Om Prakash Gupta Vs. Dig Vijendrapal
Gupta [1982] INSC 31 (5 March 1982)
MISRA, R.B. (J) MISRA, R.B. (J) KOSHAL, A.D.
ERADI, V. BALAKRISHNA (J)
CITATION: 1982 AIR 1230 1982 SCR (3) 491 1982
SCC (2) 61 1982 SCALE (1)153
CITATOR INFO :
C 1984 SC 87 (18,20) 1985 SC 817 (8) D 1985
SC 817 (14) F 1987 SC2284 (4,11,13) F 1988 SC2031 (9) 1988 SC2164 (8) E&D
1990 SC 897 (8,9,10,11,14) D 1991 SC 266 (7) D 1992 SC1106 (6,10)
ACT:
U.P. Urban Buildings (Regulation of Letting,
Rent and Eviction) Act 1972. S.2 (2) and Expln. I and s. 39.
Applicability of the Act-Act not to apply to
building for a period of ten years from 'date of completion of construction'.
Date of completion of construction-What
is-'Date of first assessment' if assessed-'Date of occupation' when no record
of completion of construction or of assessment.
Interpretation of Statutes-Intention of
legislature-To be ascertained primarily from words used by legislative-
Question of interpretation arises when language ambiguous.
HEADNOTE:
The U.P. Urban Buildings (Regulation of
Letting, Rent and (Eviction) Act, 1972 provided by sub-section (2) of section 2
that except as provided in the Act, the Act was not to apply to a building
during a period of 10 years from the date on which its construction was completed.
Explanation I to the sub-section provided
that the building shall be deemed to have been completed on the date on which
completion thereof is reported or otherwise recorded by the local authorities
having jurisdiction, and in case of a building subject to assessment, the date
on which the first assessment thereof comes into effect, and where the said
dates are different, the earliest of the said date, and in the absence of any
such report, record or assessment, the date on which it is actually occupied
for the first time.
The appellant-tenant was in occupation of a
shop from the 16th June, 1967 and prior to his occupation the shop was in
occupation of another tenant for about a month and a half. The first assessment
of the shop took place on 1st of April, 1968. The respondent-landlord filed a
suit for the eviction of the tenant on the ground that the Act did not apply to
the shop and the tenant was liable to eviction.
The Trial Judge finding that the construction
of the shop was completed in the year 1967 and that 10 years having not elapsed
since then, held that the provisions of the Act did not apply and decreed the
suit. The appellant's 492 petition under section 25 of the Provincial Small
Causes Courts Act was dismissed. In his revision petition to the High Court
under section 115 of the Civil Procedure Code the appellant contended that the
date of occupation should be taken to be the date of completion of the
construction of the shop and not the date of first assessment. The High Court
overruled the contention and held that the construction of the shop would be
deemed to have been completed on 1st of April, 1968 the date of the first
assessment and ten years not having elapsed, the Act would not be applicable to
the building and dismissed the revision petition.
In the appeal to this Court it was contended
on behalf of the appellant: (1) that by virtue of sub-section (2) of section 2,
the Act would be applicable to the shop in question and that the exemption
created by the sub-section did not embrace buildings constructed prior to the
commencement of the Act and (2) that the building should be deemed to have been
constructed on the date of occupation on 16th June, 1967 and not on the date of
the first assessment.
and that the appellant was entitled to the
benefit of section 39 of the Act.
Dismissing the appeal,
HELD: 1(i) The suit was rightly decreed by
the Courts below. The Act had no application and the appellant could not be
given the benefit of section 39. [498 G-H] (ii) Primarily, the language
employed is the determining factor of the intention of the legislature. The
first and primary rule of construction is that the intention of the legislature
must be found in the words used by the legislature itself. The question of
interpretation arises only when the language is ambiguous and, therefore
capable of two interpretations. [497 F] (iii) The language of sub-section (2)
of section 2 of the Act is explict and unambiguous and is not capable of two
interpretations. [497 G] In the absence of any ambiguity there is no question
of taking any external aid for the interpretation of the sub- section. The
sub-section contemplates that the Act shall not apply to a building during a
period of 10 years from the date on which its construction is completed. It no
where says that the building should have been constructed after the enforcement
of the Act and to interpret it in such a way would be to add words to the
sub-section, which is not permissible. [497 D-F] 2 (i) Explanation I makes it
abundantly clear that the date of occupation would be taken to be the date of
completion of the construction only when there is no report or record of the
completion of the construction or no assessment thereof. If there is an
assessment, as in the instant case it will be the date of the first assessment
which will be deemed to be the date of completion of the construction. The
building had not therefore become more than ten years's old on the date when
the revision came to be decided by the High Court and consequently there was no
question of giving the benefit of section 39 of the Act to the appellant. [498
D-F] 493 (ii) In order to attract section 39 the suit must be pending on the
date of the commencement of the Act which was 15th of July, 1972. [498 F] In
the instant case the suit was filed on 23rd of March 1974 long after the
commencement of the Act. [498 F] (iii) In view of sub-section (2) of section 2,
the Act is not applicable to a building which has not a standing of ten years.
If the Act itself was not applicable, it would be absurd to say that section 39
thereof would be applicable.
[498 G] Rattan Lal Shinghal v. Smt. Murti
Devi (1980)4 S.C.C. 258 and Ram Saroop Rai v. Lilavati (1980) 3 S.C.C. 452,
over-ruled.
CIVIL APPELLATE JURISDICTION: Civil Appeal
No. 1314 of 1978.
Appeal by special leave from the judgment and
order dated the 23rd March, 1978 of the Allahabad High Court in Civil Revision
No. 1906 for 1976.
WITH
CIVIL APPEAL No. 2436 OF 1981 Appeal by special leave from the judgment and
order dated the 20th August, 1981 of the Allahabad High Court in Civil Writ
Petition No. 6909 of 1979.
AND CIVIL APPEAL No. 1710 OF 1981 From the
judgment and Decree dated the 13th March, 1981 of the Allahabad High Court in
Writ Petition No. 6167 of 1979.
AND SPECIAL LEAVE PETITION (CIVIL) NO. 3573
OF 1979 494 From the judgment and order dated the 3rd January, 1979 of the
Allahabad High Court in Civil Revision No. 3714 of 1978.
G.L.Sanghi, Mrs. A. Verma and D.N. Mishra for
the Appellant in CA. No. 1314 of 1978.
J.P. Goyal, S.Markandeya and C.K.Ratnaparkhi
for the Respondent in CA. 1314 of 1978.
A.K. Srivastava for the Appellant in CA.
1710/80.
R.B. Mehrotra for Respondent in CA. 1710/80.
Pramod Swarup and Mrs. S. Markandeya for the
appellant in CA. 2436 of 1980.
S.N. Kacker and K.K Gupta for the Respondent
in CA.
2436 of 1980.
P.R.Mridul, Praveen Jain and K.B. Rohatgi for
the Petitioner in SLP (Civil) No. 3573 of 1979 R.H. Dhebar for the Respondent.
The Judgment of the Court was delivered by
MISRA J. The first two appeals by special leave and the third by certificate
and the special leave petition raise a common question of law and, therefore,
we propose to dispose of them by a common judgment.
The pattern of facts in all these cases is
similar. We, therefore set out the facts of Civil Appeal No. 1314 of 1978 to
bring out the point for consideration in these matters.
The appellant Om Prakash Gupta is a tenant of
a shop on a monthly rent of Rs. 150/-.The respondent-landlord filed a suit for
the eviction of the tenant on the ground that the U.P. Urban Buildings
(Regulation of Letting, Rent and Eviction) Act, 1972 (Act 13 of 1972 and
hereinafter referred to as 'the Act') did not apply to the shop and the tenant
was liable to eviction. The Judge, Small Causes Court, Mainpuri decreed the
suit on the finding inter alia that the construction of the shop in suit was
completed in the year 1967 and 495 that ten years having not elapsed since
then, the provisions of the Act did not apply to the case. The defendant went
up in revision under section 25 of the Provincial Small Causes Courts Act
against the judgment and decree of the trial Court but the same was
substantially dismissed. The defendant thereupon filed a revision under section
115 of the Civil Procedure Code in the High Court which came up for hearing
before a learned Single Judge who remitted the following issue to the trial
court:
"On what date was the construction of
the building in dispute completed within the meaning of section 2 (2) of the
U.P. Urban Buildings (Regulation of Letting, Rent and Eviction) Act, 1972, and
deemed to have been completed as contemplated by Explanation I (a)
thereto." The Judge Small Causes Court by his order dated 26th of November
1977 returned the following finding:
"The construction of the disputed shop
will be deemed to have been completed on the date of the first assessment i.e.
1.4.68 within the meaning of section 2 (2) of the U.P. Urban Buildings Act,
1972." The finding returned by the trial court was sought to be challenged
on behalf of the tenant on the ground that the date of occupation should be
taken to be the date of completion of the construction of the shop and not the
date of the first assessment. In Tilak Raj v. Sardar Devendra Singh,(1) a
learned Single Judge of the same High Court had the occasion to consider
section 2 (2) of the Act. He held:
"It is apparent from this provision that
for purposes of this Act, a building is to be deemed to be constructed, if it
is subject to assessment, on the date with effect from which the first
assessment is made. It is immaterial whether the building was constructed
actually prior to that date or it had come into occupation prior to that date.
The law recognised for the purposes of this Act, the date of assessment as the
date of the completion of the building. There is thus no error in the judgment
of the court below." 496 The learned Single Judge before whom the revision
in the instant case came up for hearing doubted the correctness of the above
decision. He, therefore, referred the case to a Division Bench.
There is no dispute that the first assessment
of the shop took place on 1st of April, 1968. It is also not in dispute that
the shop in question was occupied by the defendant on 16th of June, 1967, and
prior to his occupation the shop was in occupation of another tenant for about
a month and a half. The appellant sought the benefit of section 39 of the Act
on the ground that if the date of occupation was taken to be the date of the
completion of the construction of the shop, then ten years having elapsed
during the pendency of the revision before the High Court, the Act would be
applicable. The Division Bench, however, over-ruled the contention of the
appellant and held that the construction of the shop in question would be
deemed to have been completed on 1st of April 1968 and, therefore, the Act
would not be applicable to the building till the date of the decision of the
revision on March 23, 1968. The defendant undaunted by the failure came to this
Court to challenge the judgment of the High Court.
Mr. G.L. Sanghi, senior counsel. appearing
for the appellant strongly contended that on a correct interpretation of
sub-section (2) of section 2, the Act would be applicable to the shop in
question. It would be appropriate at this stage to extract sub-section (2) of
section 2 of the Act insofar as it is material for the purposes of the case:
"Except as provided in sub-section (5)
of section 12, sub-section (1-A) of section 21, sub-section (2) of section 24,
sections 24A, 24B, 24C or sub-section (3) of section 29, nothing in this Act
shall apply to a building during a period of ten years from the date on which
its construction is completed:
Explanation I. For the purposes of this sub-
section:
(a) the construction of a building shall be
deemed to have been completed on the date on which the completion thereof is
reported to or otherwise recorded by the local authority having jurisdiction
and in the case of a building subject to assessment the date on which the first
assessment thereof 497 comes into effect, and where the said dates are
different, the earliest of the said dates, and in the absence of any such
report, record or assessment, the date on which it is actually occupied (not
including occupation merely for the purposes of supervising the construction or
guarding the building under construction) for the first time :.." The
precise contention on behalf of the appellant is that the exemption created by
this sub-section does not embrace buildings constructed prior to the
enforcement of the Act. In support of his contention, Mr. Sanghi, relied upon
Rattan Lal Shinghal v. Smt. Murti Devi.(1) The same contention was raised by
him in that case also and a Division Bench of this Court accepted the
contention and held that Act 13 of 1972 was prospective and applied only to
buildings brought into being de novo after the Act came into force. In that
case there is no discussion except this bald observation. This Court in a
subsequent case Ram Saroop Rai v. Lilavati(2) held to the contrary. It is on this
account that the present appeals were referred to a larger Bench.
There is no ambiguity in the language of
sub-section (2) of section 2 and in the absence of any ambiguity there is no
question of taking any external aid for the interpretation of the sub-section.
In plain words the sub-section contemplates that the Act shall not apply to a
building during a period of ten years from the date on which its construction
is completed. It nowhere says that the building should have been constructed
after the enforcement of the Act and to interpret it in the way the learned
counsel for the appellant seeks to interpret it, we would be adding words to
the sub-section, which is not permissible.
Primarily the language employed is the
determining factor of the intention of the legislature. The first and primary
rule of construction is that the intention of the legislature must be found in
the words used by the legislature itself.
The question of interpretation arises only
when the language is ambiguous and, therefore, capable of two interpretations.
In the present case the language of
sub-section (2) of section 2 of the Act is explicit and unambiguous and it is
not capable of two interpretations.
498 As a second limb to the first argument,
it is contended that the building will be deemed to have been constructed on
the date of occupation on 16th of June, 1967 and not on the date of the first
assessment, and that if this be so, the appellant would be entitled to the
benefit of section 39 of the Act on the date when the revision came to be
decided by the High Court on 23rd of March, 1978. In order to appreciate this
argument it will be expedient to refer to Explanation I to sub-section (2) of
section 2 which has already been extracted. Explanation I provides that the building
shall be deemed to have been completed on the date on which completion thereof
is reported to or otherwise recorded by the local authorities having
jurisdiction, and in case of a building subject to assessment the date on which
the first assessment thereof comes into effect and where the said dates are
different, the earliest of the said dates, and in the absence of any such
report, record or assessment, the date on which it is actually occupied for the
first time. A perusal of Explanation I makes it abundantly clear that the date
of occupation would be taken to be the date of completion of the construction
only when there is no report or record of the completion of the construction or
no assessment, thereof. If there is an assessment, as in the present case it
is, it will be the date of the first assessment which will be deemed to be the
date of completion of the construction and in that view of the matter the
building had not become more than ten years' old on the date when the revision
came to be decided by the High Court, and therefore there was no question of
giving the benefit of section 39 of the Act to the appellant.
Further, in order to attract section 39 the
suit must be pending on the date of commencement of the Act which is 15th of
July, 1972 but the suit giving rise to the present appeal was filed on 23rd of
March, 1974 long after the commencement of the Act. There is yet another reason
why section 39 will have no application to the present case. In view of
sub-section (2) of section 2 of the Act the Act is not applicable to a building
which has not a standing of ten years and if the Act itself was not applicable,
it would be absurd to say that section 39 thereof would be applicable.
Considered from any angle the Act has no
application to the present case and the appellant could not be given the
benefit of section 39. The suit has, therefore, been rightly decreed by the
courts below.
We find no force in either of the contentions
raised by Mr. Sanghi. The counsel for the appellants in the other appeals and
499 the petitioner in the special leave petition, adopted the arguments of Mr.
Sanghi.
For the foregoing discussion the appeals and
the special leave petition are dismissed. There shall, however, be no order as
to costs.
We, however, direct that the order of
eviction in each case shall not be executed before 30th of June, 1982 on
condition that each of the appellants in the appeals and the petitioner in the
special leave petition files an undertaking in this Court within four weeks
from today to the following effect:
1. that he will hand over vacant and peaceful
possession of the suit premises to the landlord-respondent on or before 30th of
June, 1982;
2. that he will pay to the respondent arrears
of rent, if any, within a month from today;
3. that he will pay to the respondent future
compensation for use and occupation of the suit premises for each calendar
month by the 10th of the succeeding month; and
4. that he will not induct any other person
in the suit premises as a sub-tenant or licensee or in any other capacity
whatsoever.
We further direct that in default of
compliance with any one or more of the conditions of the undertaking or if the
undertaking is not filed within the stipulated time, the decree of eviction
shall become executable forthwith.
N.V.K. Appeal dismissed.
Back