State of
Karnataka Vs. Shri Rameshwara Rice Mills Thirthahalli
[1987] INSC 58 (24
February 1987)
Natrajan,
S. (J) Natrajan, S. (J) Reddy, O. Chinnappa (J)
CITATION:
1987 AIR 1359 1987 SCR (2) 398 1987 SCC (2) 160 JT 1987 (1) 578 1987 SCALE
(1)448
ACT:
Indian
Contract Act, 1872--s. 73 --Agreement--Clause 12Interpretation of--Right to
assess damages when arises--Damages for breach of condition of
agreement--Assessment to be made by an independent body and not by parties to
the contract.
Revenue
Recovery Act--Damages for breach of conditions of contract--Whether recoverable
as arrears of land revenue.
HEAD NOTE:
Clause
12 of the agreements separately entered into between the respondents and the
appellant-State provided that "for any breach of conditions the first
party (the respondent) shall be liable to pay damages to the second party (the
State) as may be assessed by the second party in addition to the forfeiture in
part or full of the security amount deposited by the first party and that any
amount that may become due or payable by the first party to the second party
under any part of the agreement, shall be deemed to be and may be recovered
from the first party as if they were arrears of land revenue.
According
to the State the respondents committed a breach of their respective contract
and, therefore, demanded payment of damages as assessed by the authorities
representing the State. As the respondents failed to pay the damages, the State
initiated recovery proceedings under the Revenue Recovery Act. The respondents
challenged the recovery proceedings by filing suit/writ petition.
The
Full Bench of the High Court dismissed the Second Appeal (out of which C .A.
No. 471 of 1975 arises) preferred by the State holding that the State is not
competent to adjudicate upon the question whether the respondent committed
breach of contract, that the State is not competent to assess the damages for
any breach of contract not admitted by the respondent and that the damages so
assessed cannot be recovered as if they were arrears of land revenue. Following
this decision, the High Court allowed the writ petitions filed by the other
respondents and quashed the recovery proceedings.
399 In
the appeal to this Court on behalf of the State it was contended that the
authorities representing the State, even though a party to the agreement are
empowered under Clause 12 to not only assess the damages occasioned by the
breach of the conditions but also to adjudication any issue concerning the
commission of the breach itself.
Dismissing
the Appeals, HELD: 1. On a plain reading of the words in Clause 12:
"and
for any breach of conditions set forth herein-before, the first party shall be
liable to pay damages to the second party as may be assessed by the second
party", it is clear that the right of the second party to assess damages
would arise only if the breach of conditions is admitted or if no issue is made
of it. If it was the intention of the parties that the officer acting on behalf
of the State was also entitled to adjudicate upon a dispute regarding the
breach of conditions the wording of Clause 12 would have been entirely
different. A right to adjudicate upon an issue relating to a breach of
conditions of the contract would not flow or is not inhered in the right
conferred to assess the damages arising from a breach of conditions. The power
to assess damages is a subsidiary and consequential power and not the primary
power. [403A-C]
2.
Adjudication by the Officer regarding the breach of the contract cannot be
sustained under law because a party to the agreement cannot be an arbiter in
his own cause.
Interests
of justice and equity require that where a party to the contract disputes the
committing of any breach of conditions the adjudication should be by an
independent person or body and not by the other party to the contract.
The
position will, however, be different where there is no dispute or there is
consensus between the contracting parties regarding the breach of conditions.
In such a case the Officer of the State even though a party to the contract
will be well within his rights in assessing the damages occasioned by the
breach in view of the specific terms of Clause 12. [403D-F]
3. The
Full Banch while taking the view that the State is not entitled to recover
damages as arrears of land revenue because damages for breach of conditions
will not amount to "money due under the contract" has wrongly relied
upon the decision of this Court in Divisional Forest Officer v. Mool Chand AIR
1971 SC 694. Here the Court is concerned with cases where the agreement entered
into between the Government and the private persons specifically provides for
recovery of damages as arrears of land revenue. The Full Bench has failed to
notice that even though the damages become payable on ac400 count of breach of
conditions of contract, the liability to pay damages does not fail outside the
terms of the contract but within the terms of the contract. The words "any
amount that may become due or payable by the first party to the second party under
any part of this agreement" have to be read in conjunction with the
earlier portion of the Clause stipulating liability on the party contracting
with the State to pay damages for breach of conditions. Therefore, it follows
that though damages become payable on account of breach of conditions of the
agreement they nevertheless constitute amount payable under the contract, that
is, under one of the terms of the contract imposing liabilities to pay damages
for breach of conditions. Therefore, the opinion of the Full Bench in so far as
the recovery of damages as arrears of land revenue is concerned is not in
accordance with law. [403H; 404A-F]
CIVIL
APPELLATE JURISDICTION: Civil Appeal No. 471 of 1975. etc.
From
the Judgment and Order dated 25.9.72 of the Karnataka High Court in Regular
Second Appeal No. 311 of 1969.
B.R.L.
Iyengar and T.R. Ramasesh for the Appellants.
M.S. Ganesh,
R.B. Datar, Mrs. B. Tamta, N. Nettar, S.S. Jabali and B .P. Singh for the
Respondents.
The
Judgment of the Court was delivered by NATARAJAN, J.C.A. No. 471 of 1975 by
certificate and C.A. No. 3602 of 1984 and C.A. No. 461 of 1987 (arising out of
S.L.P. (Civil) No. 13120 of 1985) by Special Leave raise common questions of
law and hence they were heard together and are disposed of by this common
judgment. The judgments of the High Court in all the three cases have been
rendered in accordance with the opinion rendered by a Full Bench of the High
Court in a reference made in Regular Second Appeal No. 311 of 1969. The opinion
of the Full Bench was sought for in the following circumstances.
The
respondent in C.A. No. 471 of 1975 entered into an agreement with the State of Mysore
to purchase paddy on its behalf under the Paddy Procurement Scheme, 1959 and to
hull the paddy and supply rice. Clause 12 of the agreement relates to breach of
conditions of the agreement and the consequences that would ensue on such
breach. The said clause, referring to the respondent and the State as first
party 401 and second party respectively is worded as under:" In token of
the first party's willingness to abide by the above conditions, the first party
has hereby deposited as security a sum of Five Hundred Rupees only with the
second party and for any breach of conditions set forth hereinbefore, the first
party shall be liable to pay damages to the second party as may be assessed by
the second party, in addition to the forfeiture in part or whole of the amount
deposited by him. Any amount that may become due or payable by the first party
to the second party under any part of the agreement, shall be deemed to be and
may be recovered from the first party as if they were arrears of land
revenue." The State alleged that the respondent had committed a breach of
the contract by making short delivery of rice and demanded payment of damages
assessed at Rs.7,344.16ps. by the Deputy Commissioner.
As the
respondent failed to pay the damages the State initiated proceedings under the
Revenue Recovery Act to recover the amount as if it were arrears of land
revenue. The respondent filed a suit to challenge the recovery proceeding as
being illegal and for a permanent injunction to restrain the State from
pursuing the recovery proceedings. The trial court dismissed the suit but the
Appellate Court decreed the suit. The State preferred a Second Appeal to the
High Court. In the Second Appeal a reference was made to the Full Bench for its
opinion since there were two conflicting decisions of Division Benches of the
High Court on the questions of law raised in the appeal.
The
Full Bench answered the reference in the following manner: "Where an
agreement between the State and a private person provides that for any breach
of any of the conditions of such agreement by such person he shall be liable to
pay such damages as may be assessed by the State and that any amount that may
become due or payable by such person to the State under any part of that
agreement, shall be deemed to be and may be recovered from such person as if
they were arrears of land revenue-(i) the State is not competent to adjudicate
upon the question whether such a person committed breach of contract and that
the State is not competent to assess 402 damages for any breach of the contract
which is not admitted by the other side:
(ii) damages
so assessed cannot be recovered from such person as if they were arrears of
land revenue".
In
accordance with the opinion of the Full Bench the Second Appeal preferred by
the State was dismissed. The High Court, however, granted a certificate of
leave to the State and that is how this appeal by certificate has come to be
filed.
The
other two appeals relate to two contractors who had entered into agreements
with the State of Mysore for constructing certain buildings. As the contractors
failed to complete the works their contracts were terminated and in terms of
the agreements entered into by them the damages payable by them for breach of
contract were assessed and the damages were sought to be recovered as arrears
of land revenue. Both the contractors filed writ petitions under Article 226 of
the Constitution and challenged the validity of the assessment of the damages
and the recovery proceedings. Following the ruling of the Full Bench referred
to above the High Court allowed both the writ petitions and quashed the
proceedings for recovery of damages. Against the judgments of the High Court
the State has preferred the other two appeals.
Mr.
B.R.L. Iyenger, learned counsel for the appellant contended that the terms of
clause 12 of the agreement are wide and comprehensive enough to hold that the
Deputy Commissioner representing the State has competence and sanction to
decide whether any breach of the conditions of the contract had been committed
and also to determine the quantum of damages payable for the breach. In other
words, the argument was that the Deputy Commissioner, even though a party to
the agreement is empowered under Clause 12 to not only assess the damages
occasioned by the breach of the conditions but also to adjudicate upon any
issue concerning the commission of the breach itself. The learned counsel,
therefore, submitted that the opinion rendered by the Full Bench and the
judgments rendered in pursuance thereof are unsustainable and hence the appeals
by the State should be allowed.
On a
consideration of the matter we find ourselves unable to accept the contentions
of Mr. Iyenger. The terms of Clause 12 do not afford scope for a liberal
construction being made regarding the power 403 of the Deputy Commissioner to
adjudicate upon a disputed question of breach as well as to assess the damages
arising from the breach. The crucial words in clause 12 are "and for any
breach of conditions set forth hereinbefore, the first party shall be liable to
pay damages to the second party as may be assessed by the second party". On
a plain reading of the words it is clear that the right of the second party to
assess damages would arise only if the breach of conditions is admitted or if
no issue is made of it. If it was the intention of the parties that the officer
acting on behalf of the State was also entitled to adjudicate upon a dispute
regarding the breach of conditions the wording of Clause 12 would have been
entirely different. It cannot also be argued that a right to adjudicate upon an
issue relating to a breach of conditions of the contract would flow from or is
inhered in the right conferred to assess the damages arising from a breach of
conditions. The power to assess damages, as pointed out by the Full Bench, is a
subsidiary and consequential power and not the primary power. Even assuming for
argument's sake that the terms of Clause 12 afford scope for being construed as
empowering the officer of the State to decide upon the question of breach as
well as assess the quantum of damages, we do not think that adjudication by the
Officer regarding the breach of the contract can be sustained under law because
a party to the agreement cannot be an arbiter in his own cause. Interests or
justice and equity require that where a party to a contract disputes the
committing of any breach of conditions the adjudication should be by an
independent person or body and not by the other party to the contract. The
position will, however, be different where there is no dispute or there is
consensus between the contracting parties regarding the breach of conditions. In
such a case the Officer of the State, even though a party to the contract will
be well within his rights in assessing the damages occasioned by the breach in
view of the specific terms of Clause 12.
We
are, therefore, in agreement with the view of the Full Bench that the powers of
the State under an agreement entered into by it with a private person providing
for assessment of damages for breach of conditions and recovery of the damages
will stand confined only to those cases where the breach of conditions is
admitted or it is disputed.
The
further question requiring consideration is regarding the power of the State to
recover damages as arrears of land revenue under the Revenue Recovery Act. The
Full Bench has taken the view that the State is not entitled to recover damages
as arrears of land revenue because damages for breach of conditions will not
amount to 404 "money due under the contract". The Full Bench has
relied upon a decision of this Court in Divisional Forest Officer v. Mool Chand,
AIR 1971 S.C. 694 in support of its view.
This
decision cannot be an authority for the view taken by the Full Bench because it
has been rendered with reference to facts which are entirely different. What
fell for consideration in that case was whether a tender amount could be
recovered from a defaulting forest contractor as arrears of land revenue when
Section 75 of the Forest Regulation and Rule 10 of the Rules made thereunder
did not provide for such realisation. We are, however, concerned with cases
where the agreement entered into between the Government and the private persons
specifically provides for recovery of damages as arrears of land revenue. What
the Full Bench has failed to notice is that even though the damages become
payable on account of breach of conditions of the contract, the liability to
pay damages does not fall outside the terms of the contract but within the
terms of the contract. The words "any amount that may become due or
payable by the first party to the second party under any part of this
agreement" have to be read in conjunction with the earlier portion of the
clause stipulating liability on the party contracting with the State to pay
damages for breach of conditions. Therefore, it follows that though damages
become payable on account of breach of conditions of the agreement they
nevertheless constitute amounts payable under the contract i.e. under one of
the terms of the contract imposing liability to pay damages for breach of
conditions. To illustrate the position if the agreement provides for a
liquidated sum being paid as damages for breach of conditions instead of a sum
to be assessed by the Deputy Commissioner, it cannot be said that the specified
damages will not be money due under the contract and hence the damages cannot
be recovered under the Revenue Recovery Act. What applies to specified damages
will likewise apply to damages which are quantified after assessment. We,
therefore, hold that the opinion of the Full Bench in so far as the recovery of
damages and arrears of land revenue is concerned is not in accordance with law.
As it
is not disputed that in all the three cases the Officers acting on behalf of
the State have not only assessed the damages but have also acted as arbiters in
the dispute regarding the alleged breach of contract, the High Court was
justified in dismissing the Second Appeal preferred by the State in R.S.A. No.
311 of 1969 and in allowing the writ petitions filed by the two contractors.
All the appeals, therefore, have to fail and will accordingly stand dismissed.
The parties will pay and bear their respective costs.
A.P.J.
Appeals dismissed.
Back