Inder Pal Yadav & Ors Vs. Union of
India & Ors [1985] INSC 93 (18 April 1985)
DESAI, D.A. DESAI, D.A.
MISRA RANGNATH
CITATION: 1985 SCR (3) 837 1985 SCC (2) 648
1985 SCALE (1)703
ACT:
Constitution of India, Art 41 and 42-Right to
work- Casual labour employed on project for a number of years- Services of
casual labour terminated on completion of Project-Scheme framed subsequently
for casual labour- Validity of-Guidelines or implementation of Scheme- S.25 G,
I.D. Act and Art. 14 of the Constitution
HEADNOTE:
The petitioner-workmen styled as 'Project
Casual Labour' in these writ petitions and special leave petitions contended
that even though they had put in continuous service for years, their services
were terminated on the ground that the project on which they were employed has
been wound up on its completion and their services were no more needed. After
the conclusion of the hearing in some of the matters, the Railway Ministry
framed a scheme to find a just and humane solution affecting the livelihood of
the petitioner It provided that casual labour employed on projects may be
treated as temporary on completion of 360 days of continuous employment.
Disposing of the petitions, ^
HELD: 1. (i) By and large the scheme
certainly is an improvement on the present situation though not wholly
satisfactory. However the Railway being the biggest employer and having regard
to the nature of its work, it would have to engage casual labour and therefore,
as a preliminary step towards realisation of the ideal enshrined in Articles 41
and 42, this Court proposes to put its stamp of approval on the scheme with one
major variation which is herein set out.
[841D]
1. (ii) The scheme envisages that it would be
applicable to casual labour on projects who were In service as on January 1,
1984. The choice of this date does not commend, for it is likely to introduce
an invidious distinction between similarly situated persons and expose some
workmen to arbitrary discrimination flowing from fortuitous court's order,
since, in some matters, the court granted interim stay before the workmen could
be retrenched while some other were not so fortunate. Those in respect of when
the Court granted interim relief by stay suspension of the order of
retrenchment, they would be treated in service on l. l. 1981 while others who
fail to obtain interim rel if though similarly situated 838 would be pushed
down in the implementation of the scheme.
Therefore, those who could not come to the
Court need not be at a comparative disadvantage to those who rushed in here.
If they are otherwise similarly situated,
they are entitled to similar treatment. Keeping in view all the aspects of the
matter, the Court modifies part 5.1 (a) (i) of the scheme by modifying the date
from 1.1.1984 to 1.1. 1981. With this modification and consequent rescheduling
in absorption from that date onward, the scheme framed by Railway Ministry is
accepted and a direction is given that it must be implemented by re-casting the
stages consistent with the change in the date as herein directed. [841E-G;
842B-C] (2) To avoid violation of Art. 14, the scientific and equitable way of
implementing the scheme is for the Railway administration to prepare, a list of
project casual labour with reference to each division OF each railway and then
start absorbing those with the longest service. If in the process any
adjustments are necessary, the same must be done. In giving this direction, the
court is considerably influenced by the statutory recognition of the principle
of last come first go or to reverse it first come last go as enunciated in
s.25G of the Industrial Disputes Act, 1947.
[842D-F]
ORIGINAL JURISDICTION: Writ Petitions Nos.
147, 320-69, 459, 4335 4434/85 etc.
(Under Article 32 of the Constitution).
For the Appearing Parties: B. Datta RishiKesh
M.K. Rama murti MA. Krishnamurty. Anis Suhrawardy M S. Gujaral S.C.
Maheshwari PP Singh C. V. Subba Rao R.N.
Poddar C.P. Pardey V.R Verma R P. Singh Indira Sawhney S.C. Patel Harbans Singh
G.N. Chowdhary Narinder R D. Uradhyay PK. Jain K.R.
Nagaraja Shakil Ahmed Syed NS. Das Bahl K
R.P. Pillai D.Goburdhan C. Malhotra SN. Chowdhary V.K. Pandit Manoj Saxena
Madan, Sharma G.S. Narayan Ms. Halida Khatoon K K Gupta C. Agarwala h. Satish
Ms. A. Subhashini Sambandam and Pillai P.N. Gupta Mrs. Jayashree Wad and Raju
Ramachandran.
The Judgment of the Court was delivered by
DESAI,J. Articles 41 and 42 of the Constitution notwithstanding, there are
certain grey areas where the rule of hire and fire, a legacy of laissez-faire
even in Government employment still rules the roost. Casual labour employed on
projects also known as 'projects casual labour' is one such segment of
employment where one may serve for years and remain a daily rated worker
without a weekly off, without any security of service, without the protection
of equal pay for equal work. In short at the sweet will and mercy of the local
839 satraps. Even the formidable railwaymen's unions least cared for these
helpless and hapless workmen. Suddenly a torrent of writ petitions and
petitions for special leave awakened this Court to the plight of these workmen.
In quick succession, 48 writ petitions and 32 petitions for special leave
flooded this Court. In each writ petition / S.L.P., the grievance was that even
though the workmen styled as 'project casual labour' had put in continuous
service for years on end to wit ranging from 1974 till 1983, yet their services
were terminated with impunity under the specious plea that the project on which
they were employed has been wound np on its completion and their services were
no more needed. No one is unaware of the fact that Railway Ministry has a
perspective plan spreading over years say decades and projects are waiting in
queue for execution and year these workmen were shunted out (to use a cliche
from the railway vocabulary) without any chance of being re-employed. Some of
them rushed to the court and obtained interim relief. Some were not so
fortunate. At one stage some of these petitions were set down for final hearing
and the judgment was reserved. When some other similar matters came up, Mr.
K.G. Bhagat, the then learned Additional Solicitor General, requested the Court
not to render the judgment because he would take up the matter with the Railway
Ministry to find a just and humane solution affecting the livelihood of these
unfortunate workmen. As the future of lakhs of workmen going under the label of
casual project labour was likely to be affected, we repeatedly adjourned these
matters to enable the Railway Ministry to work out a scientific scheme.
Railway Ministry framed a Scheme and
circulated the same amongst others to all the General Managers of Indian
Railways including production units as per its circular No.
E(NG)II/84/CL/41 dated June 1, 1984. In the
Scheme it was stated that all the General Managers were directed to implement
the decision of the Railway Ministry by the target dates It was further stated
that a detailed letter regarding group 5 1(ii) would follow. Such a letter was
issued on June 25, 1984. Thereafter, these matters were set out for examining
the fairness and justness of the Scheme and whether the Court would be in a
position to dispose of these petitions in view of the Scheme. That is how these
matters came up before us.
The relevant portions of the Scheme read as
under:
840 "5.1. As a result of such
deliberations, the Ministry of Railways have now decided in principle that
casual labour employed on project (also known as 'project casual labour') may
be treated as temporary on completion of 360 days of continuous employment. The
Ministry have decided further as under:
(a) These orders will cover:
(i) Casual labour on projects who are in
service as on 1.1.84; and (ii) Casual labour on projects who, though not In
service on 1.1.84, had been in service on Railways earlier and had already
completed the above prescribed period (360 days) of continuous employment or
will complete the said prescribed period of continuous employment on
re-engagement in future. (A detailed letter regarding this group follows).
(b) The decision should be implemented in
phases according to the schedule given below:
Length of service Date from which Date by
which (i.e. (i.e.continuous may be treated decision should employment). as
temporary be implemented (i) Those who have 1.1.1984 31.12.1984 completed five
yearsof service as on 1.1.84 (ii) Those who have 1.1.1985 31.12.1985 completed
three years but less than five years of service as on 1.1.1984 (iii) Those who
have 1.1.1986 31.12.1986 ted 360 days but less than three years of service on
1.1.1984 841 (iv) Those who complete 1.1.1987 or 31.3.1987 360 days after the
date on which 1.1.1984 360 days are completed which ever is later.
5.2. The Ministry would like to clarify here
that casual labour on projects who have completed 180 days of continuous
employment would continue to be entitled to the benefits now admissible to them
(so long as they fulfil the conditions in this regard) till they become due for
the benefits mentioned in the preceding sub-paragraph." By and large the
scheme certainly is an improvement on the present situation though not wholly
satisfactory.
However, the railway being the biggest
employer and having regard to the nature of its work, it would have to engage
casual labour and therefore, as a preliminary step towards realisation of the
ideal enshrined in Articles 41 and 42, we propose to put our stamp of approval
on the scheme with one major variation which we proceed to herein set out.
The Scheme envisages that it would be
applicable to casual labour on projects who were in service as on January 1,
1984. The choice of this date does not commend to us, for it is likely to
introduce an invidious distinction between similarly situated persons and
expose some workmen to arbitrary discrimination flowing from fortuitous court's
order. To illustrate, in some matters, the court granted interim stay before
the workmen could be retrenched while some other were not so fortunate. Those
in respect of whom the court granted interim relief be stay/suspension of the
order of retrenchment, they would be treated in service on 1.1.1984 while
others who fail to obtain interim relief though similarly situated would be
pushed down in the implementation of the Scheme. There is another area where
discrimination is likely to rear its ugly head. These workmen come from the
lowest grade of railway service. They can ill afford to rush to court. Their
Federations have hardly been of any assistance. They had individually to
collect money and rush to court which in case of some may be beyond their
reach. Therefore, some of the retrenched workmen failed to knock 842 at the
doors of the court of justice because these doors do not open unless huge
expenses are incurred. Choice in such a situation, even without crystal gazing
is between incurring expenses for a litigation with uncertain outcome and
hunger from day to day. It is a Hobson's choice. Therefore, those who could not
come to the court need not be at a comparative disadvantage to those who rushed
in here. If they are otherwise similarly situated, they are entitled to similar
treatment if not by anyone else at the hands of this Court.
Burdened by all these relevant considerations
and keeping in view all the aspects of the matter, we would modify part 5.1 (a)
(i) by modifying the date from 1.1.1984 to 1.1.1981.
With this modification and consequent
rescheduling in absorption from that date onward, the Scheme framed by Railway
Ministry is accepted and a direction is given that it must be implemented by
re-casting the stages consistent with the change in the date as herein
directed.
To avoid violation of Art. 14, the scientific
and equitable way if implementing the scheme is for the Railway administration
to prepare, a list of project casual labour with reference to each division of
each railway and then start absorbing those with the longest service. If in the
process any adjustments are necessary, the same must be done. In giving this
direction, we are considerably influenced by the statutory recognition of a
principle well known in industrial jurisprudence that the men with longest
service shall have priority over those who have joined later on. In other
words, the principle of last come first go or to reverse it first come last go
as enunciated in Sec. 25G of the Industrial Disputes Act, 1947 has been
accepted. We direct accordingly.
All these writ petitions and special leave
petitions shall stand disposed of consistent with the scheme as modified by
this judgment and the directions herein given.
The scheme as would stand modified by the
directions here in given forms part of this judgment and a copy of it shall be
annexed to this judgment.
Learned counsel Shri Anis Suhrawardy has put
in the maximum labour in making a very useful compilation. He must have spent
days and months! The compilation helped us the most 843 in dealing with the
writ petitions and the special leave petitions and in ascertaining the proper
principle. Such a compilation ought to have been prepared by the Railway
administration. Therefore, we direct the Union of India to pay Rs. 5,000 as and
by way of costs to Shri Anis Suhrawardy, advocate, Supreme Court.
M.L.A. Petitions dismissed.
Back