Kamaluddin Ansari & Co. V. Union
Of India [1983] INSC 94 (12 August 1983)
MISRA, R.B. (J) MISRA, R.B. (J) DESAI, D.A.
ERADI, V. BALAKRISHNA (J)
CITATION: 1984 AIR 29 1983 SCR (3) 607 1983
SCC (4) 417 1983 SCALE (2)107
CITATOR INFO :
F 1989 SC1498 (28)
ACT:
Arbitration Act, 1940 - cls. (a) and (b) of
s. 41- Interpretation of-Court has power under cl. (b) to issue interim
injunctions only for the purpose of and in relation to the arbitration
proceedings before the Court.
Contracts with Government of India-cl. 18 of
Standard Form of Contract -Interpretation of- Whether for fulfillment of a
claim for payment of a sum of money arising under a contract the Government has
power to withhold sum due under other contracts ?.
Interpretation- 'Headings' cannot be used to
give different effect to clear words in the section.
HEADNOTE:
The DGS&D, representing the Government of
India, had entered into a contract with the appellant firm for supply of some
timber. Clause 18 of the standard form of contract, under the head
"Recovery of sums due", provided inter alia that whenever any claim
for payment of a sum of money arose out of or under the contract against. The
contractor, the purchaser shall be entitled to recover such sum by
appropriating any sum then due or which at any time thereafter may become due
to the contractor under any other contract with the purchaser. Clause 24
thereof provided for arbitration in the event of any dispute arising between
the parties. The appellant failed to supply the timber. The DGS&D cancelled
the contract, made risk purchases at extra cost and issued notice calling upon
the appellant to pay the extra cost incurred and threatening to withhold the
amount from the payments due under the pending bills of other contracts. The
appellant moved a petition under s. 33 of the Arbitration Act, 1940 alleging
that there was no concluded contract in existence between the parties,
containing any arbitration clause and praying for an injunction restraining the
Union of India from appropriating, withholding or recovering the amount claimed
from its other bills. The High Court held that under s. 41 of the Act it could
only grant an injunction restraining the Union of India from appropriating or
recovering the amount of damages claimed from the other pending bills of the
appellant, and rejected the prayer for grant of injunction restraining the
Union of India from withholding payments of the other pending bills.
Dismissing the appeal,
HELD: 1. Clause 18 of the standard form of
contract confers ample power upon the Union of India to withhold the amount and
no injunction 608 order could be passed restraining the Union of India from
withholding the amount [623 B] (i) The golden rule of construction is that when
the words of a statute are clear, plain and unambiguous, that is, they are
reasonably susceptible to only one meaning, the Courts are bound to give effect
to that meaning irrespective of the consequences. 'The duty of a judge is to
expound and not to legislate is fundamental rule. If this principle is applied
to the interpretation of cl. 18 of the standard form of contract it would be
clear that the clause unequivocally contemplates a claim for payment. It does
not contemplate the amount due and, therefore, the heading of this clause which
talks of only 'Recovery of sums due' will not control cl. 18. Headings cannot
be used to give a different effect to clear words in the section where there
cannot be any doubt as to the ordinary meaning of the words. The clause gives
wide powers to the Union of India to recover the amount claimed by
appropriating any sum then due or which at any time thereafter may become due to
the contractor under other contracts. [620 A-G] (ii) Clause 18 was slightly
differently worded earlier when it read 'whenever under this contract any sum
of money is recoverable from and payable by the contractor'. But this formula
was deliberately and advisedly altered when the present standard form was
introduced by substituting the words 'whenever any claim for payment of a sum
of money arises' and this change in phraseology indicated that in order to
attract the applicability of the present cl. 18, it was not necessary that
there should be a sum of money due and payable by the contractor to the
purchaser, but it was enough if there was a mere claim on the part of the
purchaser for payment of a sum of money by the contractor irrespective of the
fact whether such sum of money was presently due and payable or not. Even after
the change in the language of cl 18 the Union of India cannot be injuncted from
withholding the amount under other bills of the contractor. But it can
certainly be injuncted from recovering or appropriating it to the damages
claimed. [620 H-621A, G] Union of India v. Raman Iron Foundry, [1974] 3 S.C.R.
556 overruled.
2. An injunction order restraining the Union
of India from withholding the amount due to the contractor under other pending
bills virtually amounts to a direction to pay the amount to the
contractor-appellant. Such an order was beyond the purview of cl. (b) of s. 41
of the Arbitration Act. [621 H-622 A] (i) Clause (b) of s. 41 confers power on
the court to pass orders in respect of any of the matters set out in the Second
Schedule which inter alia includes `interim junction'. But this power to pass
an order of injunction can only be excercised 'for the purpose of and in
relation to arbitration proceedings' before the Court. [61 5H] In the instant
case the proceedings before the Court were pursuant to an application made
under s. 33 of the Act in which the appellant had taken the stand that there
was no concluded contract between the parties containing an arbitration clause.
Therefore, it is difficult to say that the 609 application for injunction moved
by the appellant was for the purpose of and in relation to arbitration
proceedings.
That apart, the amount due to the appellant
under the pending bills was not the subject-matter of the present proceedings
and, therefore, the injunction order restraining the respondent from
withholding the amount due to the appellant under the pending bills in respect
of other contracts could not be said to be for the purpose of and in relation
to the present arbitration proceedings. [616 A, C, 617 A-B] Union of India v.
Raman Iron Foundry [1974] 3 S.C.R.
556, referred to.
Mohan Meaken Breweries v. Union of India,
A.I.R. 1975 Delhi 248, approved.
(ii) The contention that cl. (a) of s. 41
makes the Code of Civil Procedure applicable to all proceedings before the
Court and to all appeals under the Act and, therefore, the appellant was
entitled lo invoke o. 39 of the Code to get an injunction order even if the
conditions of cl. (b) of s. 41 were not satisfied cannot be accepted. Clause
(a) of s. 41 makes only the procedural rules of the Code applicable to the proceedings
in court under the Arbitration Act. This clause does not authorise the court to
pass an order of injunction. If the above contention is accepted, appeals would
lie under ss. 96, 100 or 104 of the Code. But the Act itself provides for
appeal under s. 39. Besides, if cl, -(a) of s. 41 gave wide powers to pass all
order of injunction, cl. (b) of s. 41 would become otiose. [616 D-F] (iii) If
an order injuncted a party from withholding the amount due to the other side
under pending bills in other contracts, the order necessarily means that the
amount must be paid. It will be a contradiction in terms to say that a party is
injuncted from withholding the amount and yet it can withhold the amount as of
right. In any case if the injunction order is one which a party was not bound
to comply with, the Court would he loath and reluctant to pass such an
ineffective injunction order. In injunction order is passed only for the
purpose of being carried out. [618 D-E] Union of India v. Raman lron Foundry,
[1974] 3 S.C.R. 556; observations to the contrary held inconsistent with the
law laid down in the case.
CIVIL APPELLATE JURISDICTION: Civil Appeal
Nos. 2853 and 2863 of 1982.
From the Judgment and order dated the 24th
January, 1980 of the Allahabad High Court in Civil Revision No. 3452 of 1978.
D.C. Singhania, Raju Ramachandran, Muhul
Mudgal, JP Gupta for the appellant in C.A. No. 2854/82.
S.N. Kacker, D.C. Singhania, Raju
Ramachandran, Mukul judgal J.P. Gupta for the appellant in C.A. No. 2863/82.
610 KG. Bhagat Addl. Solicitor General for
the respondent in C.A. No. 2853/82.
Girish Chandra, C. V. Subba Rao and R.N.
Poddar for respondent in C.A. No. 2863/82.
The Judgment of the Court was delivered by
MISRA J. These two connected appeals by special leave are directed against the
judgment and order of the Allahabad High Court and Delhi High Court dated 24th
January, 1980 and 13th November, 1979 respectively. The first one arises out of
proceedings under s 20 of the Arbitration Act while the other arises out of
proceedings under s. 33 of the Arbitration Act.
These appeals raise a common question
regarding the inter pretation of cl. 18 of the general conditions of contract
contained in the standard form of contract entered into by the parties and the
ambit and scope of s. 41 of the Arbitration Act. The facts giving rise to these
appeals follow a common pattern and it would, therefore, be sufficient if we
set out the facts relating to Civil Appeal No. 2863 of 1982 to bring out
clearly the points which arise for consideration in these appeals.
The appellant in this appeal is a registered
firm and carries on the business of manufacturing and selling timber.
The Directorate General of Supplies and
Disposals (for short, DGS&D) functions as a purchase organisation for the
Government of India and makes purchases for various departments. In response to
an invitation for tender by the DGS&D for the supply of Bijasal logs first
class the appellant firm made an offer to supply 1016 cubic metres at a flat
rate of Rs. 669 per cubic metre. The DGS&D accepted the tender on 24th of
December, 1973. Pursuant to the acceptance of the tender a standard form of
contract was drawn up containing various clauses. Two important clauses of that
standard form of contract with which we are mainly concerned are cls; 18 and
24, which read:
"18. Recovery of Sums Due: Whenever any
claim for the payment of a sum of money arises out of or under the contract
against the contractor, the purchaser shall be entitled to recover such sum by
appropriating in whole or in part, the security, if any, deposited by the
contrac- 611 tor, and for the purpose aforesaid, shall be entitled to sell
and/or realise securities forming the whole or part of any such security
deposit. In the event of the security being insufficient, the balance and if no
security has been taken from the contractor, the entire sum recoverable shall
be recovered by appropriating any sum then due or which at any time thereafter
may become due to the contractor under the contract or any other contract with
the purchaser or the Government or any person contracting through the
Secretary. If such sum even be not sufficient to cover the full amount
recoverable, the contractor shall on demand pay to the purchaser the balance
remaining due ........." "24. Arbitration: In the event of any
question, dispute or difference arising under these conditions or any special
conditions of contract, or in connections with this contract (except as to any
matters the decision of which is specially provided for by these or the special
conditions) the same shall be referred to the sole arbitration of any officer
in the Ministry of Law, appointed to be the arbitrator by the Director General
of Supplies and Disposals. It will be no objection that the arbitrator is a
Government servant that he had to deal with the matters to which the contract
relates or that in the course of his duties as a Government servant he has
expressed views on all or any of the matters in dispute or difference. The
award of the arbitrator shall be final and binding on the parties to this
contract." The appellant, however, ailed to supply the goods. The contract
was cancelled on 28th of August, 1974 at the risk and cost of the appellant.
The DGS&D claims to have made risk purchases incurring an extra cost of Rs.
92,364. By notice dated 27th December, 1974 the DGS&D called upon the
appellants to pay that amount failing which alternating arrangements would be
made to recover the same.
It appears that there were some other
contracts between the appellant and the respondent whereunder the appellant has
supplied goods and payments were due to it under pending bills.
The appellant firm moved a petition under s
33 of the Arbitration Act before the court alleging that there was no concluded
612 contract in existence between the parties containing any arbitration clause
and prayed inter alia for determining the. Existence, validity and effect of
the alleged arbitration agreement. The stand of the Union of India on the other
hand is that there was a concluded contract between the parties and the
appellant firm was bound by the acceptance of the tender.
As the Union of India threatened to withhold
the amount of Rs. 92,364 from the payments due under the pending bills of other
contracts, the appellant firm sought for an injunction. Under s. 41 read with
Second Schedule of the Arbitration Act, and o. 39, rr. 1 and 2 read with s. 151
of the Code of Civil Procedure, restraining the respondents from appropriating,
withholding or recovering the amount claimed from its other bills in any manner
whatsoever.
As there was cleavage of opinion between the
Judges of the same High Court on the question whether such an injunction as
prayed for could be issued under s. 41 of the Arbitration Act, the learned
Single Judge referred the matter to a larger Bench. The learned Single Judge's
own view was that such an injunction could be issued under s.
41. The Division Bench on reference, however,
held that the Court could grant an injunction restraining the respondent from
appropriating or recovering the amount of damages claimed from appellant's
other pending bills, but No order restraining the Union of India from
withholding payments of the other pending bills could be issued under s. 41 of
the Arbitration Act in as much as it would amount to a direction to pay the
amount due Under other bills and such a prayer would virtually amount to
seeking a relief for decreeing the claim of the appellant in Those contracts.
The appellant has come up before this Court against this order by special
leave, as stated earlier.
It appears that a large number of
applications under s. 33 of the Arbitration Act had been moved in Delhi High
Court in similar matters. In some of the cases injunctions were also issued by
the learned Single- Judge restraining the respondents from recovering,
appropriating or withholding the amount from other bills of the contractors.
One of these matters Union of India v. Air Foam Industries was taken to this
Court, which was decided by the Court along with Union of India v. Raman iron
Foundry.(1) In that case 613 the Union of India put forward the extreme claim
that by virtue of cl. 18 of General Conditions of Contract it was entitled to
recover damages claimed by appropriating any sum which may become due to the
contractor under other pending bills from the Union of India. This Court,
however, negative the plea on the ground that the amount of damages claimed by
the Union was only a claim and unless there was adjudication of the claim by
Court or admission by the contractor the Union of India had no authority to
appropriate the amount due under pending bills of the contractor towards the
satisfaction of its claim for damages.
While construing the scope of s. 41 (b) of
the Arbitration Act this Court held:
"The Court has, therefore, power under
s. 41 (b) read with Second Schedule to issue interim injunction, but such
interim injunction can only be "for the purpose of and in relation to
arbitration proceedings". The arbitration proceedings in the present case
were for determination of the mutual claims of the appellant and the respondent
arising out of the contract contained in the acceptance of tender dated 16th
July, 1968. The question whether any amounts were payable by the appellant to
the respondent under other contracts was not the subject matter of the
arbitration proceedings. The Court obviously could not, therefore, make an
interim order which, though ostensibly in form and order of interim injunction,
in substance amounted to a direction to the appellant to pay the amounts due to
the respondent under other contracts. Such an interim order would clearly not
be for the purpose of or in relation to the arbitration proceedings as required
by s. 41 (b)." Having laid down the above dictum on the interpretation of
s. 41 of the Arbitration Act this Court proceeded to analyse the impugned order
of injunction in that case. In its opinion the order of injunction did not
expressly or by necessary implication carry any direction to the Union of India
to pay the amounts due to the respondent under other contracts. It is not only
in form but also in substance a negative injunction. It has no positive
content. What it does is merely to injunct the appellant from recovering suo
motu the damages claimed by it from out of the pending bills of the 614 respondent.
It does not direct that the appellant shall pay such amounts to the respondent.
The appellant Union of India can still refuse to pay such amounts if it thinks
it has a valid defence and if the appellant does so, the only remedy to the
respondent would be to take measures in an appropriate forum for recovery of
such amounts, where it would be decided whether the appellant is liable to pay
such amounts to the respondent or not. No breach of the order of interim
injunction as such would be involved in nonpayment of such amounts by the
respondent to the appellant. The only thing which the appellant is interdicted
from doing is to make recovery of its claim for damages by appropriating such
amounts in satisfaction of the claim. That is clearly within the power of the
Court under s. 41 (b) because the claim for damages forms the subject matter of
the arbitration proceedings and. the Court can always say that until such claim
is adjudicated upon, the appellant shall be restrained from recovering it by
appropriating other amounts due to the respondent. The order of interim
injunction made by the learned Judge cannot, therefore, be said to be outside
the scope of his power under s. 41 (b) read with the Second Schedule.
Following this judgment of the Supreme Court
the Delhi High Court started modulating its injunctions accordingly and refused
to include the word "withholding" in the order of injunction on the
ground that the order in those terms really Would mean an order to make the
payment which was specifically forbidden in terms of the above judgment of this
Court.
As some doubt was raised in the Delhi High
Court as to the exact scope of the ratio of the Union of India v. Raman Iron
Foundry (supra) the matter was referred to a full Bench apparently to reconsider
the earlier Division Bench judgments in Marwar Tent Factory v. Union of
India(1) and Air Foam Industries v. Union & India.(2) The full Bench Mohan
Meakin Breweries v. Union of India(3) took the view that though an injunction
could be granted in those matters restraining the Union of India from adjusting
of recovering any damages claimed by it from other pending bills of the
contractor no order of injunction restraining the Union of India from
withholding the payments due to the contractor under other pending bills could
be issued.
615 Following the Full Bench decision the
Division Bench in the present case held that the Court in arbitration
proceedings was not competent to issue an injunction restraining the Union of
India from withholding the amount due to the appellant-contractor under other
pending bills.
The only remedy of the appellant is to
proceed outside the arbitration proceedings for the payments due under the
pending bills, from the respondent. The Court can, however, restrain the Union
of India from recovering or appropriating the amount due to the
appellant-contractor under pending bills towards the damages claimed by the
Union, unless it has been adjudicated upon or admitted by the other side.
The first question that falls for consideration
in this appeal is about the exact scope and ambit of s. 41 of the Arbitration
Act It will be appropriate at this stage to read s. 41 in order to appreciate
the contention raised on behalf of the appellant:
"41. Procedure and powers of Court:-
Subject to the provisions of this Act and of rules made thereunder- (a) the
provisions of the Code of Civil Procedure, 1908 shall apply to all proceedings
before the Court, and to all appeals, under this Act, and (b) the Court shall
have, for the purpose of, and in relation to, arbitration proceeding, the same
power of making orders in respect of any of the matters set out in the Second
Schedule as it has for the purpose of, and in relation to, any proceedings
before the Court:- provided that nothing in clause (b) shall be taken to
prejudice any power which may be vested in an arbitrator or umpire for making
orders with respect to any of such matters." In view of cl. (b) of s. 41
the Court has been given power of passing orders in respect of any of the
matters set out in second Schedule for the purpose of and in relation to any
proceedings before the Court. The Second Schedule of the Arbitration Act inter
alia includes `interim injunction' and the 'appointment of receiver'. But the
Court has got the power to pass an order of injunction only 'for the purpose of
and in relation to arbitration proceedings' before the Court.
616 The proceedings before the Court in the
instant case was an application under s. 33 of the Arbitration Act.
Section 33 of the Arbitration Act in so far
as material for the case, provides:
"33. Any party to an arbitration
agreement or any person claiming under him desiring to challenge the existence
or validity of an arbitration agreement or an award or to have the effect of either
determined shall apply to the Court and the Court shall decide the question on
affidavits." The appellant in the instant case took the stand that there
was no concluded contract between the parties including arbitration. Therefore,
the order of injunction passed in the instant case could not be for the purpose
of and in relation to arbitration proceedings. Faced with this difficulty Shri
S. N. Kacker, learned counsel for the appellant, fell back upon cl. (a) of s.
41 to contend that cl. (a) makes the Code of Civil Procedure applicable to all
proceedings before the Court and to all appeals under the Act and, therefore,
the appellant was entitled to invoke order 39 of the Code to get an injunction
order even if the conditions of cl. (b) of s 41 were not satisfied. We are
afraid this contention cannot be accepted.
Clause (a) of s. 41 makes only the procedural
rules of the Code of Civil Procedure applicable to the proceedings in Court
under the Arbitration Act. This clause does not authoritse the Court to pass an
order of injunction. The power is conferred by cl. (b) of s. 41. The source of
power, therefore, cannot be traced to cl. (a). If the contention of Shri Kacker
is accepted, the appeals would lie under ss. 96, 100 or 104 of the I.P.C. but
the Arbitration Act itself provides for appeal under s. 39. Besides, if cl.(a)
of s.41 gave wide powers to pass an order of injunction, cl. (b) of s.41 would
become otiose.
The learned counsel for the appellant,
however, contends that the arbitration proceedings relate to the claim for
damages by the Union of India. Any act of the Union of India which purports to
enforce the said claim for damages, before it has been duly adjudicated upon in
arbitration proceedings is an act which relates to such arbitration
proceedings.
On the own case of the appellant that there
was no concluded contract between the parties containing an arbitration clause
it will 617 be difficult to say that the application for injunction moved by
the appellant was for the purpose of and in relation to arbitration
proceedings. This apart, the amount due under the pending bills to the
appellant was not the subject matter of the present proceedings and, therefore,
the injunction order restraining the respondents from withholding the amount
due to the appellant under the pending bills in respect of other contracts
could not be said to be for the purpose of and in relation to the present
arbitration proceedings. In this view of the matter it was not open to the
Court to pass the interim injunction restraining the respondents from
withholding the amount due to the appellant under pending bills in respect of
other contracts.
The learned counsel Shri Kacker, however,
strongly relied on the following observations of the Court in Union of India v.
Raman Iron Foundry (supra):
"But here the order of interim
injunction made by the learned Judge does not, expressly or by necessary
implication carry any direction to the appellant to pay the amounts due to the
respondent under other contracts. It is not only in form but also in substance
a negative in Junction. It has no positive content. What it does is merely to
injunct the appellant from recovering, suo moto, the damages claimed by it from
out of other amounts due to the respondent.
It does not direct that the appellant shall
pay such amounts to the respondents. The appellant can still refuse to pay such
amounts if it thinks it has a valid defence and if the appellant does so, the
only remedy open to the respondent would be to take measures in an appropriate
forum for recovery of such amounts where it would be decided whether the
appellant is liable to pay such amounts to the respondent or not. No breach of
the order of interim injunction as such would be involved in non-payment of
such amounts by the appellant to the respondent. The only thing which the
appellant is interdicted from doing is to make recovery of its claim for damages
by appropriating such amounts in satisfaction of the claim. That is clearly
within the power of the Court under s. 41 (b) because the claim for damages
forms the subject matter of the arbitration proceedings and the Court can
always say that until such claim is adjudicated upon, the appellant 618 shall
be restrained from recovering it by appropriating other amounts due to the
respondent.
The order of interim injunction made by the
learned judge cannot, therefore, be said to be outside the scope of his power
under s. 41 (b) read with the Second Schedule".
With profound respect we find that the
aforesaid observation is incongrous with the proposition of law laid down by
this Court just before this observation. We find it difficult to agree with the
observation of the Court that the impugned order in form and substance being
the negative the respondent could refuse to pay such amounts if it thinks it
has a valid defence, and if it chooses to do so there would be no breach of the
injunction order.
It is true that the order of injunction in
that case was in negative form. But if an order injuncted a party from
withholding the amount due to the other side under pending bills in other
contracts, the order necessarily means that the amount must be paid. If the
amount ii withheld there will be a defiance of the injunction order and that
party could be hauled up for infringing the injunction order. It will be a
contradiction in terms to say that a party is injuncted from withholding the
amount and yet it can withhold the amount as of right. In any case if the
injunction order is one which a party was not bound to comply with, the Court
would be loath and reluctant to pass such an ineffective injunction order. The
court never passes an order for the fun of passing it. It is passed only for
the purpose of being carried out. Once this Court came to the conclusion that
the Court has power under s. 41 (b) read with Second Schedule to issue interim
injunction but such interim injunction can only be for the purpose of and in
relation to arbitration proceedings and further that the question whether any
amounts were payable by the appellant to the respondent under other contracts,
was not the subject matter of the arbitration proceedings and, therefore, the
Court obviously could not make any interim order which though ostensibly in
form an order of interim injunction, in substance amount to a direction to the
appellant to pay the amounts due to the respondent under other contracts, and
such an order would clearly be not for the purpose of and in relation to the
arbitration proceedings; the subsequent observation of the Court that the order
of injunction being negative in form and substance, there was no direction to
the respondent to pay the amount due to the appellant under pending bills of
other contracts, is manifestly inconsistent with the proposition of law laid
down by this Court in the same case.
619 This leads us to the question of
interpretation of cl. 18 of the standard contract. Clause 18 has been quoted in
extenso in the earlier part of the judgment.
The argument by Shri K. G. Bhagat, Addl.
Solicitor General on behalf of the Union of India is that what is required for
attracting the applicability of cl. 18 is a mere claim for payment of a sum of
money arising out of or under the contract against the contractor and it is not
necessary that a sum of money must be actually due and payable from the
contractor to the purchaser. According to him, if the purchaser has a claim for
payment of a sum of money against the contractor, he would be entitled to
exercise the right given under cl. 18, even though such a claim may not be for
a sum due and payable but may be for damages and it may be disputed by the
contractor and may not have been adjudicated upon in a Court of law or by
arbitration. Shri Bharat further submits that if the claim of the purchaser is
not well founded and the appropriation made by the Union of India is
unjustified, the contractor can always institute a suit or start arbitration
proceedings for recovering the sums due to him which have been wrongly
appropriated by the purchaser and in such suit or arbitration proceedings, the
court or the arbitrator, as the case may be, would examine the validity of the
claim against which appropriation has been made by the purchaser and if the
claim is found to be unsustainable, set at naught the appropriation and pass a
decree or award for the sums due to the contractor. But the court cannot and
should not restrain the Union of India from exercising its right of appropriation
merely because the claim against which appropriation is sought to be made by
the purchaser is disputed by the contractor and is pending adjudication before
a court of law or arbitrator.
Shri Kacker on the other hand contends that
though the words used in the opening part of cl. 18 are "any claim for the
payment of a sum of money", which are general words of apparently wide
amplitude sufficient to cover even a claim for damages arising out of the
contract, a proper construction of the clause read as a whole clearly suggests
that these words are intended to refer only to a claim for a sum due and
payable and do not take in a claim for damages which is disputed by the
contractor. It is only when a claim for damages is adjudicated upon by a civil
court or an arbitrator and the breach of the contract is established and the
amount of damages ascertained and decreed that a debt due and payable comes
into 620 existence; till then it is nothing more than a mere right to sue for
damages, and it does not fall within the words of cl. 18. Moreover, cl. 18
merely provides a mode of recovery and it can have no application where a
claim, even though it be for a sum due and payable, is disputed by the
contractor and has to be established in a court of law or by arbitration.
Clause 18 applies only where a claim is either admitted, or in case of dispute,
substantiated by resort to the judicial process. Therefore, when a purchaser
has a claim for damages which is disputed by the contractor, the purchaser is
not entitled under cl. 18 to recover the amount of its claim for damages by
appropriating other sums due to the contractor until the claim for damages is
adjudicated upon and culminates in a decree. The respondent had consequently no
right under cl. 18 to appropriate sums due to the appellant under other
contracts in satisfaction of its claim for damages against the appellant, when
the claim for damages was pending adjudication This Court in Union v. Raman
Iron Foundry (supra) while construing cl. 18 of the standard contract observed:
"It is true that the words "any
claim for the payment of a sum of money" occurring in the opening part of
cl. 18 are words of great amplitude, wide enough to cover even a claim for
damages, but it is a well settled rule of interpretation applicable alike to
instruments as to statutes that the meaning of ordinary words is to be found
not so much in strict etymological propriety of language nor even in popular
use as in the subject or occasion on which they are used and the object which
is intended to be attained.
The context and collocation of a particular
expression may show that it was not intended to be used in the sense which it
ordinarily bears.
Language is at best an imperfect medium of
expression and a variety of meanings may often lie in a word or expression. The
exact colour and shape of the meaning of any word or expression should not be
ascertained by reading it in isolation, but it should be read structurally and
in its context, for its meaning may vary with its contextual setting. We must,
therefore, read the words 'any claim for the payment of a sum of money'
occurring in the opening part of cl. 18 not in isolation but in the context of
the whole clause, for the intention Of the parties is to be gathered not from
one part of the 621 clause or the other but from the clause taken as a whole.
It is in the light of this principle of interpretation that we must determine
whether the words 'any claim for the payment of a sum of money' refer only to a
claim for a sum due and payable which is admitted or in case of disputes,
established in court of a law or by arbitration or they also include a claim
for damages which is disputed by the contractor." The headings prefixed to
a section or a group of sections in some modern statutes are regarded as
preambles to those sections. They cannot control the plain words of the
statutes but they may explain ambiguous words. The view is now well settled
that the headings or titles prefixed to a section or a group of sections can be
referred to in determining the meaning of doubtful expressions. It is true that
the court is entitled to look at the headings in an Act of Parliament to
resolve any doubt they may have as to ambiguous words. The law is clear that
those headings cannot be used to give a different effect to clear words in the
section where there cannot be any doubt as to the ordinary meaning of the
words. The golden rule is that when the words of a statute are clear, plain and
unambiguous, that is, they are reasonably susceptible to only one meaning, the
courts are bound to give effect to that meaning irrespective of the
consequences. The duty of a Judge is to expound and not to legislate, is a
fundamental rule. If we apply the same principle to the interpretation of cl.
18 of the standard form of contract, it would be clear that the clause
unequivocally contemplates a claim for the payment and it is open to the Union
of India to appropriate any amount due to the contractor under other pending
bills. It does not contemplate the amount due and, therefore, the heading of
this clause which talks of only 'Recovery of sum due' will not control cl. 18.
The clause in our opinion gives wide powers to the Union of India to recover
the amount claimed by appropriating any sum then due or which at any time thereafter
may become due to the contractor under other contracts.
Clause 18 of the standard form of contract
earlier was slightly differently worded and it read 'whenever under this
contract any sum of money is recoverable from and payable by the contractor'. But
this formula was deliberately and advisedly altered when the present standard
form was introduced and instead the words 'whenever any claim for payment of a
sum of money arises' were substituted and this change in phraseology indicated
that in order 622 to attract the applicability of the present cl. 18, it was
not necessary that there should be a sum of money due and payable by the
contractor to the purchaser, but it was enough if there was a mere claim on the
part of the purchaser for payment of a sum of money 't by the contractor
irrespective of the fact whether such sum of money was presently due and
payable or not. This Court, however, did not attach importance to this aspect
of the matter by observing:
"We do not think it is legitimate to
construe cl. 18 of the contract between the parties by reference to a
corresponding clause which prevailed in an earlier standard form of contract.
This is not a statute enacted by the
legislature where it can be said that if the legislature has departed from the language
used by it in an earlier enactment, it would be a fair presumption to make that
the alteration in the language was deliberate and it was intended to convey a
different meaning. It is a clause in a contract which we are construing and
there any reference to a similar or dissimilar clause in another contract would
be irrelevant.
The Court itself while interpreting cl. 18 of
the contract has observed:
"It is true that the words "any
claim for the payment of a sum of money" occurring in the opening part of
cl. 18 are words of great amplitude, wide enough to cover even a claim for
damages, but it is well settled rule of interpretation applicable alike to
instruments as to statutes .......".
But while dealing with another aspect of cl.
18 observed to the contrary that it should not be construed as a statute.
It may, however, be pointed out that even
after the change in the language of cl. 18 of the standard agreement the Union
of India cannot be injuncted from withholding the amount under other bills of
the contractor. But it can certainly be injuncted from recovering or
appropriating it to the damages claimed.
Shri D. C. Singhania appearing along with
Shri Kackar substantially reiterated the same argument in his written note.
We are clearly of the view that an injunction
order restraining respondents from withholding the amount due under other
pending 623 bills to the contractor virtually amounts to a direction to pay the
amount to the contractor-appellant. Such an order was clearly beyond the purview
of cl. (b) of s. 41 of the Arbitration Act. The Union of India has no objection
to the grant of an injunction restraining it from recovering or appropriating
the amount lying with it in respect of other claims of the contractor towards
its claim for damages. But certainly cl. 18 of the standard contract confers
ample power upon the Union of India to withhold the amount and no injunction
order could be passed restraining the Union of India from withholding the
amount.
We find no error in the impugned order passed
by the Allahabad or the Delhi High Courts in the two cases. The appeals,
therefore, must fail and they are accordingly dismissed. In the circumstances
of the case, however, we direct that the parties should bear their own costs.
H.L.C. Appeals dismissed.