Shiv Chand Amolak Chand Vs. Regional
Transport Authority & ANR [1983] INSC 152 (7 October 1983)
BHAGWATI, P.N.
BHAGWATI, P.N.
MISRA, R.B. (J)
CITATION: 1984 AIR 9 1984 SCR (1) 288 1983
SCC (4) 433 1983 SCALE (2)611
CITATOR INFO :
R 1984 SC 790 (16) RF 1986 SC1980 (18,19,27)
ACT:
Motor Vehicles Act, 1939-Section 47(3) and
57(8) scope of-Whether Section 47(3) of the Act will be applicable when an
application is made by a holder of a permit for extension of the route
specified in the permit.
HEADNOTE:
The appellants held stage carriage permit
granted to them by the Regional Transport Authority for the route Dabra-Karera
Via Lodi Mato-extended upto Gwalior. On 22-6- 1978, this route for which the
permit was held by the appellants was modified, at their own request, by
deleting the portion of the route from Karera to Shivpuri. By a notification
dated 4-8-1978 certain routes were nationalised under Scheme No. 11-M which
came into effect from 25-9-1978, including deletion of the portion of the route
from Shivpuri to Satanwara, with the result the permit of the appellants
remained operative only for the remaining portion of the route namely,
Satanwara-Gwalior Via Dabra. Effective from 19-12-1978, the State Government
issued another Notification making modifications in the route schemes. Since
this modification permitted plying of stage carriages by private operators even
on a portion of a nationalised route connecting a district headquarters and not
more than 20 KMs in length, the appellants made an application to the Regional
Transport Authority-for restoring the portion of the route from Shivpuri to
Satanwara on the ground that Shivpuri was a district headquarter and the
portion of the route from Shivpuri and Satanwara was less than 20 KMs. The
Regional Transport Authority rejected the said application on the ground that
the Notification dated 18-12-1978 did not have any retrospective effect and
therefore, the appellants were not entitled to automatic restoration of the
portion of the route from Shivpuri to Satanwara.
The appellants thereupon filed an application
in the prescribed form for extension of the route specified in their permit
from Satanwara to Shivpuri. The said application was rejected after hearing the
objections on two grounds, namely (i) the specific order of the State Govt.
Curtailing the Satanwara-Shivpuri portion of
the applicants' permit, while approving Scheme 11-M cannot be treated as having
been amended by the General Amendment to the Scheme, and (ii) no extension of
the route could be granted without following the procedure laid down in Section
47(3) of the Act. This order of the Regional Transport Authority was challenged
by the appellants in a writ petition filed in the High Court of Madhya Pradesh.
The High Court rejected the petition holding that by reason of the express
language of Sub-Section (8) of Section 57, an application for extension of the
route specified in an existing permit was tantamount to an application for
grant of a new permit and hence 289 it was subject to the provisions of Section
47(3) and it could not be considered without following the procedure prescribed
by Section 47(3). Hence the appeal after obtaining special leave of the Court.
Allowing the appeal, the Court
HELD: 1.1 The application made by the
appellants for extension of the route specified in their permit from Satanwara
to Shivpuri could be considered by the Regional Transport Authority without
following the procedure prescribed under Sub-Section (3) of Section 47. [297
E-H]
1.2 However, under the terms of Sub-Section
(8) of Section 57 this application of the appellants was liable to be treated
as an application for the grant of a new permit, since in effect and substance,
it was an application for varying the condition of the permit by extending the route
from Shivpuri to Satanwara. But the question is for what purpose? [297 G-H]
2.1 Having regard to the several decisions of
the Supreme Court and particularly the decision in Mohd. Ibrahim v. State
Transport Appellate, Tribunal, Madras, [1971] 1 S.C.R. 474, the law is well
settled that an application for grant of a new permit cannot be entertained by
the Regional Transport Authority under Section 48, unless the limit of the
number of stage-carriages for which permits may be granted is first determined
under section 47(3). There are two independent steps required to be taken in
connection with the grant of a permit, the first being the determination by the
Regional Transport Authority under Section 47(3) of the number of
stage-carriages for which permits may be granted and the second being that
"thereafter applications for stage carriage permits can be
entertained" and, therefore, it would mean that before an application for
grant of a permit can be entertained by the Regional Transport Authority, there
should be a determination under Section 47(3). Therefore, if an application for
varying the condition of a permit by extension of the route specified in the
permit were equated wholly with an application for grant of a new permit and
the permit for the extended route were to be regarded as a new permit, the
procedure prescribed in Section 47(3) would have to be followed and the number
of stage carriages for which permits may be granted on the extended route would
have to be determined before the application could be entertained by the
Regional Transport Authority.
[298 C-E; 299 E-F]
2.2 But, the prescription in Sub Section (8)
of Section 57 that an application for varying the condition of a permit by
extension of the route shall be treated as an application for grant of a new
permit has not the effect of equating of such an application with an
application for grant of a new permit for all purposes so as to attract the
applicability of Sub Section (3) of Section 47. [299 F-G]
3.1 Section 57 deals with the procedure in
applying for and granting permits and Sub Sections (3) to (7) lays down the
procedure which must be followed in considering and deciding, inter-alia, an
application for grant of a stage- carriage permit. Sub Section (8) follows upon
Sub Sections (3) to (7) 290 and is a part of the same Section which has a
definite object and Scheme of providing the procedure for considering and
granting an application and therefore, when it provides that an application to
vary the conditions of a permit by the inclusion of new route or routes or new
area or by increasing the number of trips above the specified maximum or by
altering the route covered by it shall be treated as an application for grant
of a new stage carriage permit, it is obviously intended to incorporate and
make applicable the procedure set out in the preceding Sub Sections (3) to (7)
to such an application. The context in which Sub-Section (8) occurs and its
juxtaposition with Sub Section (3) to (7) in Section 58 clearly indicate that
what is sought to be made applicable to an application referred to in Sub
Section (8) by treating it as an application for grant of a new permit is the
procedure set out in Sub Section (3) to (7) of Section 58 and nothing more.
[299 G-H; 300 A-C]
3.2 The requirement spelt out in Sub Section
(3) of Section 47 that the number of stage carriages for which permits may be
granted on any particular route must be first determined before an application
for grant of a stage carriage permit can be entertained by the Regional Transport
Authority under Section 48, is obviously not a part of the procedure for
considering an application for grant of a permit; it is a condition precedent
before an application for grant of a permit can be considered and granted. This
condition cannot be said to have been incorporated by reference under Sub
Section (8) of Section 57. An application to vary the conditions of a permit as
set out in Sub Section (8) of Section 57 is undoubtedly to be treated as an
application for grant of a new permit, but that is only for the purpose of
applying the procedure set out in Sub Sections (3) to (7) of Section 57. It is
not an application for a new permit and if it is granted, the permit for the
extended route does not become a new permit in the hands of the applicant. It
is the same permit which now after granting of the application covers the
extended route. [300 C-F]
3.3 Where a totally new route is sought to be
included by an application to vary the conditions of a permit or the alteration
of the route sought by such an application is of such a drastic character that
it becomes substantially a new route, the application, though in form an
application to vary the conditions of the permit, would in effect and
substance, be an application for grant of a new permit and in such a case, a
view may conceivably be taken with some degree of plausibility that the number
of stage-carriages for which permits may be granted on such new route should
first be determined under Sub Section (3) of Section 47 before the application
to vary the conditions of the permit can be entertained. [300 F-H] An applicant
for a permit on a route which is not merely technically, but in truth and
reality a different route, distinct from the original route, may not be
permitted to defeat the provision, enacted in Sub Section (3) of Section 47, by
labelling his application as one for varying the conditions of the permit and
in such a case, the procedure set out in Section 47 (3) may have to be complied
with before the Regional Transport Authority can consider and grant the
application. [300 H; 301 A] 291 But where an application merely seeks a short
extension of the route specified in the permit, as in the present case, it
would not be appropriate to say that it is an application for grant of a new
permit, though technically the extended route may not be regarded as the same
as the original route and where such is the case, it would not be necessary to
comply with the procedure set out in Sub Section (3) of Section 47 of the Motor
Vehicles Act. [301 B- C]
CIVIL APPELLATE JURISDICTION: Civil Appeal
No. 3787 of 1983.
Appeal by Special leave from the Judgment and
Order dated the 19th March, 1971 of the Madhya Pradesh High Court in Misc.
Petition No. 565 of 1980.
S.Q. Hassan, S.K. Mehta, P.N. Puri and M.K.
Dua for the Appellant.
Rameshwar Nath for the Respondent.
The Judgment of the Court was delivered by
BHAGWATI, J. This appeal by special leave raises a short but interesting
question of law relating to the interpretation of certain provisions of the
Motor Vehicles Act 1939 (hereinafter referred to as the Act). The question is
whether section 47 sub-section (3) of the Act is attracted when an application
is made by the holder of a permit for extension of the route for which the
permit has been granted to him. In order to appreciate the question, it is
necessary to state a few facts giving rise to the appeal.
The appellants are a partnership firm and at
all material times they held a stage carriage permit granted to them by the
Regional Transport Authority for the route Dabra-Karera via Lodi Mata extended
upto Gwalior. It appears that on 22nd June 1978 this route for which the permit
was held by the appellants was modified at the request of the appellants and
the portion of the route from Karera to Shivpuri was deleted. Thereafter by a
Notification dated 4th August 1978 certain routes were nationalised under
Scheme No. 11-M which came into force with effect from 25th September 1978 and
under clause 7 (b) of this Scheme, the portion of the route from Shivpuri to
Satanwara was deleted and the permit of the appellants remained operative only
for the remaining portion of the route, namely, Satanwara- Gwalior via Dabra.
This state of affairs conti- 292 nued from 25th September 1978 until 18th
December 1978 when the State Government by a Notification issued in exercise of
the powers conferred under sub-section (2) of section 68 F of the Act made the
following modifications in the various schemes approved by it under section 68
D sub-section (2), including Scheme No. 11-M:
"Notwithstanding anything contained in
this Scheme, the private operators may be permitted to ply stage carriages for
hire or reward subject to the following conditions, namely:
(1) Whereas the notified route connects a
district Head-quarter, the portion thereof covered by the permit shall not
exceed 20 kilometers and in other cases it shall not exceed 10 kilometers.
(2) The private operators shall ply the stage
carriage over the distance, other than the distance of the notified route,
which shall not be less than twice the distance of the notified route covered
by the permit;
(3) The private operators shall not pick-up
or set- down passengers on the notified route.
Since this modification permitted plying of
stage carriages by private operators even on portion of a nationalised route
connecting a district head-quarter and not more than 20 kms.
in length, the appellants made an application
to the Regional Transport Authority for restoring the portion of the route from
Shivpuri to Satanwara on the ground that Shivpuri was a district head-quarter
and the portion of the route between Shivpuri and Satanwara was less than 20
kilometers. The Regional Transport Authority however took the view and in our
opinion rightly, that the modification made by the State Government in Scheme
No. 11-M under the Notification dated 18th December 1978 did not have any
retrospective effect and the appellants were therefore not entitled to
automatic restoration of the portion of the route from Shivpuri to Satanwara and
in this view, the Regional Transport Authority rejected the application of the
appellants.
The appellants thereupon filed a regular
application in the prescribed form for extension of the route specified in
their permit 293 from Satanwara to Shivpuri. The application was published in
the Gazette on 11th April 1980 and on coming to know about it, M.P. State Road
Transport Corporation which is the 2nd respondent before us filed its
objections against the grant of such extension. The application together with
the objections was heard by the Regional Transport Authority and by an order
dated 11th September 1980 the Regional Transport Authority rejected the
application on two grounds. The first ground was that "the specific order
of the State Government curtailing the Satanwara-Shivpuri portion of
applicant's permit while approving Scheme No. 11-M cannot be treated as having
been amended by the general amendment made to the scheme" and the other
was that no extension of the route could be granted without following the
procedure laid down in Section 47 sub-section (3) of the Act.
This order made by the Regional Transport
Authority was challenged by the appellants in a writ petition filed in the High
Court of Madhya Pradesh. There were two grounds of challenge urged on behalf of
the appellants in support of the writ petition but we are concerned in this
appeal with only one ground and hence we need not refer to the other ground and
burden our judgment with a discussion of that ground. The ground which was
seriously pressed before the High Court and repeated before us was that Section
47 sub- section (3) has no application where what is sought by an applicant is
not the grant of a new permit on a specified route under section 48 but merely
an extension of the route under an existing permit under sub-section (8) of
section 57 and the order made by the Regional Transport Authority rejecting the
application of the appellants on the ground of non-compliance with sub-Section
(3) of section 47 was therefore plainly wrong. The appellants sought to support
this ground by relying on the decision of the Madhya Pradesh High Court in
Dewan Chand v. State Transport Authority. But the learned Judge who heard the
writ petition observed that the decision in Dewan Chand's case (supra) was
contrary to the view taken by this Court in R. Obliswamy Naidu v.
Regional State Transport Appellate Tribunal
and Delhi Transport Undertaking v. Zamindar Motor Transport Company and held
that by reason of the express language of sub- section (8) of section 57 an
application for 294 extension of the route specified in an existing permit was
tantamount to an application for grant of a new permit and hence it was subject
to the provisions of section 47 sub- section (3) and it could not be considered
without following the procedure prescribed by sub-section (3) of section 47.
The learned Judge on this view rejected the
writ petition of the appellants. The appellants thereupon preferred the present
appeal with special leave obtained from this Court.
The only question which arises for
consideration in this appeal is as whether section 47 sub-section (3) is
attracted when an application is made by a holder of a permit for extension of
the route specified in the permit.
The determination of this question depends
upon a true interpretation of some of the relevant provisions of the Act.
Section 2 is the definition section and clause (28A) of this section defines
route to mean "a line of travel which specifies the high-way which may be
traversed by a motor vehicle between one terminus and another". Chapter IV
is the only material chapter for our purpose and as its heading shows, it deals
with control of transport vehicles. Section 42 provides that no owner of a
transport vehicle shall use or permit the use of the vehicle in any public
place save in accordance with the conditions of a permit granted or
countersigned by a Regional or State Transport Authority or the Commission
authorising the use of the vehicle in that place in the manner in which the
vehicle is being used.
Section 43 confers certain powers on the
State Government to issue directions to the State Transport Authority and
section 44 provides for the constitution of State Transport Authority and
Regional Transport Authorities for each State.
Section 45 specifies the authority to which
an application for a permit must be made and what particulars an application
for a permit shall contain is prescribed in section 46. Section 47 sub-section
(1) lays down what matters shall be taken into account by the Regional
Transport Authority in considering an application for a stage carriage permit
and various other provisions regarding reservation of certain percentage of
stage carriage permits for Scheduled Castes and Scheduled Tribes and persons
belonging to economically weaker sections of the community are made in
sub-section (1A) to sub-section (1H) of section
47. Then follows sub-section (3) of section
47 which is in the following terms:
"47 (3). A Regional Transport Authority
may, having regard to the matters mentioned in sub-section (1) limit the number
of stage carriages generally or of any specified 295 type for which stage
carriage permits may be granted in the region or in any specified area or on
any specified route within the region." Section 48 sub section (1)
provides that, subject to the provisions of section 47, a Regional Transport
Authority may, on an application made to it under section 46, grant a stage
carriage permit in accordance with the application or with such modifications
as it deems fit or refuse to grant such a permit, provided that no such
permission shall be granted in respect of any route or area not specified in
the application. Sub-section (3) of section 48 empowers the Regional Transport
Authority while granting a stage carriage permit to attach to the permit any
one or more of the conditions set out in that sub-section. One of the
conditions which may be attached to the permit is that set out in clause (xxi)
and it reads as follows:
"48(xxi): that the Regional Transport
Authority may, after giving notice of not less than one month- (a) vary the
conditions of the permit;
(b) attach to the permit further conditions;
Provided that the conditions specified in
pursuance of clause (i) shall not be varied so as to alter the distance covered
by the original route by more than 24 kilometres, and any variation within such
limits shall be made only after the Regional Transport Authority is satisfied
that such variation will serve the public convenience and that it is not
expedient to grant a separate permit in respect of the original route as so
varied or any part thereof." Sections 49 to 51 deal with an application
for grant of contract carriage permit while sections 52 and 53 deal with an
application for grant of private carrier's permit. We are not concerned with
these provisions and hence we need not refer to them. So also we are not
concerned with sections 54 to 56 which deal with application for public
carrier's permit. Section 57 is however an important section and in its various
provisions it lays down the procedure in applying for and granting permits.
Sub-section (2) of section 57 296 prescribes the time within which an
application for a stage carriage permit should be made and sub-Sections (3) to
(7) lay down the procedure which must be followed by the Regional Transport
Authority while dealing with an application for a stage carriage permit made
before it. Sub- section (8) of section 57 is the material provision which calls
for interpretation and it runs as follows:
"57 (8): An application to vary the
conditions of any permit, other than a temporary permit, by the inclusion of a
new route or routes or a new area or, in, the case of a stage carriage permit,
by increasing the (number of trips above the specified maximum or by altering the
route covered by it) or in the case of a contract carriage permit or a public
carrier's permit, by increasing the number of vehicles covered by the permit,
shall be treated as an application for the grant of a new permit." The
argument of the respondents on these provisions was, and this argument found
favour with the High Court, that an application for extension of the route
specified in a permit is nothing but an application to vary the conditions of
the permit by altering the route covered by it and it is therefore required by
sub-section (8) of section 57 to be treated as an application for grant of a
new permit and hence, by reason of section 48, the grant of such an application
for extension must be held to be subject to the provisions of section 47
sub-section (3) and no such extension can be granted without following the
procedure prescribed by sub-section (3) of section 47. The validity of this
argument was assailed before us on behalf of the appellants and it was
contended that the fulfillment of the condition set out in sub-section (3) of
section 47 was not a part of the procedure for consideration of an application
for extension of the route specified in a permit and when sub-section (8) of
section 57 provided that such an application shall be treated as an application
for grant of a new permit, what was sought to be incorporated was merely the
procedure set out in sub-section (3) to (7) of Section 57 and not pre-condition
for consideration of such an application set out in sub-section (3) of Section
(47). This contention, it was submitted on behalf of the appellants, was
supported by Clause (xxi) of sub-section (3) of Section 48, because if the
condition set out in that clause is attached to a permit, the Regional
Transport Authority can suo motu extend the route specified in the permit up to
a distance of 297 24 k.ms. for serving the public convenience, without being
subject to the provisions of sub-section (3) of Section 47 and if the Regional
Transport can do so suo motu without being required to follow the procedure of
sub-section (3) of Section 47, there is no reason why the Regional Transport
Authority should not be entitled to do so on an application for extension made
by the holder of the permit. These were the rival arguments urged on behalf of
the parties and we shall now proceed to consider them.
The permit held by the appellants in the
present case, after the deletion of the portion of the route from Shivpuri to
Satanwara was operative only for the remaining portion of the route namely, Satanwara-Gwalior
via Dabra and in view of the modification made in Scheme No. 11-M by the
notification issued by the State Government under section 68F sub-section (2)
on 18th December, 1978, the appellants applied for extension of the route from
Satanwara to Shivpuri, a distance less than 20 kilometers. The question it
whether this application could be considered by the Regional Transport
Authority without first determining under section 47 sub-section (3) the number
of stage carriages for which permits may be granted for the route
Shivpuri-Satanwara- Gwalior via Dabra, because if the extension applied for
were granted, that would be the route for which the permit would be operative.
Now, it is clear that it was a condition of the permit, after the deletion of
the portion of the route from Shivpuri to Satanwara, that the appellants shall
use their vehicle or vehicles only on the route Satanwara- Gwalior via Dabra.
The application of the appellants for extension of this route by including the
portion from Shivpuri to Satanwara was, therefore, in effect and substance, an
application for varying this condition of the permit by extending the route and
it clearly fell within the terms of sub-section (8) of section 57. So far there
was no dispute between the parties, but at this point the agreement between the
parties ended and a controversy arose as to what was the consequence and effect
of the applicability of sub- section (8) of section 57 to this application made
by the appellants. There can be little doubt that under terms of sub-section
(8) of section 57, this application of the appellants was liable to be
"treated as an application for the grant of a new permit". But the
question is: for what purpose and which of the provisions of the Act could be
said to be attracted to this application by reason of the requirement that it
should be treated as an application for the grant a new permit. The argument of
the respondents was that no application for grant of a new permit can be
entertained by the Regional Transport Authority under section 48, unless the
number of stage carriages 298 for which permits may be granted for the
particular route is first determined by the Regional Transport Authority under
sub-section (3) of section 47, and, therefore, the consequence of treating the
application of the appellants for extension of the route as an application for
grant of a new permit was that no extension could be granted by the Regional
Transport Authority unless the requirement of section 47 sub-section (3) was
first complied with and the number of stage carriages for which permits may be
granted on the extended route was determined under that provision.
But we do not think this argument is
well-founded.
It is undoubtedly true that having regard to
the several decisions of this Court and particularly, the decision in Mohd.
Ibrahim v. State Transport Appellate Tribunal, Madras, the law must now be
taken to be well- settled that an application for grant of a new permit cannot
be entertained by the Regional Transport Authority under section 48, unless the
limit of the number of stage carriages for which permits may be granted is
first determined under section 47 sub-section (3). There are two independent
steps required to be taken in connection with the grant of a permit, the first
being the determination by the Regional Transport Authority under section 47
sub- section (3) of the number of stage carriages for which permits may be
granted and the second being that "thereafter applications for stage
carriage permits can be entertained" and, therefore, it would mean that
before an application for grant of a permit can be entertained by the Regional
Transport Authority, there would be a determination under section 47 subsection
(3). Ray, J., as he then was speaking on behalf of the Court observed in
Ibrahim's case (supra):
"In our opinion, the provisions of the
Act in regard to stage carriage permits have the following consequences. If the
Regional Transport Authority were to appoint a date for the receipt of
applications for the grant of stage carriage permits, the Regional Transport
Authority should fix the limit of the number of permits which might be granted
and then notify the same under section 57 (2) of the Act. If, on the other
hand, applications were sent by persons suo motu for the grant of permit the
applications would have to be published and the representations would have to
be asked for. The proviso of 299 section 57 (3) of the Act furnishes the answer
that if the grant of any permit in accordance with the application would have
the effect of increasing the number of permits beyond the limit fixed under
section 47 (3) of the Act, the Regional Transport Authority might summarily
refuse the application without following the procedure laid down in section 57
of the Act. In other cases, the proper stage for fixing the limit under section
47 (3) of the Act would be after applications are received and before the same
would be published under section 57 (3) of the Act asking for representations.
If however the Regional Transport Authority would not increase or modify the
number of permits which already exist, the grant of an application would mean
transgressing the limit fixed, and procedure laid down in section 57 (3) of the
Act need not than be followed. On the other hand, if the Regional Transport
Authority on receipt of applications would decide upon the limit of permits and
the grant thereof would be with-in the limit prescribed then the procedure laid
down in section 57 (3) of the Act would be followed." There can, therefore,
be no doubt that if an application for varying the condition of a permit by
extension of the route specified in the permit were equated wholly with an
application for grant of a new permit and the permit for the extended route
were to be regarded as a new permit, the procedure prescribed in section 47
sub-section (3) would have to be followed and the number of stage carriages for
which permits may be granted on the extended route would have to be determined
before the application could be entertained by the Regional Transport
Authority. But we do not think that the prescription in sub-section (8) of
section 57 that an application for varying the condition of a permit by
extension of the route shall be treated as an application for grant of a new
permit has effect of equating such an application with an application for grant
of a new permit for all purposes so as to attract the applicability of
sub-section (3) of section 47. Section 57 deals with the procedure in applying
for and granting permits and sub- section (3) to (7) lay down the procedure
which must be followed in considering and deciding, inter alia, an application
for grant of a stage carriage permit. Sub- section (8) follows upon sub-section
(3) to (7) and is part of the same section which has a definite object and
scheme of providing the procedure for considering and granting an application
and therefore, when it 300 provides that an application to vary the conditions
of a permit by the inclusion of new route or routes or new area or by increasing
the number of trips above the specified maximum or by altering the route
covered by it shall be treated as an application for grant of a new stage
carriage permit it is obviously intended to incorporate and make applicable the
procedure set out in the preceding sub- section (3) to (7) to such an
application. The context in which sub-section (8) occurs and its juxtaposition
with sub- section (3) to (7) in section 58 clearly indicate that what is sought
to be made applicable to an application referred to in sub-section (8) by
treating it as an application for grant of a new permit, is the procedure set
out in sub- section (3) to (7) of section 58 and nothing more. The requirement
spelt out in sub-section (3) of section 47 that the number of stage carriages for
which permits may be granted on any particular route must be first determined
before an application for grant of a stage carriage permit can be entertained
by the Regional Transport Authority under section 48, is obviously not a part
of the procedure for considering an application for grant of a permit; it is a
condition precedent before an application for grant of a permit can be
considered and granted. This condition precedent cannot be said to have been
incorporated by reference under sub-section (8) of section 57. An application
to vary the conditions of a permit as set out is undoubtedly to be treated as
an application for grant of a new permit, but that is only for the purpose of
applying the procedure set out in sub-section (3) to (7) of that section.
It is not an application for a new permit and
if it is granted, the permit for the extended route does not become a new
permit in the hands of the applicant. It is the same permit which now, after
the granting of the application, covers the extended route. It may be possible
to say that where a totally new route is sought to be included by an
application to vary the conditions of a permit or the alteration of the route
sought by such an application is of such a drastic character that it becomes
substantially a new route, the application, though in form an application to
vary the conditions of the permit, would in effect a and substance, be an
application for grant of a new permit and in such a case, a view may
conceivably be taken with some degree of plausibility that the number of stage
carriages for which permits may be granted on such new route should first be
determined under section 47 sub-section (3) before the application to vary the
conditions of the permit can be entertained. An applicant for a permit on a
route which is not merely technically, but in truth and reality a different
route, distinct from the original route, may not be permitted to defeat the
provision enacted in section 47 sub- section (3) by 301 labeling his
application as one for varying the conditions of the permit and in such a case,
the procedure set out in section 47 sub-section (3) may have to be complied
with before the Regional Transport Authority can consider and grant the
application. But where an application merely seeks a short extension of the
route specified in the permit as in the present case, it would not be
appropriate to say that it is an application for grant of a new permit, though
technically the extended route may not be regarded as the same as the original route
and where such is the case, it would not be necessary to comply with the
procedure set out in sub-section (3) of Section 47.
We are, therefore, of the view that the High
Court was in error in holding that the application made by the appellants for
extension of the route specified in their permit from Satanwara to Shivpuri
could not be considered by the Regional Transport Authority without following
the procedure prescribed under sub-section (3) of Section 47. We accordingly
allow the appeal, set aside the judgment of the High Court as also the order
made by the Regional Transport Authority and remit the case back to the
Regional Transport Authority for considering the application of the appellants
in accordance with law in the light of the observations contained in this
judgment. There will be no order as to costs of the appeal.
S.R. Appeal allowed.