this section that a dispute as to whether any meter referred to in
sub-section (1) is or is not correct has to be decided by the Electrical
Inspector upon application made by either of the parties. It is for the
Inspector to determine whether the meter is correct or not and in case the Inspector
is of the opinion that the meter is not correct he shall estimate the amount of
energy supplied to the consumer or the electrical quantity contained in the
supply during a period not exceeding six months and direct the consumer to pay
the same. If there is an allegation of fraud committed by the consumer in
tampering with the meter or manipulating the supply line or breaking the body
seal of the meter resulting in not registering the amount of energy supplied to
the Consumer or the electrical quantity contained in the supply, such a dispute
does not fall within the purview of sub- section 6 of section 26. Such a
dispute regarding the commission 896 Of fraud in tampering with the meter and
breaking the body seal is A outside the ambit of section 26(6) of the said Act.
An Electrical inspector has, therefore, no jurisdiction to decide such cases of
fraud. It is only the dispute as to whether the meter is/is not correct or it
is inherently defective or faulty not recording correctly the electricity
consumed, can be decided by the Electrical Inspector under the provisions of
the said Act.
In
the instant case it appears from the report of the Assistant Engineer of the
State Electricity Board that one phase of the meter was not working at all, so
there is undoubtedly a dispute as to whether the meter in question is a correct
one or a faulty meter and this dispute has to be decided by the Electrical
Inspector whose decision will be final. It is also evident from the said
provision that till the decision is made no supplementary bill can be prepared
by the Board estimating the energy supplied to the consumer, as the Board is
not empowered to do so by the said Act. It is pertinent to refer in this
connection to the observations made in the case of Gadag Betgiri, Municipal
Borough, Gadag v. The Electrical lnspector. Government Electrical Inspectorate,
Government of Mysore, AIR 1962 Mysore 209 as follows:- "What the Inspector
may decide under sub- section 6 is whether or not the readings obtainable from
the meter are accurate and whether the meter is faulty or mechanically
defective, producing erroneous readings. That is the limited adjudication which
in my opinion, an Inspector or other authority functioning under sub-section 6
may make under its provisions. " x x x x x x x x x "In my opinion,
the legislative intent underlying section 26(6) of the Act is similar.
The
only question into which the Inspector or other authority functioning under
that sub-section might investigate is, whether the meter is a false meter capable
of improper use or whether it registers correctly and accurately the quantity
of electrical energy passing through it. If in that sense, the meter installed
by respondent 2 this case was a correct meter as it undoubtedly was and as it
has been admitted to be, the fact that respondent 2, even if what the
petitioner states is true, so manipulated the supply lines that more energy
than what was consumed by the petitioner was allowed to pass through the 897
meter, would not render the meter which was otherwise correct, an incorrect
meter." This decision was followed in M.P. Electricity Board, Jabalpur and
another v. Chhanganlal, AIR 1981 M.P. 170 where it has been observed:-
"Where an electric meter is not registering correct consumption of energy
not because there is any defect in the meter but because the wiring is
defective Section 26(6) will not be attracted and the meter not being defective
the question of arbitration by Electrical Inspector will not also arise .
" A contrary view was however taken in the case of Abdul Razak v. M.P.
Electricity Board, [1982] M.P.L.J. 22 where it has been held that:- "About
the fittings on the meter and tampering them in such a manner that the reading
of the energy would not be correct, such a dispute in view of the language of
section 26(6) read with Rule 3 of Schedule VI of the Electricity Act squarely
falls within the jurisdiction of the Electrical Inspector.
We
are however, unable to accept this contrary view as it is obvious from the
provisions of section 26 sub-section 6 of the said Act that dispute whether a
meter is correct or faulty would come under the said provisions and not the
dispute regarding tampering of meter. In our view, the view taken about the
scope of section 26(6) in the decisions cited above are correct. In the instant
case the dispute relates to whether the meter is correct one or it is faulty
not recording the actual energy consumed in running the oil mill of the
respondent. So this dispute squarely falls within the provisions of the said
Act and as such it has been rightly found by the High Court that it is the
Electrical Inspector who alone is empowered to decide the dispute. If the
Electrical Inspector comes to the finding that the meter is faulty and due to
some defect it has not registered the actual consumption of electrical energy,
then the Inspector will estimate the amount of energy consumed and will fix the
amount to be paid in respect of such energy consumed within a period not
exceeding six months. The appellant No. 1 is not competent pending the
determination of this dispute by the Electrical Inspector to issue the impugned
notice threatening 898 disconnection of supply of electricity for non payment
of supplementary bill prepared and sent by it. The Board is also not competent
to prepare and send a supplementary bill in respect of energy consumed by the
respondent from the one phase which stopped functioning and did not record any
consumption of energy. For the reasons, aforesaid we affirm the order of High
Court and dismiss the appeal without costs.
N.P.V.
Appeal dismissed.
Back